SlideShare a Scribd company logo
1 of 22
Increasing Availability at
Mom’s Bake Shop
Autumn Bilbao
Final Project
QSO 360
DMAIC Exercise
Tollgate Description
• The process of preparing and prebaking pies needs to be more efficient and
effective at Mom’s Bake Shop.
– The lack of pies available for purchase due to inefficiencies in preparation
causes complaints from customers
– This also causes a loss in profits because customers will leave if pies are
not immediately available or available within the next 15-20 minutes
• The DMAIC model should be used to improve this process
– Data can be used to show the gaps between current performance and goal
performance
• For example, all pie flavors should be available at least 85% of the time
that a customer asks for the pie flavor
– The risk of not having pies not readily available and having non-functional
equipment are high
• It is important to improve the efficiency and effectiveness of pie pre-preparation
– It will improve customer satisfaction
– It will increase revenue
– It will ensure the equipment remains functional
• If the issues remain unresolved, it could lead to the loss of customers and
revenue, as well as the inability to efficiently prepare pies to due a lack of
working equipment
Tollgate Description Cont.
• The goals of this project are as follows:
– Define the reason behind the inability to prepare enough pies for the
next day’s service
– Measure the process regarding the preparation of pies
– Analyze the root cause behind the inability to prepare enough pies for
the next day’s service
– Improve the efficiency behind pie preparation
– Control the process behind pie preparation to ensure enough pies are
prepared to meet customer demand each day
• The constraints on this project are as follows:
– The scope of this project only includes the pies bought by walk-in
customers
– Online and phone orders are outside of the scope
– Only the minimum number of resources can be used per day
Project Charter
Autumn Bilbao
DEFINE – Milestone One
Problem Statement Business Justification / Expected Benefits
The number of pies prepped at night for the next day’s
service at Mom’s Bake Shop has not met customer demand
since October 17, 2018. This issue has been identified based
on the loss of an average of 7 customers per day due to the
fact that the pies they want are not immediately available for
purchase and has been estimated to impact monthly profits
by $5,000. CUSTOMERS EXPECT ALL 10 FLAVORS TO BE
AVAILABLE UPON ENTRY INTO THE STORE.
Effectively estimating the next day’s sales each night
would make the pie preparation process more
efficient, which would increase the number of pie
flavors available upon walk-in and thus customer
satisfaction. This may increase the number of walk-
in customers, which would increase the business’s
monthly profit by at least $5,000.
Project Scope Out of Scope
Process Begins: Each night when the next day’s
sales are estimated
Process Ends: After store closes the next day
Orders purchased by walk-in customers are in
scope; all other orders bought ahead of time through
online or by call-in are out of scope.
Project Sponsor and Team High-Level Schedule
Sponsor: Mom’s Bake Shop Business Owner/Head
Baker
Project Manager: Autumn Bilbao
Define: COMPLETED
Measure: COMPLETED
Analyze: COMPLETED
Improve: COMPLETED
Control: 02/24/19
SIPOC
Autumn Bilbao
DEFINE – Milestone One
Suppliers Input Process Output Customer
Business
Owner/Head Baker
Ingredients/
Services/Time
Estimate next day’s
sales
List of ingredients for
preparation
Head Baker/Associate
Bakers
Head Baker/Associate
Bakers
Time and service of
gathering ingredients
Gather ingredients Collection of
ingredients to put
together
Head Baker/Associate
Bakers
Head Baker/Associate
Bakers
Time and service of
making pie crust and
filling
Make pie filling and
crust
Prepared pie Head Baker/Associate
Bakers
Head Baker/Associate
Bakers
Time and service of
prebaking prepared
pies for 45 minutes ea
Prebake Prepared
Pies
Prebaked Pie Head Baker/Associate
Bakers
Head Baker/
Associate Bakers
Time and service of
putting pies in fridge
Chilling Prebaked
Pies
Refrigerated pie Head Baker/Associate
Bakers
Associate Bakers Time and service of
rebaking one pie of
each flavor
Rebaking one pie of
each flavor
Rebaked Pies Customer
Customer Customer pays for pie Customer payment Business revenue Business
Head Baker/Associate
Bakers
Time and service of
prebaking another pie
of the same flavor(s)
of pie that was bought
by the customer
Pre-bake another pie
(occurs every time a
customer buys a pie
until store closes)
Pies Customer
Voice of the Customer
Autumn Bilbao
DEFINE – Milestone One
Customer Business
More pie flavors available upon walk in Ensure equipment will continue to be
functional
Use minimal number of resources
Part 1 – Generic Requirements
Customer and Business
Req
Measurements Goals
More flavors readily
available for purchase
# times flavor is unavailable <2 times per day per flavor
Ensure equipment will
continue to be functional
# failures/month <3 failures per month
Use minimal number of
resources
# staff working per day ≤5 per day
Part 2 – Translation to Measurements and Goals
Process Map – Multiple Pages
Autumn Bilbao
MEASURE – Milestone Two
FunctionAFunctionBFunctionCFunctionDFunctionEFunctionF
Estimate next
day’s sales
Gather
Ingredients
Make Pie
Crust and
Filling
Prebake
Prepared
Pies
Put Prebaked
Pies in Fridge
B
A
Head
Baker
Head/
Associate
Bakers
Associate
Bakers
Customers
Process Map – Multiple Pages
Autumn Bilbao
MEASURE – Milestone Two
FunctionAFunctionBFunctionCFunctionDFunctionEFunctionF
A
Rebake one pie of
each flavor that is
not on display
Put rebaked
pies on display
Customer buys
pie
End
of
Day?
B
A
Yes
No
Head
Baker
Head/
Associate
Bakers
Associate
Bakers
Customers
Value-Added Flow Analysis
Autumn Bilbao
MEASURE – Milestone Two
Definitions:
• Value-Added Step
• The customer must be willing to pay for this step.
• The “thing” is physically changed.
• The tasks are done right the first time.
• Non-Value-Added Step / Waste
• Any step that meets the definition of TIM WOOD in the announcements.
• Business Required
• Any non-value-added step that either the company or a government
regulation requires.
Value-Added Flow Analysis
Autumn Bilbao
MEASURE – Milestone Two
Step Value-Added Waste Required
Estimate Next Day’s
Sales
x
Gather Ingredients x
Make Pie Crust and
Filling
X
Prebake Prepared Pies X
Put Prebaked Pies in
Fridge
X
Rebake one pie of each
flavor that is not on
display
X
Put rebaked pie(s) on
display
X
Customer buys pie X
Data Collection Plan – Quantify the Problem
Autumn Bilbao
MEASURE – Milestone Two
Metric Output Process Sample Size Duration
Frequency at which
flavor(s) are unavailable/day
X 100% 30 days
# failures/month in
equipment
X 100% 90 days
# staff working/day X 100% 30 days
# pies that were not bought
each day (overproduction)
X 100% 30 days
% accuracy in next day’s
estimated sales (total and
per flavor)
X 75% 30 days
# times equipment checked
for mechanical issues
X 30% 30 days
# times failures in
equipment were avoided
due to checking equipment
X 100% 90 days
Frequency at which each
pie flavor is bought
X 75% 30 days each
season
• Summary of Data Collection:
– Frequency at which a flavor is unavailable per day
• Each flavor/day
• Pareto
– Frequency of failures/month in equipment
• Frequency of failures in each type of equipment (fridge, oven, mixer, heated display)
• Pareto
– # staff working/day
• frequency at which # (3,4,5 staff members) of staff works
• Histogram
– # pies that were not bought each day
• Total # pies that were not bought per day (created on weekly basis)
• Total # pies not bought per day in each flavor (created on daily basis)
• Bar chart
– % error in next day’s estimated sales
• (# of potential sales - # of times a pie is bought per day) / # potential sales x 100
• Eg. 37 (customers that walk in to buy pies) – 30 (pies actually bought) = 7 / 37(# potential sales) =
.189 x 100 = 18.9%
• Bar Chart showing % error per day (updated daily, reviewed weekly and at the end of the month)
– Frequency equipment checked for mechanical issues/month
• Total # of times equipment is checked for mechanical issues per month
• Histogram
– Frequency potential failures in equipment were avoided due to checking equipment
• Frequency of potential failures in equipment were avoided for each type of equipment (fridge, oven,
mixer, heated display)
• Pareto
– Frequency at which each pie flavor is bought
• Per flavor
• Pareto
Autumn Bilbao
MEASURE – Milestone Two
Autumn Bilbao
ANALYZE – Milestone Three
Cause – Effect Diagram
Autumn Bilbao
ANALYZE – Milestone Three
Potential Root Cause Identification
Potential Root Causes
Ineffective Sales Estimates
Equipment Failures
Number of Staff Working Per Day
Autumn Bilbao
IMPROVE – Milestone Four
Solution Selection
Proposed Solution Feasibility Effect Cost FxExC
Reduce occurrence of
equipment failures
3 2 2 12
Standardize process
for daily sales
estimates
4 4 4 64
Train all team
members on estimation
of daily sales
4 3 4 48
Standardize scheduling
of staff
5 2 4 40
Autumn Bilbao
IMPROVE – Milestone Four
Risk Assessment – FMEA
Process Step What Can Go
Wrong
Severity Occ Detect RPN Action
Gather the day’s
sales information
Information could be
inaccurate if online
and phone orders are
included
1 3 1 3 Keep copies of receipts
from walk-in orders
separate each day for
processing after the store
closes
Statistically
compare the day’s
sales to sales over
the past week
Using only the
previous week’s sales
may not be accurate
3 6 4 72 Trail-and-error, see which
time span results in a
higher accuracy
Use the average
number of pies
sold in each flavor
to estimate sales
for next day
Because the average
generally comes out
as decimals there
could be confusion
on whether to make
or not make one
more pie. Extra
unneeded pies may
be made, while some
pies that are needed
may not be made.
3 2 7 42 Standardize the choice of
making an extra pie
based on the numbers. If
the decimal after the
whole number is <.5,
then no extra pie should
be made. If the decimal
after the whole number
is ≥.5, then an extra pie
should be made
Autumn Bilbao
IMPROVE – Milestone Four
Implementation Plan
Task Resp Due Date
Gather a week’s worth of receipts/order
information from walk-in orders
Head baker 2/19/2019
Install Excel or other statistical software
(business owner’s choice)
Project
Manager
2/19/2019
Input all sales information for the past week into
excel or other statistical software
Head baker 2/21/2019
Use statistical software to show the last week’s
average sales in each pie flavor
Head baker 2/21/2019
Use calculated averages for each flavor to
estimate the next day’s sales
Head baker 2/21/2019
Autumn Bilbao
CONTROL
Monitoring Plan
What is Monitored Resp Target Frequency Escalation
% error in next day’s
estimated sales
Project
Manager
<10% Daily Head Baker
# failures/month in
equipment
Project
Manager
≤3 Monthly Head Baker
# days with under- or
over- staffing
Head Baker 0 Daily Head Baker
Six Sigma Belt Process Owner
Champion Finance
Project Sign-Off
Appendix
QSO 360
DMAIC Exercise
Analysis Roadmap
Student Name
MEASURE – Milestone Two
This is for reference only; students will not be required to do this in QSO 360.
Student Name
ANALYZE – Milestone Three
Potential Root Cause Validation With Hypothesis Testing
This is for reference only; students will not be required to do this in QSO 360.
Student Name
ANALYZE – Milestone Three
Potential Root Cause Validation With Hypothesis Testing
This is for reference only; students will not be required to do this in QSO 360.

More Related Content

What's hot

cv_raquel_gombard__autosaved_
cv_raquel_gombard__autosaved_cv_raquel_gombard__autosaved_
cv_raquel_gombard__autosaved_raquel gombard
 
Restaurant management software
Restaurant management softwareRestaurant management software
Restaurant management softwarehotel management
 
Distillery, Fmcg Manufacturing
Distillery, Fmcg ManufacturingDistillery, Fmcg Manufacturing
Distillery, Fmcg ManufacturingTony Doubell
 
Stocker Team Training with E-Commerce
Stocker Team Training with E-CommerceStocker Team Training with E-Commerce
Stocker Team Training with E-CommerceTaylor Haase
 
Picosskusandmerchandisingguidelines
PicosskusandmerchandisingguidelinesPicosskusandmerchandisingguidelines
PicosskusandmerchandisingguidelinesZulqernanePbc
 
Resume for Business Manager
Resume for Business ManagerResume for Business Manager
Resume for Business ManagerBhuvnendra Bhati
 
Nyonya Kueh the food project
Nyonya Kueh the food project Nyonya Kueh the food project
Nyonya Kueh the food project Nafis Nirman
 
Production Planning
Production Planning Production Planning
Production Planning Asif Qureshi
 
C store positions
C store positionsC store positions
C store positionsriaslater1
 
CV_ Acey Taytayon Alejandro
CV_ Acey Taytayon AlejandroCV_ Acey Taytayon Alejandro
CV_ Acey Taytayon AlejandroAcey Alejandro
 
Jose Olivares Resume 2015
Jose Olivares Resume 2015Jose Olivares Resume 2015
Jose Olivares Resume 2015Meza Jose
 

What's hot (15)

cv_raquel_gombard__autosaved_
cv_raquel_gombard__autosaved_cv_raquel_gombard__autosaved_
cv_raquel_gombard__autosaved_
 
Restaurant management software
Restaurant management softwareRestaurant management software
Restaurant management software
 
Distillery, Fmcg Manufacturing
Distillery, Fmcg ManufacturingDistillery, Fmcg Manufacturing
Distillery, Fmcg Manufacturing
 
Stocker Team Training with E-Commerce
Stocker Team Training with E-CommerceStocker Team Training with E-Commerce
Stocker Team Training with E-Commerce
 
Picosskusandmerchandisingguidelines
PicosskusandmerchandisingguidelinesPicosskusandmerchandisingguidelines
Picosskusandmerchandisingguidelines
 
Resume for Business Manager
Resume for Business ManagerResume for Business Manager
Resume for Business Manager
 
Nyonya Kueh the food project
Nyonya Kueh the food project Nyonya Kueh the food project
Nyonya Kueh the food project
 
Production Planning
Production Planning Production Planning
Production Planning
 
C store positions
C store positionsC store positions
C store positions
 
GANESH BIO-DATA
GANESH BIO-DATAGANESH BIO-DATA
GANESH BIO-DATA
 
RESUME 2015
RESUME 2015RESUME 2015
RESUME 2015
 
CV_ Acey Taytayon Alejandro
CV_ Acey Taytayon AlejandroCV_ Acey Taytayon Alejandro
CV_ Acey Taytayon Alejandro
 
online resume
online resumeonline resume
online resume
 
Jose Olivares Resume 2015
Jose Olivares Resume 2015Jose Olivares Resume 2015
Jose Olivares Resume 2015
 
CMaiorano CV2016
CMaiorano CV2016CMaiorano CV2016
CMaiorano CV2016
 

Similar to Increasing Availability of Mom's Bake Shop

Six sigma on burning brownie
Six sigma on burning brownieSix sigma on burning brownie
Six sigma on burning brownieYamna Rashid
 
Project six sigma
Project  six sigmaProject  six sigma
Project six sigmaUrooj Iqbal
 
Attachment 1 Inventory Management training.ppt
Attachment 1 Inventory Management training.pptAttachment 1 Inventory Management training.ppt
Attachment 1 Inventory Management training.pptBayardoPrado1
 
Moving From Art To Science
Moving From Art To ScienceMoving From Art To Science
Moving From Art To Sciencerudy_westervelt
 
Digital business analysis of Grilled onion
Digital business analysis of Grilled onionDigital business analysis of Grilled onion
Digital business analysis of Grilled onionVaishactMech
 
Sales Force & Merchandiser Enablement Through Mobility
Sales Force & Merchandiser Enablement Through MobilitySales Force & Merchandiser Enablement Through Mobility
Sales Force & Merchandiser Enablement Through MobilityThe Information Company
 
Sales Force & Merchandiser Enablement Through Mobility
Sales Force & Merchandiser Enablement Through MobilitySales Force & Merchandiser Enablement Through Mobility
Sales Force & Merchandiser Enablement Through MobilityThe Information Company
 
How Online Retailers Can Benefit from Enhanced Ecommerce?
How Online Retailers Can Benefit from Enhanced Ecommerce?How Online Retailers Can Benefit from Enhanced Ecommerce?
How Online Retailers Can Benefit from Enhanced Ecommerce?Tatvic Analytics
 
HEB EZ-PIC 8-22-12
HEB EZ-PIC 8-22-12HEB EZ-PIC 8-22-12
HEB EZ-PIC 8-22-12Jim Keegan
 
Reducing Production costs, SKUs & Waste Through Efficient Coding & Marking Te...
Reducing Production costs, SKUs & Waste Through Efficient Coding & Marking Te...Reducing Production costs, SKUs & Waste Through Efficient Coding & Marking Te...
Reducing Production costs, SKUs & Waste Through Efficient Coding & Marking Te...PT Asia Limited
 
Bakery products final project report cd version
Bakery products final project report   cd versionBakery products final project report   cd version
Bakery products final project report cd versionDavidEdem4
 
Chapter 4: Production and Supply Chain Management Information Systems
Chapter 4: Production and Supply Chain Management Information SystemsChapter 4: Production and Supply Chain Management Information Systems
Chapter 4: Production and Supply Chain Management Information SystemsQuang Ngoc
 
Pepsi sales force enablement & merchandising through mobility
Pepsi  sales force enablement & merchandising through mobilityPepsi  sales force enablement & merchandising through mobility
Pepsi sales force enablement & merchandising through mobilityThe Information Company
 
Solving Standard Costing Problems with Lean Accounting
Solving Standard Costing Problems with Lean AccountingSolving Standard Costing Problems with Lean Accounting
Solving Standard Costing Problems with Lean AccountingSafetyChain Software
 
Position Responsibilities
Position ResponsibilitiesPosition Responsibilities
Position ResponsibilitiesRegina Pringle
 

Similar to Increasing Availability of Mom's Bake Shop (20)

Six sigma on burning brownie
Six sigma on burning brownieSix sigma on burning brownie
Six sigma on burning brownie
 
Project six sigma
Project  six sigmaProject  six sigma
Project six sigma
 
iKEG IS NOW A REALITY
iKEG IS NOW A REALITYiKEG IS NOW A REALITY
iKEG IS NOW A REALITY
 
Hidden Grounds Proposal
Hidden Grounds ProposalHidden Grounds Proposal
Hidden Grounds Proposal
 
Attachment 1 Inventory Management training.ppt
Attachment 1 Inventory Management training.pptAttachment 1 Inventory Management training.ppt
Attachment 1 Inventory Management training.ppt
 
Moving From Art To Science
Moving From Art To ScienceMoving From Art To Science
Moving From Art To Science
 
Digital business analysis of Grilled onion
Digital business analysis of Grilled onionDigital business analysis of Grilled onion
Digital business analysis of Grilled onion
 
Sales Force & Merchandiser Enablement Through Mobility
Sales Force & Merchandiser Enablement Through MobilitySales Force & Merchandiser Enablement Through Mobility
Sales Force & Merchandiser Enablement Through Mobility
 
Sales Force & Merchandiser Enablement Through Mobility
Sales Force & Merchandiser Enablement Through MobilitySales Force & Merchandiser Enablement Through Mobility
Sales Force & Merchandiser Enablement Through Mobility
 
How Online Retailers Can Benefit from Enhanced Ecommerce?
How Online Retailers Can Benefit from Enhanced Ecommerce?How Online Retailers Can Benefit from Enhanced Ecommerce?
How Online Retailers Can Benefit from Enhanced Ecommerce?
 
HEB EZ-PIC 8-22-12
HEB EZ-PIC 8-22-12HEB EZ-PIC 8-22-12
HEB EZ-PIC 8-22-12
 
Reducing Production costs, SKUs & Waste Through Efficient Coding & Marking Te...
Reducing Production costs, SKUs & Waste Through Efficient Coding & Marking Te...Reducing Production costs, SKUs & Waste Through Efficient Coding & Marking Te...
Reducing Production costs, SKUs & Waste Through Efficient Coding & Marking Te...
 
Bakery products final project report cd version
Bakery products final project report   cd versionBakery products final project report   cd version
Bakery products final project report cd version
 
Chapter 4: Production and Supply Chain Management Information Systems
Chapter 4: Production and Supply Chain Management Information SystemsChapter 4: Production and Supply Chain Management Information Systems
Chapter 4: Production and Supply Chain Management Information Systems
 
Market development
Market development Market development
Market development
 
Pepsi sales force enablement & merchandising through mobility
Pepsi  sales force enablement & merchandising through mobilityPepsi  sales force enablement & merchandising through mobility
Pepsi sales force enablement & merchandising through mobility
 
Solving Standard Costing Problems with Lean Accounting
Solving Standard Costing Problems with Lean AccountingSolving Standard Costing Problems with Lean Accounting
Solving Standard Costing Problems with Lean Accounting
 
Proposal Final
Proposal FinalProposal Final
Proposal Final
 
Position Responsibilities
Position ResponsibilitiesPosition Responsibilities
Position Responsibilities
 
Current job overview
Current job overviewCurrent job overview
Current job overview
 

Recently uploaded

Hyderabad Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Hyderabad Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceHyderabad Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Hyderabad Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceDamini Dixit
 
How to structure your pitch - B4i template
How to structure your pitch - B4i templateHow to structure your pitch - B4i template
How to structure your pitch - B4i templateFerruccio Martinelli
 
NEON LIGHT CITY pitch deck for the new PC game
NEON LIGHT CITY pitch deck for the new PC gameNEON LIGHT CITY pitch deck for the new PC game
NEON LIGHT CITY pitch deck for the new PC gametess51
 
Tirupati Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Tirupati Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceTirupati Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Tirupati Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceDamini Dixit
 
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.in
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.inEV Electric Vehicle Startup Pitch Deck- StartupSprouts.in
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.inStartupSprouts.in
 
Dive into Angel Investing s 2024 0502.pptx
Dive into Angel Investing s 2024 0502.pptxDive into Angel Investing s 2024 0502.pptx
Dive into Angel Investing s 2024 0502.pptxElaine Werffeli
 
Dehradun Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Dehradun Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceDehradun Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Dehradun Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceDamini Dixit
 
How Multicultural Toys Helps in Child Development.pptx
How Multicultural Toys Helps in Child Development.pptxHow Multicultural Toys Helps in Child Development.pptx
How Multicultural Toys Helps in Child Development.pptxDiversity In Toys
 
Famedesired Project portfolio1 . Fullsail
Famedesired Project portfolio1 . FullsailFamedesired Project portfolio1 . Fullsail
Famedesired Project portfolio1 . Fullsailfergusonamani
 
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...StartupSprouts.in
 
Dàni Velvet Personal Brand Exploration (1).pptx
Dàni Velvet Personal Brand Exploration (1).pptxDàni Velvet Personal Brand Exploration (1).pptx
Dàni Velvet Personal Brand Exploration (1).pptxdmtillman
 
Lucknow Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Lucknow Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceLucknow Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Lucknow Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceDamini Dixit
 
call Now 9811711561 Cash Payment乂 Call Girls in Dwarka
call Now 9811711561 Cash Payment乂 Call Girls in Dwarkacall Now 9811711561 Cash Payment乂 Call Girls in Dwarka
call Now 9811711561 Cash Payment乂 Call Girls in Dwarkavikas rana
 
Connaught Place, Delhi Call girls :8448380779 Model Escorts | 100% verified
Connaught Place, Delhi Call girls :8448380779 Model Escorts | 100% verifiedConnaught Place, Delhi Call girls :8448380779 Model Escorts | 100% verified
Connaught Place, Delhi Call girls :8448380779 Model Escorts | 100% verifiedDelhi Call girls
 
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verifiedSector 18, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verifiedDelhi Call girls
 
Sangareddy Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Sangareddy Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceSangareddy Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Sangareddy Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceDamini Dixit
 
Karol Bagh, Delhi Call girls :8448380779 Model Escorts | 100% verified
Karol Bagh, Delhi Call girls :8448380779 Model Escorts | 100% verifiedKarol Bagh, Delhi Call girls :8448380779 Model Escorts | 100% verified
Karol Bagh, Delhi Call girls :8448380779 Model Escorts | 100% verifiedDelhi Call girls
 
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893Health
 
Sohna Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Sohna Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceSohna Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Sohna Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceDamini Dixit
 
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdfEnabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdfSmartinfologiks
 

Recently uploaded (20)

Hyderabad Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Hyderabad Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceHyderabad Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Hyderabad Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
How to structure your pitch - B4i template
How to structure your pitch - B4i templateHow to structure your pitch - B4i template
How to structure your pitch - B4i template
 
NEON LIGHT CITY pitch deck for the new PC game
NEON LIGHT CITY pitch deck for the new PC gameNEON LIGHT CITY pitch deck for the new PC game
NEON LIGHT CITY pitch deck for the new PC game
 
Tirupati Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Tirupati Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceTirupati Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Tirupati Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.in
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.inEV Electric Vehicle Startup Pitch Deck- StartupSprouts.in
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.in
 
Dive into Angel Investing s 2024 0502.pptx
Dive into Angel Investing s 2024 0502.pptxDive into Angel Investing s 2024 0502.pptx
Dive into Angel Investing s 2024 0502.pptx
 
Dehradun Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Dehradun Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceDehradun Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Dehradun Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
How Multicultural Toys Helps in Child Development.pptx
How Multicultural Toys Helps in Child Development.pptxHow Multicultural Toys Helps in Child Development.pptx
How Multicultural Toys Helps in Child Development.pptx
 
Famedesired Project portfolio1 . Fullsail
Famedesired Project portfolio1 . FullsailFamedesired Project portfolio1 . Fullsail
Famedesired Project portfolio1 . Fullsail
 
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...
 
Dàni Velvet Personal Brand Exploration (1).pptx
Dàni Velvet Personal Brand Exploration (1).pptxDàni Velvet Personal Brand Exploration (1).pptx
Dàni Velvet Personal Brand Exploration (1).pptx
 
Lucknow Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Lucknow Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceLucknow Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Lucknow Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
call Now 9811711561 Cash Payment乂 Call Girls in Dwarka
call Now 9811711561 Cash Payment乂 Call Girls in Dwarkacall Now 9811711561 Cash Payment乂 Call Girls in Dwarka
call Now 9811711561 Cash Payment乂 Call Girls in Dwarka
 
Connaught Place, Delhi Call girls :8448380779 Model Escorts | 100% verified
Connaught Place, Delhi Call girls :8448380779 Model Escorts | 100% verifiedConnaught Place, Delhi Call girls :8448380779 Model Escorts | 100% verified
Connaught Place, Delhi Call girls :8448380779 Model Escorts | 100% verified
 
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verifiedSector 18, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verified
 
Sangareddy Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Sangareddy Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceSangareddy Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Sangareddy Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
Karol Bagh, Delhi Call girls :8448380779 Model Escorts | 100% verified
Karol Bagh, Delhi Call girls :8448380779 Model Escorts | 100% verifiedKarol Bagh, Delhi Call girls :8448380779 Model Escorts | 100% verified
Karol Bagh, Delhi Call girls :8448380779 Model Escorts | 100% verified
 
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
 
Sohna Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Sohna Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceSohna Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Sohna Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdfEnabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
 

Increasing Availability of Mom's Bake Shop

  • 1. Increasing Availability at Mom’s Bake Shop Autumn Bilbao Final Project QSO 360 DMAIC Exercise
  • 2. Tollgate Description • The process of preparing and prebaking pies needs to be more efficient and effective at Mom’s Bake Shop. – The lack of pies available for purchase due to inefficiencies in preparation causes complaints from customers – This also causes a loss in profits because customers will leave if pies are not immediately available or available within the next 15-20 minutes • The DMAIC model should be used to improve this process – Data can be used to show the gaps between current performance and goal performance • For example, all pie flavors should be available at least 85% of the time that a customer asks for the pie flavor – The risk of not having pies not readily available and having non-functional equipment are high • It is important to improve the efficiency and effectiveness of pie pre-preparation – It will improve customer satisfaction – It will increase revenue – It will ensure the equipment remains functional • If the issues remain unresolved, it could lead to the loss of customers and revenue, as well as the inability to efficiently prepare pies to due a lack of working equipment
  • 3. Tollgate Description Cont. • The goals of this project are as follows: – Define the reason behind the inability to prepare enough pies for the next day’s service – Measure the process regarding the preparation of pies – Analyze the root cause behind the inability to prepare enough pies for the next day’s service – Improve the efficiency behind pie preparation – Control the process behind pie preparation to ensure enough pies are prepared to meet customer demand each day • The constraints on this project are as follows: – The scope of this project only includes the pies bought by walk-in customers – Online and phone orders are outside of the scope – Only the minimum number of resources can be used per day
  • 4. Project Charter Autumn Bilbao DEFINE – Milestone One Problem Statement Business Justification / Expected Benefits The number of pies prepped at night for the next day’s service at Mom’s Bake Shop has not met customer demand since October 17, 2018. This issue has been identified based on the loss of an average of 7 customers per day due to the fact that the pies they want are not immediately available for purchase and has been estimated to impact monthly profits by $5,000. CUSTOMERS EXPECT ALL 10 FLAVORS TO BE AVAILABLE UPON ENTRY INTO THE STORE. Effectively estimating the next day’s sales each night would make the pie preparation process more efficient, which would increase the number of pie flavors available upon walk-in and thus customer satisfaction. This may increase the number of walk- in customers, which would increase the business’s monthly profit by at least $5,000. Project Scope Out of Scope Process Begins: Each night when the next day’s sales are estimated Process Ends: After store closes the next day Orders purchased by walk-in customers are in scope; all other orders bought ahead of time through online or by call-in are out of scope. Project Sponsor and Team High-Level Schedule Sponsor: Mom’s Bake Shop Business Owner/Head Baker Project Manager: Autumn Bilbao Define: COMPLETED Measure: COMPLETED Analyze: COMPLETED Improve: COMPLETED Control: 02/24/19
  • 5. SIPOC Autumn Bilbao DEFINE – Milestone One Suppliers Input Process Output Customer Business Owner/Head Baker Ingredients/ Services/Time Estimate next day’s sales List of ingredients for preparation Head Baker/Associate Bakers Head Baker/Associate Bakers Time and service of gathering ingredients Gather ingredients Collection of ingredients to put together Head Baker/Associate Bakers Head Baker/Associate Bakers Time and service of making pie crust and filling Make pie filling and crust Prepared pie Head Baker/Associate Bakers Head Baker/Associate Bakers Time and service of prebaking prepared pies for 45 minutes ea Prebake Prepared Pies Prebaked Pie Head Baker/Associate Bakers Head Baker/ Associate Bakers Time and service of putting pies in fridge Chilling Prebaked Pies Refrigerated pie Head Baker/Associate Bakers Associate Bakers Time and service of rebaking one pie of each flavor Rebaking one pie of each flavor Rebaked Pies Customer Customer Customer pays for pie Customer payment Business revenue Business Head Baker/Associate Bakers Time and service of prebaking another pie of the same flavor(s) of pie that was bought by the customer Pre-bake another pie (occurs every time a customer buys a pie until store closes) Pies Customer
  • 6. Voice of the Customer Autumn Bilbao DEFINE – Milestone One Customer Business More pie flavors available upon walk in Ensure equipment will continue to be functional Use minimal number of resources Part 1 – Generic Requirements Customer and Business Req Measurements Goals More flavors readily available for purchase # times flavor is unavailable <2 times per day per flavor Ensure equipment will continue to be functional # failures/month <3 failures per month Use minimal number of resources # staff working per day ≤5 per day Part 2 – Translation to Measurements and Goals
  • 7. Process Map – Multiple Pages Autumn Bilbao MEASURE – Milestone Two FunctionAFunctionBFunctionCFunctionDFunctionEFunctionF Estimate next day’s sales Gather Ingredients Make Pie Crust and Filling Prebake Prepared Pies Put Prebaked Pies in Fridge B A Head Baker Head/ Associate Bakers Associate Bakers Customers
  • 8. Process Map – Multiple Pages Autumn Bilbao MEASURE – Milestone Two FunctionAFunctionBFunctionCFunctionDFunctionEFunctionF A Rebake one pie of each flavor that is not on display Put rebaked pies on display Customer buys pie End of Day? B A Yes No Head Baker Head/ Associate Bakers Associate Bakers Customers
  • 9. Value-Added Flow Analysis Autumn Bilbao MEASURE – Milestone Two Definitions: • Value-Added Step • The customer must be willing to pay for this step. • The “thing” is physically changed. • The tasks are done right the first time. • Non-Value-Added Step / Waste • Any step that meets the definition of TIM WOOD in the announcements. • Business Required • Any non-value-added step that either the company or a government regulation requires.
  • 10. Value-Added Flow Analysis Autumn Bilbao MEASURE – Milestone Two Step Value-Added Waste Required Estimate Next Day’s Sales x Gather Ingredients x Make Pie Crust and Filling X Prebake Prepared Pies X Put Prebaked Pies in Fridge X Rebake one pie of each flavor that is not on display X Put rebaked pie(s) on display X Customer buys pie X
  • 11. Data Collection Plan – Quantify the Problem Autumn Bilbao MEASURE – Milestone Two Metric Output Process Sample Size Duration Frequency at which flavor(s) are unavailable/day X 100% 30 days # failures/month in equipment X 100% 90 days # staff working/day X 100% 30 days # pies that were not bought each day (overproduction) X 100% 30 days % accuracy in next day’s estimated sales (total and per flavor) X 75% 30 days # times equipment checked for mechanical issues X 30% 30 days # times failures in equipment were avoided due to checking equipment X 100% 90 days Frequency at which each pie flavor is bought X 75% 30 days each season
  • 12. • Summary of Data Collection: – Frequency at which a flavor is unavailable per day • Each flavor/day • Pareto – Frequency of failures/month in equipment • Frequency of failures in each type of equipment (fridge, oven, mixer, heated display) • Pareto – # staff working/day • frequency at which # (3,4,5 staff members) of staff works • Histogram – # pies that were not bought each day • Total # pies that were not bought per day (created on weekly basis) • Total # pies not bought per day in each flavor (created on daily basis) • Bar chart – % error in next day’s estimated sales • (# of potential sales - # of times a pie is bought per day) / # potential sales x 100 • Eg. 37 (customers that walk in to buy pies) – 30 (pies actually bought) = 7 / 37(# potential sales) = .189 x 100 = 18.9% • Bar Chart showing % error per day (updated daily, reviewed weekly and at the end of the month) – Frequency equipment checked for mechanical issues/month • Total # of times equipment is checked for mechanical issues per month • Histogram – Frequency potential failures in equipment were avoided due to checking equipment • Frequency of potential failures in equipment were avoided for each type of equipment (fridge, oven, mixer, heated display) • Pareto – Frequency at which each pie flavor is bought • Per flavor • Pareto Autumn Bilbao MEASURE – Milestone Two
  • 13. Autumn Bilbao ANALYZE – Milestone Three Cause – Effect Diagram
  • 14. Autumn Bilbao ANALYZE – Milestone Three Potential Root Cause Identification Potential Root Causes Ineffective Sales Estimates Equipment Failures Number of Staff Working Per Day
  • 15. Autumn Bilbao IMPROVE – Milestone Four Solution Selection Proposed Solution Feasibility Effect Cost FxExC Reduce occurrence of equipment failures 3 2 2 12 Standardize process for daily sales estimates 4 4 4 64 Train all team members on estimation of daily sales 4 3 4 48 Standardize scheduling of staff 5 2 4 40
  • 16. Autumn Bilbao IMPROVE – Milestone Four Risk Assessment – FMEA Process Step What Can Go Wrong Severity Occ Detect RPN Action Gather the day’s sales information Information could be inaccurate if online and phone orders are included 1 3 1 3 Keep copies of receipts from walk-in orders separate each day for processing after the store closes Statistically compare the day’s sales to sales over the past week Using only the previous week’s sales may not be accurate 3 6 4 72 Trail-and-error, see which time span results in a higher accuracy Use the average number of pies sold in each flavor to estimate sales for next day Because the average generally comes out as decimals there could be confusion on whether to make or not make one more pie. Extra unneeded pies may be made, while some pies that are needed may not be made. 3 2 7 42 Standardize the choice of making an extra pie based on the numbers. If the decimal after the whole number is <.5, then no extra pie should be made. If the decimal after the whole number is ≥.5, then an extra pie should be made
  • 17. Autumn Bilbao IMPROVE – Milestone Four Implementation Plan Task Resp Due Date Gather a week’s worth of receipts/order information from walk-in orders Head baker 2/19/2019 Install Excel or other statistical software (business owner’s choice) Project Manager 2/19/2019 Input all sales information for the past week into excel or other statistical software Head baker 2/21/2019 Use statistical software to show the last week’s average sales in each pie flavor Head baker 2/21/2019 Use calculated averages for each flavor to estimate the next day’s sales Head baker 2/21/2019
  • 18. Autumn Bilbao CONTROL Monitoring Plan What is Monitored Resp Target Frequency Escalation % error in next day’s estimated sales Project Manager <10% Daily Head Baker # failures/month in equipment Project Manager ≤3 Monthly Head Baker # days with under- or over- staffing Head Baker 0 Daily Head Baker Six Sigma Belt Process Owner Champion Finance Project Sign-Off
  • 20. Analysis Roadmap Student Name MEASURE – Milestone Two This is for reference only; students will not be required to do this in QSO 360.
  • 21. Student Name ANALYZE – Milestone Three Potential Root Cause Validation With Hypothesis Testing This is for reference only; students will not be required to do this in QSO 360.
  • 22. Student Name ANALYZE – Milestone Three Potential Root Cause Validation With Hypothesis Testing This is for reference only; students will not be required to do this in QSO 360.