The document describes several proposed construction and industrial projects in the Republic of North Ossetia-Alania, including: construction of a fruit storage and processing complex; modernization of an existing house building cluster; establishment of a year-round health resort; and construction of a fully automated cattle breeding farm and milk processing plant. The projects aim to develop agriculture, construction materials production, health tourism and dairy industries in the region.
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
6K-ton fruit complex
1. Construction of a fruit storing complex for 6 thousand tons of production and fruit processing
department
1. Project summary and
targets
Establishment of an effective modern fruit storage and processing
complex including the fruit storage for 6288 tons of production and
the unit for processing fruit into jam with the capacity of 1,5 tons
per shift. The project is strategically important for the development
of agricultural industry of the Republic of North Ossetia-Alania as
it aims at development of agricultural products processing in the
country, contributes to creation of new jobs and focuses on import
substitution.
2. Project initiator Agricultural production cooperative “De-Gusto”
75, Khetagurova st., Elkhotovo, Kirovskiy district, Republic of
North Ossetia – Alania, 363600
tel.: (8672) 54-42-41,
E-mail: degusto2002@yandex.ru,
Chairman – Ms. Rima Mukhtarovna Dzitsoeva
3. Project implementation
area
Rural area 3,2 km East of Elkhotovo village, Kirovskiy district,
RNO – Alania.
4. Targeted production The production range includes horticultural products demanded in
the market. Presumably jams will be processed from the following
fruits: apple, plum, pear and packaged into assumed 650 ml jars.
5. Potential consumers St. Petersburg - 25%
Ekaterinburg - 25%
Voronezh - 10%
Rostov-on-Don - 15%
Republic of North Ossetia – Alania - 25%.
6. Total project value 438,5 mln RUB
2. 7. Project investment period 4,8 years
8. Curre nt status of the
proje ct implementation
The business plan, design estimate documentation and permit for
construction of the fruit storage are available.
The production range of the project has been identified. Business
proposals from the equipment suppliers have been received. The
suppliers of the packaging and equipment for the project have been
also identified as well as the sales markets. There is a land plot
owned by the initiator.
9. Possible forms of
participation in the
project
Project lending
Creation ofa house building cluster with the full cycle ofmanufacturing of hi-tech resource-saving
construction materials in the Republic of North Ossetia-Alania
1. Project summary and
targets
Modernization of existing plants producing reinforced concrete
frames, brick, facing tiles, bridge beams. 3 times increase of
industrial productivity.
2. Project initiator Closed Joint-stock Company «Kavkazelectronstroy»
20 B, Butaeva st., Vladikavkaz, Republic of North Ossetia –
Alania, 362021
tel.: 8(8672)76-74-70, факс: 8(8672)76-40-71,
E-mail: kavstroy@mail.ru,
President – Mr. Felix Tembolatovich Tsakhilov
3. Project implementation
area
Beslan, Vladikavkaz, Republic of North Ossetia – Alania
4. Targeted production Hyperpressed colored dolomite brick «Tribopress» - 24 mln pieces
per year.
2. Extruded reigorced concrete products manufacturedby means of
off-form concreting «Tensyland» - 240 thous sqaure m per year.
3. 3. Sawn diabase and dolomite products - 120.0 thous square m per
year and 10.0 thous cub m of block products per year.
4. Ceramic facing brick - 20 mln pieces per year, ultra-light large-
size blocks - 30 mln of conventional brick and 10 mln pieces of
glazed brick.
5. Easily assemblable bridge beams up to 24 m long - 1200 pieces
per year.
5. Potential consumers Construction companies of the North Caucasus Federal Region,
Republic of South Ossetia
6. Total project value 6165,0 mln RUB
7. Project investments 1747,0 mln RUB
8. Project investment period 87 months
9. Project implementation
period
3 years from the project launch
10. Project payback period 63 months
11. Curre nt status of the
proje ct implementation
Business plan, financial model, process plan, estimates and
licenses are available
12. Possible forms of
participation in the
project
Project lending
13. Supporting information Estimated profit from 1sq.m. of living space is 8-10 thousand RUB
Design and industrial operation of highly efficient automatically controlled agrocomplex with the
closed-cycle cultivation and processing of organic products
1. Project summary and
targets
Automatically controlled argocomplex including greenhouse with
autonomous heating, lighting and watering for cultivating of
ecologically clean agricultural products. In-house base for
production of environmentally friendly fertilizers made using
microbiological techniques will be established in order to provide
availability of biologic fertilizers.
4. The project implementation will significantly excel (by 1,6-1,8
times) technical and operational parameters and economic
indicators of the leading foreign peers.
2. Project initiator Closed Joint-stock company Scientific and production innovation
company “Nauka” (Science) in cooperation with LLC Corporation
“IPI”
15, Griboedova st.,Vladikavkaz, Republic of North Ossetia-Alania,
362015
tel./fax: 8(8672)52-47-09, E-mail: npvladctt@mail.ru,
Director General – Mr. Leonid Zakharovich Zaseev
3. Project implementation
area
15, Griboedova st., Vladikavkaz, Republic of North Ossetia-Alania
4. Targeted production Organic vegetables, greenery, small fruits, manure
5. Potential consumers The products will be implemented in the Republic of North Ossetia-
Alania and cities.
Consumers of shops, catering.
The organization's own network of stores.
6. Total project value 36,0 mln RUB
7. Project investments
8. Project investment period 12 months
9. Project implementation
period
10. Project payback period 35 months
5. 11. Curre nt status of the
proje ct implementation
Business plan is being prepared
Technology and know-how
12. Possible forms of
participation in the
project
Direct investments.
13. Supporting information Implementation of the pilot project will provide organic products
with the output 2-3 times higher than in similar economic
enterprises with 1,6 – 1,8 times reduction of the production cost.
Production of solid wood furniture with the output of 200 000 chairs
and 50 000 tables per year
1. Project summary and
targets
The project envisages increased production output of CJSC
“Rokos”, expansion of the proposed product line, diversification
of the activities of CJSC “Rokos” with the aim of effective use of
the existing forest resources in the territory of RNO-Alania.
The project includes:
reconstruction and repair of the industrial premises;
purchase and installation of the necessary technicalequipment;
professional staff trainings;
creation of the in-house resource base
2. Project initiator Closed Joint-Stock Company “ROKOS”
8a Moskovskaya st.,Vladikavkaz, Republic of North Ossetia –
Alania, Russian Federation
tel.: +7 (8672) 40-25-11
Director General – Ms. Fatima Kermenovna Gobeeva
3. Project implementation
area
1, Zaschitnikov Ossetii st., Yuzhny, Vladikavkaz, Republic of
North Ossetia – Alania, Russian Federation
4. Targeted production chairs, armchairs, stools, benches (30 models);
6. dining tables (20 models);
case furniture (over 200 sizes).
5. Potential consumers Sale mainly on the territory of the North Caucasus,Southern and
Central Federal Districts and other regions of Russia
6. Total project value 413,1 mln RUB
7. Project investments 378,1 mln RUB
8. Project investment period
9. Project implementation
period
2014 - 2024
10. Project payback period 7,7 years
11. Curre nt status of the
proje ct implementation
Ongoing implementation
12. Possible forms of
participation in the
project
Expansion of the sales area
A year-round health resort «Cora-Ursdon»
1. Project summary and
targets
1. Establishment of a year-round climatic and balneo-therapeutic
resort of federalsignificance on the basis of
Korinskiy mineral water deposit and Ursdon area of therapeutic
tereklit clays.
2. Health-resort treatment of a wide range of diseases.
3. Equipment of the health resort with modern diagnostic and
medical devices.
4. Improvement of the demographic situation and creation of
additional jobs in Digorskiy district of RNO -Alania.
5. Maintenance and improvement of the unique ecosystem of
Korinskiy health areas using modern environmental technologies.
7. 2. Project initiator
3. Project implementation
area
Kora-Ursdon vil., Digorskiy district, Republic of North Ossetia –
Alania
4. Targeted services The project envisages year-round (seasonally adjusted)
accomodation and health services in extra-comfort conditions.
The accommodation includes daily dietary meals and also
recreational and disease prevention activities.
Disease profiles:
Locomotor diseases;
Nervous disorders;
Gynecological diseases;
Skin diseases;
Gastrointestinal diseases.
In summer the complex will be able to provide visitors with a
wide range of additional services,such as rafting, horse riding and
biking, tourism in the neighbouring areas,one-day bus trips
5. Potential consumers Russian regions, neighbouring and far-abroad countries
6. Total project value 1500,0 mln RUB
7. Project investments
8. Project investment period
9. Project implementation
period
10. Project payback period
8. 11. Curre nt status of the
proje ct implementation
Techno-economic justification is available.
12. Possible forms of
participation in the
project
Project lending, direct investments
Organization of basalt-based products manufacturing
1. Project summary and
targets
The project envisages acquisition and installation of equipment for
establishment of basalt-based products manufacturing on the basis
of FSUE "Alagirsky resistance plant ". Iit is planned to produce raw
materials (basalt) on the territory of the Republic of North Ossetia-
Alania. The output products will meet the needs of the North
Caucasus Federal District in water pipes and heat insulating
materials of high quality and other products.
2. Project initiator Ministry of tourism, business and investment strategy of North
Ossetia – Alania, Government of North Ossetia – Alania
15 Kosta pr., Vladikavkaz, Republic of North Ossetia – Alania,
362015
tel./fax: 8(8672) 40-25-87
3. Project implementation
area
202, Tolstogo st., Alagir, Alagirskiy district, Republic of North
Ossetia – Alania, 363240
4. Targeted production Basalt-plastic pipe, thread, mesh, reinforcing elements, heat
insulation in construction and railcars
5. Potential consumers Construction companies and population of the Republic of North
Ossetia – Alania, regions of North Caucasus Federal Region.
6. Total project value 1111,0 mln RUB
7. Project investment period 10 months
8. Project implementation
period
9. 9. Project payback period 56 months
10. Curre nt status of the
proje ct implementation
The business and financial model are available
11. Possible forms of
participation in the
project
Direct investments, creation of the joint venture company with
investor
Modernization ofthe system №2 Glass forming and treatment shop -3 including reconstruction of
the glass-melting tank and installation of three glass-forming machines 6 IS DG 5 ½
1. Project summary and
targets
The project envisages production of exclusive glass containers as
well as wide-mouth containers of high quality. Currently exclusive
glass containers are imported from other regions including the
central part of Russia, that incurs additional transport expenses for
buyers.
2. Project initiator Joint-Stock Company «Iristonsteklo»
1 Karabulakskaya st., Vladikavkaz, Republic of North Ossetia –
Alania
tel./fax: 8(8672) 53-46-54,
E-mail: pro@iristonsteklo.ru,
Director General – Mr. Oleg Borisovich Gapbaev
3. Project implementation
area
JSC «Irisonsteklo» territory, 1, Karabulakskaya st., Vladikavkaz,
Republic of North Ossetia – Alania
4. Targeted production Upscale glassware, light and wide-neck bottle.
5. Potential consumers Companies that produce wine and vodka, sweet and mineral water
drinks, canning production.
6. Total project value 777,8 mln RUB (upon rate of 71,7 RUB per 1 EUR)
7. Project investments
8. Project investment period 10 years.
10. 9. Project implementation
period
2016-2017
10. Project payback period
11. Curre nt status of the
proje ct implementation
Business plan available.
12. Possible forms of
participation in the
project
Direct investments, project lending
Full technological re-equipment and production expansion
1. Project summary and
targets
The project envisages full technological re-equipment and
production expansion including mine machinery; crushing and
screening equipment; construction, mastering and commissioning
of facilities for grinding of sledged dolomite. The overall
production efficiency upon reaching the rated capacity level will
come to 882 thous. tons per year.
2. Project initiator Joint-Stock Company «Kavdolomite»
25a Borodinskaya st., Vladikavkaz, Republic of North Ossetia –
Alania, 362040
tel.: 8(8672) 53-74-35, 54-49-57,
E-mail: kavkaz@dolomit.ru,
Director General – Mr. Ruslan Akhsarbekovich Aguzarov
3. Project implementation
area
Opencut of the JSC “Kavdolomite”, Balta vil., Republic of North
Ossetia – Alania
Industrial site of the JSC “Kavdolomite”, 36, Pozharskogo st.,
Vladikavkaz, Republic of North Ossetia – Alania
4. Targeted production lump dolomite and dolomite powder for the glass industry;
dolomite powder for the agricultural sector;
mineral powder for asphalt-concrete and organo-mineral
composites;
11. filler for dry construction composites.
5. Potential consumers Russian Federation and neighbouring countries
6. Total project value 700,0 mln RUB
7. Project investments 80,0 mln RUB
8. Project investment period 43 months
9. Project implementation
period
10. Project payback period
11. Curre nt status of the
proje ct implementation
Design estimate documentation and permits are available
12. Possible forms of
participation in the
project
Project lending
Resort center, year-round sport, recreation and entertainment park "Lysaya Gora"
1. Project summary and
targets
Construction and placement of the year-round complex with
four ski trails, sport grounds, a ski school for children,
restaurant, etc.
2. Project initiator Joint-Stock Company «Vladkurort»
49 P.Morozova st., Vladikavkaz, Republic of North Ossetia –
Alania, 362013
tel.:+7 (967)1371208,
E-mail: vladkurort@gmail.com,
Director General – Mr. Kazbek Dzidzoev Valeryevich
12. 3. Project implementation
area
North slope of the Lysaya mountain, Vladikavkaz, RNO –
Alania
4. Targeted production Services including trainings in alpine skiing, snowboarding and
other winter and summer sports, trainings in ski sports,
accommodation of tourists and catering.
5. Potential consumers RNO-Alania, regions of NCFR
6. Total project value 2900,0 mln RUB
7. Project investments 16,0 mln RUB
8. Project investment period 60 months
9. Project implementation
period
10. Project payback period 84 months
11. Curre nt status of the
proje ct implementation
Ongoing state expertise of the project proposal, finalization of
the business plan, filing of application to OJSC «Sberbank».
12. Possible forms of
participation in the
project
Project lending, direct investments
Construction of a fully automatized cattle breeding farm for 1,200 diary livestock units and milk
processing plant with a unit for production of cheese "Comté"
1. Project summary and
targets
The project involves construction of a livestock breeding
complex with the capacity of 3 000 livestock units, 1200 of which
belong to the dairy cattle of unique French breed "Monbelyard";
construction of a new milk processing plant, the production range
of which includes more than 80 positions as well as production of
cheese "Comté"; construction of a cottage community for high
value staff; creation of a hotel-restaurant complex and
development of agro-tourism, due to which people will get
familiar with Ossetian culture and traditions.
13. 2. Project initiator LLC «Agro-industrial holding «Master-Prime.Berezka»
63a Lenina str., Ardon 363330
Republic of North Ossetia-Alania
tel.: 8(86732) 3-35-64, 3-39-84, E-mail: master-
praim@mail.ru,
Director general – Ms. Larisa Khasanovna Bekuzarova
3. Project implementation
area
63a Lenina str., Ardon, Ardonskiy district, Republic of North
Ossetia-Alania
Khataldon village, Alagirsky district
4. Targeted production Production of the diary complex: whole milk, live weight
cattle (cows and young stock), breeding heifers.
Production of the milk processing plant: pasteurized milk,
sterilized milk, yogurt, sour cream, organic products, yogurt
drink, fermented baked milk, cottage cheese, butter, cheese
"Comté", other types of cheese and cheese products.
Production of the slaughterhouse: beef and by-products.
Crop production: grain, silage, hay, haylage.
5. Potential consumers Republic of North Ossetia-Alania, North Caucasus Federal
Disctrict, Southern Federal District.
6. Total project value 3680,0 mln RUB
7. Project investments Republic of North Ossetia-Alania, North Caucasus Federal
Disctrict, Southern Federal District.
8.
Project investment period
120 months
14. 9. Project implementation
period
112 months
10. Project payback period
11. Curre nt status of the
proje ct imple me ntation
The first stage of the project is completed. Work on attraction
of credit resources for realization of the second stage is carried
out.
12. Possible forms of
participation in the project
Project lending
Increased production of tomato paste through acquisition of additional equipment, agricultural
machinery and funding of costs for the current assets
1. Project summary and
targets
The project envisages extended activity scope of LLC “Agrofirma
“Kazbek” in tomato growing and tomato paste production. The
project will significantly increase tomato paste production (up to 5
700 tons per year) and sales volumes (180 million rubles per year).
For the purpose of the project implementation it is planned to buy
agricultural machinery and equipment for tomato growing, acquire
and equip an additional line for tomato paste production and also
finance the costs of the initial current assets.
2. Project initiator Limited Liability Company «Agrofirm Kazbek» (Farm firm)
Zmeyskaya st., Kirovskiy district, Republic of North Ossetia –
Alania
tel.: +79188224720,
E-mail: kj-company@inbox.ru,
Director General – Mr. Kazbek Nikolaevich Dzhibilov
3. Project implementation
area
Zmeyskaya st., Kirovskiy district, Republic of North Ossetia –
Alania
4. Targeted production Tomato paste
5. Potential consumers Republic of North Ossetia-Alania, Moscow region, Krasnodar
region, Stavropol region, Republic of Dagestan, Samara,
V.Novgorod, N.Novgorod
15. 6. Total project value 359,3 mln RUB
7. Project investments 30,0 mln RUB
8.
Project investment period
7 years
9. Project payback period 3,9 years.
10. Curre nt status of the
proje ct implementation
Storage buildings, service communications and boiler-house are
built.
11. Possible forms of
participation in the
project
Project lending
Establishment of the integrated fish farming complex for breeding of valuable fish species
1. Project summary and
targets
Establishment of the largest farming complex for fish breeding
stock (60% share in Russia) and commercial fish of valuable
species (25% share in Russia). Supply of high quality fish products
to the population of the Russian Federation. Creating of new jobs
and improvement of living standards of the population of North
Ossetia-Alania and other regions.
2. Project initiator Limited Liability Company "Alania Fish"
180 Zangieva str., Ardon 36330
Republic of North Ossetia-Alania,
tel. +7 (928) 856-08-16,
E-mail: apkravets@gmail.com,
Director General – Mr. Anatoly P. Kravets
3. Project implementation
area
Republic of North Ossetia-Alania, Tver region, Orel region,
Novgorod region, Republic of Karelia, Leningrad Oblast
16. 4. Targeted production Breeding trout - fry weighing 5-30 g.; portion trout weighing 170-
400 g.; table trout weighing 1000-2500 g.; breeding sturgeon
weighing 80 g.; market sturgeon weighing1600 g; trout caviar.
5. Potential consumers fish farming enterprises in the North-West Federal District, North
Caucasus Federal District, Volga Federal District;
federal and regional retail networks of the Russian Federation;
wholesale companies and food retail chains of the neighbouring
countries
6. Total project value 2 000,0 mln RUB
7. Project investments 50,0 mln RUB
8.
Project investment period
24 months
9. Project implementation
period
2015-2017
10. Project payback period 62 months
11. Curre nt status of the
proje ct implementation
Industrial production ongoing
Valid water use agreements
Business plan update
Financial model update
12. Possible forms of
participation in the
project
Project lending, direct investments
17. Creation of a modern high-tech complex for extraction and deep processing of oil
1. Project summary and
targets
The project aims to create a highly effective vertically-integrated
structure covering the full operational cycle from geological
exploration and oil extraction to its deep processing and sale of the
end product
2. Project initiator Limited Liability Company «Alania Oil»
93 Kosta pr., Vladikavkaz, Republic of North Ossetia – Alania,
362008
tel.: (8672) 55-08-18, 25-44-82,
E-mail: alaniaoil@alaniaoil.ru,
Director General – Mr. Vladimir Maratovich Gutiev
3. Project implementation
area
Vladikavkaz, Digorskiy and Ardonskiy districts, Republic of North
Ossetia – Alania
4. Targeted production Fuel and lubricant products. The overall production capacity of
"Alania-Oil" will reach 199 thous. tons of oil products per year
5. Potential consumers Republic of North Ossetia – Alania
6. Total project value 1161,0 mln RUB
7. Project investments 337,0 mln RUB
8. Project investment period 60 months
9. Project implementation
period
3 years from the bank loan approval
10. Project payback period
11. Curre nt status of the
proje ct implementation
The business plan and licenses for the use of subsurface resources
are available
18. 12. Possible forms of
participation in the
project
Upon negotiations with potential partners
13. Supporting information In order to expand the project capacity two state licenses for the
use of subsurface resources in adjacent areas were received in
2013, that increased the mineral resource base of the project by
5,2 mln tons of oil. The estimated revenue after reaching the full
capacity - 1 736, 6 mln rubles.
Production of opto-electronic elements with and without image rotation
1. Project summary and
targets
LLC Vladikavkaz Technological Center "Baspik" implements the
project of import substitution of fiber-optic elements (FOE) used
in night vision devices. In the framework of this project LLC
“VTC Baspik” at its own expense held R&D activities and is
currently finalizing the experimental realization of the project
«Development of the basic structure and production technology of
the standard series of unified high-resolution fiber-optic
components to be used in modern highly informative electro-
optical converters of the third and subsequent generations»
together with the Russian Ministry of Industry and Trade
2. Project initiator LLC «Vladikavkaz technology center BASPIK»
44 Nikolayeva st.,Vladikavkaz, Republic of North Ossetia –
Alania,
tel.: 8(8672)749366,
First Deputy of the Director General – Mr. Kubadi Soslanovich
Kulov
3. Project implementation
area
8 Moskovskaya st., Vladikavkaz, Republic of North Ossetia –
Alania
4. Targeted production Fiber optic components with and without image rotation.
The project capacity – 40 000 items per year.
5. Potential consumers JSC “KATOD”, JSC “NPO Geofizika-NV”, Closed JSC “Ekran-
OS”, Closed JSC “Ekran-FEP”
19. 6. Total project value 387,0 – mln RUB
7. Project investments 125,0 mln RUB
8. Project investment period
9. Project implementation
period
2015-2016
10. Project payback period 5,2 years
11. Curre nt status of the
proje ct implementation
Business plan and financial model available
12. Possible forms of
participation in the
project
Project lending
Production of potable glacial water
1. Project summary and
targets
The target of the project is creation of an industrial enterprise for
production of potable glacial water "Bilag." Glacial meltwater
"Bilag" flows from ecologically clean glaciers located at high
altitude in Alania wildlife reserve on the territory of the North
Caucasus. The water is produced by means of natural withdrawal
without mechanical devices and gravitational drilling at the altitude
of 1800 meters, thus preserving original properties and taste of the
water.
The project is unique because of pouring at the altitude of 1800
meters.
The project capacity - 184 mln liters of waterper year(PET,glass).
2. Project initiator Limited Liability Company «Bilag»
Vladikavkaz, Republic of North Ossetia – Alania
tel.: (8672) 53-74-03, +7(919) 427-33-33, +7(928) 487-77-67,
Director General – Mr. Kazbek Mukharbekovich Mamiev
20. 3. Project implementation
area
Irafskiy district, Republic of North Ossetia – Alania
4. Targeted production Potable glacial spring water
5. Potential consumers Russian regions
6. Total project value 1 125 mln rubles, 400 mln rubles of which have already been spent
for construction of the industrial building, warehouses and
infrastructure. Investments for purchase and installation of
equipment will amount to 725 mln rubles.
7. Project investments 400,0 mln RUB
8.
Project investment period
2014-2018
9. Project implementation
period
10. Project payback period
11. Curre nt status of the
proje ct implementation
Currently the spring is being prepared for the smooth waterflow to
the factory. Production and storage premises are ready for use.
Energy and transport communications are connected; roads were
widened and cleaned to manage safe transportation. For the further
implementation equipment should be bought and installed.
12. Possible forms of
participation in the
project
Direct investments, project lending