2. STATUS REPORT OF MY HOME ABHRA Tower-
”A” As On 19.10.13
1.10th Floor Slab : Except 3rd Flat Remain All Flats Completed, 3rd Flat Slab shuttering work Under Progress.
3. STATUS REPORT OF MY HOME ABHRA Tower-
”B” As On 19.10.13
1.10th Floor Slab : Flat No 1 and 2 flat Slab Completed, 4 & 5 flats Bar Bending work under Progress , 3 rd flat Shuttering
work In Progress
4. STATUS REPORT OF MY HOME ABHRA Tower-
”C” As On 19.10.13
1.8th Floor Slab : Flat No 01 Shuttering Completed ,Flat No 02 Columns work completed.
5. STATUS REPORT OF MY HOME ABHRA Tower-
”D” As On 19.10.13
3.10th Floor Slab : Except 3rd Remain all Flats Slabs Completed.3rd flat Slab Shuttering Work Completed .
6. STATUS REPORT OF MY HOME ABHRA Tower-
”E” As On 19.10.13
1.10th Floor Slab : Completed
2.11th Floor Slab : Flat No 01 Beam Bottom Shuttering Work In Progress Flat No 02 Columns work In progress
7. STATUS REPORT OF MY HOME ABHRA Tower-
”E” As On 19.10.13
1.10th Floor Slab : Completed
2.11th Floor Slab : Flat No 01 Beam Bottom Shuttering Work In Progress Flat No 02 Columns work In progress