SlideShare a Scribd company logo
1 of 69
Retake Test (/tools/test_intro.php?tid=6408)
Final Score: 38 / 120 Points
Attempts: 1 out of unlimited 6.01 Practice Exam
1
Your score does not meet the minimum score required for passin
g this assessment,
which is 70. You should review the questions you answered inc
orrectly below and
retake this assessment until you pass. Once you pass the assess
ment, you will be
shown the correct answer for each question, and you will be pro
vided with
feedback for each question, if it is available.
Results by category
The following table lists the topic areas tested by this assessme
nt. When applicable,
questions are tagged to multiple categories.
Analysis and Design 2 of 8 Correct
Communications 1 of 4 Correct
Estimation 1 of 7 Correct
Interpersonal Skills 2 of 5 Correct
Knowledge and Skills 19 of 56 Correct
Level 1 14 of 37 Correct
Level 2 3 of 13 Correct
Level 3 2 of 6 Correct
Metrics 2 of 5 Correct
https://strayer.mindedgeonline.com/tools/test_intro.php?tid=640
8
Planning, Monitoring, and Adapting 3 of 8 Correct
Process Improvement 2 of 7 Correct
Product Quality 1 of 5 Correct
Risk Management 3 of 7 Correct
Tools and Techniques 19 of 64 Correct
Value-based Prioritization 2 of 8 Correct
Question 1
Value stream analysis can be best described as a ________.
a) product quality process
b) project estimating process
c) risk management process
d) continuous improvement process
Question 2
A member of an Agile team has activated an alarm to tell her co
lleagues that a
problem has been detected. The team then gathers at the site of t
he problem to
quickly correct them problem and allow work to continue. This
problem-resolution
activity is known as ________.
a) a pre-mortem
b) fishbone diagram analysis
c) kaizen
d) variance analysis
Question 3
Question 3
Ideal time can be defined as ________.
a) a prediction of work duration that does not compensate for i
nterruptions
that may occur
b) a prediction of work duration that takes into account interru
ptions that may
occur
c) the amount of time that the team agrees it should take to co
mplete an
average story point given the team's velocity
d) the budgeted amount of time that the team adjusts to reflect
updates made
to the story board
Question 4
Diamond Software is conducting an Agile project and wants to u
se a metric to
determine how many unfinished tasks it has at the end of its iter
ations. Which metric
would be best to track?
a) cycle time
b) work in progress
c) defect rate
d) velocity
Question 5
When does an Agile project leader not need to hold a final proje
ct retrospective to
close out the project?
a) when there has been a retrospective following each iteration
b) when team members have urgent priorities and all project is
sues have
been previously addressed
c) if senior management prefers to have documented feedback
instead
d) None of the above are reasons to skip the project retrospecti
ve.
Question 6
How does the Agile Declaration of Interdependence suggest that
practitioners can
boost performance?
a) through the acquisition of skills by individual team member
s
b) through an increased return on investment
c) through the accountability and shared responsibility of the e
ntire group
d) through the mentoring of inexperienced team members by th
ose with more
experience
Question 7
Developing estimates based on effort hours can be very subjecti
ve–an experienced
team member may be able to complete work much faster than an
inexperienced
worker performing the same task. How can an Agile team establ
ish a common
measure to estimate work?
a) The team could develop its own story point scale to measure
the relative
size of user stories.
b) The team could use a story point scale based on industry sta
ndards to
estimate the relative difficulty of the user stories.
c) The team could apply the story point scale from another tea
m to its work.
d) The team could assign only experienced workers to tasks.
Question 8
Customer-valued prioritization places greater emphasis on custo
mer value and less
emphasis on __________.
a) cost, compliance, or market conditions
b) expenses and product users
c) cost and end users
d) marketing, promotion, and end users
Question 9
Marvin has just sent an email to a teammate, to ask for clarificat
ion on a project
issue. This is a form of ________.
a) asynchronous one-way communication
b) coincident one-way communication
c) asynchronous two-way communication
d) coincident two-way communication
Question 10
Which of the following statements is true?
a) Because Agile teams implement working products in much s
horter
increments, they can apply verification and validation technique
s on a
less-frequent basis.
b) Verification is a quality-testing process that relies on extern
al stakeholders
to test products.
c) Validation enlists end users and customers to test the produ
ct to see that it
works as they envision it to.
d) Validation is a quality-testing process that relies on the proj
ect team to test
products.
Question 11
Brenna is reviewing her team's burn charts and cumulative flow
diagrams to uncover
any differences in what they expected to achieve and what they
actually achieved.
What is Brenna doing?
a) creating a timebox
b) performing variance analysis
c) playing Planning Poker
d) completing a MoSCoW analysis
Question 12
Why is it that an Agile team leader can monitor project work wi
th a "light touch"
rather than with a "heavy hand"?
a) because the members of an Agile team understand their role
s and how
iterations will progress
b) because the role of an Agile team leader is not to direct tea
m members
c) because short iterations don't allow an Agile team leader en
ough time to
monitor a project
d) because project work should not be micro-monitored since t
he processes
used differ from one iteration to the next
Question 13
Which of the following is one of the six Agile management prin
ciples?
a) Unleash creativity and innovation by recognizing that team
members are
the ultimate source of value, creating an environment where the
y can
make a difference.
b) Improve effectiveness and reliability through documented st
rategies,
processes, and practices.
c) Increase return on investment by making continuous flow of
value the
focus.
d) Deliver reliable results by engaging customers only when ne
cessary.
Question 14
Which of the following statements regarding interpersonal skills
is true?
a) Doing Agile requires understanding Agile practices; being
Agile involves
implementing Agile practices.
b) In adaptive leadership, the leader acts as a facilitator to the
team, rather
than as a manager or director of the team.
c) Empathy is the ability to work together to reach a common
goal.
d) On highly collaborative Agile teams, the aim of negotiation
should be
ensure that team members voice their opinion but concede to the
party
with the most valid argument.
Question 15
Scrum is one of the most popular and widely used Agile method
ologies. How does
the Scrum approach differ from many other forms of Agile?
a) Scrum projects contain guidelines to help reduce confusion
and distraction
that could derail progress.
b) Scrum projects employ cycles of frequent testing and feedba
ck.
c) Scrum projects establish customer requirement up front and
then monitor
and control the project until completion.
d) Scrum projects do not use sprints in the product developme
nt cycle, in
favor of less rigorous framework.
Question 16
In which type of brainstorming do all members participate seque
ntially until everyone
has exhausted their ideas?
a) popcorn
b) freewheeling
c) card deck
d) round robin
Question 17
A user story that was selected but not completed by the end of a
n iteration is
________.
a) a defect rate
b) a spike
c) an escaped defect
d) a corrective action
Question 18
What may happen if an Agile team is distributed, rather than bei
ng co-located?
a) The team must accept that product cost and time-to-market
will be greater.
b) Success will require more effort and focus on better commu
nication and
information distribution techniques.
c) Agile will not be the best approach for accomplishing the pr
oject.
d) The product owner must develop additional management pro
cesses.
Question 19
An Agile team wants to estimate the amount of effort and compl
exity of its user
stories but doesn't want a complicated process that assigns nume
rical values to the
stories. What tool should they use?
a) Planning Poker
b) the Five Whys
c) t-shirt sizing
d) internal rate of return
Question 20
Kyra and her team are following the Agile development cycle an
d have just created
a product vision and product backlog. What is their next step?
a) execute the work
b) create timeboxes
c) perform a daily standup
d) plan an iteration
Question 21
How does the process of progressive elaboration work in an Agi
le project?
a) Progressive elaboration provides detailed plans of story boa
rds that lead to
specific insight as to how iterations should be planned.
b) Progressive elaboration organizes a project at a high-level a
nd lets the
details of the project evolve over time.
c) Progressive elaboration communicates ideas, verifies design
assumptions,
and validates project concepts, which minimizes uncertainty by
allowing
users to "see" what the product will do.
d) Progressive elaboration adds requirements to the product ba
cklog as the
project nears the release date to prepare for subsequent releases.
Question 22
Agile uses incremental and iterative development cycles to creat
e new products or
to modify existing products. Which of the following is a benefit
of this approach?
a) It creates complete, innovative, and reliable products that ca
n be released
to the market sooner.
b) It ensures that the product meets the team's needs.
c) It limits new ideas from stakeholders to ensure product cons
istency.
d) It helps establish project requirements up front.
Question 23
Which of the following statements is false?
a) Scrum teams should include no fewer than five members an
d no more
than nine members.
b) Daily scrums provide status updates to team members.
c) The Scrum process begins with a product vision and detaile
d customers
requirements.
d) Sprint planning meetings are open forums in which any inte
rested party
can participate.
Question 24
Which of the following would be least helpful in recognizing pr
oject trends and
variation?
a) story maps
b) earned value management
c) burn charts
d) cumulative flow diagrams
Question 25
Requirements in a product backlog may be incorrect or misleadi
ng due to several
common causes. Which of the following is not a common cause
of an inaccurate
product backlog?
a) The product owner may be overworked.
b) The organization may have too many ways of collecting req
uirements.
c) The requirements may be incorrectly prioritized.
d) The requirement descriptions may be too vague or too descr
iptive.
Question 26
Piotr wants to use rolling wave planning on an upcoming Scrum
project but his
superior has suggested that he use progressive elaboration. Wha
t should Piotr do?
a) Insist that rolling wave planning would be a better fit for a
Scrum project.
b) Agree to use progressive elaboration but secretly use rolling
wave
planning instead.
c) Agree with his superior as rolling wave planning is a form o
f progressive
elaboration.
d) Ask his superior to consider rolling wave planning but abid
e by whatever
decision his superior insists on.
Question 27
An iteration can be of whatever length a team designs it to be b
ut is generally
________.
a) one month in length
b) one to four weeks in length
c) four to eight weeks in length
d) five to ten days in length
Question 28
Agile methods primarily approach accomplishing work through
________.
a) processes
b) people
c) plans
d) technology
Question 29
When an Agile team continually combines completed work into
the customer
solution, it is practicing _________.
a) test-driven development
b) continuous integration
c) frequent verification
d) six sigma
Question 30
Large displays of critical team information that are continuousl
y updated and located
where teams can see them constantly are called _________.
a) information sinks
b) information radiators
c) information boards
d) common rooms
Question 31
The document issued by the project initiator or sponsor that for
mally authorizes the
existence of a project and provides the project manager with the
authority to apply
project resources to project activities is the _________.
a) product roadmap
b) sponsorship document
c) project charter
d) product budget
Question 32
Why do teams hold daily stand-up meetings?
a) to specifically solve team member problems
b) to encourage each team member to provide an accurate in-d
epth progress
report
c) to limit the need for visual displays or story boards
d) to make sure communication is among the team, not to the p
roduct owner
Question 33
_________ is a facilitation technique that Agile leaders may use
to improve
interaction among practitioners.
a) Emotional intelligence
b) The planning game
c) Refactoring
d) Brainwriting
Question 34
The bottom of a value stream map looks like this:
How much of the work in the process is value-added?
a) 22 days
b) 28 days
c) 6 days
d) 50 days
Question 35
If Lee wants to be a good active listener, which of the following
should he avoid
doing?
a) taking notes to ensure he has heard correctly
b) listening without thinking about a response
c) maintaining eye contact
d) asking clarifying questions
Question 36
What is an architectural spike?
a) a dramatic increase or decrease on a burndown chart
b) a graphic representation of the product backlog that shows
interdependencies of risks
c) a section of the project charter that lists potential problems
that could occur
d) an experiment that looks for potential risks or issues in the
structural,
foundational, or technical aspects of a project
Question 37
In addition to strong technical skills, Agile team members must
possess robust
interpersonal skills such as the ability to resolve conflicts. Whic
h of the following
statements about conflict resolution is false?
a) A collaborative environment and good negotiating skills can
eliminate the
potential for conflict between stakeholders.
b) Conflicts will inevitably arise whenever individuals work as
closely together
as Agile practitioners do.
c) Agile teams must create an environment where conflicts can
be identified
and resolved quickly.
d) Conflict resolution is an interpersonal skill.
Question 38
What is value-based prioritization?
a) the ordering of the stories in a product backlog based on the
value that
they bring to the project
b) the ordering of iterations that ensures project phases are exe
cuted in order
of importance
c) the arrangement of Agile project requirements to satisfy the
product owner
d) a method for developing useful user stories
Question 39
As her team is clarifying its definition of "done" in an initial me
eting, Penelope
realizes that the definition seems incomplete because it doesn't
specify whether
"done" means that the product is ready to ship–
the definition ends by stating that the
product is "ready to move on to the next phase of its cycle." Pen
elope realizes that
this ambiguity could be used as an excuse at a later date if the t
eam fails to meet an
organizational deadline. When asked if she had anything to add
to the definition,
Penelope replies by saying that the definition "did a good job cl
arifying the terms it
used." By hiding behind this half-truth, Penelope is failing to ab
ide by elements of
which of the following documents?
a) PMI 's Code of Ethics and Professional Conduct
b) the project charter
c) The Agile Manifesto
d) the project release plan
Question 40
Actions undertaken to ensure that all relevant specifications, reg
ulations, policies, or
laws are followed and satisfied are referred to as _________.
a) customer-valued prioritization
b) financial regulation
c) compliance
®
d) legal prioritization
Question 41
For Agile teams to build trust, team members should do which o
f the following?
a) Team members should select tasks from the tasks list that w
ill be most
easy and enjoyable for them to complete.
b) Team members should try to resolve conflicts themselves be
fore engaging
an Agile team leader.
c) Team members with experience handling difficult tasks sho
uld assume
responsibility for all of these tasks to help the team complete ite
rations on
time.
d) Team members that are effective at handling long or difficu
lt tasks should
be assigned to handle these types of issues.
Question 42
Which of the following statements regarding risk management is
false?
a) Teams may choose to use a technique called fail late in whi
ch they get
highly risky stories out of the way first so that any problems tha
t might
happen will occur late in the process when the team has time to
fix them.
b) To prioritize user stories based on risk, a team may develop
a risk score for
each iteration.
c) Calculating risk scores is a highly subjective process that sh
ould yield
results that provide "close-enough" approximations for prioritiz
ation.
d) Managing risk is a core project management process.
Question 43
Mark is a member of a newly formed Agile team and is having t
rouble understanding
and implementing Agile principles. He is also not clear about hi
s role on the team.
Who would be the best person to help Mark?
a) an Agile coach
b) the product sponsor
c) the team leader
d) his department manager
Question 44
On an Agile project, what does "done" mean?
a) The team can begin work on the next product increment.
b) The increment is ready for implementation.
c) The product is ready for customer use.
d) whatever team members and stakeholders collectively decid
e
Question 45
According to the Agile Manifesto, Agile does not value ______
__.
a) working products over comprehensive documentation
b) individuals and interactions over processes and tools
c) customer collaboration over contract negotiation
d) following a plan over responding to change
Question 46
Which of the following statements is false?
a) Agile metrics should be simple, easy to collect, and easy to
analyze.
b) Every metric should have a target to show what success loo
ks like.
c) A team should establish a target before they begin collectin
g any data.
d) Metrics should lead to obvious conclusions and drive appro
priate behavior.
Question 47
Question 47
John is a senior manager who occasionally drops in on Agile tea
m meetings. During
meetings, he suggests ways to improve the product. Recently he
has gained support
for a number of his additions. What risk does the Agile team run
if it informally
adopts too many of John's changes?
a) The scope creep could have a negative effect on other proje
ct parameters.
b) John will override the role of the product owner, disrupting
authority and
communication.
c) The customer will not like the final product when it is relea
sed.
d) Daily stand-ups will not be effective forums of communicati
on.
Question 48
A visual mock-up of a product that developers use to verify desi
gn concepts and test
functionality with users is called a __________.
a) story map
b) wireframe
c) model
d) persona
Question 49
Following completion of an iteration, an Agile team holds an inf
ormal meeting with
stakeholders to demonstrate the products completed during the i
teration. This
meeting is referred to as ___________.
a) a daily standup
b) an iteration retrospective
c) an iteration review
d) a wrap-up
Question 50
Question 50
Ingrid has begun planning an upcoming project. She is collectin
g customer
requirements and developing a document that the team has to fol
low to sequentially
complete the project. She has several monitoring processes plan
ned to help her
control the processes and correct any missteps or deviations that
occur. What Agile
methodology is she employing?
a) Ingrid is using Scrum.
b) Ingrid is using Lean Software Development.
c) Ingrid is using a combination of XP and Scrum.
d) Ingrid is not employing an Agile methodology.
Question 51
An effective Agile environment ________.
a) thoroughly outlines plans and processes, allowing team me
mbers to focus
on tasks
b) uses frequent stakeholder feedback to achieve cost and time
savings
c) supports innovation through individual team member work
d) fosters continuous innovation and adaptation
Question 52
What are story points?
a) an estimate of the effort required to satisfy customer require
ments
b) time-delineated development cycles
c) a list of prioritized customer requirements that the team and
product owner
choose from to determine which customer needs will be met in a
n iteration
d) the amount of work that a team can complete in a given amo
unt of time
(usually one iteration)
Question 53
Question 53
When planning an iteration, an Agile team must consider its vel
ocity to ensure the
team does not exhaust itself. The calculation of a team's velocit
y includes which of
the following?
a) only completed work
b) completed and partially completed work
c) complete, partially completed, and incomplete work
d) all remaining story points
Question 54
Which of the following is not a goal of the daily stand-up meeti
ng?
a) give team members a forum to discuss problems in depth
b) recommit team members to the project as a team
c) communicate the project status and discuss any obstacles
d) set the day's direction
Question 55
The line chart that tracks the amount of work remaining in an it
eration or release
where the line intersects the x-axis at the probable completion d
ate is known as a
___________.
a) burndown chart
b) burn-up chart
c) story board
d) Kanban board
Question 56
An Agile coach ________.
a) solves problems for the team
b) sets the project direction
c) describes and delineates roles on Agile projects
d) prevents scope creep on projects
Question 57
When presented with the following information regarding items
in the product
backlog, which one is most valuable and therefore most importa
nt to include in the
next iteration?
a) a user story with an internal rate of return IRR of 10%
b) a user story with an internal rate of return IRR of 0%
c) a user story with an internal rate of return IRR of 20%
d) a user story with an uncertain IRR
Question 58
When a team produces a risk-adjusted backlog it may use a risk
score to
__________.
a) determine the objective risk level associated with user stori
es
b) calculate how long high-risk user stories will take to imple
ment
c) subjectively develop a close-enough approximation for prior
itization
d) decide whether user stories are correct
Question 59
Which of the following statements regarding risk burndown gra
phs is false?
a) A risk burndown graph is used to visually track the amount
of risk left in a
project.
b) A risk burndown graph can be created after risk scores are c
alculated for
each user story.
c) As user stories are implemented the associated risks are eith
er resolved or
avoided.
d) The expected downward trend of the chart illustrates that th
e number of
risks resolved or avoided in an iteration increase as work progre
sses.
Question 60
An Agile team must adapt to situations as they arise. Variations
occur because,
although the iterations repeated throughout a project may be sim
ilar, they are never
exactly the same. Which of the following is a result of the adapt
ive nature of an Agile
team?
a) The Agile team will need to budget more time given the exp
erimental
nature of adapting to changes.
b) An Agile team can minimize planning and monitoring activi
ties.
c) Adapting to variations helps to complete iterations but caus
es problems
when the project to be done will change.
d) Adapting to variation results in a different product and less
customer value.
Question 61
Which of the following statements is true?
a) A Kanban board shows the potential risks that could occur i
n each phase
of a project.
b) A Kanban board is a type of story board that lists the user st
ories in each
phase of a project.
c) The terms Kanban and task board are not interchangeable an
d have
different meanings and uses.
d) Kanban boards show how much work will be involved in the
current phase
of the project but cannot show the work to be completed over th
e project
lifecycle.
Question 62
________ involves discussions to explore options and reach an
agreement.
a) Collaboration
b) Negotiation
c) Conflict resolution
d) Servant leadership
Question 63
For some projects, budgeting is easy; the budget is predefined a
nd the _________
will include as many features as can be created within the budge
ted total amount.
a) iteration
b) project
c) story board
d) release
Question 64
Which of the following statements concerning risk-based spikes
is false?
a) Risk-based spikes should be used sparingly because they do
not deliver
customer value.
b) A spike is an experiment used to acquire information and un
derstand
complex issues.
c) Risk-based spikes should capture just enough information to
resolve any
uncertainty.
d) A risk-based spike allows a team to analyze the benefits ass
ociated with a
user story.
Question 65
Eli is an Agile team leader who needs to conduct quality testing
. Because it is
inconvenient to access external stakeholders for quality testing,
he is looking to have
the project team authenticate requirements. To accomplish this,
Eli should use
_________.
a) incremental development
b) validation
c) verification
d) continuous integration
Question 66
Jules has convened a meeting at the beginning of an iteration to
ask his teammates
to envision a "perfect project", and then describe why the projec
t exceeded all
expectations. They would have to explain what could happen on
the project, how it
could affect the project, and what the team could do to enhance
the chances that
this perfect outcome will occur. What is this meeting better kno
wn as?
a) a wireframe
b) osmotic communication
c) a pre-mortem
d) exploratory testing
Question 67
Which of the following takes into account the relative value of
benefits and costs
over time?
a) internal rate of return
b) net present value
c) return on investment
d) relative benefit value
Question 68
Agile practices can be described with which of the following sta
tements?
a) the ability to balance flexibility and stability
b) the ability to predictably operate and profit in a stable busin
ess
environment
c) the practice of determining and executing team requirement
s
d) the ability to predict and act on user stories quickly and effe
ctively
Question 69
What is a story map?
a) a rough sketch with text descriptions that explain how the p
roduct will
function
b) a list of prioritized customer requirements
c) a graphic representation that shows how individual user stor
ies are
combined to create a solution
d) a two-to-five year vision that describes what you would like
the product to
do and when you would like it to be done
Question 70
The image below is most often used as part of ________.
a) earned value management
b) Kano analysis
c) fishbone diagram analysis
d) value stream mapping
Question 71
Graphic visual displays that present work status and team progr
ess in quick, easy-
to-understand formats are called _______.
a) information sinks
b) story boards
c) progress boards
d) product roadmaps
Question 72
Agile teams should always consider any important information a
nd lessons learned
from previous iterations as they plan upcoming work. What is th
e incorporation of
such information into iteration or release plans called?
a) requirements review
b) the learning cycle
c) compliance
d) an intraspective
Question 73
Which of the following statements regarding affinity estimating
is false?
a) It relies on the knowledge and experience of team members
to rank-order
the user stories in a project.
b) Once the team lays out the user stories of the product backl
og, team
members collectively discuss how best to re-order the stories so
that there
is consensus as to where each story belongs.
c) If there is disagreement during the ordering process, the tea
m discusses
the discrepancy to gain a common understanding, and then retur
ns to the
silent ordering process.
d) At the end of the affinity estimating process the team can q
uickly estimate
the number of story points in each iteration.
Question 74
When an Agile team creates a two-to-five-year plan that describ
es what they would
like a product to do and when it should be done, the team is crea
ting a _________.
a) retrospective
b) product roadmap
c) project charter
d) user story
Question 75
What is the difference between real time and ideal time?
a) Real time is used in Agile projects, while ideal time is used
in Waterfall
projects.
b) Ideal time accounts for interruptions; real time does not acc
ount for
interruptions.
c) Ideal time does not account for interruptions; real time acco
unts for
interruptions.
d) Ideal time is an estimate of how long a team thinks a task w
ill take; real
time measures the amount of time that a task actually took.
Question 76
Wideband Delphi can be defined as _________.
a) an estimation technique in which teams use pre-labeled card
s to express
work estimates
b) estimates of the effort required to satisfy customer requirem
ents that are
scaled in relation to other requirements
c) an estimation technique in which team members jointly disc
uss user
stories, then individually estimate the amount of work needed to
complete
the stories
d) an estimating technique that asks team members to silently
order user
stories before estimating the amount of work they could complet
e in an
iteration
Question 77
Before handing a project over to a production or operations dep
artment or to an
external customer, effective Agile teams hold one last ________
_ to officially close
the project.
a) retrospective
b) review
c) stand-up
d) iteration
Question 78
The technique that Agilists use to track work completed against
the cost to complete
that work at a specific point in time is called ________.
a) net present value
b) a cost-benefit ratio
c) an accounting benefit rate
d) earned value management
Question 79
Which of the following methodologies has five stages of develo
pment that include
modeling, feature lists, planning, design, and software construct
ion?
a) Extreme Programming
b) Feature-list Development
c) Crystal
d) Feature-driven Development
Question 80
What is Agile modeling?
a) a visual mock-up that developers use to verify design conce
pts and test
functionality with users
b) fictional characters that represent the users of a product
c) the act of using models on projects to illustrate relationship
s among project
elements
d) the process of making assumptions about how a role or mod
el will interact
with a product
Question 81
Agile development can be defined as which of the following?
a) traditional, sequential project management
b) a form of project management and product development bas
ed on a
process of incremental and iterative improvements
c) an approach characterized by handling projects concurrently
using product
teams
d) a form of project management that establishes customer req
uirements up
front and then monitors and controls the project plan until comp
lete
Question 82
Which of the following statements is true?
a) Agile project teams should be staffed first with specialists t
o ensure that the
team has all the necessary skills to complete the project.
b) Team members should refer to iteration planning when deve
loping
solutions as finding new ways of meeting goals inevitably decre
ases
velocity.
c) Teams should clarify project boundaries but allow the defini
tion of "done" to
change and allow multitasking to increase team cohesion and ve
locity.
d) Organizations should encourage team members to explore o
ptions and
make it clear that this exploration occurs without repercussions.
Question 83
Which of the following principles is one of the six key manage
ment principles in the
Agile Declaration of Interdependence?
a) increase productivity
b) deliver predictable results
c) control creativity and innovation
d) improve effectiveness and reliability
Question 84
During _________ an XP team determines what subsequent prod
uct releases will
entail by balancing business/customer priorities (from the produ
ct owner) and
technical estimates to complete the project tasks (from the devel
opment team).
a) the planning game
b) continuous integration
c) pair planning
d) the kick-off
Question 85
An Agile team has a limited amount of time and needs to impos
e time constraints to
force important prioritization decisions and pressure to complet
e activities. This
preset period of time is referred to as __________.
a) an iteration
b) a burndown chart
c) a release
d) a timebox
Question 86
Which of the following statements is false?
a) Value stream maps show the amount of work completed and
the duration
of work in each project phase.
b) Burn charts show project trends over time but they don't pro
vide a sense
for how work is progressing within a life cycle.
c) Cumulative flow diagrams are area charts that show the pro
gress of each
part of a project life cycle.
d) Story maps show the interdependencies of user stories in a p
roject.
Question 87
Which of the following statements regarding relative prioritizati
on is true?
a) Relative prioritization ranks the product backlog into specif
ic detailed
categories.
b) Relative prioritization helps to rank the product backlog int
o simple high-
level categories, which may be further refined as necessary.
c) Relative prioritization is a method of determining which use
r stories can be
disregarded.
d) Relative prioritization is a method of prioritization that inco
rporates both
customer-valued prioritization and financial prioritization techn
iques.
Question 88
A risk burndown graph demonstrates __________.
a) the amount of time remaining before an iteration will be co
mpleted
b) the amount of risk remaining in the product backlog
c) how much risk can be completed in one iteration
d) what will happen if the team fails to complete the project
Question 89
Which of the following best describes user stories?
a) iteration results
b) customer requirements
c) fictional representations of the users of a product
d) estimates of perceived value
Question 90
How does a risk-based spike help Agilists to identify, assess, an
d track risk?
a) Each spike looks at a segment of the burn chart to determine
progress.
b) Risk-based spikes investigate benefits associated with user
stories.
c) A risk-based spike uses timeboxed experiments to investigat
e risks
associated with user stories to further discussions and make deci
sions.
d) A risk-based spike allows the team to discuss how well they
worked
together to create the product and what improvements they coul
d make.
Question 91
Which of the following would be least helpful to teams impleme
nting value-based
prioritization?
a) MMFs
b) NPV
c) VOC
d) WIP
Question 92
Which of the following statements is true?
a) Affinity estimating allows teams to combine user stories int
o groups of
similar size.
b) Affinity estimating often uses a Fibonacci sequence to estim
ate stories.
c) Affinity estimating allows team members to estimate stories
they have an
affinity for.
d) Affinity estimating is a specific form of Wideband Delphi.
Question 93
When do customers and stakeholders provide product feedback t
o the team?
a) during iteration retrospectives
b) during iteration reviews
c) during daily stand-ups
d) during iteration planning meetings
Question 94
Which of the following is not an advantage to using a value stre
am map?
a) It shows how much work is in each step of a process at any
one point in
time.
b) It shows all of the steps in a process as an integrated series.
c) It helps expose non-value-added work and inefficiencies.
d) It helps teams evaluate each task for customer value.
Question 95
Keith is watching a user interact with an unfinished product to s
ee if the product
increment will do things that it is not supposed to do. This activ
ity is better known as
________.
a) progressive elaboration
b) exploratory testing
c) external rate of return
d) compliance
Question 96
What is the Scrum-specific term for the meeting that coordinate
s activities across
teams in an organization?
a) an iteration review
b) a daily scrum
c) a scrum retrospective
d) a scrum of scrums
Question 97
Which of the following statements is false?
a) Personas describe generic roles for the prototypical users of
a product.
b) The goal is to identify one persona to represent the perfect
user of a
product under development.
c) After creating and verifying personas, the team can then ma
ke decisions
based on the persona rather than convening with individual user
s to
validate work.
d) Persona descriptions allow the team to make certain decisio
ns and
assumptions about how a user will interact with a product.
Question 98
Business cases ________.
a) must be completed in detail before a project charter can be i
nitiated
b) could be progressively elaborated as the Agile project conti
nues
c) are not relevant to Agile projects because these projects ada
pt as needed
d) should specify how many iterations a project can include
Question 99
Why would a team create a minimal viable product?
a) to help a development team understand which parts of a pro
duct are
working and which parts need to be modified
b) to provide a standard for use in relative prioritization
c) to enhance negotiation among team members
d) to demonstrate work-in-progress results to ensure continued
funding of a
project
Question 100
The larger product development process that includes multiple i
terations and results
in the transition of a finished product into production, operation
s, or the customer is
a __________.
a) release cycle
b) product roadmap
c) iteration retrospective
d) burndown chart
Question 101
In their daily stand-up meeting, team members explain what the
y accomplished
yesterday, what they are working on today, and what obstacles a
re impeding
progress. How long should this meeting take?
a) thirty minutes
b) fifteen minutes
c) ten minutes
d) as much time as possible
Question 102
Which of the following would not be included in an Agile proje
ct charter?
a) a detailed description of deliverables
b) customer and stakeholder names
c) team member names
d) iteration lengths
Question 103
Cindy is an Agile team leader who works to eliminate as many b
arriers to success
for her team as possible. She tries to facilitate and empower the
team so it becomes
a high-performing unit. Which of the following interpersonal sk
ills is Cindy
practicing?
a) adaptive leadership
b) servant leadership
c) collaboration
d) emotional intelligence
Question 104
Why is conflict resolution important for an Agile team?
a) Conflict resolution discourages conflicts from arising durin
g collaboration.
b) Conflict resolution ensures that conflict is dealt with during
iteration reviews
and retrospectives.
c) Conflict resolution enables team members to understand the
ir feelings and
the feelings of others.
d) Conflict resolution skills allow conflicts to be identified an
d resolved quickly.
Question 105
Which of the following is a form of prototyping?
a) a burn chart
b) an information radiator
c) a wireframe
d) a risk-based spike
Question 106
An organization evaluated a value stream map and made adjust
ments to its
processes to improve its development and delivery to customers.
As a result, its
value stream would now include ________ non-value-added wor
k.
a) no
b) some
c) a lot of
d) only
Question 107
Which XP core practice involves compiling completed tasks int
o a completed
product multiple times each day?
a) continuous testing
b) continuous integration
c) small releases
d) design refactoring
Question 108
The Agile product owner and team meet at the beginning of an i
teration to determine
which stories from the product backlog they will complete in th
e iteration. This
process is referred to as _________.
a) backlog grooming
b) iteration planning
c) timeboxing
d) making a story board
Question 109
Juan is inspecting the product backlog for the Agile project he i
s working on. He
needs to select one more item to include in the next iteration. W
hich of the follow
should he pick?
a) the item with a NPV of $5000
b) the item with a NPV of $2000
c) the item with a NPV of - $1000
d) the item with a NPV of zero
Question 110
An assumption that nothing is built perfectly the first time and t
hat a team's focus
should be on delivering 80% of a product that can be deployed i
n 20% of the time
are fundamental assertions of which of the following?
a) DSDM
b) FDD
c) AUP
d) XP
Question 111
One way that the product owner supports the project is by shapi
ng the product
vision. To achieve the vision the product owner creates and mai
ntains a prioritized
list of customer requirements called a __________.
a) product backlog
b) control sheet
c) scrum
d) burndown chart
Question 112
Beth is a member of an Agile team who wants to improve a port
ion of a product
without changing its behavior or functionality. What product qu
ality technique should
she use?
a) refactoring
b) verification
c) continuous integration
d) validation
Question 113
A user story that provides $1500 in benefit will costs $1000 to i
mplement; therefore,
the return on investment (ROI) would be ________.
a) 10%
b) 30%
c) $500
d) 50%
Question 114
At the end of an iteration, an Agile team has completed five use
r stories, partially
completed two user stories, and did not begin one user story. W
hat was the team's
velocity?
a) five user stories per iteration
b) six user stories per iteration
c) eight user stories per iteration
d) seven user stories per iteration
Question 115
Once the project boundaries are set, who ultimately decides how
the product will be
built?
a) the team, stakeholders, and senior management
b) the team
c) the project manager
d) the product owner
Question 116
The process that Julia and her team are following to produce sof
tware includes
designing the software, writing the code, initially testing the co
de, correcting any
problems, testing the code again, and shipping to the customer.
Which of the steps
could be considered non-value-added work?
a) designing the code
b) initially testing the code
c) correcting problems
d) shipping to the customer
Question 117
When an Agile team works with customers or stakeholders to de
velop a contract for
a project, the customer may set each of the following parameter
s except ________.
a) the project scope
b) the priorities for completing the work
c) the number of iterations used to complete the work
d) the project budget
Question 118
When leading an Agile team, an effective product owner should
do all of the
following except _________.
a) set project boundaries but allow the boundaries to fluctuate
b) maintain a constant flow of communication
c) provide accountability and team guidance
d) provide instructions and assign tasks
Question 119
Which of the following statements is true?
a) Agile projects are designed to be informal so additional com
munication
tools and techniques should be developed to drive activities.
b) Agile tooling is helpful for reporting project progress to sta
keholders and
keeping the team integrated.
c) Information radiators should not include accomplishments fr
om the
previous day or week.
d) Team members not co-located cannot benefit from osmotic
communication.
Question 120
Which of the following statements is true?
a) Agile teams do not move through the analysis and design ph
ases quickly
because they can only commit to as much work as they can com
plete in
an iteration.
b) An Agile team spends a lot of time trying to analyze every p
ossible
scenario that could arise to prevent surprises as the project is
progressively elaborated.
c) Each user story in an Agile product backlog is written with
as much detail
as possible so the team can move directly into executing project
work.
d) The start of each iteration is the best time to analyze and de
sign project
solutions because that is when the project team revalidates requi
rements.
Results by category
The following table lists the topic areas tested by this assessme
nt. When applicable,
questions are tagged to multiple categories.
Analysis and Design 2 of 8 Correct
Communications 1 of 4 Correct
Estimation 1 of 7 Correct
Interpersonal Skills 2 of 5 Correct
Knowledge and Skills 19 of 56 Correct
Level 1 14 of 37 Correct
Level 2 3 of 13 Correct
Level 3 2 of 6 Correct
Metrics 2 of 5 Correct
Planning, Monitoring, and Adapting 3 of 8 Correct
Process Improvement 2 of 7 Correct
Product Quality 1 of 5 Correct
Risk Management 3 of 7 Correct
38 / 120 Points
Tools and Techniques 19 of 64 Correct
Value-based Prioritization 2 of 8 Correct
Final Score:
Back
Copyright © 2014, 2017 MindEdge Inc. All rights reserved. Dup
lication prohibited.
Project Management Institute, PMI, the Registered Education Pr
ovider logo, Project Management Professional, PMP, Project Ma
nagement Body of
Knowledge, PMBOK, PMI Agile Certified Practitioner, PMI-AC
P, PMI Risk Management Professional, PMI-RMP, the PMI Tale
nt Triangle, and the
PMI Talent Triangle logo are marks of the Project Management
Institute, Inc.
Information in this course has been taken from A Guide to the P
roject Management Body of Knowledge, (PMBOK Guide) —
Fifth Edition, Project
Management Institute Inc., 2013.
®
HS Long Study_[student] (5).sav
Retake Test Results and Next Steps

More Related Content

Similar to Retake Test Results and Next Steps

Project Management - A ________________ is a document that formally recogni...
Project Management - A   ________________ is a document that formally recogni...Project Management - A   ________________ is a document that formally recogni...
Project Management - A ________________ is a document that formally recogni...Suma Kamadod
 
Project Management - The theory of constraints (toc) is successfully applied ...
Project Management - The theory of constraints (toc) is successfully applied ...Project Management - The theory of constraints (toc) is successfully applied ...
Project Management - The theory of constraints (toc) is successfully applied ...Suma Kamadod
 
Project Management - Complication to the critical path represents the formati...
Project Management - Complication to the critical path represents the formati...Project Management - Complication to the critical path represents the formati...
Project Management - Complication to the critical path represents the formati...Suma Kamadod
 
Project Management - _____________ generates ideas for quality improvements...
Project Management -   _____________ generates ideas for quality improvements...Project Management -   _____________ generates ideas for quality improvements...
Project Management - _____________ generates ideas for quality improvements...Suma Kamadod
 
Project Management - Initiating involves developing a project charter and pre...
Project Management - Initiating involves developing a project charter and pre...Project Management - Initiating involves developing a project charter and pre...
Project Management - Initiating involves developing a project charter and pre...Suma Kamadod
 
Project Management - Project management software helps you develop a ______...
Project Management - Project management software helps you develop a   ______...Project Management - Project management software helps you develop a   ______...
Project Management - Project management software helps you develop a ______...Suma Kamadod
 
Project Management - ________________ is a term used to describe various pr...
Project Management -   ________________ is a term used to describe various pr...Project Management -   ________________ is a term used to describe various pr...
Project Management - ________________ is a term used to describe various pr...Suma Kamadod
 
Project Management - Project portfolio management addresses _______________...
Project Management - Project portfolio management addresses   _______________...Project Management - Project portfolio management addresses   _______________...
Project Management - Project portfolio management addresses _______________...Suma Kamadod
 
Project Management - Which communication skill is most important for informat...
Project Management - Which communication skill is most important for informat...Project Management - Which communication skill is most important for informat...
Project Management - Which communication skill is most important for informat...Suma Kamadod
 
Project Management - Above figure shows two activities a & b; b cannot st...
Project Management - Above figure shows two activities a & b; b cannot st...Project Management - Above figure shows two activities a & b; b cannot st...
Project Management - Above figure shows two activities a & b; b cannot st...Suma Kamadod
 
Project Management - _____________ refer(s) to all the work involved in cre...
Project Management -   _____________ refer(s) to all the work involved in cre...Project Management -   _____________ refer(s) to all the work involved in cre...
Project Management - _____________ refer(s) to all the work involved in cre...Suma Kamadod
 
Project Management - To determine the cost of particular element in advance o...
Project Management - To determine the cost of particular element in advance o...Project Management - To determine the cost of particular element in advance o...
Project Management - To determine the cost of particular element in advance o...Suma Kamadod
 
Project Management - Scope __________________ is often achieved by a custom...
Project Management - Scope   __________________ is often achieved by a custom...Project Management - Scope   __________________ is often achieved by a custom...
Project Management - Scope __________________ is often achieved by a custom...Suma Kamadod
 
Project Management - In the above figure calculate the eet (earliest event ti...
Project Management - In the above figure calculate the eet (earliest event ti...Project Management - In the above figure calculate the eet (earliest event ti...
Project Management - In the above figure calculate the eet (earliest event ti...Suma Kamadod
 
Project Management - Which risk management process involves prioritizing base...
Project Management - Which risk management process involves prioritizing base...Project Management - Which risk management process involves prioritizing base...
Project Management - Which risk management process involves prioritizing base...Suma Kamadod
 
Project Management - We’re standing on this hill here. we want to be on that ...
Project Management - We’re standing on this hill here. we want to be on that ...Project Management - We’re standing on this hill here. we want to be on that ...
Project Management - We’re standing on this hill here. we want to be on that ...Suma Kamadod
 
Project Management - Which of the following is not a potential advantage of u...
Project Management - Which of the following is not a potential advantage of u...Project Management - Which of the following is not a potential advantage of u...
Project Management - Which of the following is not a potential advantage of u...Suma Kamadod
 
Project Management - Icom model, which is one of the major roles of project m...
Project Management - Icom model, which is one of the major roles of project m...Project Management - Icom model, which is one of the major roles of project m...
Project Management - Icom model, which is one of the major roles of project m...Suma Kamadod
 
Project Management - The term ‘hedgehog syndrome’ means a) management problem...
Project Management - The term ‘hedgehog syndrome’ means a) management problem...Project Management - The term ‘hedgehog syndrome’ means a) management problem...
Project Management - The term ‘hedgehog syndrome’ means a) management problem...Suma Kamadod
 
Project Management - …………………. Involves going through the cycle several times...
Project Management - ………………….  Involves going through the cycle several times...Project Management - ………………….  Involves going through the cycle several times...
Project Management - …………………. Involves going through the cycle several times...Suma Kamadod
 

Similar to Retake Test Results and Next Steps (20)

Project Management - A ________________ is a document that formally recogni...
Project Management - A   ________________ is a document that formally recogni...Project Management - A   ________________ is a document that formally recogni...
Project Management - A ________________ is a document that formally recogni...
 
Project Management - The theory of constraints (toc) is successfully applied ...
Project Management - The theory of constraints (toc) is successfully applied ...Project Management - The theory of constraints (toc) is successfully applied ...
Project Management - The theory of constraints (toc) is successfully applied ...
 
Project Management - Complication to the critical path represents the formati...
Project Management - Complication to the critical path represents the formati...Project Management - Complication to the critical path represents the formati...
Project Management - Complication to the critical path represents the formati...
 
Project Management - _____________ generates ideas for quality improvements...
Project Management -   _____________ generates ideas for quality improvements...Project Management -   _____________ generates ideas for quality improvements...
Project Management - _____________ generates ideas for quality improvements...
 
Project Management - Initiating involves developing a project charter and pre...
Project Management - Initiating involves developing a project charter and pre...Project Management - Initiating involves developing a project charter and pre...
Project Management - Initiating involves developing a project charter and pre...
 
Project Management - Project management software helps you develop a ______...
Project Management - Project management software helps you develop a   ______...Project Management - Project management software helps you develop a   ______...
Project Management - Project management software helps you develop a ______...
 
Project Management - ________________ is a term used to describe various pr...
Project Management -   ________________ is a term used to describe various pr...Project Management -   ________________ is a term used to describe various pr...
Project Management - ________________ is a term used to describe various pr...
 
Project Management - Project portfolio management addresses _______________...
Project Management - Project portfolio management addresses   _______________...Project Management - Project portfolio management addresses   _______________...
Project Management - Project portfolio management addresses _______________...
 
Project Management - Which communication skill is most important for informat...
Project Management - Which communication skill is most important for informat...Project Management - Which communication skill is most important for informat...
Project Management - Which communication skill is most important for informat...
 
Project Management - Above figure shows two activities a & b; b cannot st...
Project Management - Above figure shows two activities a & b; b cannot st...Project Management - Above figure shows two activities a & b; b cannot st...
Project Management - Above figure shows two activities a & b; b cannot st...
 
Project Management - _____________ refer(s) to all the work involved in cre...
Project Management -   _____________ refer(s) to all the work involved in cre...Project Management -   _____________ refer(s) to all the work involved in cre...
Project Management - _____________ refer(s) to all the work involved in cre...
 
Project Management - To determine the cost of particular element in advance o...
Project Management - To determine the cost of particular element in advance o...Project Management - To determine the cost of particular element in advance o...
Project Management - To determine the cost of particular element in advance o...
 
Project Management - Scope __________________ is often achieved by a custom...
Project Management - Scope   __________________ is often achieved by a custom...Project Management - Scope   __________________ is often achieved by a custom...
Project Management - Scope __________________ is often achieved by a custom...
 
Project Management - In the above figure calculate the eet (earliest event ti...
Project Management - In the above figure calculate the eet (earliest event ti...Project Management - In the above figure calculate the eet (earliest event ti...
Project Management - In the above figure calculate the eet (earliest event ti...
 
Project Management - Which risk management process involves prioritizing base...
Project Management - Which risk management process involves prioritizing base...Project Management - Which risk management process involves prioritizing base...
Project Management - Which risk management process involves prioritizing base...
 
Project Management - We’re standing on this hill here. we want to be on that ...
Project Management - We’re standing on this hill here. we want to be on that ...Project Management - We’re standing on this hill here. we want to be on that ...
Project Management - We’re standing on this hill here. we want to be on that ...
 
Project Management - Which of the following is not a potential advantage of u...
Project Management - Which of the following is not a potential advantage of u...Project Management - Which of the following is not a potential advantage of u...
Project Management - Which of the following is not a potential advantage of u...
 
Project Management - Icom model, which is one of the major roles of project m...
Project Management - Icom model, which is one of the major roles of project m...Project Management - Icom model, which is one of the major roles of project m...
Project Management - Icom model, which is one of the major roles of project m...
 
Project Management - The term ‘hedgehog syndrome’ means a) management problem...
Project Management - The term ‘hedgehog syndrome’ means a) management problem...Project Management - The term ‘hedgehog syndrome’ means a) management problem...
Project Management - The term ‘hedgehog syndrome’ means a) management problem...
 
Project Management - …………………. Involves going through the cycle several times...
Project Management - ………………….  Involves going through the cycle several times...Project Management - ………………….  Involves going through the cycle several times...
Project Management - …………………. Involves going through the cycle several times...
 

More from ronak56

According to the textbook, the Federal Disaster Assistance Act of 19.docx
According to the textbook, the Federal Disaster Assistance Act of 19.docxAccording to the textbook, the Federal Disaster Assistance Act of 19.docx
According to the textbook, the Federal Disaster Assistance Act of 19.docxronak56
 
According to the Council on Social Work Education, Competency 5 Eng.docx
According to the Council on Social Work Education, Competency 5 Eng.docxAccording to the Council on Social Work Education, Competency 5 Eng.docx
According to the Council on Social Work Education, Competency 5 Eng.docxronak56
 
According to the text, economic outcomes measured by economic gr.docx
According to the text, economic outcomes measured by economic gr.docxAccording to the text, economic outcomes measured by economic gr.docx
According to the text, economic outcomes measured by economic gr.docxronak56
 
According to the Council on Social Work Education, Competency 5.docx
According to the Council on Social Work Education, Competency 5.docxAccording to the Council on Social Work Education, Competency 5.docx
According to the Council on Social Work Education, Competency 5.docxronak56
 
According to the Council for Exceptional Children (CEC), part of.docx
According to the Council for Exceptional Children (CEC), part of.docxAccording to the Council for Exceptional Children (CEC), part of.docx
According to the Council for Exceptional Children (CEC), part of.docxronak56
 
According to the article, Answer these two questions. Why did Ma.docx
According to the article, Answer these two questions. Why did Ma.docxAccording to the article, Answer these two questions. Why did Ma.docx
According to the article, Answer these two questions. Why did Ma.docxronak56
 
According to Neuman’s theory, a human being is a total person as a c.docx
According to Neuman’s theory, a human being is a total person as a c.docxAccording to Neuman’s theory, a human being is a total person as a c.docx
According to Neuman’s theory, a human being is a total person as a c.docxronak56
 
According to Rolando et al. (2012), alcohol socialization is the pr.docx
According to Rolando et al. (2012), alcohol socialization is the pr.docxAccording to Rolando et al. (2012), alcohol socialization is the pr.docx
According to Rolando et al. (2012), alcohol socialization is the pr.docxronak56
 
According to your readings, cloud computing represents one of th.docx
According to your readings, cloud computing represents one of th.docxAccording to your readings, cloud computing represents one of th.docx
According to your readings, cloud computing represents one of th.docxronak56
 
According to this idea that gender is socially constructed, answer.docx
According to this idea that gender is socially constructed, answer.docxAccording to this idea that gender is socially constructed, answer.docx
According to this idea that gender is socially constructed, answer.docxronak56
 
According to Thiel (2015, p. 40), CSR literature lacks consensus fo.docx
According to Thiel (2015, p. 40), CSR literature lacks consensus fo.docxAccording to Thiel (2015, p. 40), CSR literature lacks consensus fo.docx
According to Thiel (2015, p. 40), CSR literature lacks consensus fo.docxronak56
 
According to recent surveys, China, India, and the Philippines are t.docx
According to recent surveys, China, India, and the Philippines are t.docxAccording to recent surveys, China, India, and the Philippines are t.docx
According to recent surveys, China, India, and the Philippines are t.docxronak56
 
According to Rolando et al. (2012), alcohol socialization is th.docx
According to Rolando et al. (2012), alcohol socialization is th.docxAccording to Rolando et al. (2012), alcohol socialization is th.docx
According to Rolando et al. (2012), alcohol socialization is th.docxronak56
 
According to the author, Social Security is an essential program, .docx
According to the author, Social Security is an essential program, .docxAccording to the author, Social Security is an essential program, .docx
According to the author, Social Security is an essential program, .docxronak56
 
According to Morrish, the blame for the ever-growing problem of disc.docx
According to Morrish, the blame for the ever-growing problem of disc.docxAccording to Morrish, the blame for the ever-growing problem of disc.docx
According to Morrish, the blame for the ever-growing problem of disc.docxronak56
 
According to DuBrin (2015), Cultural intelligence is an outsiders .docx
According to DuBrin (2015), Cultural intelligence is an outsiders .docxAccording to DuBrin (2015), Cultural intelligence is an outsiders .docx
According to DuBrin (2015), Cultural intelligence is an outsiders .docxronak56
 
According to Edgar Schein, organizational culture are the shared.docx
According to Edgar Schein, organizational culture are the shared.docxAccording to Edgar Schein, organizational culture are the shared.docx
According to Edgar Schein, organizational culture are the shared.docxronak56
 
According to DuBrin (2015), the following strategies or tactics are .docx
According to DuBrin (2015), the following strategies or tactics are .docxAccording to DuBrin (2015), the following strategies or tactics are .docx
According to DuBrin (2015), the following strategies or tactics are .docxronak56
 
According to DuBrin (2015), the following strategies or tactics .docx
According to DuBrin (2015), the following strategies or tactics .docxAccording to DuBrin (2015), the following strategies or tactics .docx
According to DuBrin (2015), the following strategies or tactics .docxronak56
 
Access the Mental Measurements Yearbook, located in the Univer.docx
Access the Mental Measurements Yearbook, located in the Univer.docxAccess the Mental Measurements Yearbook, located in the Univer.docx
Access the Mental Measurements Yearbook, located in the Univer.docxronak56
 

More from ronak56 (20)

According to the textbook, the Federal Disaster Assistance Act of 19.docx
According to the textbook, the Federal Disaster Assistance Act of 19.docxAccording to the textbook, the Federal Disaster Assistance Act of 19.docx
According to the textbook, the Federal Disaster Assistance Act of 19.docx
 
According to the Council on Social Work Education, Competency 5 Eng.docx
According to the Council on Social Work Education, Competency 5 Eng.docxAccording to the Council on Social Work Education, Competency 5 Eng.docx
According to the Council on Social Work Education, Competency 5 Eng.docx
 
According to the text, economic outcomes measured by economic gr.docx
According to the text, economic outcomes measured by economic gr.docxAccording to the text, economic outcomes measured by economic gr.docx
According to the text, economic outcomes measured by economic gr.docx
 
According to the Council on Social Work Education, Competency 5.docx
According to the Council on Social Work Education, Competency 5.docxAccording to the Council on Social Work Education, Competency 5.docx
According to the Council on Social Work Education, Competency 5.docx
 
According to the Council for Exceptional Children (CEC), part of.docx
According to the Council for Exceptional Children (CEC), part of.docxAccording to the Council for Exceptional Children (CEC), part of.docx
According to the Council for Exceptional Children (CEC), part of.docx
 
According to the article, Answer these two questions. Why did Ma.docx
According to the article, Answer these two questions. Why did Ma.docxAccording to the article, Answer these two questions. Why did Ma.docx
According to the article, Answer these two questions. Why did Ma.docx
 
According to Neuman’s theory, a human being is a total person as a c.docx
According to Neuman’s theory, a human being is a total person as a c.docxAccording to Neuman’s theory, a human being is a total person as a c.docx
According to Neuman’s theory, a human being is a total person as a c.docx
 
According to Rolando et al. (2012), alcohol socialization is the pr.docx
According to Rolando et al. (2012), alcohol socialization is the pr.docxAccording to Rolando et al. (2012), alcohol socialization is the pr.docx
According to Rolando et al. (2012), alcohol socialization is the pr.docx
 
According to your readings, cloud computing represents one of th.docx
According to your readings, cloud computing represents one of th.docxAccording to your readings, cloud computing represents one of th.docx
According to your readings, cloud computing represents one of th.docx
 
According to this idea that gender is socially constructed, answer.docx
According to this idea that gender is socially constructed, answer.docxAccording to this idea that gender is socially constructed, answer.docx
According to this idea that gender is socially constructed, answer.docx
 
According to Thiel (2015, p. 40), CSR literature lacks consensus fo.docx
According to Thiel (2015, p. 40), CSR literature lacks consensus fo.docxAccording to Thiel (2015, p. 40), CSR literature lacks consensus fo.docx
According to Thiel (2015, p. 40), CSR literature lacks consensus fo.docx
 
According to recent surveys, China, India, and the Philippines are t.docx
According to recent surveys, China, India, and the Philippines are t.docxAccording to recent surveys, China, India, and the Philippines are t.docx
According to recent surveys, China, India, and the Philippines are t.docx
 
According to Rolando et al. (2012), alcohol socialization is th.docx
According to Rolando et al. (2012), alcohol socialization is th.docxAccording to Rolando et al. (2012), alcohol socialization is th.docx
According to Rolando et al. (2012), alcohol socialization is th.docx
 
According to the author, Social Security is an essential program, .docx
According to the author, Social Security is an essential program, .docxAccording to the author, Social Security is an essential program, .docx
According to the author, Social Security is an essential program, .docx
 
According to Morrish, the blame for the ever-growing problem of disc.docx
According to Morrish, the blame for the ever-growing problem of disc.docxAccording to Morrish, the blame for the ever-growing problem of disc.docx
According to Morrish, the blame for the ever-growing problem of disc.docx
 
According to DuBrin (2015), Cultural intelligence is an outsiders .docx
According to DuBrin (2015), Cultural intelligence is an outsiders .docxAccording to DuBrin (2015), Cultural intelligence is an outsiders .docx
According to DuBrin (2015), Cultural intelligence is an outsiders .docx
 
According to Edgar Schein, organizational culture are the shared.docx
According to Edgar Schein, organizational culture are the shared.docxAccording to Edgar Schein, organizational culture are the shared.docx
According to Edgar Schein, organizational culture are the shared.docx
 
According to DuBrin (2015), the following strategies or tactics are .docx
According to DuBrin (2015), the following strategies or tactics are .docxAccording to DuBrin (2015), the following strategies or tactics are .docx
According to DuBrin (2015), the following strategies or tactics are .docx
 
According to DuBrin (2015), the following strategies or tactics .docx
According to DuBrin (2015), the following strategies or tactics .docxAccording to DuBrin (2015), the following strategies or tactics .docx
According to DuBrin (2015), the following strategies or tactics .docx
 
Access the Mental Measurements Yearbook, located in the Univer.docx
Access the Mental Measurements Yearbook, located in the Univer.docxAccess the Mental Measurements Yearbook, located in the Univer.docx
Access the Mental Measurements Yearbook, located in the Univer.docx
 

Recently uploaded

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 

Recently uploaded (20)

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 

Retake Test Results and Next Steps

  • 1. Retake Test (/tools/test_intro.php?tid=6408) Final Score: 38 / 120 Points Attempts: 1 out of unlimited 6.01 Practice Exam 1 Your score does not meet the minimum score required for passin g this assessment, which is 70. You should review the questions you answered inc orrectly below and retake this assessment until you pass. Once you pass the assess ment, you will be shown the correct answer for each question, and you will be pro vided with feedback for each question, if it is available. Results by category The following table lists the topic areas tested by this assessme nt. When applicable, questions are tagged to multiple categories. Analysis and Design 2 of 8 Correct Communications 1 of 4 Correct Estimation 1 of 7 Correct Interpersonal Skills 2 of 5 Correct Knowledge and Skills 19 of 56 Correct
  • 2. Level 1 14 of 37 Correct Level 2 3 of 13 Correct Level 3 2 of 6 Correct Metrics 2 of 5 Correct https://strayer.mindedgeonline.com/tools/test_intro.php?tid=640 8 Planning, Monitoring, and Adapting 3 of 8 Correct Process Improvement 2 of 7 Correct Product Quality 1 of 5 Correct Risk Management 3 of 7 Correct Tools and Techniques 19 of 64 Correct Value-based Prioritization 2 of 8 Correct Question 1 Value stream analysis can be best described as a ________. a) product quality process b) project estimating process c) risk management process d) continuous improvement process
  • 3. Question 2 A member of an Agile team has activated an alarm to tell her co lleagues that a problem has been detected. The team then gathers at the site of t he problem to quickly correct them problem and allow work to continue. This problem-resolution activity is known as ________. a) a pre-mortem b) fishbone diagram analysis c) kaizen d) variance analysis Question 3 Question 3 Ideal time can be defined as ________. a) a prediction of work duration that does not compensate for i nterruptions that may occur b) a prediction of work duration that takes into account interru ptions that may occur
  • 4. c) the amount of time that the team agrees it should take to co mplete an average story point given the team's velocity d) the budgeted amount of time that the team adjusts to reflect updates made to the story board Question 4 Diamond Software is conducting an Agile project and wants to u se a metric to determine how many unfinished tasks it has at the end of its iter ations. Which metric would be best to track? a) cycle time b) work in progress c) defect rate d) velocity Question 5 When does an Agile project leader not need to hold a final proje ct retrospective to close out the project? a) when there has been a retrospective following each iteration
  • 5. b) when team members have urgent priorities and all project is sues have been previously addressed c) if senior management prefers to have documented feedback instead d) None of the above are reasons to skip the project retrospecti ve. Question 6 How does the Agile Declaration of Interdependence suggest that practitioners can boost performance? a) through the acquisition of skills by individual team member s b) through an increased return on investment c) through the accountability and shared responsibility of the e ntire group d) through the mentoring of inexperienced team members by th ose with more experience
  • 6. Question 7 Developing estimates based on effort hours can be very subjecti ve–an experienced team member may be able to complete work much faster than an inexperienced worker performing the same task. How can an Agile team establ ish a common measure to estimate work? a) The team could develop its own story point scale to measure the relative size of user stories. b) The team could use a story point scale based on industry sta ndards to estimate the relative difficulty of the user stories. c) The team could apply the story point scale from another tea m to its work. d) The team could assign only experienced workers to tasks. Question 8 Customer-valued prioritization places greater emphasis on custo mer value and less emphasis on __________. a) cost, compliance, or market conditions b) expenses and product users
  • 7. c) cost and end users d) marketing, promotion, and end users Question 9 Marvin has just sent an email to a teammate, to ask for clarificat ion on a project issue. This is a form of ________. a) asynchronous one-way communication b) coincident one-way communication c) asynchronous two-way communication d) coincident two-way communication Question 10 Which of the following statements is true? a) Because Agile teams implement working products in much s horter increments, they can apply verification and validation technique s on a less-frequent basis. b) Verification is a quality-testing process that relies on extern al stakeholders to test products.
  • 8. c) Validation enlists end users and customers to test the produ ct to see that it works as they envision it to. d) Validation is a quality-testing process that relies on the proj ect team to test products. Question 11 Brenna is reviewing her team's burn charts and cumulative flow diagrams to uncover any differences in what they expected to achieve and what they actually achieved. What is Brenna doing? a) creating a timebox b) performing variance analysis c) playing Planning Poker d) completing a MoSCoW analysis Question 12 Why is it that an Agile team leader can monitor project work wi th a "light touch" rather than with a "heavy hand"? a) because the members of an Agile team understand their role
  • 9. s and how iterations will progress b) because the role of an Agile team leader is not to direct tea m members c) because short iterations don't allow an Agile team leader en ough time to monitor a project d) because project work should not be micro-monitored since t he processes used differ from one iteration to the next Question 13 Which of the following is one of the six Agile management prin ciples? a) Unleash creativity and innovation by recognizing that team members are the ultimate source of value, creating an environment where the y can make a difference. b) Improve effectiveness and reliability through documented st rategies, processes, and practices. c) Increase return on investment by making continuous flow of
  • 10. value the focus. d) Deliver reliable results by engaging customers only when ne cessary. Question 14 Which of the following statements regarding interpersonal skills is true? a) Doing Agile requires understanding Agile practices; being Agile involves implementing Agile practices. b) In adaptive leadership, the leader acts as a facilitator to the team, rather than as a manager or director of the team. c) Empathy is the ability to work together to reach a common goal. d) On highly collaborative Agile teams, the aim of negotiation should be ensure that team members voice their opinion but concede to the party with the most valid argument. Question 15
  • 11. Scrum is one of the most popular and widely used Agile method ologies. How does the Scrum approach differ from many other forms of Agile? a) Scrum projects contain guidelines to help reduce confusion and distraction that could derail progress. b) Scrum projects employ cycles of frequent testing and feedba ck. c) Scrum projects establish customer requirement up front and then monitor and control the project until completion. d) Scrum projects do not use sprints in the product developme nt cycle, in favor of less rigorous framework. Question 16 In which type of brainstorming do all members participate seque ntially until everyone has exhausted their ideas? a) popcorn b) freewheeling c) card deck
  • 12. d) round robin Question 17 A user story that was selected but not completed by the end of a n iteration is ________. a) a defect rate b) a spike c) an escaped defect d) a corrective action Question 18 What may happen if an Agile team is distributed, rather than bei ng co-located? a) The team must accept that product cost and time-to-market will be greater. b) Success will require more effort and focus on better commu nication and information distribution techniques. c) Agile will not be the best approach for accomplishing the pr oject.
  • 13. d) The product owner must develop additional management pro cesses. Question 19 An Agile team wants to estimate the amount of effort and compl exity of its user stories but doesn't want a complicated process that assigns nume rical values to the stories. What tool should they use? a) Planning Poker b) the Five Whys c) t-shirt sizing d) internal rate of return Question 20 Kyra and her team are following the Agile development cycle an d have just created a product vision and product backlog. What is their next step? a) execute the work b) create timeboxes c) perform a daily standup d) plan an iteration
  • 14. Question 21 How does the process of progressive elaboration work in an Agi le project? a) Progressive elaboration provides detailed plans of story boa rds that lead to specific insight as to how iterations should be planned. b) Progressive elaboration organizes a project at a high-level a nd lets the details of the project evolve over time. c) Progressive elaboration communicates ideas, verifies design assumptions, and validates project concepts, which minimizes uncertainty by allowing users to "see" what the product will do. d) Progressive elaboration adds requirements to the product ba cklog as the project nears the release date to prepare for subsequent releases. Question 22 Agile uses incremental and iterative development cycles to creat e new products or to modify existing products. Which of the following is a benefit of this approach? a) It creates complete, innovative, and reliable products that ca
  • 15. n be released to the market sooner. b) It ensures that the product meets the team's needs. c) It limits new ideas from stakeholders to ensure product cons istency. d) It helps establish project requirements up front. Question 23 Which of the following statements is false? a) Scrum teams should include no fewer than five members an d no more than nine members. b) Daily scrums provide status updates to team members. c) The Scrum process begins with a product vision and detaile d customers requirements. d) Sprint planning meetings are open forums in which any inte rested party can participate. Question 24
  • 16. Which of the following would be least helpful in recognizing pr oject trends and variation? a) story maps b) earned value management c) burn charts d) cumulative flow diagrams Question 25 Requirements in a product backlog may be incorrect or misleadi ng due to several common causes. Which of the following is not a common cause of an inaccurate product backlog? a) The product owner may be overworked. b) The organization may have too many ways of collecting req uirements. c) The requirements may be incorrectly prioritized. d) The requirement descriptions may be too vague or too descr iptive. Question 26 Piotr wants to use rolling wave planning on an upcoming Scrum project but his
  • 17. superior has suggested that he use progressive elaboration. Wha t should Piotr do? a) Insist that rolling wave planning would be a better fit for a Scrum project. b) Agree to use progressive elaboration but secretly use rolling wave planning instead. c) Agree with his superior as rolling wave planning is a form o f progressive elaboration. d) Ask his superior to consider rolling wave planning but abid e by whatever decision his superior insists on. Question 27 An iteration can be of whatever length a team designs it to be b ut is generally ________. a) one month in length b) one to four weeks in length c) four to eight weeks in length
  • 18. d) five to ten days in length Question 28 Agile methods primarily approach accomplishing work through ________. a) processes b) people c) plans d) technology Question 29 When an Agile team continually combines completed work into the customer solution, it is practicing _________. a) test-driven development b) continuous integration c) frequent verification d) six sigma Question 30 Large displays of critical team information that are continuousl y updated and located where teams can see them constantly are called _________.
  • 19. a) information sinks b) information radiators c) information boards d) common rooms Question 31 The document issued by the project initiator or sponsor that for mally authorizes the existence of a project and provides the project manager with the authority to apply project resources to project activities is the _________. a) product roadmap b) sponsorship document c) project charter d) product budget Question 32 Why do teams hold daily stand-up meetings? a) to specifically solve team member problems b) to encourage each team member to provide an accurate in-d epth progress report
  • 20. c) to limit the need for visual displays or story boards d) to make sure communication is among the team, not to the p roduct owner Question 33 _________ is a facilitation technique that Agile leaders may use to improve interaction among practitioners. a) Emotional intelligence b) The planning game c) Refactoring d) Brainwriting Question 34 The bottom of a value stream map looks like this: How much of the work in the process is value-added? a) 22 days b) 28 days c) 6 days d) 50 days
  • 21. Question 35 If Lee wants to be a good active listener, which of the following should he avoid doing? a) taking notes to ensure he has heard correctly b) listening without thinking about a response c) maintaining eye contact d) asking clarifying questions Question 36 What is an architectural spike? a) a dramatic increase or decrease on a burndown chart b) a graphic representation of the product backlog that shows interdependencies of risks c) a section of the project charter that lists potential problems that could occur d) an experiment that looks for potential risks or issues in the structural, foundational, or technical aspects of a project Question 37
  • 22. In addition to strong technical skills, Agile team members must possess robust interpersonal skills such as the ability to resolve conflicts. Whic h of the following statements about conflict resolution is false? a) A collaborative environment and good negotiating skills can eliminate the potential for conflict between stakeholders. b) Conflicts will inevitably arise whenever individuals work as closely together as Agile practitioners do. c) Agile teams must create an environment where conflicts can be identified and resolved quickly. d) Conflict resolution is an interpersonal skill. Question 38 What is value-based prioritization? a) the ordering of the stories in a product backlog based on the value that they bring to the project b) the ordering of iterations that ensures project phases are exe
  • 23. cuted in order of importance c) the arrangement of Agile project requirements to satisfy the product owner d) a method for developing useful user stories Question 39 As her team is clarifying its definition of "done" in an initial me eting, Penelope realizes that the definition seems incomplete because it doesn't specify whether "done" means that the product is ready to ship– the definition ends by stating that the product is "ready to move on to the next phase of its cycle." Pen elope realizes that this ambiguity could be used as an excuse at a later date if the t eam fails to meet an organizational deadline. When asked if she had anything to add to the definition, Penelope replies by saying that the definition "did a good job cl arifying the terms it used." By hiding behind this half-truth, Penelope is failing to ab ide by elements of which of the following documents? a) PMI 's Code of Ethics and Professional Conduct b) the project charter c) The Agile Manifesto d) the project release plan
  • 24. Question 40 Actions undertaken to ensure that all relevant specifications, reg ulations, policies, or laws are followed and satisfied are referred to as _________. a) customer-valued prioritization b) financial regulation c) compliance ® d) legal prioritization Question 41 For Agile teams to build trust, team members should do which o f the following? a) Team members should select tasks from the tasks list that w ill be most easy and enjoyable for them to complete. b) Team members should try to resolve conflicts themselves be fore engaging an Agile team leader. c) Team members with experience handling difficult tasks sho
  • 25. uld assume responsibility for all of these tasks to help the team complete ite rations on time. d) Team members that are effective at handling long or difficu lt tasks should be assigned to handle these types of issues. Question 42 Which of the following statements regarding risk management is false? a) Teams may choose to use a technique called fail late in whi ch they get highly risky stories out of the way first so that any problems tha t might happen will occur late in the process when the team has time to fix them. b) To prioritize user stories based on risk, a team may develop a risk score for each iteration. c) Calculating risk scores is a highly subjective process that sh ould yield results that provide "close-enough" approximations for prioritiz ation. d) Managing risk is a core project management process.
  • 26. Question 43 Mark is a member of a newly formed Agile team and is having t rouble understanding and implementing Agile principles. He is also not clear about hi s role on the team. Who would be the best person to help Mark? a) an Agile coach b) the product sponsor c) the team leader d) his department manager Question 44 On an Agile project, what does "done" mean? a) The team can begin work on the next product increment. b) The increment is ready for implementation. c) The product is ready for customer use. d) whatever team members and stakeholders collectively decid e Question 45 According to the Agile Manifesto, Agile does not value ______ __.
  • 27. a) working products over comprehensive documentation b) individuals and interactions over processes and tools c) customer collaboration over contract negotiation d) following a plan over responding to change Question 46 Which of the following statements is false? a) Agile metrics should be simple, easy to collect, and easy to analyze. b) Every metric should have a target to show what success loo ks like. c) A team should establish a target before they begin collectin g any data. d) Metrics should lead to obvious conclusions and drive appro priate behavior. Question 47 Question 47 John is a senior manager who occasionally drops in on Agile tea
  • 28. m meetings. During meetings, he suggests ways to improve the product. Recently he has gained support for a number of his additions. What risk does the Agile team run if it informally adopts too many of John's changes? a) The scope creep could have a negative effect on other proje ct parameters. b) John will override the role of the product owner, disrupting authority and communication. c) The customer will not like the final product when it is relea sed. d) Daily stand-ups will not be effective forums of communicati on. Question 48 A visual mock-up of a product that developers use to verify desi gn concepts and test functionality with users is called a __________. a) story map b) wireframe c) model
  • 29. d) persona Question 49 Following completion of an iteration, an Agile team holds an inf ormal meeting with stakeholders to demonstrate the products completed during the i teration. This meeting is referred to as ___________. a) a daily standup b) an iteration retrospective c) an iteration review d) a wrap-up Question 50 Question 50 Ingrid has begun planning an upcoming project. She is collectin g customer requirements and developing a document that the team has to fol low to sequentially complete the project. She has several monitoring processes plan ned to help her control the processes and correct any missteps or deviations that occur. What Agile methodology is she employing? a) Ingrid is using Scrum.
  • 30. b) Ingrid is using Lean Software Development. c) Ingrid is using a combination of XP and Scrum. d) Ingrid is not employing an Agile methodology. Question 51 An effective Agile environment ________. a) thoroughly outlines plans and processes, allowing team me mbers to focus on tasks b) uses frequent stakeholder feedback to achieve cost and time savings c) supports innovation through individual team member work d) fosters continuous innovation and adaptation Question 52 What are story points? a) an estimate of the effort required to satisfy customer require ments b) time-delineated development cycles c) a list of prioritized customer requirements that the team and product owner
  • 31. choose from to determine which customer needs will be met in a n iteration d) the amount of work that a team can complete in a given amo unt of time (usually one iteration) Question 53 Question 53 When planning an iteration, an Agile team must consider its vel ocity to ensure the team does not exhaust itself. The calculation of a team's velocit y includes which of the following? a) only completed work b) completed and partially completed work c) complete, partially completed, and incomplete work d) all remaining story points Question 54 Which of the following is not a goal of the daily stand-up meeti ng? a) give team members a forum to discuss problems in depth b) recommit team members to the project as a team
  • 32. c) communicate the project status and discuss any obstacles d) set the day's direction Question 55 The line chart that tracks the amount of work remaining in an it eration or release where the line intersects the x-axis at the probable completion d ate is known as a ___________. a) burndown chart b) burn-up chart c) story board d) Kanban board Question 56 An Agile coach ________. a) solves problems for the team b) sets the project direction c) describes and delineates roles on Agile projects d) prevents scope creep on projects Question 57
  • 33. When presented with the following information regarding items in the product backlog, which one is most valuable and therefore most importa nt to include in the next iteration? a) a user story with an internal rate of return IRR of 10% b) a user story with an internal rate of return IRR of 0% c) a user story with an internal rate of return IRR of 20% d) a user story with an uncertain IRR Question 58 When a team produces a risk-adjusted backlog it may use a risk score to __________. a) determine the objective risk level associated with user stori es b) calculate how long high-risk user stories will take to imple ment c) subjectively develop a close-enough approximation for prior itization d) decide whether user stories are correct Question 59
  • 34. Which of the following statements regarding risk burndown gra phs is false? a) A risk burndown graph is used to visually track the amount of risk left in a project. b) A risk burndown graph can be created after risk scores are c alculated for each user story. c) As user stories are implemented the associated risks are eith er resolved or avoided. d) The expected downward trend of the chart illustrates that th e number of risks resolved or avoided in an iteration increase as work progre sses. Question 60 An Agile team must adapt to situations as they arise. Variations occur because, although the iterations repeated throughout a project may be sim ilar, they are never exactly the same. Which of the following is a result of the adapt ive nature of an Agile team?
  • 35. a) The Agile team will need to budget more time given the exp erimental nature of adapting to changes. b) An Agile team can minimize planning and monitoring activi ties. c) Adapting to variations helps to complete iterations but caus es problems when the project to be done will change. d) Adapting to variation results in a different product and less customer value. Question 61 Which of the following statements is true? a) A Kanban board shows the potential risks that could occur i n each phase of a project. b) A Kanban board is a type of story board that lists the user st ories in each phase of a project. c) The terms Kanban and task board are not interchangeable an d have
  • 36. different meanings and uses. d) Kanban boards show how much work will be involved in the current phase of the project but cannot show the work to be completed over th e project lifecycle. Question 62 ________ involves discussions to explore options and reach an agreement. a) Collaboration b) Negotiation c) Conflict resolution d) Servant leadership Question 63 For some projects, budgeting is easy; the budget is predefined a nd the _________ will include as many features as can be created within the budge ted total amount. a) iteration b) project c) story board
  • 37. d) release Question 64 Which of the following statements concerning risk-based spikes is false? a) Risk-based spikes should be used sparingly because they do not deliver customer value. b) A spike is an experiment used to acquire information and un derstand complex issues. c) Risk-based spikes should capture just enough information to resolve any uncertainty. d) A risk-based spike allows a team to analyze the benefits ass ociated with a user story. Question 65 Eli is an Agile team leader who needs to conduct quality testing . Because it is inconvenient to access external stakeholders for quality testing, he is looking to have
  • 38. the project team authenticate requirements. To accomplish this, Eli should use _________. a) incremental development b) validation c) verification d) continuous integration Question 66 Jules has convened a meeting at the beginning of an iteration to ask his teammates to envision a "perfect project", and then describe why the projec t exceeded all expectations. They would have to explain what could happen on the project, how it could affect the project, and what the team could do to enhance the chances that this perfect outcome will occur. What is this meeting better kno wn as? a) a wireframe b) osmotic communication c) a pre-mortem d) exploratory testing Question 67 Which of the following takes into account the relative value of
  • 39. benefits and costs over time? a) internal rate of return b) net present value c) return on investment d) relative benefit value Question 68 Agile practices can be described with which of the following sta tements? a) the ability to balance flexibility and stability b) the ability to predictably operate and profit in a stable busin ess environment c) the practice of determining and executing team requirement s d) the ability to predict and act on user stories quickly and effe ctively Question 69 What is a story map?
  • 40. a) a rough sketch with text descriptions that explain how the p roduct will function b) a list of prioritized customer requirements c) a graphic representation that shows how individual user stor ies are combined to create a solution d) a two-to-five year vision that describes what you would like the product to do and when you would like it to be done Question 70 The image below is most often used as part of ________. a) earned value management b) Kano analysis c) fishbone diagram analysis d) value stream mapping Question 71 Graphic visual displays that present work status and team progr ess in quick, easy-
  • 41. to-understand formats are called _______. a) information sinks b) story boards c) progress boards d) product roadmaps Question 72 Agile teams should always consider any important information a nd lessons learned from previous iterations as they plan upcoming work. What is th e incorporation of such information into iteration or release plans called? a) requirements review b) the learning cycle c) compliance d) an intraspective Question 73 Which of the following statements regarding affinity estimating is false? a) It relies on the knowledge and experience of team members to rank-order
  • 42. the user stories in a project. b) Once the team lays out the user stories of the product backl og, team members collectively discuss how best to re-order the stories so that there is consensus as to where each story belongs. c) If there is disagreement during the ordering process, the tea m discusses the discrepancy to gain a common understanding, and then retur ns to the silent ordering process. d) At the end of the affinity estimating process the team can q uickly estimate the number of story points in each iteration. Question 74 When an Agile team creates a two-to-five-year plan that describ es what they would like a product to do and when it should be done, the team is crea ting a _________. a) retrospective b) product roadmap c) project charter d) user story
  • 43. Question 75 What is the difference between real time and ideal time? a) Real time is used in Agile projects, while ideal time is used in Waterfall projects. b) Ideal time accounts for interruptions; real time does not acc ount for interruptions. c) Ideal time does not account for interruptions; real time acco unts for interruptions. d) Ideal time is an estimate of how long a team thinks a task w ill take; real time measures the amount of time that a task actually took. Question 76 Wideband Delphi can be defined as _________. a) an estimation technique in which teams use pre-labeled card s to express work estimates
  • 44. b) estimates of the effort required to satisfy customer requirem ents that are scaled in relation to other requirements c) an estimation technique in which team members jointly disc uss user stories, then individually estimate the amount of work needed to complete the stories d) an estimating technique that asks team members to silently order user stories before estimating the amount of work they could complet e in an iteration Question 77 Before handing a project over to a production or operations dep artment or to an external customer, effective Agile teams hold one last ________ _ to officially close the project. a) retrospective b) review c) stand-up d) iteration
  • 45. Question 78 The technique that Agilists use to track work completed against the cost to complete that work at a specific point in time is called ________. a) net present value b) a cost-benefit ratio c) an accounting benefit rate d) earned value management Question 79 Which of the following methodologies has five stages of develo pment that include modeling, feature lists, planning, design, and software construct ion? a) Extreme Programming b) Feature-list Development c) Crystal d) Feature-driven Development Question 80 What is Agile modeling? a) a visual mock-up that developers use to verify design conce pts and test
  • 46. functionality with users b) fictional characters that represent the users of a product c) the act of using models on projects to illustrate relationship s among project elements d) the process of making assumptions about how a role or mod el will interact with a product Question 81 Agile development can be defined as which of the following? a) traditional, sequential project management b) a form of project management and product development bas ed on a process of incremental and iterative improvements c) an approach characterized by handling projects concurrently using product teams d) a form of project management that establishes customer req uirements up front and then monitors and controls the project plan until comp
  • 47. lete Question 82 Which of the following statements is true? a) Agile project teams should be staffed first with specialists t o ensure that the team has all the necessary skills to complete the project. b) Team members should refer to iteration planning when deve loping solutions as finding new ways of meeting goals inevitably decre ases velocity. c) Teams should clarify project boundaries but allow the defini tion of "done" to change and allow multitasking to increase team cohesion and ve locity. d) Organizations should encourage team members to explore o ptions and make it clear that this exploration occurs without repercussions. Question 83 Which of the following principles is one of the six key manage ment principles in the Agile Declaration of Interdependence? a) increase productivity
  • 48. b) deliver predictable results c) control creativity and innovation d) improve effectiveness and reliability Question 84 During _________ an XP team determines what subsequent prod uct releases will entail by balancing business/customer priorities (from the produ ct owner) and technical estimates to complete the project tasks (from the devel opment team). a) the planning game b) continuous integration c) pair planning d) the kick-off Question 85 An Agile team has a limited amount of time and needs to impos e time constraints to force important prioritization decisions and pressure to complet e activities. This preset period of time is referred to as __________. a) an iteration
  • 49. b) a burndown chart c) a release d) a timebox Question 86 Which of the following statements is false? a) Value stream maps show the amount of work completed and the duration of work in each project phase. b) Burn charts show project trends over time but they don't pro vide a sense for how work is progressing within a life cycle. c) Cumulative flow diagrams are area charts that show the pro gress of each part of a project life cycle. d) Story maps show the interdependencies of user stories in a p roject. Question 87 Which of the following statements regarding relative prioritizati on is true?
  • 50. a) Relative prioritization ranks the product backlog into specif ic detailed categories. b) Relative prioritization helps to rank the product backlog int o simple high- level categories, which may be further refined as necessary. c) Relative prioritization is a method of determining which use r stories can be disregarded. d) Relative prioritization is a method of prioritization that inco rporates both customer-valued prioritization and financial prioritization techn iques. Question 88 A risk burndown graph demonstrates __________. a) the amount of time remaining before an iteration will be co mpleted b) the amount of risk remaining in the product backlog c) how much risk can be completed in one iteration d) what will happen if the team fails to complete the project Question 89
  • 51. Which of the following best describes user stories? a) iteration results b) customer requirements c) fictional representations of the users of a product d) estimates of perceived value Question 90 How does a risk-based spike help Agilists to identify, assess, an d track risk? a) Each spike looks at a segment of the burn chart to determine progress. b) Risk-based spikes investigate benefits associated with user stories. c) A risk-based spike uses timeboxed experiments to investigat e risks associated with user stories to further discussions and make deci sions. d) A risk-based spike allows the team to discuss how well they worked together to create the product and what improvements they coul
  • 52. d make. Question 91 Which of the following would be least helpful to teams impleme nting value-based prioritization? a) MMFs b) NPV c) VOC d) WIP Question 92 Which of the following statements is true? a) Affinity estimating allows teams to combine user stories int o groups of similar size. b) Affinity estimating often uses a Fibonacci sequence to estim ate stories. c) Affinity estimating allows team members to estimate stories they have an affinity for. d) Affinity estimating is a specific form of Wideband Delphi.
  • 53. Question 93 When do customers and stakeholders provide product feedback t o the team? a) during iteration retrospectives b) during iteration reviews c) during daily stand-ups d) during iteration planning meetings Question 94 Which of the following is not an advantage to using a value stre am map? a) It shows how much work is in each step of a process at any one point in time. b) It shows all of the steps in a process as an integrated series. c) It helps expose non-value-added work and inefficiencies. d) It helps teams evaluate each task for customer value. Question 95 Keith is watching a user interact with an unfinished product to s ee if the product
  • 54. increment will do things that it is not supposed to do. This activ ity is better known as ________. a) progressive elaboration b) exploratory testing c) external rate of return d) compliance Question 96 What is the Scrum-specific term for the meeting that coordinate s activities across teams in an organization? a) an iteration review b) a daily scrum c) a scrum retrospective d) a scrum of scrums Question 97 Which of the following statements is false? a) Personas describe generic roles for the prototypical users of a product.
  • 55. b) The goal is to identify one persona to represent the perfect user of a product under development. c) After creating and verifying personas, the team can then ma ke decisions based on the persona rather than convening with individual user s to validate work. d) Persona descriptions allow the team to make certain decisio ns and assumptions about how a user will interact with a product. Question 98 Business cases ________. a) must be completed in detail before a project charter can be i nitiated b) could be progressively elaborated as the Agile project conti nues c) are not relevant to Agile projects because these projects ada pt as needed d) should specify how many iterations a project can include Question 99
  • 56. Why would a team create a minimal viable product? a) to help a development team understand which parts of a pro duct are working and which parts need to be modified b) to provide a standard for use in relative prioritization c) to enhance negotiation among team members d) to demonstrate work-in-progress results to ensure continued funding of a project Question 100 The larger product development process that includes multiple i terations and results in the transition of a finished product into production, operation s, or the customer is a __________. a) release cycle b) product roadmap c) iteration retrospective d) burndown chart Question 101
  • 57. In their daily stand-up meeting, team members explain what the y accomplished yesterday, what they are working on today, and what obstacles a re impeding progress. How long should this meeting take? a) thirty minutes b) fifteen minutes c) ten minutes d) as much time as possible Question 102 Which of the following would not be included in an Agile proje ct charter? a) a detailed description of deliverables b) customer and stakeholder names c) team member names d) iteration lengths Question 103 Cindy is an Agile team leader who works to eliminate as many b arriers to success for her team as possible. She tries to facilitate and empower the team so it becomes
  • 58. a high-performing unit. Which of the following interpersonal sk ills is Cindy practicing? a) adaptive leadership b) servant leadership c) collaboration d) emotional intelligence Question 104 Why is conflict resolution important for an Agile team? a) Conflict resolution discourages conflicts from arising durin g collaboration. b) Conflict resolution ensures that conflict is dealt with during iteration reviews and retrospectives. c) Conflict resolution enables team members to understand the ir feelings and the feelings of others. d) Conflict resolution skills allow conflicts to be identified an d resolved quickly. Question 105
  • 59. Which of the following is a form of prototyping? a) a burn chart b) an information radiator c) a wireframe d) a risk-based spike Question 106 An organization evaluated a value stream map and made adjust ments to its processes to improve its development and delivery to customers. As a result, its value stream would now include ________ non-value-added wor k. a) no b) some c) a lot of d) only Question 107 Which XP core practice involves compiling completed tasks int o a completed product multiple times each day? a) continuous testing
  • 60. b) continuous integration c) small releases d) design refactoring Question 108 The Agile product owner and team meet at the beginning of an i teration to determine which stories from the product backlog they will complete in th e iteration. This process is referred to as _________. a) backlog grooming b) iteration planning c) timeboxing d) making a story board Question 109 Juan is inspecting the product backlog for the Agile project he i s working on. He needs to select one more item to include in the next iteration. W hich of the follow should he pick? a) the item with a NPV of $5000 b) the item with a NPV of $2000
  • 61. c) the item with a NPV of - $1000 d) the item with a NPV of zero Question 110 An assumption that nothing is built perfectly the first time and t hat a team's focus should be on delivering 80% of a product that can be deployed i n 20% of the time are fundamental assertions of which of the following? a) DSDM b) FDD c) AUP d) XP Question 111 One way that the product owner supports the project is by shapi ng the product vision. To achieve the vision the product owner creates and mai ntains a prioritized list of customer requirements called a __________. a) product backlog b) control sheet c) scrum d) burndown chart
  • 62. Question 112 Beth is a member of an Agile team who wants to improve a port ion of a product without changing its behavior or functionality. What product qu ality technique should she use? a) refactoring b) verification c) continuous integration d) validation Question 113 A user story that provides $1500 in benefit will costs $1000 to i mplement; therefore, the return on investment (ROI) would be ________. a) 10% b) 30% c) $500 d) 50% Question 114 At the end of an iteration, an Agile team has completed five use
  • 63. r stories, partially completed two user stories, and did not begin one user story. W hat was the team's velocity? a) five user stories per iteration b) six user stories per iteration c) eight user stories per iteration d) seven user stories per iteration Question 115 Once the project boundaries are set, who ultimately decides how the product will be built? a) the team, stakeholders, and senior management b) the team c) the project manager d) the product owner Question 116 The process that Julia and her team are following to produce sof tware includes designing the software, writing the code, initially testing the co de, correcting any problems, testing the code again, and shipping to the customer.
  • 64. Which of the steps could be considered non-value-added work? a) designing the code b) initially testing the code c) correcting problems d) shipping to the customer Question 117 When an Agile team works with customers or stakeholders to de velop a contract for a project, the customer may set each of the following parameter s except ________. a) the project scope b) the priorities for completing the work c) the number of iterations used to complete the work d) the project budget Question 118 When leading an Agile team, an effective product owner should do all of the following except _________. a) set project boundaries but allow the boundaries to fluctuate
  • 65. b) maintain a constant flow of communication c) provide accountability and team guidance d) provide instructions and assign tasks Question 119 Which of the following statements is true? a) Agile projects are designed to be informal so additional com munication tools and techniques should be developed to drive activities. b) Agile tooling is helpful for reporting project progress to sta keholders and keeping the team integrated. c) Information radiators should not include accomplishments fr om the previous day or week. d) Team members not co-located cannot benefit from osmotic communication. Question 120 Which of the following statements is true? a) Agile teams do not move through the analysis and design ph ases quickly
  • 66. because they can only commit to as much work as they can com plete in an iteration. b) An Agile team spends a lot of time trying to analyze every p ossible scenario that could arise to prevent surprises as the project is progressively elaborated. c) Each user story in an Agile product backlog is written with as much detail as possible so the team can move directly into executing project work. d) The start of each iteration is the best time to analyze and de sign project solutions because that is when the project team revalidates requi rements. Results by category The following table lists the topic areas tested by this assessme nt. When applicable, questions are tagged to multiple categories. Analysis and Design 2 of 8 Correct Communications 1 of 4 Correct Estimation 1 of 7 Correct
  • 67. Interpersonal Skills 2 of 5 Correct Knowledge and Skills 19 of 56 Correct Level 1 14 of 37 Correct Level 2 3 of 13 Correct Level 3 2 of 6 Correct Metrics 2 of 5 Correct Planning, Monitoring, and Adapting 3 of 8 Correct Process Improvement 2 of 7 Correct Product Quality 1 of 5 Correct Risk Management 3 of 7 Correct 38 / 120 Points Tools and Techniques 19 of 64 Correct Value-based Prioritization 2 of 8 Correct Final Score: Back Copyright © 2014, 2017 MindEdge Inc. All rights reserved. Dup lication prohibited. Project Management Institute, PMI, the Registered Education Pr
  • 68. ovider logo, Project Management Professional, PMP, Project Ma nagement Body of Knowledge, PMBOK, PMI Agile Certified Practitioner, PMI-AC P, PMI Risk Management Professional, PMI-RMP, the PMI Tale nt Triangle, and the PMI Talent Triangle logo are marks of the Project Management Institute, Inc. Information in this course has been taken from A Guide to the P roject Management Body of Knowledge, (PMBOK Guide) — Fifth Edition, Project Management Institute Inc., 2013. ® HS Long Study_[student] (5).sav