CURRICULUM VITAE
Eng. Abu Sreaa Mohammed Abu Sreaa
Dear Sir,
I'm a Civil Engineer with a total working experience of 14 years in
Construction and Consultancy industries. Currently finalizing my Master
Degree of Engineering from "Faculty of Engineering, Helwan University,
Egypt" in "Construction Project Management" and my Master thesis
under the title of "Survey Engineering in Quality control and construction
management"
Through my work period in Egypt & Saudi Arabia I've worked as Civil
Engineer, Senior Survey Engineer in roads projects as well as reviewing of
roads design, in addition to overseeing the implementation where and
Quantity Survey Cost planning and commercial management throughout
the entire life cycle of the project from inception to post-completion.
My tasks also included: "Value engineering, Risk management and
calculation, Procurement advice and assistance during the tendering
procedures, Tender analysis and agreement of the contract sum,
Commercial management and contract administration, Assistance in
dispute resolution, Asset capitalization, Interim valuations and payment
assessment, Cost management process, Assessing the additional costs of
design variations and Follow-up time schedule
To prepare periodic reports for the project"
I'm keen to personal development and continuous learning which
encouraged me to develop myself in the field of Construction Management
by taking many courses
KEY WORDS
1
Planner, Quantity survey, Road works and Surveying Works
PERSONAL DETAILS
07-08-1978, 21Elola Mosque St. Saft El-Laban–Giza.
•Date and Place of Birth
Egyptian.
•Nationality
AAW Consulting Engineers &Partners Co. Company Saudi Arabia.
•Work address
Planner &Quantity Survey Engineer, "Design, built & upgrade of north Jeddah STP
(Airport-1) Project", Jeddah, Saudi Arabia.•Current Job
Excellent user for all of surveying instruments like : Level & Theodolite & Total
station & G.P.S•Personal Skills
Primavera (6.8& 15.2) &AutoCAD & Microsoft office & Surfer(6,7,&8) & land desk
top 3&4 & civil 3d 2013 & Arc GIS 10.2•Computer Skills
00966541673079
•Phone
AD_SPEED2002@YAHOO.COM
•E-mail
Arabic (Native Language) & English (excellent).
•Languages
Qualifications
Civil Public works, Faculty of Engineering, Banha branch Shubra Zagazig
University, 2002.
Surveying project.
•B Sc.
Passing in the exam of qualifying courses and going to complete Thesis.
The studied courses were:
Planning and Schedule Using Primavera, Value Engineering, Specialized
Costs, Tenders and contracts, Enterprise Resource Management, Quality and
construction Management,
•Engineering Construction
Management Postgraduate,
Helwan University, Matreya
Faculty of Engineering
(2014:now)
Work Experience
Quantity Survey and planner Engineer: King Abdel_Aziz National Airport
Treating Planet Project, Jeddah Saudi Arabia.
AAW Consulting Engineers &Partners Co. Company, (2015: now).
Key Responsibility
• Check and Review the current contractor's Payments and submit them
to the project manager
• Review documents contract the contractor& Bill of Quantities For the
project
• Preparation and work payments for the Consulting Engineers AAW
and submit them to the project manager
• calculation of quantities of design drawings& executed
accomplishment
• Review Quality Management Plan
•Quantity Survey and
Planner Engineer
2
• Review Risk Management Plan
• Reviewing the time schedule of the contractor and the work of daily,
weekly and monthly reports
Civil Engineer: supervising of oversee the implementation of the Survey
Works and road works, Housing Project of the National Guard,
Madina El Monawara Saudi Arabia,
AAW Consulting Engineers &Partners Co. Company, (2012:2015.(
Key Responsibility
• Make Traverse between ground control points and closing error
correction
• Receipt of RFI and review the attached data and filling
• Directing the surveyors team on how to check the work in site
• Follow-up calibration of surveying instruments
• Write daily report for the work that has been done in site
• make update drawing for project activities every week
• Review the as built drawing and match them with what has been
received by RFI
• Supervising the implementation of road works& asphalt mix design
review and follow-up tests for layers
• Supervising the implementation fences villa precast concrete
• Review of cross-sections and elevations between roads and fences
•Supervising Engineer
• Survey Engineer: Sulaymaniyah Village Company, Cairo-Alexandria
Desert Road, Km 55, (2011:2012)
Key Responsibility
• Make Traverse between ground control points and closing error
correction
• Receipt of RFI and review the attached data and filling
• Directing the surveyors team on how to check the work in site
• Follow-up calibration of surveying instruments
• Write daily report for the work that has been done in site
• make update drawing for project activities every week
• Supervising the implementation fences villa
• Review of cross-sections and elevations between roads and fences
•Surveying Works
3
• Survey Engineer: Private business, graphic design, estimated quantities for
cutting and filling and supervisor of the implementation (2010:2012, as a
part time).
• Survey and technical office Engineer: General Contracting Office (FAA),
(2007:2010):
Up town Cairo project, Emmar Misr, Elmokatm Road. Earthwork: 7
Mm3 cut & 7M m3 fill.
Marasy project, Sedy Abd Alrhman. Earthwork & Villas construction.
Key Responsibility
• Make Traverse between ground control points and closing error
correction
• Receipt of RFI and review the attached data and filling
• Directing the surveyors team on how to check the work in site
• Follow-up calibration of surveying instruments
• Write daily report for the work that has been done in site
• make update drawing for project activities every week
• Preparation and work payments for Road & calculation of quantities of
design drawings& executed
• Survey Manger: Arab Contractor, Tunnel dep., Contract 13 A, Dar EL
Salam, El Jazeera and EL Khiala pipe jacking, diameter 2.5m & 1.50 m,
(2006:2007).
Key Responsibility
• Make Traverse between ground control points and closing error
correction
• Receipt of RFI and review the attached data and filling
• Directing the surveyors team on how to check the work in site
• Follow-up calibration of surveying instruments
• Write daily report for the work that has been done in site
• make update drawing for project activities every week
• Survey Engineer: Industrial Construction & Engineering Co. (SIAC),
(2006):
1- Sugar factory Project, Ain El Skhona port.
2- Grand Mouzem Project, Medan Elremaia, Cairo-Alexandria desert
road.
Key Responsibility
• Make Traverse between ground control points and closing error
4
correction
• Receipt of RFI and review the attached data and filling
• Directing the surveyors team on how to check the work in site
• Follow-up calibration of surveying instruments
• Write daily report for the work that has been done in site
• make update drawing for project activities every week
• calculation of quantities of design drawings & executed(Cutting and
filling volumes )
• Survey Engineer: General Contracting Office (FAA), (2003:2006):
- Sheikh Zaid city: Land scape (General Garden), internal road ( road
construction ), earth moving and the major road of city
- EI-Khamael city: Land scape for 76 Fadden
- ELwahat -ElFayom road for 200km length.
- New Qena city: External and internal road for 26 km length.
Key Responsibility
• Make Traverse between ground control points and closing error
correction
• Receipt of RFI and review the attached data and filling
• Directing the surveyors team on how to check the work in site
• Follow-up calibration of surveying instruments
• Write daily report for the work that has been done in site
• make update drawing for project activities every week
Training Courses, Seminars
No. Title Institution Date
1
PMP Exam Preparation course V5 Aldarayn Academy
2016
2
Planning and Schedule Using Primevera Saudi Council of Engineer
2016
3
Planning , Control and EVM Using Primevera Saudi Council of Engineer
2016
4
Participate as VE team, Value Eng. study of
Master Planning of Water& Sewage Systems in
Khulais city, Jeddah
National Water Company and Al
Kuwaiter Value Engineering 2016
5 Project Management Science & Technology Institute for
Training
2015
5
6
Planning and Follow-up Science & Technology Institute for
Training 2015
7
Project Management Professional (PMP) Saudi Council of Engineer
2015
8
Total Quality Management Science & Technology Institute for
Training
2015
9
Enterprise Resource Management Science & Technology Institute for
Training
2014
10
Value Engineering Science & Technology Institute for
Training
2014
11
Specialized Costs Science & Technology Institute for
Training
2014
6
6
Planning and Follow-up Science & Technology Institute for
Training 2015
7
Project Management Professional (PMP) Saudi Council of Engineer
2015
8
Total Quality Management Science & Technology Institute for
Training
2015
9
Enterprise Resource Management Science & Technology Institute for
Training
2014
10
Value Engineering Science & Technology Institute for
Training
2014
11
Specialized Costs Science & Technology Institute for
Training
2014
6

Abu Srea Mohammed 2016-finall 112

  • 1.
    CURRICULUM VITAE Eng. AbuSreaa Mohammed Abu Sreaa Dear Sir, I'm a Civil Engineer with a total working experience of 14 years in Construction and Consultancy industries. Currently finalizing my Master Degree of Engineering from "Faculty of Engineering, Helwan University, Egypt" in "Construction Project Management" and my Master thesis under the title of "Survey Engineering in Quality control and construction management" Through my work period in Egypt & Saudi Arabia I've worked as Civil Engineer, Senior Survey Engineer in roads projects as well as reviewing of roads design, in addition to overseeing the implementation where and Quantity Survey Cost planning and commercial management throughout the entire life cycle of the project from inception to post-completion. My tasks also included: "Value engineering, Risk management and calculation, Procurement advice and assistance during the tendering procedures, Tender analysis and agreement of the contract sum, Commercial management and contract administration, Assistance in dispute resolution, Asset capitalization, Interim valuations and payment assessment, Cost management process, Assessing the additional costs of design variations and Follow-up time schedule To prepare periodic reports for the project" I'm keen to personal development and continuous learning which encouraged me to develop myself in the field of Construction Management by taking many courses KEY WORDS 1
  • 2.
    Planner, Quantity survey,Road works and Surveying Works PERSONAL DETAILS 07-08-1978, 21Elola Mosque St. Saft El-Laban–Giza. •Date and Place of Birth Egyptian. •Nationality AAW Consulting Engineers &Partners Co. Company Saudi Arabia. •Work address Planner &Quantity Survey Engineer, "Design, built & upgrade of north Jeddah STP (Airport-1) Project", Jeddah, Saudi Arabia.•Current Job Excellent user for all of surveying instruments like : Level & Theodolite & Total station & G.P.S•Personal Skills Primavera (6.8& 15.2) &AutoCAD & Microsoft office & Surfer(6,7,&8) & land desk top 3&4 & civil 3d 2013 & Arc GIS 10.2•Computer Skills 00966541673079 •Phone AD_SPEED2002@YAHOO.COM •E-mail Arabic (Native Language) & English (excellent). •Languages Qualifications Civil Public works, Faculty of Engineering, Banha branch Shubra Zagazig University, 2002. Surveying project. •B Sc. Passing in the exam of qualifying courses and going to complete Thesis. The studied courses were: Planning and Schedule Using Primavera, Value Engineering, Specialized Costs, Tenders and contracts, Enterprise Resource Management, Quality and construction Management, •Engineering Construction Management Postgraduate, Helwan University, Matreya Faculty of Engineering (2014:now) Work Experience Quantity Survey and planner Engineer: King Abdel_Aziz National Airport Treating Planet Project, Jeddah Saudi Arabia. AAW Consulting Engineers &Partners Co. Company, (2015: now). Key Responsibility • Check and Review the current contractor's Payments and submit them to the project manager • Review documents contract the contractor& Bill of Quantities For the project • Preparation and work payments for the Consulting Engineers AAW and submit them to the project manager • calculation of quantities of design drawings& executed accomplishment • Review Quality Management Plan •Quantity Survey and Planner Engineer 2
  • 3.
    • Review RiskManagement Plan • Reviewing the time schedule of the contractor and the work of daily, weekly and monthly reports Civil Engineer: supervising of oversee the implementation of the Survey Works and road works, Housing Project of the National Guard, Madina El Monawara Saudi Arabia, AAW Consulting Engineers &Partners Co. Company, (2012:2015.( Key Responsibility • Make Traverse between ground control points and closing error correction • Receipt of RFI and review the attached data and filling • Directing the surveyors team on how to check the work in site • Follow-up calibration of surveying instruments • Write daily report for the work that has been done in site • make update drawing for project activities every week • Review the as built drawing and match them with what has been received by RFI • Supervising the implementation of road works& asphalt mix design review and follow-up tests for layers • Supervising the implementation fences villa precast concrete • Review of cross-sections and elevations between roads and fences •Supervising Engineer • Survey Engineer: Sulaymaniyah Village Company, Cairo-Alexandria Desert Road, Km 55, (2011:2012) Key Responsibility • Make Traverse between ground control points and closing error correction • Receipt of RFI and review the attached data and filling • Directing the surveyors team on how to check the work in site • Follow-up calibration of surveying instruments • Write daily report for the work that has been done in site • make update drawing for project activities every week • Supervising the implementation fences villa • Review of cross-sections and elevations between roads and fences •Surveying Works 3
  • 4.
    • Survey Engineer:Private business, graphic design, estimated quantities for cutting and filling and supervisor of the implementation (2010:2012, as a part time). • Survey and technical office Engineer: General Contracting Office (FAA), (2007:2010): Up town Cairo project, Emmar Misr, Elmokatm Road. Earthwork: 7 Mm3 cut & 7M m3 fill. Marasy project, Sedy Abd Alrhman. Earthwork & Villas construction. Key Responsibility • Make Traverse between ground control points and closing error correction • Receipt of RFI and review the attached data and filling • Directing the surveyors team on how to check the work in site • Follow-up calibration of surveying instruments • Write daily report for the work that has been done in site • make update drawing for project activities every week • Preparation and work payments for Road & calculation of quantities of design drawings& executed • Survey Manger: Arab Contractor, Tunnel dep., Contract 13 A, Dar EL Salam, El Jazeera and EL Khiala pipe jacking, diameter 2.5m & 1.50 m, (2006:2007). Key Responsibility • Make Traverse between ground control points and closing error correction • Receipt of RFI and review the attached data and filling • Directing the surveyors team on how to check the work in site • Follow-up calibration of surveying instruments • Write daily report for the work that has been done in site • make update drawing for project activities every week • Survey Engineer: Industrial Construction & Engineering Co. (SIAC), (2006): 1- Sugar factory Project, Ain El Skhona port. 2- Grand Mouzem Project, Medan Elremaia, Cairo-Alexandria desert road. Key Responsibility • Make Traverse between ground control points and closing error 4
  • 5.
    correction • Receipt ofRFI and review the attached data and filling • Directing the surveyors team on how to check the work in site • Follow-up calibration of surveying instruments • Write daily report for the work that has been done in site • make update drawing for project activities every week • calculation of quantities of design drawings & executed(Cutting and filling volumes ) • Survey Engineer: General Contracting Office (FAA), (2003:2006): - Sheikh Zaid city: Land scape (General Garden), internal road ( road construction ), earth moving and the major road of city - EI-Khamael city: Land scape for 76 Fadden - ELwahat -ElFayom road for 200km length. - New Qena city: External and internal road for 26 km length. Key Responsibility • Make Traverse between ground control points and closing error correction • Receipt of RFI and review the attached data and filling • Directing the surveyors team on how to check the work in site • Follow-up calibration of surveying instruments • Write daily report for the work that has been done in site • make update drawing for project activities every week Training Courses, Seminars No. Title Institution Date 1 PMP Exam Preparation course V5 Aldarayn Academy 2016 2 Planning and Schedule Using Primevera Saudi Council of Engineer 2016 3 Planning , Control and EVM Using Primevera Saudi Council of Engineer 2016 4 Participate as VE team, Value Eng. study of Master Planning of Water& Sewage Systems in Khulais city, Jeddah National Water Company and Al Kuwaiter Value Engineering 2016 5 Project Management Science & Technology Institute for Training 2015 5
  • 6.
    6 Planning and Follow-upScience & Technology Institute for Training 2015 7 Project Management Professional (PMP) Saudi Council of Engineer 2015 8 Total Quality Management Science & Technology Institute for Training 2015 9 Enterprise Resource Management Science & Technology Institute for Training 2014 10 Value Engineering Science & Technology Institute for Training 2014 11 Specialized Costs Science & Technology Institute for Training 2014 6
  • 7.
    6 Planning and Follow-upScience & Technology Institute for Training 2015 7 Project Management Professional (PMP) Saudi Council of Engineer 2015 8 Total Quality Management Science & Technology Institute for Training 2015 9 Enterprise Resource Management Science & Technology Institute for Training 2014 10 Value Engineering Science & Technology Institute for Training 2014 11 Specialized Costs Science & Technology Institute for Training 2014 6