SlideShare a Scribd company logo
1 of 2
Test Closure Report:
Test Closure report is a report that is created once the testing phase is successfully
completed by meeting exit criteria defined for the project.
Test Closure is created by Test Lead, reviewed by various stake holders like Test architect,
Test manager, Business Analyst, Project manager and finally approved by clients.
Test Closure memo contains details of the test passes carried out, results of each pass,
outstanding defects and how they would be dealt with once the post production goes live
etc.
What are test closure documents?
In my company, a Test Closure Document contains a checklist of all of the items that must
be met in order to close a test project as well as a list of activities that must be performed
after the project is closed. This document may include (not an exhaustive list):
BEFORE CLOSING A TEST PROJECT
1) Exit criteria is met
2) Testing performed against test plan
3) All test cases are mapped to requirements
4) All test cases have been executed unless known and agreed upon
5) All defects addressed
AFTER CLOSING A TEST PROJECT
1) Highlights and lowlights
2) Lessons learned
3) Process improvements
4) Test estimation evaluation
5) Defect trend analysis
6) Properly archive all relevant test collateral
- test plan(s)
- test report(s)
- test data
- Relevant emails
In contrast, a Test Closure Report is typically a simple email sent to all relevant stake
holders which indicates that testing is complete and QA either approves or disapproves the
release of the application based on whether or not it had met the company's exit criteria.
This report provides details which substantiate the "Go / No-Go" decision such as:
- # defects found
- # defects fixed
- # open total defects
- # open by Severity and Priority
- # postponed defects
- # not-run test cases
- # blocked test cases
- Items of concern

More Related Content

What's hot

Failure mode effect_analysis_fmea
Failure mode effect_analysis_fmeaFailure mode effect_analysis_fmea
Failure mode effect_analysis_fmeaJitesh Gaurav
 
An Introduction to Performance Testing
An Introduction to Performance TestingAn Introduction to Performance Testing
An Introduction to Performance TestingSWAAM Tech
 
QA. Load Testing
QA. Load TestingQA. Load Testing
QA. Load TestingAlex Galkin
 
Introduction to performance testing
Introduction to performance testingIntroduction to performance testing
Introduction to performance testingTharinda Liyanage
 
Performance testing : An Overview
Performance testing : An OverviewPerformance testing : An Overview
Performance testing : An Overviewsharadkjain
 
Testing artifacts test cases
Testing artifacts   test casesTesting artifacts   test cases
Testing artifacts test casesPetro Chernii
 
Fundamentals of Software Quality Assurance & Testing
Fundamentals of Software Quality Assurance & TestingFundamentals of Software Quality Assurance & Testing
Fundamentals of Software Quality Assurance & Testingrongbaz
 
Performance and load testing
Performance and load testingPerformance and load testing
Performance and load testingsonukalpana
 
Five Common Mistakes made when Conducting a Software FMECA
Five Common Mistakes made when Conducting a Software FMECAFive Common Mistakes made when Conducting a Software FMECA
Five Common Mistakes made when Conducting a Software FMECAAnn Marie Neufelder
 
Load and performance testing
Load and performance testingLoad and performance testing
Load and performance testingQualitest
 
Performance Requirement Gathering
Performance Requirement GatheringPerformance Requirement Gathering
Performance Requirement GatheringAtul Pant
 
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3Abbas (Bob) Youssef MBA, PhD
 
Intro to Manual Testing
Intro to Manual TestingIntro to Manual Testing
Intro to Manual TestingAyah Soufan
 
Software Testing - Part 1 (Techniques, Types, Levels, Methods, STLC, Bug Life...
Software Testing - Part 1 (Techniques, Types, Levels, Methods, STLC, Bug Life...Software Testing - Part 1 (Techniques, Types, Levels, Methods, STLC, Bug Life...
Software Testing - Part 1 (Techniques, Types, Levels, Methods, STLC, Bug Life...Ankit Prajapati
 
An Introduction to Software Failure Modes Effects Analysis (SFMEA)
An Introduction to Software Failure Modes Effects Analysis (SFMEA)An Introduction to Software Failure Modes Effects Analysis (SFMEA)
An Introduction to Software Failure Modes Effects Analysis (SFMEA)Ann Marie Neufelder
 
Getting start with Performance Testing
Getting start with Performance Testing Getting start with Performance Testing
Getting start with Performance Testing Yogesh Deshmukh
 
Infographic: Importance of Performance Testing
Infographic: Importance of Performance TestingInfographic: Importance of Performance Testing
Infographic: Importance of Performance TestingKiwiQA
 

What's hot (20)

Failure mode effect_analysis_fmea
Failure mode effect_analysis_fmeaFailure mode effect_analysis_fmea
Failure mode effect_analysis_fmea
 
FMEA
FMEAFMEA
FMEA
 
An Introduction to Performance Testing
An Introduction to Performance TestingAn Introduction to Performance Testing
An Introduction to Performance Testing
 
QA. Load Testing
QA. Load TestingQA. Load Testing
QA. Load Testing
 
Introduction to performance testing
Introduction to performance testingIntroduction to performance testing
Introduction to performance testing
 
Performance testing : An Overview
Performance testing : An OverviewPerformance testing : An Overview
Performance testing : An Overview
 
Testing artifacts test cases
Testing artifacts   test casesTesting artifacts   test cases
Testing artifacts test cases
 
Fundamentals of Software Quality Assurance & Testing
Fundamentals of Software Quality Assurance & TestingFundamentals of Software Quality Assurance & Testing
Fundamentals of Software Quality Assurance & Testing
 
Performance and load testing
Performance and load testingPerformance and load testing
Performance and load testing
 
Five Common Mistakes made when Conducting a Software FMECA
Five Common Mistakes made when Conducting a Software FMECAFive Common Mistakes made when Conducting a Software FMECA
Five Common Mistakes made when Conducting a Software FMECA
 
Load and performance testing
Load and performance testingLoad and performance testing
Load and performance testing
 
Performance Requirement Gathering
Performance Requirement GatheringPerformance Requirement Gathering
Performance Requirement Gathering
 
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
 
01 fmea
01 fmea01 fmea
01 fmea
 
Intro to Manual Testing
Intro to Manual TestingIntro to Manual Testing
Intro to Manual Testing
 
Process fmea work_instructions
Process fmea work_instructionsProcess fmea work_instructions
Process fmea work_instructions
 
Software Testing - Part 1 (Techniques, Types, Levels, Methods, STLC, Bug Life...
Software Testing - Part 1 (Techniques, Types, Levels, Methods, STLC, Bug Life...Software Testing - Part 1 (Techniques, Types, Levels, Methods, STLC, Bug Life...
Software Testing - Part 1 (Techniques, Types, Levels, Methods, STLC, Bug Life...
 
An Introduction to Software Failure Modes Effects Analysis (SFMEA)
An Introduction to Software Failure Modes Effects Analysis (SFMEA)An Introduction to Software Failure Modes Effects Analysis (SFMEA)
An Introduction to Software Failure Modes Effects Analysis (SFMEA)
 
Getting start with Performance Testing
Getting start with Performance Testing Getting start with Performance Testing
Getting start with Performance Testing
 
Infographic: Importance of Performance Testing
Infographic: Importance of Performance TestingInfographic: Importance of Performance Testing
Infographic: Importance of Performance Testing
 

Similar to Test closurereport

Test planning & estimation
Test planning & estimationTest planning & estimation
Test planning & estimationLeslie Smart
 
Health Care Project Testing Process
Health Care Project Testing ProcessHealth Care Project Testing Process
Health Care Project Testing ProcessH2Kinfosys
 
R!!! ria-gui-test plan 1.0
R!!! ria-gui-test plan 1.0R!!! ria-gui-test plan 1.0
R!!! ria-gui-test plan 1.0hanumanthunembi
 
Test Report Preparation
Test Report PreparationTest Report Preparation
Test Report PreparationDucat India
 
Software-Testing-Chapgdgdgsghshshshshshshs
Software-Testing-ChapgdgdgsghshshshshshshsSoftware-Testing-Chapgdgdgsghshshshshshshs
Software-Testing-Chapgdgdgsghshshshshshshsshaikbab
 
Testing documents
Testing documentsTesting documents
Testing documentsHari Tiru
 
STLC (Software Testing Life Cycle)
STLC (Software Testing Life Cycle)STLC (Software Testing Life Cycle)
STLC (Software Testing Life Cycle)Ch Fahadi
 
unit-2_20-july-2018 (1).pptx
unit-2_20-july-2018 (1).pptxunit-2_20-july-2018 (1).pptx
unit-2_20-july-2018 (1).pptxPriyaFulpagare1
 
Testing documents
Testing documentsTesting documents
Testing documentssuhasreddy1
 
Test Execution
Test ExecutionTest Execution
Test ExecutionRajathi-QA
 
Fundamentaltestprocess windirohmaheny11453205427 kelase
Fundamentaltestprocess windirohmaheny11453205427 kelaseFundamentaltestprocess windirohmaheny11453205427 kelase
Fundamentaltestprocess windirohmaheny11453205427 kelasewindi rohmaheny
 
Chapter 1 Fundamental of Testing
Chapter 1 Fundamental of TestingChapter 1 Fundamental of Testing
Chapter 1 Fundamental of TestingSiti Deny Nadiroha
 
Software testing interview Q&A – Part 2
Software testing interview Q&A – Part 2Software testing interview Q&A – Part 2
Software testing interview Q&A – Part 2Khoa Bui
 

Similar to Test closurereport (20)

Test planning & estimation
Test planning & estimationTest planning & estimation
Test planning & estimation
 
All about testing
All about testingAll about testing
All about testing
 
Health Care Project Testing Process
Health Care Project Testing ProcessHealth Care Project Testing Process
Health Care Project Testing Process
 
R!!! ria-gui-test plan 1.0
R!!! ria-gui-test plan 1.0R!!! ria-gui-test plan 1.0
R!!! ria-gui-test plan 1.0
 
Test Report Preparation
Test Report PreparationTest Report Preparation
Test Report Preparation
 
Software-Testing-Chapgdgdgsghshshshshshshs
Software-Testing-ChapgdgdgsghshshshshshshsSoftware-Testing-Chapgdgdgsghshshshshshshs
Software-Testing-Chapgdgdgsghshshshshshshs
 
Fundamental test process
Fundamental test processFundamental test process
Fundamental test process
 
Testing documents
Testing documentsTesting documents
Testing documents
 
STLC (Software Testing Life Cycle)
STLC (Software Testing Life Cycle)STLC (Software Testing Life Cycle)
STLC (Software Testing Life Cycle)
 
unit-2_20-july-2018 (1).pptx
unit-2_20-july-2018 (1).pptxunit-2_20-july-2018 (1).pptx
unit-2_20-july-2018 (1).pptx
 
Testing documents
Testing documentsTesting documents
Testing documents
 
Test Execution
Test ExecutionTest Execution
Test Execution
 
stlc
stlcstlc
stlc
 
stlc
stlcstlc
stlc
 
Qa documentation pp
Qa documentation ppQa documentation pp
Qa documentation pp
 
Fundamentaltestprocess windirohmaheny11453205427 kelase
Fundamentaltestprocess windirohmaheny11453205427 kelaseFundamentaltestprocess windirohmaheny11453205427 kelase
Fundamentaltestprocess windirohmaheny11453205427 kelase
 
Chapter 1 Fundamental of Testing
Chapter 1 Fundamental of TestingChapter 1 Fundamental of Testing
Chapter 1 Fundamental of Testing
 
Stlc ppt
Stlc pptStlc ppt
Stlc ppt
 
Software testing interview Q&A – Part 2
Software testing interview Q&A – Part 2Software testing interview Q&A – Part 2
Software testing interview Q&A – Part 2
 
Test plan
Test planTest plan
Test plan
 

More from TestingGeeks

Istqb question-paper-dump-14
Istqb question-paper-dump-14Istqb question-paper-dump-14
Istqb question-paper-dump-14TestingGeeks
 
Istqb question-paper-dump-13
Istqb question-paper-dump-13Istqb question-paper-dump-13
Istqb question-paper-dump-13TestingGeeks
 
Istqb question-paper-dump-12
Istqb question-paper-dump-12Istqb question-paper-dump-12
Istqb question-paper-dump-12TestingGeeks
 
Istqb question-paper-dump-11
Istqb question-paper-dump-11Istqb question-paper-dump-11
Istqb question-paper-dump-11TestingGeeks
 
Istqb question-paper-dump-10
Istqb question-paper-dump-10Istqb question-paper-dump-10
Istqb question-paper-dump-10TestingGeeks
 
Istqb question-paper-dump-9
Istqb question-paper-dump-9Istqb question-paper-dump-9
Istqb question-paper-dump-9TestingGeeks
 
Istqb question-paper-dump-8
Istqb question-paper-dump-8Istqb question-paper-dump-8
Istqb question-paper-dump-8TestingGeeks
 
Istqb question-paper-dump-7
Istqb question-paper-dump-7Istqb question-paper-dump-7
Istqb question-paper-dump-7TestingGeeks
 
Istqb question-paper-dump-6
Istqb question-paper-dump-6Istqb question-paper-dump-6
Istqb question-paper-dump-6TestingGeeks
 
Istqb question-paper-dump-5
Istqb question-paper-dump-5Istqb question-paper-dump-5
Istqb question-paper-dump-5TestingGeeks
 
Istqb question-paper-dump-4
Istqb question-paper-dump-4Istqb question-paper-dump-4
Istqb question-paper-dump-4TestingGeeks
 
Istqb question-paper-dump-3
Istqb question-paper-dump-3Istqb question-paper-dump-3
Istqb question-paper-dump-3TestingGeeks
 
Istqb question-paper-dump-2
Istqb question-paper-dump-2Istqb question-paper-dump-2
Istqb question-paper-dump-2TestingGeeks
 
Istqb question-paper-dump-1
Istqb question-paper-dump-1Istqb question-paper-dump-1
Istqb question-paper-dump-1TestingGeeks
 
Istqb iseb bh0-010-ajoy_singha
Istqb iseb bh0-010-ajoy_singhaIstqb iseb bh0-010-ajoy_singha
Istqb iseb bh0-010-ajoy_singhaTestingGeeks
 

More from TestingGeeks (20)

Sql
SqlSql
Sql
 
Qtp
QtpQtp
Qtp
 
Qtp ans
Qtp ansQtp ans
Qtp ans
 
Selenium
SeleniumSelenium
Selenium
 
Password
PasswordPassword
Password
 
Istqb question-paper-dump-14
Istqb question-paper-dump-14Istqb question-paper-dump-14
Istqb question-paper-dump-14
 
Istqb question-paper-dump-13
Istqb question-paper-dump-13Istqb question-paper-dump-13
Istqb question-paper-dump-13
 
Istqb question-paper-dump-12
Istqb question-paper-dump-12Istqb question-paper-dump-12
Istqb question-paper-dump-12
 
Istqb question-paper-dump-11
Istqb question-paper-dump-11Istqb question-paper-dump-11
Istqb question-paper-dump-11
 
Istqb question-paper-dump-10
Istqb question-paper-dump-10Istqb question-paper-dump-10
Istqb question-paper-dump-10
 
Istqb question-paper-dump-9
Istqb question-paper-dump-9Istqb question-paper-dump-9
Istqb question-paper-dump-9
 
Istqb question-paper-dump-8
Istqb question-paper-dump-8Istqb question-paper-dump-8
Istqb question-paper-dump-8
 
Istqb question-paper-dump-7
Istqb question-paper-dump-7Istqb question-paper-dump-7
Istqb question-paper-dump-7
 
Istqb question-paper-dump-6
Istqb question-paper-dump-6Istqb question-paper-dump-6
Istqb question-paper-dump-6
 
Istqb question-paper-dump-5
Istqb question-paper-dump-5Istqb question-paper-dump-5
Istqb question-paper-dump-5
 
Istqb question-paper-dump-4
Istqb question-paper-dump-4Istqb question-paper-dump-4
Istqb question-paper-dump-4
 
Istqb question-paper-dump-3
Istqb question-paper-dump-3Istqb question-paper-dump-3
Istqb question-paper-dump-3
 
Istqb question-paper-dump-2
Istqb question-paper-dump-2Istqb question-paper-dump-2
Istqb question-paper-dump-2
 
Istqb question-paper-dump-1
Istqb question-paper-dump-1Istqb question-paper-dump-1
Istqb question-paper-dump-1
 
Istqb iseb bh0-010-ajoy_singha
Istqb iseb bh0-010-ajoy_singhaIstqb iseb bh0-010-ajoy_singha
Istqb iseb bh0-010-ajoy_singha
 

Test closurereport

  • 1. Test Closure Report: Test Closure report is a report that is created once the testing phase is successfully completed by meeting exit criteria defined for the project. Test Closure is created by Test Lead, reviewed by various stake holders like Test architect, Test manager, Business Analyst, Project manager and finally approved by clients. Test Closure memo contains details of the test passes carried out, results of each pass, outstanding defects and how they would be dealt with once the post production goes live etc. What are test closure documents? In my company, a Test Closure Document contains a checklist of all of the items that must be met in order to close a test project as well as a list of activities that must be performed after the project is closed. This document may include (not an exhaustive list): BEFORE CLOSING A TEST PROJECT 1) Exit criteria is met 2) Testing performed against test plan 3) All test cases are mapped to requirements 4) All test cases have been executed unless known and agreed upon 5) All defects addressed AFTER CLOSING A TEST PROJECT 1) Highlights and lowlights 2) Lessons learned 3) Process improvements 4) Test estimation evaluation 5) Defect trend analysis 6) Properly archive all relevant test collateral - test plan(s) - test report(s) - test data - Relevant emails
  • 2. In contrast, a Test Closure Report is typically a simple email sent to all relevant stake holders which indicates that testing is complete and QA either approves or disapproves the release of the application based on whether or not it had met the company's exit criteria. This report provides details which substantiate the "Go / No-Go" decision such as: - # defects found - # defects fixed - # open total defects - # open by Severity and Priority - # postponed defects - # not-run test cases - # blocked test cases - Items of concern