Turning Lemons Into Lemonade: How to Remediate and Redevelop Underfunded Contaminated Sites, Including Formerly Used Defense Sites and Other Contaminated
Former Military and Federal Facilities
Invited to provide guidance and expertise to the Commission regarding their proposed new Master Plan and issues of water quality, stream buffers, and restoration.
Invited to provide guidance and expertise to the Commission regarding their proposed new Master Plan and issues of water quality, stream buffers, and restoration.
Day-Of PowerPoint Presentation for June 2015 Amplify Event
North Coast Stakeholders reveal some of the newest developments in the district.
The Amplify Speaker Series, now in its ninth year, continues
to draw more business leaders. The luncheon series is
recognized as one of Cleveland’s best corporate networking
events. The goal is to bring professionals together to network
and to hear from a panel of industry experts in specific
categories/industries that adhere to that month’s theme in
Cleveland Business Connects (CBC) magazine.
LID LEED and Policy Barriers to Implementation (Dec-2010)Jon Barsanti
There are many reasons that people give for not using LID or LEED standards when developing property. It basically comes down to perceived costs and perceived benefits/barriers
Transboundary Diagnostic Anaylsis: The Mediterreanean RegionIwl Pcu
Objective: To scale the relative importance of sources and causes, both immediate and root, of the problems of transboundary ‘waters’.
To identify potential preventive and remedial actions.
Unblocking the Roadblocks to Environmentally Beneficial Re-Mining mlMark Levin
This presentation was part of a talk by the author at the San Juan Mine Reclamation Conference in 2016. It discusses obstacles to the potentially beneficial re-mining of formerly mined lands and suggests a policy framework going forward.
Sea Level Rise & the Conservation of Wetlands: Issues and Opportunities for C...riseagrant
Incorporating SLAMM Maps and Recommendation into Local Plans
Chelsea Siefert, RI Statewide Planning Program
Teresa Crean, URI Coastal Resources Center / RI Sea Grant
Submission by Lake Ontario Waterkeeper for the Darlington Nuclear Relicensing...LOWaterkeeper
On September 28, 2015, Lake Ontario Waterkeeper submitted a request to the Canadian Nuclear Safety Committee to intervene during the Day 2 Relicensing Hearing for the Darlington Nuclear Generating Station.
Day-Of PowerPoint Presentation for June 2015 Amplify Event
North Coast Stakeholders reveal some of the newest developments in the district.
The Amplify Speaker Series, now in its ninth year, continues
to draw more business leaders. The luncheon series is
recognized as one of Cleveland’s best corporate networking
events. The goal is to bring professionals together to network
and to hear from a panel of industry experts in specific
categories/industries that adhere to that month’s theme in
Cleveland Business Connects (CBC) magazine.
LID LEED and Policy Barriers to Implementation (Dec-2010)Jon Barsanti
There are many reasons that people give for not using LID or LEED standards when developing property. It basically comes down to perceived costs and perceived benefits/barriers
Transboundary Diagnostic Anaylsis: The Mediterreanean RegionIwl Pcu
Objective: To scale the relative importance of sources and causes, both immediate and root, of the problems of transboundary ‘waters’.
To identify potential preventive and remedial actions.
Unblocking the Roadblocks to Environmentally Beneficial Re-Mining mlMark Levin
This presentation was part of a talk by the author at the San Juan Mine Reclamation Conference in 2016. It discusses obstacles to the potentially beneficial re-mining of formerly mined lands and suggests a policy framework going forward.
Sea Level Rise & the Conservation of Wetlands: Issues and Opportunities for C...riseagrant
Incorporating SLAMM Maps and Recommendation into Local Plans
Chelsea Siefert, RI Statewide Planning Program
Teresa Crean, URI Coastal Resources Center / RI Sea Grant
Submission by Lake Ontario Waterkeeper for the Darlington Nuclear Relicensing...LOWaterkeeper
On September 28, 2015, Lake Ontario Waterkeeper submitted a request to the Canadian Nuclear Safety Committee to intervene during the Day 2 Relicensing Hearing for the Darlington Nuclear Generating Station.
Junior Professional Legal and Regulatory Group: Session 1 Lecture and Tutorial
Remediation and Redevelopment of Formerly Used Defense Sites
1. Turning Lemons Into Lemonade: How to
Remediate and Redevelop Underfunded
Contaminated Sites, Including Formerly
Used Defense Sites and Other Contaminated
Former Military and Federal Facilities
2. SPEAKERS
• Mr. Timothy Rogers, A.A.E.,
Executive Director, Salina Airport
, p
Authority
• Mr. Jeffrey A. Bolin, M.S., CHMM,
Bolin M.S. CHMM
Vice President - Technical
Operations,
Operations The Dragun Corporation
• Ms. Shawna Bligh, J.D., LL.M., The
Session Law Firm
• Mr. Chris Wendelbo, J.D. , LL.M.,
The S i Law Fi
Th Session L Firm
4. Presentation Objectives
Knowledge –Identify remediation and fi
• K l d Id tif di ti d financing
i
techniques that work.
• Control – Discuss techniques to Assume gr gr.
• Quality – Achieve genuine environmental protection.
Efficiency – F
• Effi i Focus resources on relevant issues and
l ti d
avoid missteps.
• Collaboration– Session participants share other
successful techniques.
7. Redevelopment of Former
Federal Facilities
d l l
• BRAC SITES
– Status
– Funding
– Redevelopment momentum / Remediation
• FUDS SITES
– Lack of funding g
– Site control issues
– Inability to address residual contamination
y
8. Redevelopment of Former
Federal Facilities
d l l
• Mi d BRAC / FUDS
Mixed
– Effective coordination among Federal Entities
– Continuity of redevelopment with lack of ability
to address FUDS environmental issues.
• Military Munitions
10. Local Community
Considerations
d
Timothy F. Rogers, A.A.E.
Timothy F Rogers A A E
Executive Director
Salina Airport Authority
Salina Airport Authority
12. Schilling Air Force Base: Site
Background
• SAC Base
• Operated from 1942 to 1965
• Conventional and Nuclear Weapons Systems
• Twelve (12) Nuclear Missile Silos
• Transferred to Salina Entities in 1965
• Current Uses Include:
l d
– Municipal Airport
– University and Vo Tech Facilities
Vo-Tech
– Active Military Operations
– Private Business/Light Industrial
13. Schilling Air Force Base: Site
Background
• FUDS Site
• Significant Environmental Contamination, including VOCs,
SVOCs, Metals, POL, Military Munitions/Lead, Landfills with
Unknown Contents
U k C t t
• Groundwater Plumes On Base and Off-Site, Moving towards
City’s Water Supply
y pp y
• Currently negotiating with COE and DOJ for a compromised
settlement with the United States
• Salina Entities would assume remedial tasks/obligations
15. Richards Gebaur: Site Background
Richards‐Gebaur: Site Background
• Former Air Force Base that has been conveyed to the City of Kansas City,
MO and the Port Authority of Kansas City, MO over the last twenty years.
• Contains BRAC, FUDS and IRP
• Contamination includes: VOCs, SVOCs, landfills with unknown industrial
, ,
contaminants, pesticides, POL and lead from skeet range operations.
• BRAC Sites are well characterized and remedies are in place and on-going.
• FUDS Sites have been characterized, but no funding for remediation now
characterized
or in the foreseeable future.
• Strong team of property redevelopers, including:
– The Port Authority of Kansas City MO
City,
– Kansas City Southern Railway
– CenterPoint Properties
– Martin Marietta / Hunt Midwest Materials
16. Richards Gebaur: Site Background
Richards‐Gebaur: Site Background
• Intermodal development – above ground and belowground development
– Kansas City Southern Railway tracks in place on former runway
– CenterPoint Surface Phase I complete, infrastructure in place and ready for buildings
– Martin Marietta / Hunt Midwest – Leased underground and preparing to proceed.
• FUDS Portion is interfering with the velocity of the redevelopment of the
f h h f h d f h
Site.
• The Port Authority has placed the entire Site (BRAC and FUDS) into the
Missouri Brownfields / Voluntary Cleanup Program
f ld l l
– Goal of using risk-based remedial standards
– Allows for “phasing” remediation efforts to threats to health/environment and address
those areas where the development will proceed before later phases of the project
project.
• The Port Authority has proposed a compromise settlement with the
United States to assume remedial role using funds from United States.
18. How to Move Forward?
“Once we come to grips with the fact that the contaminants
g p
were moving toward our water supply, that cleaning the
former Schilling Air Force Base was going to take at least 20 to
30 years, and realizing that we were going to have to compete
years
with every other FUDS Site for funding each year, we knew
that we had to take control of this process and be the ones
who took responsibility for cleaning the Site.”
h k bl f l h
“We realized what an undertaking it was, but felt like there
We was
was no other way and when the Corps offered to settle the
United States’ liability in exchange for our undertaking the
remedial work, we b
d l k began pursuing it.”
Tim Rogers, SAA
19. How to Move Forward?
“Knowing that we had to take ownership of the Site and the
g p
remediation process to ensure the safety of the citizens of
Salina and continue the redevelopment of the former Schilling
Air Force Base, we decided that we had to assemble sufficient
Base
environmental technical and legal expertise and add that
expertise to our existing team to ascertain:
(1) the full scope of the environmental contamination and an
appropriate remedy;
(2) whether a negotiated settlement could be achieved with
the United States; and
( )
(3) what steps were necessary to implement the remedy.”
p y p y
Tim Rogers, SAA
20. Tim Rogers’ Critical Thoughts
g g
• Key points that Tim wanted to convey:
– There are no shortcuts
– Use original source documents to learn the true
nature of the past historic uses at the Site
– Engage in a more collaborative process with the
United States, EPA and state regulators earlier in
the process
– Essential to have a locally unified team
– Verification of environmental technical and legal
g
requirements
24. Clarify…
y
•Historical Documents
•Previous Investigations
•Previous Work Plans
•Analytical Data
•Conclusions
•Calculations
•Basis for Conclusions
•Site Inspection
29. Quantify…
How Much $$$$$ or “Cost to Complete”
Cost Complete
• Data Gaps
• Additional Investigation
• Remedial Selection and Design
• Short and Long Term Monitoring
• Uncertainties and Unknowns
• Regulatory Interaction
• Implementation Schedule
p
35. Traditional/Known Financing
Approaches
A h
• BRAC/IRP A
Appropriations
i i
– Traditional Congressional Appropriations
• EPA Brownfields Program
– Assessment, Cleanup, and Job Training Grants
– Revolving Loan Funds
• Tax Credits
– Federal or State
36. Emerging/Novel Financing
Approaches
A h
• E i
Environmental S i
t l Services C
Cooperative A
ti Agreements
t
(“ESCA”)
– Allows the LRA to have increased control of BRAC site and allows the
military service to “outsource” environmental responsibilities in
exchange for a military obligation to reimburse the LRA.
• National Defense A h
l f Authorization A of Fiscal Year
Act f l
1993
– DOD Indemnifies BRAC Facility Transferees from Liability for
Contamination Resulting from DOD Activities
– Includes duty to defend
37. Emerging/Novel Financing
Approaches
A h
• Stimulus Funds
– The Emergency Economic Stabilization Act of 2008 (“2008
Stimulus Bill”). Public Law 110-343
– Th American Recovery and R i
The A i R d Reinvestment Act of 2009
t tA t f
(“2009 Stimulus Bill”). Public Law 111-5.
• Public/Private Partnerships
– Private Developer Funding Environmental Oversight &
Assurance
– Developer Assistance with Environmental Remediation
costs
38. Emerging/Novel Financing
Approaches
A h
• FUDS Negotiated Settlement
– In FY 2007, the estimated “cradle to grave” cost of the
United States to address residual environmental
contamination at FUDS sites was approximately $16.272
billion dollars. For FY 2007, Congress appropriated $262.1
million to address all FUDS sites for that year
year.
– United States Army Corps of Engineers
• ER 200-3-1 Formerly Used Defense Sites (FUDS)
y ( )
Program Policy
• Chapter 5 Potentially Responsible Party Process
39. Emerging/Novel Financing
Approaches
A h
• FUDS Negotiated Settlement Process (Cont’d)
(Cont d)
– The process to achieve settlement with USACE is
necessarily site-specific but some of the common steps for
y p p
each site include:
– Identification of appropriate site for settlement;
–NNegotiation of a preliminary pro rata percentage of
i i f li i f
responsibility between the parties based on equitable
factors;
– Development of a remedial approach, implementation plan
and Cost-to-Complete;
40. Emerging/Novel Financing
Approaches
A h
• FUDS Negotiated Settlement Process (Continued)
– Development of a Stakeholder Action Plan;
– Technical discussions with the USACE District office
regarding scope of any remaining investigation and
remedial alternatives and their associated costs;
– Settlement negotiations with the assigned Department of
Justice Attorney and/or USACE District Counsel;
– Referral of Settlement Demand by USACE chain-of-
command;
– Assignment of Department of Justice Attorney;
41. Emerging/Novel Financing
Approaches
A h
• FUDS Negotiated Settlement Process (
g (Continued) )
– Implementation of all or portions of Stakeholder Action
Plan, as needed;
– Finalization of Settlement in the form of a judicially
ordered Consent Decree;
– Finalization of state Administrative Orders on Consent;
– Implementation of Cost-to-Complete;
– Five year
Five-year reviews; and
– Closure.
42. Emerging/Novel Financing
Approachese
A h
• FUDS Cost Recovery Liti ti
C tR Litigation
– CERCLA 107(a) Cost Recovery Claim
– United States v. Atlantic Research , 551 U.S. 128 (2007)
v US
• CERCLA 107(a) allows cost recovery by a private party
that has itself incurred cleanup costs.
p
• One PRP may sue anther to recover response costs
incurred in voluntary cleanup.
– Site owners need not wait for EPA enforcement
action to institute a CERCLA 113(f) Contribution
Action
A ti
43. Emerging/Novel Financing
Approaches
A h
• FUDS C t R
Cost Recovery Liti ti (C t’d)
Litigation (Cont’d)
– Next step following unsuccessful FUDS
Negotiated Settlement
– Litigation preparation
• Remedial Determination / implementation schedule
• Coordination with State and Federal Regulators
• Demand on United States through COE
• Assembling costs and evaluation of liability
44. Emerging/Novel Financing
Approaches
A h
• FUDS C t R
Cost Recovery Liti ti (C t’d)
Litigation (Cont’d)
– CERCLA 107(a) Cost Recovery Action
• Elements
• Defenses
• Objectives/Goals
j
– Recovery of past costs expended for necessary and consistent
(NCP) response costs
– Secure Judicial determination allocating CERCLA liability
among the parties
45. Emerging/Novel Financing
Approaches
A h
• FUDS Cost Recovery Litigation (Cont’d)
C tR Liti ti (C t’d)
– Objectives/Goals (Continued)
– Secure a declaration pursuant to Section 113(g) of
CERCLA of the United States’ liability for future
responses costs incurred in remediating the FUDS
Site, including:
• Judicial determination of United States’ pro rata share
States
for future response costs
• Possible judicial determination for a lump sum payment
of monetary damages for future response costs
46. Emerging/Novel Financing
Approaches
A h
• Monetary Damages for Future Response Costs???
– Court Interpretations
• CERCLA 107(a)(4)(B)
– Jacksonville Electric Authority v. Eppinger and Russell Co.
• Unpublished Opinion
• Court awarded plaintiff over $21 million in lump-sum future
response costs
– Burlington Northern & Santa Fe Railway Company v. United States.
• Supreme Court rules that when a term is undefined within
CERCLA, one looks to the ordinary meaning
• “Incur” is undefined in CERCLA
• Plain Meeting of “incur” is “to be subject to or become liable for.”
47. Other Incentives
• Obt i i Mi
Obtaining Mineral Rights
l Ri ht
– Allowed under Section 209 of the Federal Land Policy
Management Act
– Application for Minerals is Made to Bureau of Land
Management
– May Act as Inducement to Prospective Redeveloper
• Allows for Transfer of Complete Title (i.e. Surface and
Subsurface)
• May allow for the exploitation of any potential
underlying value of the minerals
y g
• End-use may determine the real “value” of the minerals
(site-specific analysis)