The project is making progress on several fronts. Retaining walls on the south and west sides are under construction, with the first lift of the south wall in progress. Columns above the south side tie beam are complete and deep beams are being cured. Backfilling is occurring on the west side for a deep beam. Excavation of blocks is ongoing and concrete work for footings is in progress. Erection of high and low tension yards is complete except for fencing. The foundation for a second batching plant is also underway.