This document outlines the design and development process for a new product. It includes the key stages of information collection, design and drawings, prototyping, mold development, testing, and production. The general schedule estimates 1.5 weeks for information collection, 2.5 weeks for design and drawings, 4.5 weeks for prototyping, 8.5 weeks for mold development, and 10.5 weeks for testing to verify and validate the design before final production approval. The overall process from design input to approval is estimated at 13.5 weeks.
1. 斯康科技
Design & Development Process
Design Input Responsible Party General Schedule Total
New product concepts Client
Original desired function and performance Desing
requirement from end-user/market improve
to avoid
Customer requirements
failure
Applicable statutory and regulatory
Client / Project supervisor 1.5 weeks
mode
requirements
Information collection -- 1.5 weeks
Experience derived from our previous
similar designs Product Enigneer
Zero day meeting
DFMEA
Design Output
Graphic Product Engineer
Desing
Pro-E 3D or AutoCAD drawing Improve
Circuit diapram Design & Drawings -- 1 week
to the
fault on
Product Specification Circuit Diagram -- 1 week 2.5 weeks
prototype
Quality plan and check list Quality Engineer
Release for Prototype
DFMEA Prototype -- 1.5 weeks
Design Review (2 weeks if electronic included) 4.5 weeks
Product Engineer
Desing
Mechanical/Electric/Security/Productivity
Improve
by mold
Release for Mold
touch-up
Off-tooling sample
Punching mold -- 3 weeks 8.5 weeks
Design Verification Plastic mold -- 4 weeks
Die cast mold -- 5 weeks
EVT Test (Engineering sample Verification Desing
Test) Quality Engineer Off-tooling sample and testing 10.5 weeks
Improve
DVT Test (Design Verification Test on off- by mold -- 2 weeks
second
tooling samples) Project Supervisor
touch-up
Engineering sample
DFMEA
Mold touch-up -- 1 week
Design Validation Trial production and testing 11.5 weeks
Project Supervisor -- 2 weeks 12.5 weeks
PVT Test (Productivity Validation Test on Improve
Trial production) Client
production
process/
Release for Pilot run
production
PMP sample
layout-IE
PFMEA
Qualified samples for
Design Approval approval--1 week 13.5 weeks
Qualified production samples for client
approval Client
Production sample
Release for production
Production Production
Production and Inspection
Shipping sample
Production Shipping
Inspection and Logistic