1. STATUS REPORT OF MY HOME ABHRA Tower-”A”As On 02.03.13
1.Basement-II Slab Completed.
2. Basement-I shuttering work and bar bending work in Progress for flat no 1
& 2
2. STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 02.03.13
1.Basement-II Slab Completed.
2.Basement-I Slab flat number 1 & 2 Completed.
3.Remain Basement I slab planning today.
3. STATUS REPORT OF MY HOME ABHRA Tower-”C”As On 02.03.13
1.BasementII Slab(-2) Completed.
2.Basement I Beam Bottom Centering work In Progress
4. STATUS REPORT OF MY HOME ABHRA Tower-”D”As On 02.03.13
1.Basement II Slab Completed.
2.Basement I Slab flat number 1& 2 Completed
3.Remain flats bar bending work in progress
5. STATUS REPORT OF MY HOME ABHRA Tower-”E”As On 02.03.13
1.Basement II Slab -80% Completed
2.Remain 20% in Basement II Slab planning today.
3.Colomuns work in progress.
6. STATUS REPORT OF MY HOME ABHRA “TOTAL SITE”As On 02.0.13
1.Total Site Grade Slabs Completed
2.Total Site Basement II slab- Completed today
3.Total Site Basement I slab 12%-Completed.
7. STATUS REPORT OF MY HOME ABHRA “CENTROL LAN”As On 02.0.13
1.PCC-Work In Progress and
2.Sand Leveling Work in Progress