2. Agenda
1. Project Consortium Status
2. Feedback from the Celtic Office
3. Project Needs
4. Per partner high-level intended contributions
5. Detecting potential start dates
6. Any Other Issues
3. Project Consortium Changes
SPAIN
Full On Net
Funding granted by CDTI
Wellness Telecom
Withdrawn due to CDTI funding
conditions
ISG
Funding by CDTI not acceptable
Funding application issued to SPRI
REDHADA
Funding by CDTI not acceptable
Looking for alternatives
National Authority
CDTI
Regional Authority
SPRI (Euskadi)
5. Project Consortium Changes
PORTUGAL
National Authority
QREN
Portugal Telecom
Slot reserved for applying in August
Ubiwhere
Slot reserved for applying in August
Wizdee
Slot reserved for applying in August
Unparallel
Slot reserved for applying in August
8. Feedback from the CELTIC Office
Conclussions of the Celtic Core Group and National
Authorities
• Celtic label extended until November ‘13
• Decission of project start date to be taken up to
October ‘13
10. Per partner Intended Contributions
Please summarise your intended contribution in 1-2
sentences
Full On Net (together with Uva) will contribute to the
semantic algorithms part. Full On Net will also provide
a biometric authentication service enabler