The document discusses the importance of properly identifying risks, their potential causes, and potential effects or consequences when performing risk analysis. It provides an example of a risk related to delays in obtaining a building permit, with the potential cause being late submission of permit documentation and the potential effect being project delays and contractor claims. The document also discusses how a single risk may have multiple causes or effects, and that mitigation measures may address either causes or effects but not necessarily both. It prompts the reader to identify three risks related to a familiar project, along with their causes, effects, and potential mitigation measures to address causes or effects.