SlideShare a Scribd company logo
1 of 1
Download to read offline
“
                                                                                                       USING POST -TENSIONING HAD
                                                                                                       MASSIVE ENVIRONMENTAL
                                                                                                       BENEFITS OVERTRADITIONAL
                                                                                                   REINFORCED CONCRETE AND
                                                                                                   STEEL STRUCTURES,WHICH
                                                                                                   WAS IMPORTANT FOR SUCH A
                                                                                                   LARGE PROJECT.”

                                                                                                   The construction phase went smoothly, even
                                                                                                   though there were areas of complexity
                                                                                                   demanding a close interface between the
                                                                                                   post-tensioning designers and the services
ST DAVID’S CENTRE CAR PARK, CARDIFF, UK                                                            engineer who required multiple penetrations
                                                                                                   through the post-tensioned beams. Clear and
                                                                                                   detailed communication was maintained with

       Greener parking                                                                             the contractor throughout the project, from
                                                                                                   design to completion on site.
                                                                                                   The quick erection of the formwork system,
                                                                                                   in conjunction with the efficient pour
       ichard Gaskill of Structural Systems – the BBR Network

R      member in the UK – explains that significantly more
       additional parking was required to service the St David’s 2
development in Cardiff which led to the construction of a five
                                                                                                   sequence offered by the Structural Systems
                                                                                                   team, enabled the contractor to complete
                                                                                                   the frame in 27 weeks.
                                                                                                   Using post-tensioning had massive
level, multi storey car park, totaling in excess of 50,000 m². This                                environmental benefits over traditional
gives the new centre a total of 3,000 parking spaces and the                                       reinforced concrete and steel structures,
                                                                                                   which was important for such a large
drama of the development is heightened by the particularly
                                                                                                   project.The use of post-tensioning reduced
striking elliptical ramp access to the car park.                                                   slab depths significantly so that, overall, less
As part of the regeneration of Cardiff city      deck slabs and a BBR CONA flat 0605               concrete and substantially less rebar was
centre, the new St David’s 2 scheme              system for the 525 mm x 16 m span beams.          used – which was extremely beneficial to the
represents a £675 million investment, totaling   The car park sits on a transfer slab at level     client in terms of program and budget. G
89,891 m² of retail-led mixed-use                three and is tied to a stair core in the centre
development, with over 100 stores and 300        of the building. By introducing post-tensioning   TEAM & TECHNOLOGY
luxury roof top apartments, built as seven       techniques, the slab depth for the car park       OWNER St David’s Partnership
towers above the shopping centre.                was reduced to typically 150 mm –                 MAIN CONTRACTOR Skanska Construction
The size of the floor plate meant that each      permissibly the thinnest depth for a car park     CONCRETE FRAME CONTRACTOR
level was typically constructed as seven         slab – with some areas at 175 mm and              P.C. Harrington Contractors Limited
pours.The frame contractor elected to utilize    nominally 300 mm thick.The beam tendons           DESIGNER Arup / Structural Systems (UK) Ltd
a slab and beam configuration. Structural        were mainly 36 m long, although in some           TECHNOLOGY BBR CONA flat
Systems supplied the BBR CONA flat 0305          instances 56 m long double end stressed           BBR NETWORK MEMBER
                                                                                                   Structural Systems (UK) Ltd
post-tensioning system for the reinforced        tendons were used.

 42 CONNÆCT

More Related Content

What's hot (6)

Arch.CE Portfolio
Arch.CE PortfolioArch.CE Portfolio
Arch.CE Portfolio
 
Sustainability In Education Facilities Diac Bfe Mena 2011
Sustainability In Education Facilities Diac Bfe Mena 2011Sustainability In Education Facilities Diac Bfe Mena 2011
Sustainability In Education Facilities Diac Bfe Mena 2011
 
MCG Concrete 2005 050725
MCG Concrete 2005 050725MCG Concrete 2005 050725
MCG Concrete 2005 050725
 
Structural analysis
Structural analysisStructural analysis
Structural analysis
 
Hermitage Gardens, Edinburgh
Hermitage Gardens, EdinburghHermitage Gardens, Edinburgh
Hermitage Gardens, Edinburgh
 
Callison Mixed Use And Retail Centers Qualifications
Callison Mixed Use And Retail Centers QualificationsCallison Mixed Use And Retail Centers Qualifications
Callison Mixed Use And Retail Centers Qualifications
 

Similar to Connect magazine st davids 2010

Connect magazine essex courts buildings 2011
Connect magazine essex courts buildings 2011Connect magazine essex courts buildings 2011
Connect magazine essex courts buildings 2011
rgaskill
 
Larsen & toubro constructions
Larsen & toubro constructionsLarsen & toubro constructions
Larsen & toubro constructions
engineeringwatch
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
Raghavendra Raghu
 
Triathlon
Triathlon Triathlon
Triathlon
rgaskill
 

Similar to Connect magazine st davids 2010 (20)

Spectra cs ratts_12.08
Spectra cs ratts_12.08Spectra cs ratts_12.08
Spectra cs ratts_12.08
 
Prefabrication​ structure ppt
Prefabrication​ structure pptPrefabrication​ structure ppt
Prefabrication​ structure ppt
 
Connect magazine essex courts buildings 2011
Connect magazine essex courts buildings 2011Connect magazine essex courts buildings 2011
Connect magazine essex courts buildings 2011
 
"The Design of High Performance Anchored Retaining Walls within the Eurocode ...
"The Design of High Performance Anchored Retaining Walls within the Eurocode ..."The Design of High Performance Anchored Retaining Walls within the Eurocode ...
"The Design of High Performance Anchored Retaining Walls within the Eurocode ...
 
fastrack technologies in bridges ppt
fastrack technologies in bridges pptfastrack technologies in bridges ppt
fastrack technologies in bridges ppt
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
 
412346228-Pragati-Towers-Mumbai.pdf
412346228-Pragati-Towers-Mumbai.pdf412346228-Pragati-Towers-Mumbai.pdf
412346228-Pragati-Towers-Mumbai.pdf
 
JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
 
Larsen & toubro constructions
Larsen & toubro constructionsLarsen & toubro constructions
Larsen & toubro constructions
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...
 
Accelerated Bridge Construction( ABC)
Accelerated Bridge  Construction( ABC)Accelerated Bridge  Construction( ABC)
Accelerated Bridge Construction( ABC)
 
Mmmp Mep Experience Sheet
Mmmp   Mep Experience SheetMmmp   Mep Experience Sheet
Mmmp Mep Experience Sheet
 
Technical textiles in Central Public Works Department
Technical textiles in Central Public Works DepartmentTechnical textiles in Central Public Works Department
Technical textiles in Central Public Works Department
 
Triathlon
Triathlon Triathlon
Triathlon
 
PT ADVANTAGES
PT ADVANTAGESPT ADVANTAGES
PT ADVANTAGES
 
IRJET- Strengthening of New Building
IRJET- Strengthening of New BuildingIRJET- Strengthening of New Building
IRJET- Strengthening of New Building
 
Analysis For Retrofitting Of An Existing Failed RC Column Using FEM Software’s
Analysis For Retrofitting Of An Existing Failed RC Column Using FEM Software’sAnalysis For Retrofitting Of An Existing Failed RC Column Using FEM Software’s
Analysis For Retrofitting Of An Existing Failed RC Column Using FEM Software’s
 
Ijsred v2 i3p86
Ijsred v2 i3p86Ijsred v2 i3p86
Ijsred v2 i3p86
 
Emin sg optimizacion del pavimento spectra tensar
Emin sg optimizacion del pavimento spectra tensarEmin sg optimizacion del pavimento spectra tensar
Emin sg optimizacion del pavimento spectra tensar
 

Connect magazine st davids 2010

  • 1. USING POST -TENSIONING HAD MASSIVE ENVIRONMENTAL BENEFITS OVERTRADITIONAL REINFORCED CONCRETE AND STEEL STRUCTURES,WHICH WAS IMPORTANT FOR SUCH A LARGE PROJECT.” The construction phase went smoothly, even though there were areas of complexity demanding a close interface between the post-tensioning designers and the services ST DAVID’S CENTRE CAR PARK, CARDIFF, UK engineer who required multiple penetrations through the post-tensioned beams. Clear and detailed communication was maintained with Greener parking the contractor throughout the project, from design to completion on site. The quick erection of the formwork system, in conjunction with the efficient pour ichard Gaskill of Structural Systems – the BBR Network R member in the UK – explains that significantly more additional parking was required to service the St David’s 2 development in Cardiff which led to the construction of a five sequence offered by the Structural Systems team, enabled the contractor to complete the frame in 27 weeks. Using post-tensioning had massive level, multi storey car park, totaling in excess of 50,000 m². This environmental benefits over traditional gives the new centre a total of 3,000 parking spaces and the reinforced concrete and steel structures, which was important for such a large drama of the development is heightened by the particularly project.The use of post-tensioning reduced striking elliptical ramp access to the car park. slab depths significantly so that, overall, less As part of the regeneration of Cardiff city deck slabs and a BBR CONA flat 0605 concrete and substantially less rebar was centre, the new St David’s 2 scheme system for the 525 mm x 16 m span beams. used – which was extremely beneficial to the represents a £675 million investment, totaling The car park sits on a transfer slab at level client in terms of program and budget. G 89,891 m² of retail-led mixed-use three and is tied to a stair core in the centre development, with over 100 stores and 300 of the building. By introducing post-tensioning TEAM & TECHNOLOGY luxury roof top apartments, built as seven techniques, the slab depth for the car park OWNER St David’s Partnership towers above the shopping centre. was reduced to typically 150 mm – MAIN CONTRACTOR Skanska Construction The size of the floor plate meant that each permissibly the thinnest depth for a car park CONCRETE FRAME CONTRACTOR level was typically constructed as seven slab – with some areas at 175 mm and P.C. Harrington Contractors Limited pours.The frame contractor elected to utilize nominally 300 mm thick.The beam tendons DESIGNER Arup / Structural Systems (UK) Ltd a slab and beam configuration. Structural were mainly 36 m long, although in some TECHNOLOGY BBR CONA flat Systems supplied the BBR CONA flat 0305 instances 56 m long double end stressed BBR NETWORK MEMBER Structural Systems (UK) Ltd post-tensioning system for the reinforced tendons were used. 42 CONNÆCT