SlideShare a Scribd company logo
1 of 38
REMEDIES FOR
BREACH OF
CONTRACT
BY:
Liew wei zhean 0331225
Loh mun tong 0323680
Remedies available to the innocent party
2
Damages
Specific
Performance
Injunction Quantum Merit
BREACH OF CONTRACT
1.
DAMAGES
3
Contracts Act 1950 - Section 74 (1)
Compensation for loss or damage caused by breach of contract
Hadley v. Baxendale
Direct loss + Indirect loss
4
❏ Arises from the natural
course of events
❏ Consequential damages
❏ Contemplated by the
parties
Contracts Act 1950 - Section 74, 75 & 76
A remedy providing money compensation for a civil wrong with the aim
to restore the injured party to the position he would have enjoyed had the
contract been performed as agreed.
▣ Injured party is entitled to damages arising naturally
▣ If the injured party claims for special damages, he must made known
to the other party, at the time of making the contract, that the special
loss is likely to result from the breach (Must not be too remote)5
Agnes contracts to repair Becky’s toilet in a certain manner and receives payment in
advance. Agnes repairs the toilet but not according to contract. Becky is entitled to
recover from Agnes the cost of making the repairs conform to the contract.
6
Expectation:
contract Reality: work done
7
Breach of contract in construction
▣ When one party fails to perform the complete performance of the
contract conditions and he has no legal excuse for the non-performance.
▣ Innocent party may decide to continue with the contract or treat the
contract as discharged
▣ If the contract is not discharged (innocent party choose to continue or
breach is one that cannot discharge the contract), innocent party may
recover damages (subject to some rules on recoverable monetary loss)
8
A contract provides maintenance works to a building for 2 years at
RM10,000 a month. After 10 months, the sum owing to contractor is
RM50,000.
Option A Option B
example
Keep the
contract alive
End the
contract
9
example
Option a option b
Sues for RM 50,000
Sues for RM 50,000
+
Loss of profits from
remaining months
10
a. Bringing contract to an end (repudiation of
contract)
1. Where one party refuses to continue with his contractual
obligations
▣ Contractor removes all his plants, materials and labour from the site
before completion and show no intention to return to complete the work.
11
2. Where the breach committed by one party goes 'of the root' of
the contract.
▣ Employer repeatedly fails to pay on the interim certificates properly
issued by the Architect.
Brani Readymixed Pte Ltd v. Yee Hong Pte Ltd (1995)
C Norman Peterson Co v. Container Corporation of America (1985)
12
B. Breach which does not discharge a contract
▣ Employer delays in giving the contractor site possession or reasonable
access to the Works
Carr v. JA Berriman Pty Ltd (1953)
▣ Employer fail to issue timely instructions for the execution of Works
Roberts v. Bury Commissioners (1870)
13
B. Breach which does not discharge a contract
▣ Employer fails to nominate specialist sub-contractors in a timely manner.
▣ Ar and QS fails to evaluate claims submitted by the contractor within the
specified time or the employer fails to pay in accordance with the terms
of contract
▣ Disruptions caused by other contractors employed directly by the
Employer.
14
Computation of damages
▣ Actual monetary loss.
▣ Innocent party should be restored to the position he would have been in
had the other party performed his obligation.
▣ Additional damages such as loss of profits and rents will depend on the
rules of remoteness.
15
Remoteness and causation
▣ Party claiming for damages for breach of contract must prove that
damage was caused by breach.
Popular Industries Ltd v Eastern Garment Manufacturing Sdn Bhd (1990)
16
Remoteness and causation
Contracts Act 1950 - Section 74:
Compensation for loss or damage caused by breach of contract
1. When a contract has been broken, the party who suffers by the breach is entitled to
receive, from the party who has broken the contract, compensation for any loss or
damage caused to him thereby, which naturally arose in the usual course of things
from the breach, or which the parties knew, when they made the contract, to be likely
to results from the breach of it
17
Remoteness and causation
Contracts Act 1950 - Section 74:
Compensation for loss or damage caused by breach of contract
1. Such compensation is not to be given for any remote and indirect loss or damage
sustained by reason of the breach
18
Mitigation for damages
▣ Innocent party must take all reasonable steps to mitigate his loss -
DUTY OF MITIGATION
Kabatasan Timber Extraction Co v. Chong Fah Shing [1969]
2.
SPECIFIC PERFORMANCE
EQUITABLE REMEDY
19
SPECIFIC PERFORMANCE
▣ A court order directing a party to perform the terms of contract. (to do exactly what the
party has promised in contract)
▣ Under Section 11 of the Specific Relief Act,1950
▣ Specific performance is a discretionary remedy. Court will refuse specific performance
where the granting will cause undue hardship to the defendant.
Section 11(1): Specific performance may be granted by the court in the following situations
❏ When the act agreed to be done is in the performance, wholly or partly of a trust
❏ When there is no standard for determining the actual damage caused by the
non-performance of the act agreed to be done
20
Example:
An art collector promised to sell one piece of art collection as shown to
MR.BLUE and them two make a legal sales contract. However, the collector
then decides that he’d rather keep the piece for now. The collector breaches
his contract with MR.BLUE. The Court decides that the piece of art is truly
priceless and MR.BLUE can’t acquire another comparable piece no matter
how much money the court awards her. Instead the court decides that the
collector should comply with the terms of contract and sell the piece to
MR.BLUE for the price he already agreed in the contract.
21
SPECIFIC PERFORMANCE
BuyerSeller
3.
INJUNCTION
EQUITABLE REMEDY
22
INJUNCTION
❏ court order instructing a defendant not to commit some act.
❏ Interlocutory injunction is granted at the discretion of the court to preserve the status quo
pending the resolution of a legal action..
Type of Injunction
23
For Specific Purpose03
● To enter into defendant's premises to search
and seize article with relevenance case
Mandatory Injunction(Must Do)02
● To prevent someone to do something which
he ordinary has no obligation to do
Prohibitory Injunction(Not to do)01
● Prevent someone from doing something
which he ordinary has the right to do
4.
QUANTUM MERUIT
24
QUANTUM MERUIT
❏ Quantum meruit is a claim for payment for work executed where no
price has been agreed or quantified, and usually a being assessed in a
❏ ‘reasonable sum’,
❏ ‘reasonable remuneration’,
❏ ‘fair market rates’,
❏ ‘fair commercial rates’ or on similar terms.
❏ Quantum meruit means ‘the amount of deserves’ or ‘what the job is
worth’
❏ Found under Section 71 of the Contract Act 1950
25
QUANTUM MERUIT
Arise under 6 circumstances: -
1. Where the contract is silent on how completed work is to be paid. For example contractor
incurred additional expenses due to a major change in the quantity of the work which
suppose to be carried out and paid but not existing in the contract.
Case law: Parkinson v Commissioners of Works (1949)
The contractor had agreed to carried out certain work on a cost plus profits basis subject
to the total profit recoverable limit. And the commissioners of the work was entitled to
instruct works up to 5 million under the contract but the instruced actual work up to
6.6million, thus exceeding the contract value. The court of appeal found that the
additional work was outside the contract and thus the contractor was entitled to be
paid on a quantum meruit basis, which is beyond the total fixed profit under the
contract. 26
QUANTUM MERUIT
2. Where parties to a contract proceed on the mistake basis that there is an
enforceable contract, but later found out that there is no valid contract.
Case Law: Ayer Itam Tin Dredging Malaysia Bhd v YC Chin Enterprise Sdn
Bhd (1994)
The parties are still negotiating and didnt intend to bound until a formal
contract was made. The letter of intent did not form a bound contract at law
but was only to record terms agreed by the parties as a basis for contract
negotiation. As on the question of compensation for the work done prior to the
dispute, the judge held that a claim on a quantum meruit basis for the
preliminary work carried out on the site was successful but was subject to max
limit RM300,000
27
QUANTUM MERUIT
3.Where one party requested the other for services which are not provided or
governed by any contract.
Case Law: Constain Civil Engineering Ltd v Zanen Dredging & Contracting Co
(1997)
The instruction given did not constitute authorized variations of the subcontract
works because they required the works to be work which are outside the scope
of the subcontract which entitling the subcontractor to payment on a
quantum meruit basis.
28
QUANTUM MERUIT
29
4. Where the contract has been discharged by the operation of the doctrine of
frustration.
Case law: BP EXploration Co ( Libya) v Hunt (No 2) (1982)
BP entered an agreement with Hunt, under which BP would explore and
develop his oil concession in Libya at their own expense. This expenditure
would be recoverable from Hunt’s share of the profits when the field
produced oil. After oil production began, the parties would share both
production and development costs. Oil came on stream in 1967 but in 1971
the Libyan government capture BP’s interest. BP had not received all its initial
expenditure from Hunt’s share, and claimed a just sum under s1 Law Reform
(Frustrated Contracts) Act 1943.
(Change of Government ‘Politic’)
QUANTUM MERUIT
30
5. Where the contract has been repudiated by the Employer and the Contractor
choose to claim for damages for breach of contract or quantum meruit in restitution
for the work performed.
Case Law: Renard Construction Ltd v Minister of Public Works (1992)
The court held that a claim in quantum meruit following a wrongful
termination should be quantified on reasonable remuneration basis, not
value of work done basis.
QUANTUM MERUIT
31
6. Where the contract contains an expressed agreement to pay reasonable sum or
on similar term.. For example, Clause 11 - Variation, Clause 11.7 - Additional
expenses or loss and/or expense cause by variation, Clause 24.0 - Loss and Expense.
Case Law: Laserbore Ltd v Morrison Biggs Wall Ltd (1993)
The learned Judge in deciding the meaning of the term ‘fair and reasonable
payments for all works executed’, considered that the cost-plus-profits basis
was wrong principle however sometimes it may produce right result. The
Judge held that in assessing quantum meruit claim the appropriate approach
was to adopt general market rates or fair commercial rate.
Q & A
What are the 2 limbs mentioned by the case of
hadley V. BAXENDALE?
33
WHAT ARE THE REMEDIES AVAILABLE TO THE CONTRACTOR IF
ISSUE OF NON-PAYMENT BY EMPLOYER ARISE ?
34
▣ The contractor can suspend execution of works until such time payment is made
(Clause 30.7)
▣ The contractor can claim interest on unpaid amount (Clause 30.17)
▣ If non-payment persists, the contractor can terminate his own employment (Clause
26.1(a))
▣ Construction Industry Payment and Adjudication Act (CIPAA)
WHAT IS A DIFFERENCES BETWEEN NORMAL
CONTRACT AND QUASI CONTRACT?
35
CONTRACT QUASI CONTRACT
A legally enforceable agreement made
between two parties
An unintended contractual relationship
between two parties created and enforced
by the court
BREACH OF CONTRACT UNJUST ENRICHMENT
DAMAGES QUANTUM MERUIT
Any legal rule need to be follow when assessing reasonable sum?
Based on guidance is given in the fifth edition of Keating on Construction Contracts, at page
80:
▣ The courts have laid down no rules limiting the way in which a reasonable sum is to
be assessed.
▣ The contractor should be paid at a fair commercial rate for the work done.
▣ Useful evidence in any particular case may include abortive negotiations as to
price, a calculation based on the net cost of labour and materials used
plus a sum for overheads and profit, measurements of work done and
materials supplied, and the opinion of quantity surveyors, experienced
builders or other experts as to a reasonable sum.36
Any legal rule need to be follow when assessing reasonable sum?
▣ Case Law: Laserbore Ltd v Morrison Biggs Wall Ltd (1993)
▣ The Judge say that cost-plus-profits basis wrong approach, and the
appropriate approach was to adopt general market rates or fair commercial
rates.
37
THANK YOU
38

More Related Content

What's hot

Breach of contract
Breach of contractBreach of contract
Breach of contractAkshay Jain
 
Offer and acceptance
Offer and acceptanceOffer and acceptance
Offer and acceptanceGurjit
 
Damages Presentation
Damages PresentationDamages Presentation
Damages Presentationiharbottle
 
Breach of Contract & Remedies
Breach of Contract & RemediesBreach of Contract & Remedies
Breach of Contract & RemediesMereia Kali
 
Meaning and Types of Offer
Meaning and Types of OfferMeaning and Types of Offer
Meaning and Types of OfferRajaKrishnan M
 
Contract law - Remedies
Contract law - RemediesContract law - Remedies
Contract law - RemediesMaliza Eza
 
Bailment and pledge
Bailment and pledgeBailment and pledge
Bailment and pledgeNcell
 
Topic 3. Actionable claim
Topic 3. Actionable claimTopic 3. Actionable claim
Topic 3. Actionable claimGagan
 
Termination of contract
Termination of contractTermination of contract
Termination of contractNcell
 
Performance of contracts
Performance of contractsPerformance of contracts
Performance of contractsBabasab Patil
 
Bailment, Pledge and Hypothecation
Bailment, Pledge and HypothecationBailment, Pledge and Hypothecation
Bailment, Pledge and HypothecationShivani Sharma
 
Performance of contract
Performance of contractPerformance of contract
Performance of contractRashmi Dubey
 
Contract Act 1872 - Business Law
Contract Act 1872 - Business LawContract Act 1872 - Business Law
Contract Act 1872 - Business LawFaHaD .H. NooR
 
Doctrine of caveat emptor - Legal Environment of Business - Business Law - Co...
Doctrine of caveat emptor - Legal Environment of Business - Business Law - Co...Doctrine of caveat emptor - Legal Environment of Business - Business Law - Co...
Doctrine of caveat emptor - Legal Environment of Business - Business Law - Co...manumelwin
 
Wagering agreements
Wagering agreementsWagering agreements
Wagering agreementsHimani Gupta
 

What's hot (20)

Breach of contract
Breach of contractBreach of contract
Breach of contract
 
Offer and acceptance
Offer and acceptanceOffer and acceptance
Offer and acceptance
 
Breach of contract
Breach of contractBreach of contract
Breach of contract
 
Damages Presentation
Damages PresentationDamages Presentation
Damages Presentation
 
Breach of Contract & Remedies
Breach of Contract & RemediesBreach of Contract & Remedies
Breach of Contract & Remedies
 
Discharge of contract
Discharge of contractDischarge of contract
Discharge of contract
 
Meaning and Types of Offer
Meaning and Types of OfferMeaning and Types of Offer
Meaning and Types of Offer
 
Contract law - Remedies
Contract law - RemediesContract law - Remedies
Contract law - Remedies
 
Bailment and pledge
Bailment and pledgeBailment and pledge
Bailment and pledge
 
Topic 3. Actionable claim
Topic 3. Actionable claimTopic 3. Actionable claim
Topic 3. Actionable claim
 
Contract act.ppt
Contract act.pptContract act.ppt
Contract act.ppt
 
Termination of contract
Termination of contractTermination of contract
Termination of contract
 
Performance of contracts
Performance of contractsPerformance of contracts
Performance of contracts
 
Bailment, Pledge and Hypothecation
Bailment, Pledge and HypothecationBailment, Pledge and Hypothecation
Bailment, Pledge and Hypothecation
 
Performance of contract
Performance of contractPerformance of contract
Performance of contract
 
Contract Act 1872 - Business Law
Contract Act 1872 - Business LawContract Act 1872 - Business Law
Contract Act 1872 - Business Law
 
Doctrine of caveat emptor - Legal Environment of Business - Business Law - Co...
Doctrine of caveat emptor - Legal Environment of Business - Business Law - Co...Doctrine of caveat emptor - Legal Environment of Business - Business Law - Co...
Doctrine of caveat emptor - Legal Environment of Business - Business Law - Co...
 
Wagering agreements
Wagering agreementsWagering agreements
Wagering agreements
 
Privity of Contract
Privity of ContractPrivity of Contract
Privity of Contract
 
Contingent contracts
Contingent contractsContingent contracts
Contingent contracts
 

Similar to Remedies for Breach of Contract

Construction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractConstruction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractPang Khai Shuen
 
Building contract introduction
Building contract  introductionBuilding contract  introduction
Building contract introductionHafizul Mukhlis
 
Breach of contract
Breach of contractBreach of contract
Breach of contractFaisal Noman
 
Contract Law II Group Assignment Presentation
Contract Law II Group Assignment PresentationContract Law II Group Assignment Presentation
Contract Law II Group Assignment PresentationTineshvaar
 
Construction law lecture 10
Construction law lecture 10Construction law lecture 10
Construction law lecture 10Jessyca Than
 
Remedies Of Breach of contract(law)
Remedies Of Breach of contract(law)Remedies Of Breach of contract(law)
Remedies Of Breach of contract(law)Kavya Rawat
 
9. SPECIFIC PERFORMANCE.ppt
9. SPECIFIC PERFORMANCE.ppt9. SPECIFIC PERFORMANCE.ppt
9. SPECIFIC PERFORMANCE.pptNikNurainFaqihah
 
Specific performance
Specific performanceSpecific performance
Specific performanceUmmi Rahimi
 
Damages under the Contract Act 1872
Damages under the Contract Act 1872Damages under the Contract Act 1872
Damages under the Contract Act 1872Arpeeta Shams Mizan
 
Dispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxDispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxPujanNeupane6
 
Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Laina Chan
 
10)Breach of Contract.pptx
10)Breach of Contract.pptx10)Breach of Contract.pptx
10)Breach of Contract.pptxQaisariqbal38
 
Substitute and vicarious_performance
Substitute and vicarious_performanceSubstitute and vicarious_performance
Substitute and vicarious_performanceHafizul Mukhlis
 
Contract act breach of contract
Contract act   breach of contractContract act   breach of contract
Contract act breach of contractMoazzam Habib
 
Breach of contract law
Breach of contract lawBreach of contract law
Breach of contract lawAjit Kumar
 
WORKSHOP 2 FIRM B1 MORTGAGES.pptx
WORKSHOP 2 FIRM B1 MORTGAGES.pptxWORKSHOP 2 FIRM B1 MORTGAGES.pptx
WORKSHOP 2 FIRM B1 MORTGAGES.pptxAchanCynthia
 
Remedies of Contract Law | Main Principles
Remedies of Contract Law | Main PrinciplesRemedies of Contract Law | Main Principles
Remedies of Contract Law | Main Principlessahansathsarawegiriy1
 
1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docxSONU61709
 
Rescission for Breach
Rescission for BreachRescission for Breach
Rescission for BreachWyeNye
 

Similar to Remedies for Breach of Contract (20)

Construction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractConstruction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of Contract
 
Building contract introduction
Building contract  introductionBuilding contract  introduction
Building contract introduction
 
Breach of contract
Breach of contractBreach of contract
Breach of contract
 
Contract Law II Group Assignment Presentation
Contract Law II Group Assignment PresentationContract Law II Group Assignment Presentation
Contract Law II Group Assignment Presentation
 
Construction law lecture 10
Construction law lecture 10Construction law lecture 10
Construction law lecture 10
 
Remedies Of Breach of contract(law)
Remedies Of Breach of contract(law)Remedies Of Breach of contract(law)
Remedies Of Breach of contract(law)
 
9. SPECIFIC PERFORMANCE.ppt
9. SPECIFIC PERFORMANCE.ppt9. SPECIFIC PERFORMANCE.ppt
9. SPECIFIC PERFORMANCE.ppt
 
Specific performance
Specific performanceSpecific performance
Specific performance
 
Damages under the Contract Act 1872
Damages under the Contract Act 1872Damages under the Contract Act 1872
Damages under the Contract Act 1872
 
Dispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxDispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptx
 
Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016
 
The specific relief act
The specific relief act The specific relief act
The specific relief act
 
10)Breach of Contract.pptx
10)Breach of Contract.pptx10)Breach of Contract.pptx
10)Breach of Contract.pptx
 
Substitute and vicarious_performance
Substitute and vicarious_performanceSubstitute and vicarious_performance
Substitute and vicarious_performance
 
Contract act breach of contract
Contract act   breach of contractContract act   breach of contract
Contract act breach of contract
 
Breach of contract law
Breach of contract lawBreach of contract law
Breach of contract law
 
WORKSHOP 2 FIRM B1 MORTGAGES.pptx
WORKSHOP 2 FIRM B1 MORTGAGES.pptxWORKSHOP 2 FIRM B1 MORTGAGES.pptx
WORKSHOP 2 FIRM B1 MORTGAGES.pptx
 
Remedies of Contract Law | Main Principles
Remedies of Contract Law | Main PrinciplesRemedies of Contract Law | Main Principles
Remedies of Contract Law | Main Principles
 
1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx
 
Rescission for Breach
Rescission for BreachRescission for Breach
Rescission for Breach
 

More from Arissa Loh

Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final ReportArissa Loh
 
Value Management Group Assignment
Value Management Group AssignmentValue Management Group Assignment
Value Management Group AssignmentArissa Loh
 
Project Management Individual Assignment
Project Management Individual AssignmentProject Management Individual Assignment
Project Management Individual AssignmentArissa Loh
 
Project Management Group Assignment Final Report
Project Management Group Assignment Final ReportProject Management Group Assignment Final Report
Project Management Group Assignment Final ReportArissa Loh
 
Project Management Presentation Slides
Project Management Presentation SlidesProject Management Presentation Slides
Project Management Presentation SlidesArissa Loh
 
Be De Workshop Cost Appraisal
Be De Workshop Cost AppraisalBe De Workshop Cost Appraisal
Be De Workshop Cost AppraisalArissa Loh
 
Financial Management Final Report
Financial Management Final ReportFinancial Management Final Report
Financial Management Final ReportArissa Loh
 
CSI Presentation Slides
CSI Presentation SlidesCSI Presentation Slides
CSI Presentation SlidesArissa Loh
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Arissa Loh
 
BE slides presentation
BE slides presentationBE slides presentation
BE slides presentationArissa Loh
 
PP2 final report
PP2 final reportPP2 final report
PP2 final reportArissa Loh
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808Arissa Loh
 
Professional Practice 1 Presentation Slides
Professional Practice 1 Presentation SlidesProfessional Practice 1 Presentation Slides
Professional Practice 1 Presentation SlidesArissa Loh
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportArissa Loh
 
Measurement 4 presentation slides
Measurement 4 presentation slidesMeasurement 4 presentation slides
Measurement 4 presentation slidesArissa Loh
 
Pp1 group presentation
Pp1 group presentation  Pp1 group presentation
Pp1 group presentation Arissa Loh
 
Tender Presentation
Tender PresentationTender Presentation
Tender PresentationArissa Loh
 
Int. ceiling finishes
Int. ceiling finishesInt. ceiling finishes
Int. ceiling finishesArissa Loh
 
Software Presentation Slides
Software Presentation SlidesSoftware Presentation Slides
Software Presentation SlidesArissa Loh
 

More from Arissa Loh (20)

Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
 
Value Management Group Assignment
Value Management Group AssignmentValue Management Group Assignment
Value Management Group Assignment
 
Project Management Individual Assignment
Project Management Individual AssignmentProject Management Individual Assignment
Project Management Individual Assignment
 
Project Management Group Assignment Final Report
Project Management Group Assignment Final ReportProject Management Group Assignment Final Report
Project Management Group Assignment Final Report
 
Project Management Presentation Slides
Project Management Presentation SlidesProject Management Presentation Slides
Project Management Presentation Slides
 
Be De Workshop Cost Appraisal
Be De Workshop Cost AppraisalBe De Workshop Cost Appraisal
Be De Workshop Cost Appraisal
 
Financial Management Final Report
Financial Management Final ReportFinancial Management Final Report
Financial Management Final Report
 
CSI Presentation Slides
CSI Presentation SlidesCSI Presentation Slides
CSI Presentation Slides
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1
 
BE slides presentation
BE slides presentationBE slides presentation
BE slides presentation
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 
Professional Practice 1 Presentation Slides
Professional Practice 1 Presentation SlidesProfessional Practice 1 Presentation Slides
Professional Practice 1 Presentation Slides
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Measurement 4 presentation slides
Measurement 4 presentation slidesMeasurement 4 presentation slides
Measurement 4 presentation slides
 
Pp1 group presentation
Pp1 group presentation  Pp1 group presentation
Pp1 group presentation
 
Tender Presentation
Tender PresentationTender Presentation
Tender Presentation
 
Int. ceiling finishes
Int. ceiling finishesInt. ceiling finishes
Int. ceiling finishes
 
Software Presentation Slides
Software Presentation SlidesSoftware Presentation Slides
Software Presentation Slides
 
Software Report
Software ReportSoftware Report
Software Report
 

Recently uploaded

Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸mathanramanathan2005
 
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...marjmae69
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@vikas rana
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxmavinoikein
 
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)Basil Achie
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSebastiano Panichella
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...NETWAYS
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfhenrik385807
 
Genshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptxGenshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptxJohnree4
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfhenrik385807
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...NETWAYS
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptxBasil Achie
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Krijn Poppe
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringSebastiano Panichella
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptssuser319dad
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxFamilyWorshipCenterD
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
SBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSebastiano Panichella
 
Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxaryanv1753
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...henrik385807
 

Recently uploaded (20)

Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸
 
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptx
 
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
 
Genshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptxGenshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptx
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software Engineering
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.ppt
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
 
SBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation Track
 
Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptx
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
 

Remedies for Breach of Contract

  • 1. REMEDIES FOR BREACH OF CONTRACT BY: Liew wei zhean 0331225 Loh mun tong 0323680
  • 2. Remedies available to the innocent party 2 Damages Specific Performance Injunction Quantum Merit BREACH OF CONTRACT
  • 4. Contracts Act 1950 - Section 74 (1) Compensation for loss or damage caused by breach of contract Hadley v. Baxendale Direct loss + Indirect loss 4 ❏ Arises from the natural course of events ❏ Consequential damages ❏ Contemplated by the parties
  • 5. Contracts Act 1950 - Section 74, 75 & 76 A remedy providing money compensation for a civil wrong with the aim to restore the injured party to the position he would have enjoyed had the contract been performed as agreed. ▣ Injured party is entitled to damages arising naturally ▣ If the injured party claims for special damages, he must made known to the other party, at the time of making the contract, that the special loss is likely to result from the breach (Must not be too remote)5
  • 6. Agnes contracts to repair Becky’s toilet in a certain manner and receives payment in advance. Agnes repairs the toilet but not according to contract. Becky is entitled to recover from Agnes the cost of making the repairs conform to the contract. 6 Expectation: contract Reality: work done
  • 7. 7 Breach of contract in construction ▣ When one party fails to perform the complete performance of the contract conditions and he has no legal excuse for the non-performance. ▣ Innocent party may decide to continue with the contract or treat the contract as discharged ▣ If the contract is not discharged (innocent party choose to continue or breach is one that cannot discharge the contract), innocent party may recover damages (subject to some rules on recoverable monetary loss)
  • 8. 8 A contract provides maintenance works to a building for 2 years at RM10,000 a month. After 10 months, the sum owing to contractor is RM50,000. Option A Option B example Keep the contract alive End the contract
  • 9. 9 example Option a option b Sues for RM 50,000 Sues for RM 50,000 + Loss of profits from remaining months
  • 10. 10 a. Bringing contract to an end (repudiation of contract) 1. Where one party refuses to continue with his contractual obligations ▣ Contractor removes all his plants, materials and labour from the site before completion and show no intention to return to complete the work.
  • 11. 11 2. Where the breach committed by one party goes 'of the root' of the contract. ▣ Employer repeatedly fails to pay on the interim certificates properly issued by the Architect. Brani Readymixed Pte Ltd v. Yee Hong Pte Ltd (1995) C Norman Peterson Co v. Container Corporation of America (1985)
  • 12. 12 B. Breach which does not discharge a contract ▣ Employer delays in giving the contractor site possession or reasonable access to the Works Carr v. JA Berriman Pty Ltd (1953) ▣ Employer fail to issue timely instructions for the execution of Works Roberts v. Bury Commissioners (1870)
  • 13. 13 B. Breach which does not discharge a contract ▣ Employer fails to nominate specialist sub-contractors in a timely manner. ▣ Ar and QS fails to evaluate claims submitted by the contractor within the specified time or the employer fails to pay in accordance with the terms of contract ▣ Disruptions caused by other contractors employed directly by the Employer.
  • 14. 14 Computation of damages ▣ Actual monetary loss. ▣ Innocent party should be restored to the position he would have been in had the other party performed his obligation. ▣ Additional damages such as loss of profits and rents will depend on the rules of remoteness.
  • 15. 15 Remoteness and causation ▣ Party claiming for damages for breach of contract must prove that damage was caused by breach. Popular Industries Ltd v Eastern Garment Manufacturing Sdn Bhd (1990)
  • 16. 16 Remoteness and causation Contracts Act 1950 - Section 74: Compensation for loss or damage caused by breach of contract 1. When a contract has been broken, the party who suffers by the breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from the breach, or which the parties knew, when they made the contract, to be likely to results from the breach of it
  • 17. 17 Remoteness and causation Contracts Act 1950 - Section 74: Compensation for loss or damage caused by breach of contract 1. Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach
  • 18. 18 Mitigation for damages ▣ Innocent party must take all reasonable steps to mitigate his loss - DUTY OF MITIGATION Kabatasan Timber Extraction Co v. Chong Fah Shing [1969]
  • 20. SPECIFIC PERFORMANCE ▣ A court order directing a party to perform the terms of contract. (to do exactly what the party has promised in contract) ▣ Under Section 11 of the Specific Relief Act,1950 ▣ Specific performance is a discretionary remedy. Court will refuse specific performance where the granting will cause undue hardship to the defendant. Section 11(1): Specific performance may be granted by the court in the following situations ❏ When the act agreed to be done is in the performance, wholly or partly of a trust ❏ When there is no standard for determining the actual damage caused by the non-performance of the act agreed to be done 20
  • 21. Example: An art collector promised to sell one piece of art collection as shown to MR.BLUE and them two make a legal sales contract. However, the collector then decides that he’d rather keep the piece for now. The collector breaches his contract with MR.BLUE. The Court decides that the piece of art is truly priceless and MR.BLUE can’t acquire another comparable piece no matter how much money the court awards her. Instead the court decides that the collector should comply with the terms of contract and sell the piece to MR.BLUE for the price he already agreed in the contract. 21 SPECIFIC PERFORMANCE BuyerSeller
  • 23. INJUNCTION ❏ court order instructing a defendant not to commit some act. ❏ Interlocutory injunction is granted at the discretion of the court to preserve the status quo pending the resolution of a legal action.. Type of Injunction 23 For Specific Purpose03 ● To enter into defendant's premises to search and seize article with relevenance case Mandatory Injunction(Must Do)02 ● To prevent someone to do something which he ordinary has no obligation to do Prohibitory Injunction(Not to do)01 ● Prevent someone from doing something which he ordinary has the right to do
  • 25. QUANTUM MERUIT ❏ Quantum meruit is a claim for payment for work executed where no price has been agreed or quantified, and usually a being assessed in a ❏ ‘reasonable sum’, ❏ ‘reasonable remuneration’, ❏ ‘fair market rates’, ❏ ‘fair commercial rates’ or on similar terms. ❏ Quantum meruit means ‘the amount of deserves’ or ‘what the job is worth’ ❏ Found under Section 71 of the Contract Act 1950 25
  • 26. QUANTUM MERUIT Arise under 6 circumstances: - 1. Where the contract is silent on how completed work is to be paid. For example contractor incurred additional expenses due to a major change in the quantity of the work which suppose to be carried out and paid but not existing in the contract. Case law: Parkinson v Commissioners of Works (1949) The contractor had agreed to carried out certain work on a cost plus profits basis subject to the total profit recoverable limit. And the commissioners of the work was entitled to instruct works up to 5 million under the contract but the instruced actual work up to 6.6million, thus exceeding the contract value. The court of appeal found that the additional work was outside the contract and thus the contractor was entitled to be paid on a quantum meruit basis, which is beyond the total fixed profit under the contract. 26
  • 27. QUANTUM MERUIT 2. Where parties to a contract proceed on the mistake basis that there is an enforceable contract, but later found out that there is no valid contract. Case Law: Ayer Itam Tin Dredging Malaysia Bhd v YC Chin Enterprise Sdn Bhd (1994) The parties are still negotiating and didnt intend to bound until a formal contract was made. The letter of intent did not form a bound contract at law but was only to record terms agreed by the parties as a basis for contract negotiation. As on the question of compensation for the work done prior to the dispute, the judge held that a claim on a quantum meruit basis for the preliminary work carried out on the site was successful but was subject to max limit RM300,000 27
  • 28. QUANTUM MERUIT 3.Where one party requested the other for services which are not provided or governed by any contract. Case Law: Constain Civil Engineering Ltd v Zanen Dredging & Contracting Co (1997) The instruction given did not constitute authorized variations of the subcontract works because they required the works to be work which are outside the scope of the subcontract which entitling the subcontractor to payment on a quantum meruit basis. 28
  • 29. QUANTUM MERUIT 29 4. Where the contract has been discharged by the operation of the doctrine of frustration. Case law: BP EXploration Co ( Libya) v Hunt (No 2) (1982) BP entered an agreement with Hunt, under which BP would explore and develop his oil concession in Libya at their own expense. This expenditure would be recoverable from Hunt’s share of the profits when the field produced oil. After oil production began, the parties would share both production and development costs. Oil came on stream in 1967 but in 1971 the Libyan government capture BP’s interest. BP had not received all its initial expenditure from Hunt’s share, and claimed a just sum under s1 Law Reform (Frustrated Contracts) Act 1943. (Change of Government ‘Politic’)
  • 30. QUANTUM MERUIT 30 5. Where the contract has been repudiated by the Employer and the Contractor choose to claim for damages for breach of contract or quantum meruit in restitution for the work performed. Case Law: Renard Construction Ltd v Minister of Public Works (1992) The court held that a claim in quantum meruit following a wrongful termination should be quantified on reasonable remuneration basis, not value of work done basis.
  • 31. QUANTUM MERUIT 31 6. Where the contract contains an expressed agreement to pay reasonable sum or on similar term.. For example, Clause 11 - Variation, Clause 11.7 - Additional expenses or loss and/or expense cause by variation, Clause 24.0 - Loss and Expense. Case Law: Laserbore Ltd v Morrison Biggs Wall Ltd (1993) The learned Judge in deciding the meaning of the term ‘fair and reasonable payments for all works executed’, considered that the cost-plus-profits basis was wrong principle however sometimes it may produce right result. The Judge held that in assessing quantum meruit claim the appropriate approach was to adopt general market rates or fair commercial rate.
  • 32. Q & A
  • 33. What are the 2 limbs mentioned by the case of hadley V. BAXENDALE? 33
  • 34. WHAT ARE THE REMEDIES AVAILABLE TO THE CONTRACTOR IF ISSUE OF NON-PAYMENT BY EMPLOYER ARISE ? 34 ▣ The contractor can suspend execution of works until such time payment is made (Clause 30.7) ▣ The contractor can claim interest on unpaid amount (Clause 30.17) ▣ If non-payment persists, the contractor can terminate his own employment (Clause 26.1(a)) ▣ Construction Industry Payment and Adjudication Act (CIPAA)
  • 35. WHAT IS A DIFFERENCES BETWEEN NORMAL CONTRACT AND QUASI CONTRACT? 35 CONTRACT QUASI CONTRACT A legally enforceable agreement made between two parties An unintended contractual relationship between two parties created and enforced by the court BREACH OF CONTRACT UNJUST ENRICHMENT DAMAGES QUANTUM MERUIT
  • 36. Any legal rule need to be follow when assessing reasonable sum? Based on guidance is given in the fifth edition of Keating on Construction Contracts, at page 80: ▣ The courts have laid down no rules limiting the way in which a reasonable sum is to be assessed. ▣ The contractor should be paid at a fair commercial rate for the work done. ▣ Useful evidence in any particular case may include abortive negotiations as to price, a calculation based on the net cost of labour and materials used plus a sum for overheads and profit, measurements of work done and materials supplied, and the opinion of quantity surveyors, experienced builders or other experts as to a reasonable sum.36
  • 37. Any legal rule need to be follow when assessing reasonable sum? ▣ Case Law: Laserbore Ltd v Morrison Biggs Wall Ltd (1993) ▣ The Judge say that cost-plus-profits basis wrong approach, and the appropriate approach was to adopt general market rates or fair commercial rates. 37

Editor's Notes

  1. In the event of breach of contract, there are 4 remedies available to the innocent party
  2. - which is the statutory enunciation of Hadley v. Baxendale. - This case confer 2 possible grounds of claiming damages and known as the first and second limb of Hadley v. Baxendale. - The first limb is direct damages arises naturally from the breach of the contract where each party being deemed aware of such natural matters. - The second limb is indirect loss or consequential damages which are damages within the reasonable contemplation of the parties at the time of entering the contract means the damages have been made known to both parties at the making of the contract.
  3. Provided the damages is not too remote
  4. An example of breach of contract by the contractor
  5. - A breach of contract is when one party fails to perform his contract obligations and has no legal excuse for non performance - which treat the contract as subsisting
  6. which is the total sum of anticipated monthly receipts for remaining months deducting the cost of providing such services provided this loss of profit is contemplated by both parties when they enter the contract The decision to end the contract / keep it alive depends on the consideration of the project profitability of the remaining works
  7. Amounts to repudiation
  8. BRANI - The court of appeal Singapore held that a mere failure or delay in making payment itself would not amount to repudiation BUT if this failure goes beyond just stalling for time and indicates an intention to not pay at all, then this amounts to an intention not to perform the contract C NORMAN - The owner made hundreds of substantial changes to the works and the californian appeal court held that the effect of these changes fundamentally changes the scope of works under the contract which entitle the contractor to bring the original contract to an end. In the above 2 cases, the effect of bringing the contract to an end is to relieve both parties from their contractual duties and rights to demand performance. The defaulting party still have the obligation to pay damages to the innocent party who has the right to be compensated
  9. Where the breach is not of a serious nature that goes to the root of the contract which entitles the innocent party to end the contract, the legal redress is an action in damages. For commercial reasons, the contractor prefer to bring an action for damages rather than bring the contract to an end. For instance, in PAM contract 2006, the contractor can claim for extension of time under relevant event in clause 23.8f and loss and expense in clause 24.3(b) of delay by the employer in giving site possession. However, in the case of Carr, the court held that if the delay is so serious and there is indication by the owner not to bound by the contract, the contractor is entitled to end the contract The court stated that there the employer and architect have the obligation to issue plans and necessary details for the execution of works within a reasonable time. A breach of this obligation entitle the contractor to a course of action in damages
  10. Where this nomination affects the progress of the works. The contractor then can claim for remedies under the contract For example, direct contractor/ specialist contractor directly appointed by the Employer
  11. In which the party need to prove and justify the remoteness and have an appropriate assessment of the amount
  12. The federal court held that the innocent party claims damages from the defaulting party due to breach of contract has to show that the loss in respect to his claim for damages in caused by the breach and that the damages are not too remote to recover
  13. The court held that the respondent has the duty to take reasonable steps to mitigate the damage by just incurring additional expense for hauling the timber logs up to the sawmill instead of purchasing the logs from elsewhere and The appropriate damages awarded is the approximate cost of hauling the logs to the sawmill instead of the new purchase amount of the timber logs. To conclude, the duty to mitigate is on the part of the claimant to take all reasonable steps to reduce the extent of damage or loss suffered as a result of a breach of contract
  14. Equitable remedies don't relate so much to monetary(Money) damages. More on action
  15. Examples of equitable remedies include remedies obtained in situations involving a breach of contract. These remedies don't relate so much to monetary(Money) damages as they do to fairness. Undue hardship- an action required significant difficulty to the defendant. Eg. ask defendant to Breaks another law
  16. Drawn by Leonardo da Vinci's , Name: Salvator Mundi
  17. Prohibitory- employer suspend the work through to his financial difficulty, and in order to prevent employer remove the material on site the contractor can apply for prohibitory injunction to prevent the employer enter the site. Mandatory- After terminate the contractor, so dont let the contractor to enter the site by apply mandatory injunction For Specific Purpose- Court order defendants to commit an act related to the case/contract Eg. If X contracts with Y to sing for 12 month at Y theatre and not to sing elsewhere, Y cannot obtain specific performance of the contract to sing but he can secure an injunction to restrain X from singing other place.
  18. Additional work was outside the contract
  19. Letter of Intent, didnt constitute to bound a contract(nego)
  20. Additional work was outside the contract
  21. Frustration - Block, eg Fire happen In the event of a frustrated contract: Money paid before frustrating event is to be repaid Sums due for payment cease to be payable Expenses incurred may be retained/recovered if incurred in the performance of the contract and before frustrating event The Law Reform (Frustrated Contracts) Act 1943, is an Act of Parliament which governs the liabilities and the rights of those parties who are involved in a frustrated contract in the United Kingdom. The Act provides a different approach to that of the common law at the time which did not permit a party in a frustrated contract to recover the money that had been paid ahead of a contract becoming impossible to perform.
  22. Repudiated- Reject or abondan Wrongful termination, Eg: Contractor submitted payment and consultant certified but not yet paid. However, contractor found out that employer wrongly terminated so contractor may take quantum meruit to claim for those certified based on reasonable remuneration instead of value of work done basis. Remuneration includes salary, commission, compensation, and wages. Salary consists of yearly gross wages. Eg basic salary.
  23. Adopt general market rates not based on cost plus profits basis. Explanation of reasonable sum
  24. Note: Unjustly Enriched means profited at the expense of another without making an effort restitution(replacement/surrender/compensation) Quasi contract eg: Letter of Intent, employer give contractor LOI and stated that need to carry out some work. After contractor carry out those work however the contractor and employer unable to form a contract during nationalisation so this may cause their relationship come to an end. In order for contractor to calm for their work done, them may use Quantum meruit.
  25. https://simplymalaysia.files.wordpress.com/2011/11/laserbore-limited-v-morrison-biggs-wall-limited-1992.pdf Page 33 Link For Further reading :Fair and Reasonable Payment
  26. https://simplymalaysia.files.wordpress.com/2011/11/laserbore-limited-v-morrison-biggs-wall-limited-1992.pdf Page 33 Page 41 Link For Further reading :Fair and Reasonable Payment