SlideShare a Scribd company logo
1 of 56
Download to read offline
NAME 457
Ship Economics
and Management
Part – 5: Economics in Ship Design
Conducted by:
Cdre M Muzibur Rahman, (E), psc, PhD, BN
Cdre Muzib, psc, PhD
Sequential Engineering Design
Concurrent
Engineering Design
Cdre Muzib, psc, PhD
The engineer is working with conflicting requirements
Example
• Physical – minimum weight
• Economic – minimum cost
• Social/Sociopolitical – maximum safety
• Environmental/Polution – minimum impact
• Commercial – maximum efficiency
• Esthetic – maximum stylishness
• Etc.
Cdre Muzib, psc, PhD
The engineer resolves these conflicts and searches
for “optimum” solutions in the design process.
Ship design is solving a problem with many VARIABLES.
It is an ITERATIVE process.
Prior to 1970, designers used
The DESIGN SPIRAL.
Ship Design Methodology
Cdre Muzib, psc, PhD
DESIGN SPIRAL:
• Hull form
• Appropriate dimensions
• Hull prismatic coefficients
• Power estimates
• Weight estimates
- Hull
- Machinery
- Outfitting
• Deadweight capacity
Design Spiral:
J H Evans (1959)
introduced the
concept of design
spiral, which
represents the
sequential and
iterative aspects
of the process
Ship Design Methodology
Cdre Muzib, psc, PhD
Buxton (1972), introduced the economical aspects in ship design
Andrews (1981), added the time dimension in Buxton design model
Ship Design Methodology
Cdre Muzib, psc, PhD
Taggart 1980
Ship Design Methodology
Cdre Muzib, psc, PhD
Taggart 1980
Ship Design Methodology
Cdre Muzib, psc, PhD
Find out the cost of design for the man-hour cost of Tk 75.00
Ship Design Methodology
Levander and
Papanikolaou
2009
Cdre Muzib, psc, PhD
Time Scale of Ship Design Stages
Cdre Muzib, psc, PhD
Economical aspect of Ship dimensioning
Cdre Muzib, psc, PhD
• Parametric Studies
– The independent variables are obtained by variation
between the lower and upper limits assumed
– Require more computing time when the number of design
variables is high
– No guarantees that the solution found is the optimal
• Optimization Methods
– The independent variables are obtained from an
optimization algorithm
– Possible to find a better and faster solution
– Only provides information about the optimal point found
(single objective methods)
Determination of the Design Variables
Cdre Muzib, psc, PhD
Size of ship is determined by number of physical
restrictions. Few of them are:
Shipbuilding facilities
Docking and undocking capacity
Shallow water en route / Canal /Straights
Conditions of loading and unloading ports
Cargo type and availability
Cdre Muzib, psc, PhD
Computers permit multiple criteria – multi variate search patterns.
“New ships should be
• 25% novelty
• 75% well proven practice.” - Baker
Cdre Muzib, psc, PhD
Economic
Analysis
MARINE COST ESTIMATING
Marine cost estimating is not an exact science. It has grown
through application of methods and historical data. It is an
area where significant improvement would help all shipyards
as it is really pricing of estimated quantities of raw material
and equipment.
World class shipyards use parametric estimating plans and
in most shipyards, Engineering is very involved in the
estimating process, usually responsible for material take-off
and definition of system design and associated equipment.
Cdre Muzib, psc, PhD
MARINE COST ESTIMATING
In addition, Engineering must estimate how much man hours
and material it will require to design and build the ship.
Because of the time and cost of preparing estimates,
shipbuilders usually are selective on what the will bid on.
Most shipyards management have a "Bid- No Bid" meeting for
each invitation to bid.
Bid decision is based on:
- ongoing work
- product fit to facilities and capabilities
- extent of competition
Cdre Muzib, psc, PhD
Cdre Muzib, psc, PhD
Bottom-up Cost Estimation: Most detailed methods of estimating the ship
building costs and are sometimes referred to as grass root or engineering
build up estimating. These methods are only valid after the design has
reached a level of significant technical maturity. It would have been a
subject of accounting where the material cost of every parts and their
assembly or labor cost is known and summarized to a total shipbuilding cost
by the estimator. Bottom-up estimations may be based on drawings, bills of
materials, historical vendor costs, and existing quotes.
Top-down Cost Estimation: Also called analogous methods or
extrapolation models. These methods are based on the comparison and
extrapolation of known data from objects, in this case ships with a satisfying
technical similarity are considered. These methods are used in the earliest
design phases like concept design and preliminary design where there is
less detailed information available. Top-down methods are used when the
amount of information available are enough to recognize a similarity to
previous objects. It is up to the estimator to judge whether a new-building
project has unique design characteristics or if it is comparable to historical
data. Some top-down methods therefore rely on “expert judgments”.
Methods of Estimating shipbuilding Cost
Cdre Muzib, psc, PhD
Parametric Cost Estimation: Between the global top-down methods and
the accounting bottom-up methods we find parametric cost estimation. The
basis for parametric cost estimation methods is the use of cost estimating
relationships (CER). CERs are mathematical expressions or formulas
relating cost as the dependent variable to selected, independent cost-driving
variables. These relations between costs and relevant parameters are
based on regression of historical data. “The implicit assumption of
parametric cost estimating is that the same forces that affected cost in the
past will affect cost in the future”. If the CERs calculate the total cost based
on global parameters like length overall (LOA) or deadweight (DWT), some
would call this a top-down approach. The opposite would be if costs of every
little subsystem were found by CERs and then used an accounting bottom-
up approach. In reality, most parametric cost estimation methods are
considered closest to top-down methods because of the independent cost
drivers chosen and the use of parametric estimation in early phases of
design.
Methods of Estimating shipbuilding Cost
Cdre Muzib, psc, PhD
Cdre Muzib, psc, PhD
Fig. 24 Optimal Ship Size
Page 97 (Buxton 1976)
Cdre Muzib, psc, PhD
Optimal Ship Speed
Page 98 (Buxton 1976)
Cdre Muzib, psc, PhD
Fig. 25 Optimal Ship Speed
Page 99 (Buxton 1976)
Factors influencing higher optimal speed : Economic
Cdre Muzib, psc, PhD
Factors influencing higher optimal speed :Technical
Cdre Muzib, psc, PhD
Cdre Muzib, psc, PhD
Cdre Muzib, psc, PhD
Economic Measures of Merit
• Initial ship cost
– The initial ship cost is not by itself a good indicator, some
design options only become economically advantageous on
the long run.
• Other criteria can be used considering running costs of the
ship along its entire operational life
• The most common measures are:
– Required Freight Rate (RFR)
– Net Present Value (NPV)
– Internal Rate of Return (IRR)
– Modified Internal Rate of Return (MIRR)
• To evaluate these criteria the knowledge of the typical ship
voyage is required.
Cdre Muzib, psc, PhD
• The specification of the typical ship voyage allows a more
comprehensive analysis of the economic aspects.
• It may include:
– The number of ports visited during the round trip
– The distance between ports
– The cargo-handling capabilities available and the
corresponding handling rates and costs
– Port fees and taxes
Economic Measures of Merit
Cdre Muzib, psc, PhD
• Ship Acquisition Cost • Costs in Shipping
Ship Economics: Cost Estimating
• Ship Acquisition Cost:
Initial Investment, I =Q⋅ (1+ Ka)
with:
Q: Ship acquisition cost = (CH + CE + CM + CX) (1 + Kb )
CH : Hull/Steel Cost,
CE : Equipment (Nav/Comm/Domestic) Cost
CM : Machinery (propulsion/auxiliary) Cost,
CX : Special Equipment (survey/surveilance/rescue) Cost
Ka : Owner’s expenses during shipbuilding and acquisition, expressed as
percentage of the acquisition cost, generally of about 5 – 15%.
Kb : Profit Margin of the shipyard, in percentage
Cdre Muzib, psc, PhD
This value can be estimated as follows:
1. Estimate the shipbuilding cost of a reference ship (QR) by
the previous expressions
2. Obtain the actual ship cost from the current market (QM)
3. The nominal profit margin can then be obtained by:
If the Kb value is too low or too high, for instance, outside of
the interval [-30%, +30%] the cost formulas should be reviewed
and updated.
Profit Margin of the Shipyard
Cdre Muzib, psc, PhD
3
/
2
3
.
. 
 V
k
WM
Machinery Weight:

 .
. 5
.
0
V
k
WS
Hull Steel Weight:
4
/
3
9
.
0
.
. 
 V
k
WE
Equipment Weight:
Light Ship Weight for cost estimation
Cdre Muzib, psc, PhD
1. Methods that consider the weights as function of the main
characteristics of the hull
• Appropriate to be used in processes for the optimization of the main
dimensions
2. Methods based on the existence of data from existing ships
– More precise estimates
– Results not satisfactory when dealing with new types of ships
3. Methods based on surfaces.
– When the hull form, the general arrangement and the subdivision are
already roughly known
4. Methods based on the midship section modulus.
– Based on the scantlings of the midship section
Methods to Estimate the Hull Weight
Cdre Muzib, psc, PhD
• Most estimate methods consider separately the weights of
the hull and of the superstructure
• For the purpose of cost estimation, the hull weight should be
subdivided into:
– Weight of structural steel (hull structure)
– Weight of outfit steel (foundations, ladders, steps, etc.)
• Each of these components should be subdivided into:
– Weight of plates
– Weight of stiffeners
• For the purpose of cost estimation, and due to the waste
from the cutting process, margin/factor should be used:
Gross Steel Weight = 1.08 ~ 1.12 x Net Steel Weight
Methods to Estimate the Hull Weight
Cdre Muzib, psc, PhD
Hull Weight estimation From statistical analysis regression
Cdre Muzib, psc, PhD
D’Almeida (2009)
Cudina et al (2010) [Tanker and bulk carrier]
f1 – reduction of hull weight due to use of high tensile steel
Cdre Muzib, psc, PhD
Propulsion Machinery Weight estimation From statistical
analysis regression
Cdre Muzib, psc, PhD
Equipment weight estimation from statistical analysis regression
D’Almeida (2009)
Cudina et al (2010) [Tanker and bulk carrier]
The coefficients k1 and k2 are characteristic of each ship type, obtained from
statistical regression analysis
Equipment Weight
Cdre Muzib, psc, PhD
Ship Acquisition: Hull Steel Cost
Cdre Muzib, psc, PhD
Ship Acquisition : Equipment Cost
Cdre Muzib, psc, PhD
Cdre Muzib, psc, PhD
Cdre Muzib, psc, PhD
Cdre Muzib, psc, PhD
Cdre Muzib, psc, PhD
Ship Acquisition : Machinery Cost
Cdre Muzib, psc, PhD
Ship Acquisition Cost (Alternative)
Total cost, CT = CH + CE + CM + GE + S + EC
with:
CH - Cost of hull
CE - Cost of equipment
CM - Cost of machinery
GE - General expenses (about 90% labor cost)
S - Profit of the shipyard (about 5% labor cost)
EC - Extra Costs
Each component can be divided into two parts:
- cost of materials or equipments, and
- labor cost.
Cdre Muzib, psc, PhD
Costs in Shipping
Operating cost - expenses involved in day-to-day running of the
ship: essentially costs for crew, stores and maintenance.
Periodic maintenance cost - incurred when the ship is dry-
docked for major repairs, usually at the time of its special
survey. In older ships this may involve considerable
expenditure, so shipping companies often include a ‘dry-
docking provision’ in their operating costs.
Voyage cost - variable costs associated with a specific voyage
and include such items as fuel, port charges and canal dues.
Capital cost - depend on how the ship is financed. They may
take the form of dividends to equity or interest and capital
payments on debt finance.
Cargo handling cost - expenses of loading, stowing and
discharging cargo. Cdre Muzib, psc, PhD
Costs in Shipping: Crew Costs
Crew cost includes basic salaries and wages, social insurance,
repatriation expenses, victuals, recruitment and training and others
Cdre Muzib, psc, PhD
Costs in Shipping: Crew Complements
Cdre Muzib, psc, PhD
Complement:
The term “complement” is used to describe the number of
people who will be manning the ship. This is an important
variable when predicting the size or complexity of the
vessels because the distance between ports increases the
space needed to store supplies and waste.
Cdre Muzib, psc, PhD
Costs in Shipping: Stores Costs
Cdre Muzib, psc, PhD
Costs in Shipping: Maintenance Costs
Cdre Muzib, psc, PhD
Costs in Shipping: Insurance Costs
Cdre Muzib, psc, PhD
Costs in Shipping: Admin Costs
Cdre Muzib, psc, PhD
Costs in Shipping: Docking Costs
Cdre Muzib, psc, PhD
Costs in Shipping: Voyage Costs
Variable costs associated to a specific voyage
CVOY = CFO + CPD + CTP + CD
with:
CFO – fuel costs for main and auxiliary machinery
CPD – port and light dues
CTP – tug and pilotage costs
CD – canal dues
SFC for Medium-speed diesel engines = 0.200~0.250
[kg/kW.h]
Cdre Muzib, psc, PhD
Costs in Shipping: Cargo Handling Costs
CCH = CLOAD + CDISC + CCLM
with:
CLOAD – cargo loading charges
CDISC – cargo discharge costs
CCLM – allowance for cargo claims
Information about charge/discharge rates can be generally
obtained from the Internet sites of the ports.
Cdre Muzib, psc, PhD

More Related Content

What's hot

Ship terminologies – organizations & chartering
Ship terminologies – organizations & charteringShip terminologies – organizations & chartering
Ship terminologies – organizations & charteringKevin Philip Joseph
 
1 dry cargo chartering
1 dry cargo chartering1 dry cargo chartering
1 dry cargo charteringcmmindia2017
 
Glossary of shipping terms
Glossary of shipping termsGlossary of shipping terms
Glossary of shipping termsNavneet Gera
 
Glossary of Port and Shipping Terms
Glossary of Port and Shipping TermsGlossary of Port and Shipping Terms
Glossary of Port and Shipping TermsSam Thai Aladeen
 
Shipping tonnages
Shipping tonnagesShipping tonnages
Shipping tonnagesAjith Albi
 
Logistica y distribución glosario (1)
Logistica y distribución glosario (1)Logistica y distribución glosario (1)
Logistica y distribución glosario (1)camiquinchis
 
Transportation strategy
Transportation strategyTransportation strategy
Transportation strategyTimotius Febry
 
Trident warrior advancing future capabilities through fleet experimentation
Trident warrior advancing future capabilities through fleet experimentationTrident warrior advancing future capabilities through fleet experimentation
Trident warrior advancing future capabilities through fleet experimentationMaster Chief Petty Officer of the Navy
 
Shipping industry planning, optimization & scheduling
Shipping industry planning, optimization & schedulingShipping industry planning, optimization & scheduling
Shipping industry planning, optimization & schedulingPuneet Mishra
 
Mr Ganguly - Shipping Agency
Mr Ganguly - Shipping AgencyMr Ganguly - Shipping Agency
Mr Ganguly - Shipping AgencyMarexmedia
 
Time Charter vs Voyage Charter - 19 Nov 2014 - Capt. Richard Creet
Time Charter vs Voyage Charter - 19 Nov 2014 - Capt. Richard CreetTime Charter vs Voyage Charter - 19 Nov 2014 - Capt. Richard Creet
Time Charter vs Voyage Charter - 19 Nov 2014 - Capt. Richard CreetMarexmedia
 
Jd 12 sea & othetr transportation system
Jd 12 sea & othetr transportation systemJd 12 sea & othetr transportation system
Jd 12 sea & othetr transportation systemsamjune
 
Probabilisitc analysis of marine fuels in emission controlled areas
Probabilisitc analysis of marine fuels in emission controlled areasProbabilisitc analysis of marine fuels in emission controlled areas
Probabilisitc analysis of marine fuels in emission controlled areasKamal Kannan
 

What's hot (20)

Ship terminologies – organizations & chartering
Ship terminologies – organizations & charteringShip terminologies – organizations & chartering
Ship terminologies – organizations & chartering
 
1 dry cargo chartering
1 dry cargo chartering1 dry cargo chartering
1 dry cargo chartering
 
Laytime Linkedin
Laytime   LinkedinLaytime   Linkedin
Laytime Linkedin
 
Chartering concepts
Chartering conceptsChartering concepts
Chartering concepts
 
Glossary of shipping terms
Glossary of shipping termsGlossary of shipping terms
Glossary of shipping terms
 
Ship Construction- Ship Dimensions
Ship Construction- Ship DimensionsShip Construction- Ship Dimensions
Ship Construction- Ship Dimensions
 
Glossary of Port and Shipping Terms
Glossary of Port and Shipping TermsGlossary of Port and Shipping Terms
Glossary of Port and Shipping Terms
 
Shipping tonnages
Shipping tonnagesShipping tonnages
Shipping tonnages
 
Logistica y distribución glosario (1)
Logistica y distribución glosario (1)Logistica y distribución glosario (1)
Logistica y distribución glosario (1)
 
Transportation strategy
Transportation strategyTransportation strategy
Transportation strategy
 
Trident warrior advancing future capabilities through fleet experimentation
Trident warrior advancing future capabilities through fleet experimentationTrident warrior advancing future capabilities through fleet experimentation
Trident warrior advancing future capabilities through fleet experimentation
 
Shipping industry
Shipping industryShipping industry
Shipping industry
 
DEMURRAGE, DETENTION AND PER DIEM - WHAT IS THE DIFFERENCE?
DEMURRAGE, DETENTION AND PER DIEM - WHAT IS THE DIFFERENCE?DEMURRAGE, DETENTION AND PER DIEM - WHAT IS THE DIFFERENCE?
DEMURRAGE, DETENTION AND PER DIEM - WHAT IS THE DIFFERENCE?
 
Shipping industry planning, optimization & scheduling
Shipping industry planning, optimization & schedulingShipping industry planning, optimization & scheduling
Shipping industry planning, optimization & scheduling
 
Mr Ganguly - Shipping Agency
Mr Ganguly - Shipping AgencyMr Ganguly - Shipping Agency
Mr Ganguly - Shipping Agency
 
Time Charter vs Voyage Charter - 19 Nov 2014 - Capt. Richard Creet
Time Charter vs Voyage Charter - 19 Nov 2014 - Capt. Richard CreetTime Charter vs Voyage Charter - 19 Nov 2014 - Capt. Richard Creet
Time Charter vs Voyage Charter - 19 Nov 2014 - Capt. Richard Creet
 
UNDERSTANDING THE FREIGHT RATE SHEET
UNDERSTANDING THE FREIGHT RATE SHEETUNDERSTANDING THE FREIGHT RATE SHEET
UNDERSTANDING THE FREIGHT RATE SHEET
 
Jd 12 sea & othetr transportation system
Jd 12 sea & othetr transportation systemJd 12 sea & othetr transportation system
Jd 12 sea & othetr transportation system
 
Probabilisitc analysis of marine fuels in emission controlled areas
Probabilisitc analysis of marine fuels in emission controlled areasProbabilisitc analysis of marine fuels in emission controlled areas
Probabilisitc analysis of marine fuels in emission controlled areas
 
KSL Profile
KSL ProfileKSL Profile
KSL Profile
 

Similar to Name 457 maritime economics and management ship design

A practical approach for ship construction cost estimation
A practical approach for ship construction cost estimationA practical approach for ship construction cost estimation
A practical approach for ship construction cost estimationGopalakrishnan P
 
LV4_optimization_white_paper
LV4_optimization_white_paperLV4_optimization_white_paper
LV4_optimization_white_paperIan Zabel
 
Ship powering performance – learning from the challenges faced by owners
Ship powering performance – learning from the challenges faced by ownersShip powering performance – learning from the challenges faced by owners
Ship powering performance – learning from the challenges faced by ownersJohn Wills
 
DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...
DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...
DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...Alec Maclean
 
4. Joe Kraft, Minemax - Minemax Scheduler Applications
4. Joe Kraft, Minemax - Minemax Scheduler Applications4. Joe Kraft, Minemax - Minemax Scheduler Applications
4. Joe Kraft, Minemax - Minemax Scheduler ApplicationsKristy Marshall
 
Decision support system for petrobras ship scheduling
Decision support system for petrobras ship schedulingDecision support system for petrobras ship scheduling
Decision support system for petrobras ship schedulingJiayu Chen
 
Commercial Crew Program status-update-1-9-13
Commercial Crew Program status-update-1-9-13Commercial Crew Program status-update-1-9-13
Commercial Crew Program status-update-1-9-13Dmitry Tseitlin
 
LNG facilities with conceptual designing and construction support for Wind an...
LNG facilities with conceptual designing and construction support for Wind an...LNG facilities with conceptual designing and construction support for Wind an...
LNG facilities with conceptual designing and construction support for Wind an...KatthyLucas2100
 
Intelligent Decision Making Framework for Ship Collision Avoidance based on C...
Intelligent Decision Making Framework for Ship Collision Avoidance based on C...Intelligent Decision Making Framework for Ship Collision Avoidance based on C...
Intelligent Decision Making Framework for Ship Collision Avoidance based on C...Lokukaluge Prasad Perera
 
Intro to Marine Structures.pptx
Intro to Marine Structures.pptxIntro to Marine Structures.pptx
Intro to Marine Structures.pptxSameerAdnanAnsari
 
9 Essential services naval architects supply for the shipbuilding industry
9 Essential services naval architects supply for the shipbuilding industry9 Essential services naval architects supply for the shipbuilding industry
9 Essential services naval architects supply for the shipbuilding industryAlexandrą Maŋafu
 
energies-13-01758-v2 (1).pdf
energies-13-01758-v2 (1).pdfenergies-13-01758-v2 (1).pdf
energies-13-01758-v2 (1).pdfzeidali3
 
Optimal ship form based on artificial neural network10
Optimal ship form based on artificial neural network10Optimal ship form based on artificial neural network10
Optimal ship form based on artificial neural network10HussienMohamed40
 
Cost-Estimates-for-Surface-Mining.pdf
Cost-Estimates-for-Surface-Mining.pdfCost-Estimates-for-Surface-Mining.pdf
Cost-Estimates-for-Surface-Mining.pdfDarioVivancoHuaytara
 
4 Super Lightweight Tank - Risk Management
4 Super Lightweight Tank - Risk Management4 Super Lightweight Tank - Risk Management
4 Super Lightweight Tank - Risk Managementpmb25
 
ABIJU_Software _project _scheduling.pptx
ABIJU_Software _project _scheduling.pptxABIJU_Software _project _scheduling.pptx
ABIJU_Software _project _scheduling.pptxBVimala1
 
A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...
A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...
A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...IJERA Editor
 

Similar to Name 457 maritime economics and management ship design (20)

A practical approach for ship construction cost estimation
A practical approach for ship construction cost estimationA practical approach for ship construction cost estimation
A practical approach for ship construction cost estimation
 
LV4_optimization_white_paper
LV4_optimization_white_paperLV4_optimization_white_paper
LV4_optimization_white_paper
 
Ship powering performance – learning from the challenges faced by owners
Ship powering performance – learning from the challenges faced by ownersShip powering performance – learning from the challenges faced by owners
Ship powering performance – learning from the challenges faced by owners
 
DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...
DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...
DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...
 
4. Joe Kraft, Minemax - Minemax Scheduler Applications
4. Joe Kraft, Minemax - Minemax Scheduler Applications4. Joe Kraft, Minemax - Minemax Scheduler Applications
4. Joe Kraft, Minemax - Minemax Scheduler Applications
 
Decision support system for petrobras ship scheduling
Decision support system for petrobras ship schedulingDecision support system for petrobras ship scheduling
Decision support system for petrobras ship scheduling
 
Commercial Crew Program status-update-1-9-13
Commercial Crew Program status-update-1-9-13Commercial Crew Program status-update-1-9-13
Commercial Crew Program status-update-1-9-13
 
LNG facilities with conceptual designing and construction support for Wind an...
LNG facilities with conceptual designing and construction support for Wind an...LNG facilities with conceptual designing and construction support for Wind an...
LNG facilities with conceptual designing and construction support for Wind an...
 
Stabilty -2
Stabilty -2Stabilty -2
Stabilty -2
 
Intelligent Decision Making Framework for Ship Collision Avoidance based on C...
Intelligent Decision Making Framework for Ship Collision Avoidance based on C...Intelligent Decision Making Framework for Ship Collision Avoidance based on C...
Intelligent Decision Making Framework for Ship Collision Avoidance based on C...
 
Intro to Marine Structures.pptx
Intro to Marine Structures.pptxIntro to Marine Structures.pptx
Intro to Marine Structures.pptx
 
9 Essential services naval architects supply for the shipbuilding industry
9 Essential services naval architects supply for the shipbuilding industry9 Essential services naval architects supply for the shipbuilding industry
9 Essential services naval architects supply for the shipbuilding industry
 
energies-13-01758-v2 (1).pdf
energies-13-01758-v2 (1).pdfenergies-13-01758-v2 (1).pdf
energies-13-01758-v2 (1).pdf
 
Optimal ship form based on artificial neural network10
Optimal ship form based on artificial neural network10Optimal ship form based on artificial neural network10
Optimal ship form based on artificial neural network10
 
Cost-Estimates-for-Surface-Mining.pdf
Cost-Estimates-for-Surface-Mining.pdfCost-Estimates-for-Surface-Mining.pdf
Cost-Estimates-for-Surface-Mining.pdf
 
4 Super Lightweight Tank - Risk Management
4 Super Lightweight Tank - Risk Management4 Super Lightweight Tank - Risk Management
4 Super Lightweight Tank - Risk Management
 
ABIJU_Software _project _scheduling.pptx
ABIJU_Software _project _scheduling.pptxABIJU_Software _project _scheduling.pptx
ABIJU_Software _project _scheduling.pptx
 
Bio data dr elangovan
Bio data   dr elangovanBio data   dr elangovan
Bio data dr elangovan
 
A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...
A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...
A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...
 
Autoonomous vtol
Autoonomous vtolAutoonomous vtol
Autoonomous vtol
 

More from Military Institute of Science & Technology (MIST) (11)

Name 457 maritime economics and management payments
Name 457 maritime economics and management  paymentsName 457 maritime economics and management  payments
Name 457 maritime economics and management payments
 
Name 457 maritime economics and management 1
Name 457 maritime economics and management 1Name 457 maritime economics and management 1
Name 457 maritime economics and management 1
 
Name 409 pipes and piping
Name 409 pipes and pipingName 409 pipes and piping
Name 409 pipes and piping
 
Name 409 refrigeration and air conditioning
Name 409 refrigeration and air conditioningName 409 refrigeration and air conditioning
Name 409 refrigeration and air conditioning
 
Name 409 marine engineering ii steering system
Name 409 marine engineering ii steering systemName 409 marine engineering ii steering system
Name 409 marine engineering ii steering system
 
Name 479 5 sm
Name 479 5 smName 479 5 sm
Name 479 5 sm
 
Name 479 4 mm
Name 479 4 mmName 479 4 mm
Name 479 4 mm
 
Name 479 3 ob
Name 479 3 obName 479 3 ob
Name 479 3 ob
 
Name 479 2 hrm
Name 479 2 hrmName 479 2 hrm
Name 479 2 hrm
 
Name 479 1 pm
Name 479 1 pmName 479 1 pm
Name 479 1 pm
 
Gebs 101 finance & banking
Gebs 101 finance & bankingGebs 101 finance & banking
Gebs 101 finance & banking
 

Recently uploaded

9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 

Recently uploaded (20)

9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 

Name 457 maritime economics and management ship design

  • 1. NAME 457 Ship Economics and Management Part – 5: Economics in Ship Design Conducted by: Cdre M Muzibur Rahman, (E), psc, PhD, BN Cdre Muzib, psc, PhD
  • 3. The engineer is working with conflicting requirements Example • Physical – minimum weight • Economic – minimum cost • Social/Sociopolitical – maximum safety • Environmental/Polution – minimum impact • Commercial – maximum efficiency • Esthetic – maximum stylishness • Etc. Cdre Muzib, psc, PhD The engineer resolves these conflicts and searches for “optimum” solutions in the design process.
  • 4. Ship design is solving a problem with many VARIABLES. It is an ITERATIVE process. Prior to 1970, designers used The DESIGN SPIRAL. Ship Design Methodology Cdre Muzib, psc, PhD DESIGN SPIRAL: • Hull form • Appropriate dimensions • Hull prismatic coefficients • Power estimates • Weight estimates - Hull - Machinery - Outfitting • Deadweight capacity
  • 5. Design Spiral: J H Evans (1959) introduced the concept of design spiral, which represents the sequential and iterative aspects of the process Ship Design Methodology Cdre Muzib, psc, PhD
  • 6. Buxton (1972), introduced the economical aspects in ship design Andrews (1981), added the time dimension in Buxton design model Ship Design Methodology Cdre Muzib, psc, PhD
  • 7. Taggart 1980 Ship Design Methodology Cdre Muzib, psc, PhD
  • 8. Taggart 1980 Ship Design Methodology Cdre Muzib, psc, PhD Find out the cost of design for the man-hour cost of Tk 75.00
  • 9. Ship Design Methodology Levander and Papanikolaou 2009 Cdre Muzib, psc, PhD
  • 10. Time Scale of Ship Design Stages Cdre Muzib, psc, PhD
  • 11. Economical aspect of Ship dimensioning Cdre Muzib, psc, PhD
  • 12. • Parametric Studies – The independent variables are obtained by variation between the lower and upper limits assumed – Require more computing time when the number of design variables is high – No guarantees that the solution found is the optimal • Optimization Methods – The independent variables are obtained from an optimization algorithm – Possible to find a better and faster solution – Only provides information about the optimal point found (single objective methods) Determination of the Design Variables Cdre Muzib, psc, PhD
  • 13. Size of ship is determined by number of physical restrictions. Few of them are: Shipbuilding facilities Docking and undocking capacity Shallow water en route / Canal /Straights Conditions of loading and unloading ports Cargo type and availability Cdre Muzib, psc, PhD Computers permit multiple criteria – multi variate search patterns. “New ships should be • 25% novelty • 75% well proven practice.” - Baker
  • 14. Cdre Muzib, psc, PhD Economic Analysis
  • 15. MARINE COST ESTIMATING Marine cost estimating is not an exact science. It has grown through application of methods and historical data. It is an area where significant improvement would help all shipyards as it is really pricing of estimated quantities of raw material and equipment. World class shipyards use parametric estimating plans and in most shipyards, Engineering is very involved in the estimating process, usually responsible for material take-off and definition of system design and associated equipment. Cdre Muzib, psc, PhD
  • 16. MARINE COST ESTIMATING In addition, Engineering must estimate how much man hours and material it will require to design and build the ship. Because of the time and cost of preparing estimates, shipbuilders usually are selective on what the will bid on. Most shipyards management have a "Bid- No Bid" meeting for each invitation to bid. Bid decision is based on: - ongoing work - product fit to facilities and capabilities - extent of competition Cdre Muzib, psc, PhD
  • 17. Cdre Muzib, psc, PhD Bottom-up Cost Estimation: Most detailed methods of estimating the ship building costs and are sometimes referred to as grass root or engineering build up estimating. These methods are only valid after the design has reached a level of significant technical maturity. It would have been a subject of accounting where the material cost of every parts and their assembly or labor cost is known and summarized to a total shipbuilding cost by the estimator. Bottom-up estimations may be based on drawings, bills of materials, historical vendor costs, and existing quotes. Top-down Cost Estimation: Also called analogous methods or extrapolation models. These methods are based on the comparison and extrapolation of known data from objects, in this case ships with a satisfying technical similarity are considered. These methods are used in the earliest design phases like concept design and preliminary design where there is less detailed information available. Top-down methods are used when the amount of information available are enough to recognize a similarity to previous objects. It is up to the estimator to judge whether a new-building project has unique design characteristics or if it is comparable to historical data. Some top-down methods therefore rely on “expert judgments”. Methods of Estimating shipbuilding Cost
  • 18. Cdre Muzib, psc, PhD Parametric Cost Estimation: Between the global top-down methods and the accounting bottom-up methods we find parametric cost estimation. The basis for parametric cost estimation methods is the use of cost estimating relationships (CER). CERs are mathematical expressions or formulas relating cost as the dependent variable to selected, independent cost-driving variables. These relations between costs and relevant parameters are based on regression of historical data. “The implicit assumption of parametric cost estimating is that the same forces that affected cost in the past will affect cost in the future”. If the CERs calculate the total cost based on global parameters like length overall (LOA) or deadweight (DWT), some would call this a top-down approach. The opposite would be if costs of every little subsystem were found by CERs and then used an accounting bottom- up approach. In reality, most parametric cost estimation methods are considered closest to top-down methods because of the independent cost drivers chosen and the use of parametric estimation in early phases of design. Methods of Estimating shipbuilding Cost
  • 20. Cdre Muzib, psc, PhD Fig. 24 Optimal Ship Size Page 97 (Buxton 1976)
  • 21. Cdre Muzib, psc, PhD Optimal Ship Speed Page 98 (Buxton 1976)
  • 22. Cdre Muzib, psc, PhD Fig. 25 Optimal Ship Speed Page 99 (Buxton 1976)
  • 23. Factors influencing higher optimal speed : Economic Cdre Muzib, psc, PhD
  • 24. Factors influencing higher optimal speed :Technical Cdre Muzib, psc, PhD
  • 27. Economic Measures of Merit • Initial ship cost – The initial ship cost is not by itself a good indicator, some design options only become economically advantageous on the long run. • Other criteria can be used considering running costs of the ship along its entire operational life • The most common measures are: – Required Freight Rate (RFR) – Net Present Value (NPV) – Internal Rate of Return (IRR) – Modified Internal Rate of Return (MIRR) • To evaluate these criteria the knowledge of the typical ship voyage is required. Cdre Muzib, psc, PhD
  • 28. • The specification of the typical ship voyage allows a more comprehensive analysis of the economic aspects. • It may include: – The number of ports visited during the round trip – The distance between ports – The cargo-handling capabilities available and the corresponding handling rates and costs – Port fees and taxes Economic Measures of Merit Cdre Muzib, psc, PhD
  • 29. • Ship Acquisition Cost • Costs in Shipping Ship Economics: Cost Estimating • Ship Acquisition Cost: Initial Investment, I =Q⋅ (1+ Ka) with: Q: Ship acquisition cost = (CH + CE + CM + CX) (1 + Kb ) CH : Hull/Steel Cost, CE : Equipment (Nav/Comm/Domestic) Cost CM : Machinery (propulsion/auxiliary) Cost, CX : Special Equipment (survey/surveilance/rescue) Cost Ka : Owner’s expenses during shipbuilding and acquisition, expressed as percentage of the acquisition cost, generally of about 5 – 15%. Kb : Profit Margin of the shipyard, in percentage Cdre Muzib, psc, PhD
  • 30. This value can be estimated as follows: 1. Estimate the shipbuilding cost of a reference ship (QR) by the previous expressions 2. Obtain the actual ship cost from the current market (QM) 3. The nominal profit margin can then be obtained by: If the Kb value is too low or too high, for instance, outside of the interval [-30%, +30%] the cost formulas should be reviewed and updated. Profit Margin of the Shipyard Cdre Muzib, psc, PhD
  • 31. 3 / 2 3 . .   V k WM Machinery Weight:   . . 5 . 0 V k WS Hull Steel Weight: 4 / 3 9 . 0 . .   V k WE Equipment Weight: Light Ship Weight for cost estimation Cdre Muzib, psc, PhD
  • 32. 1. Methods that consider the weights as function of the main characteristics of the hull • Appropriate to be used in processes for the optimization of the main dimensions 2. Methods based on the existence of data from existing ships – More precise estimates – Results not satisfactory when dealing with new types of ships 3. Methods based on surfaces. – When the hull form, the general arrangement and the subdivision are already roughly known 4. Methods based on the midship section modulus. – Based on the scantlings of the midship section Methods to Estimate the Hull Weight Cdre Muzib, psc, PhD
  • 33. • Most estimate methods consider separately the weights of the hull and of the superstructure • For the purpose of cost estimation, the hull weight should be subdivided into: – Weight of structural steel (hull structure) – Weight of outfit steel (foundations, ladders, steps, etc.) • Each of these components should be subdivided into: – Weight of plates – Weight of stiffeners • For the purpose of cost estimation, and due to the waste from the cutting process, margin/factor should be used: Gross Steel Weight = 1.08 ~ 1.12 x Net Steel Weight Methods to Estimate the Hull Weight Cdre Muzib, psc, PhD
  • 34. Hull Weight estimation From statistical analysis regression Cdre Muzib, psc, PhD D’Almeida (2009) Cudina et al (2010) [Tanker and bulk carrier] f1 – reduction of hull weight due to use of high tensile steel
  • 35. Cdre Muzib, psc, PhD Propulsion Machinery Weight estimation From statistical analysis regression
  • 36. Cdre Muzib, psc, PhD Equipment weight estimation from statistical analysis regression D’Almeida (2009) Cudina et al (2010) [Tanker and bulk carrier] The coefficients k1 and k2 are characteristic of each ship type, obtained from statistical regression analysis
  • 38. Ship Acquisition: Hull Steel Cost Cdre Muzib, psc, PhD
  • 39. Ship Acquisition : Equipment Cost Cdre Muzib, psc, PhD
  • 44. Ship Acquisition : Machinery Cost Cdre Muzib, psc, PhD
  • 45. Ship Acquisition Cost (Alternative) Total cost, CT = CH + CE + CM + GE + S + EC with: CH - Cost of hull CE - Cost of equipment CM - Cost of machinery GE - General expenses (about 90% labor cost) S - Profit of the shipyard (about 5% labor cost) EC - Extra Costs Each component can be divided into two parts: - cost of materials or equipments, and - labor cost. Cdre Muzib, psc, PhD
  • 46. Costs in Shipping Operating cost - expenses involved in day-to-day running of the ship: essentially costs for crew, stores and maintenance. Periodic maintenance cost - incurred when the ship is dry- docked for major repairs, usually at the time of its special survey. In older ships this may involve considerable expenditure, so shipping companies often include a ‘dry- docking provision’ in their operating costs. Voyage cost - variable costs associated with a specific voyage and include such items as fuel, port charges and canal dues. Capital cost - depend on how the ship is financed. They may take the form of dividends to equity or interest and capital payments on debt finance. Cargo handling cost - expenses of loading, stowing and discharging cargo. Cdre Muzib, psc, PhD
  • 47. Costs in Shipping: Crew Costs Crew cost includes basic salaries and wages, social insurance, repatriation expenses, victuals, recruitment and training and others Cdre Muzib, psc, PhD
  • 48. Costs in Shipping: Crew Complements Cdre Muzib, psc, PhD
  • 49. Complement: The term “complement” is used to describe the number of people who will be manning the ship. This is an important variable when predicting the size or complexity of the vessels because the distance between ports increases the space needed to store supplies and waste. Cdre Muzib, psc, PhD
  • 50. Costs in Shipping: Stores Costs Cdre Muzib, psc, PhD
  • 51. Costs in Shipping: Maintenance Costs Cdre Muzib, psc, PhD
  • 52. Costs in Shipping: Insurance Costs Cdre Muzib, psc, PhD
  • 53. Costs in Shipping: Admin Costs Cdre Muzib, psc, PhD
  • 54. Costs in Shipping: Docking Costs Cdre Muzib, psc, PhD
  • 55. Costs in Shipping: Voyage Costs Variable costs associated to a specific voyage CVOY = CFO + CPD + CTP + CD with: CFO – fuel costs for main and auxiliary machinery CPD – port and light dues CTP – tug and pilotage costs CD – canal dues SFC for Medium-speed diesel engines = 0.200~0.250 [kg/kW.h] Cdre Muzib, psc, PhD
  • 56. Costs in Shipping: Cargo Handling Costs CCH = CLOAD + CDISC + CCLM with: CLOAD – cargo loading charges CDISC – cargo discharge costs CCLM – allowance for cargo claims Information about charge/discharge rates can be generally obtained from the Internet sites of the ports. Cdre Muzib, psc, PhD