SlideShare a Scribd company logo
1 of 46
Download to read offline
Project Management Fundamentals Workshop 
Participant Notebook 
Notebook Overviews 
Action Plan............................................................................................................. 3 
Communications Plan.............................................................................................. 4 
Core Project Team Analysis ..................................................................................... 6 
Cost/Benefit Analysis............................................................................................... 7 
Critical Requirements Checklist ................................................................................ 8 
Final Report ........................................................................................................... 9 
Kick-Off Meeting ................................................................................................... 10 
Lessons Learned................................................................................................... 11 
Milestone Chart .................................................................................................... 12 
Network Diagram.................................................................................................. 13 
Post-Implementation Review Meeting..................................................................... 14 
Project Charter ..................................................................................................... 15 
Project Scoping Meeting ........................................................................................ 16 
Risk Assessment Chart .......................................................................................... 17 
Risk Management Plan .......................................................................................... 18 
Stakeholder Analysis ............................................................................................. 19 
Task Responsibility Matrix...................................................................................... 20 
Work Breakdown Structure (WBS).......................................................................... 21
Project Management Fundamentals Workshop 
Tools and Templates 
Action Plan Template ............................................................................................ 22 
Communications Plan Template ............................................................................. 23 
Core Project Team Analysis Template ..................................................................... 24 
Cost/Benefit Analysis Worksheet ............................................................................ 25 
Critical Requirements Checklist .............................................................................. 26 
Final Report Template........................................................................................... 27 
Kick-Off Meeting Checklist ..................................................................................... 28 
Lessons Learned Checklist ..................................................................................... 29 
Milestone Chart Template...................................................................................... 30 
Network Diagram Sample ...................................................................................... 31 
Post-Implementation Review Meeting Agenda......................................................... 32 
Project Charter Sample ......................................................................................... 33 
Project Scoping Meeting Agenda Template.............................................................. 37 
Risk Assessment Chart Tool/Template .................................................................... 38 
Risk Management Plan Tool/Template .................................................................... 39 
Stakeholder Analysis Tool/Template ....................................................................... 40 
Task Responsibility Matrix Tool/Template................................................................ 41 
Work Breakdown Structure (WBS) Template ........................................................... 42 
Work Breakdown Structure (WBS) Formats............................................................. 44 
Work Breakdown Structure (WBS) Samples............................................................. 45
Project Management Fundamentals Workshop 
Action Plan 
What? 
Document to establish and track action items or project steps including: 
Ɣ Agreements made during team meetings 
Ɣ Steps to be taken 
Ɣ Responsible team member(s) 
Ɣ Start and completion dates 
Ɣ Any clarifying notes 
Ɣ Status of action items 
When? 
During the project implementation and control phase. 
How? 
1. Record the steps that need to be taken, who is responsible, start and 
completion dates, clarifying notes, and the status. 
2. Update the status of the steps on a regular basis. 
3. Use the information on the Action Plan for status reporting. 
View an action plan template. 
Notebook Overview 3
Project Management Fundamentals Workshop 
Communications Plan 
What? 
Provides the process for documenting work performed during the project and the 
communication of this information to the project team and stakeholders. 
Note: Depending on the complexity or size of a project, other elements will also 
be included, such as multiple, concurrent work breakdown structures for large 
projects or contractual documents for projects that outsource tasks. 
When? 
During the project planning phase. 
How? 
1. Create an agenda. 
2. Identify the project audience(s). 
3. Determine what stakeholders need, want, and expect to know, taking into 
consideration frequency and length of involvement of all stakeholders. 
4. Identify information sources and assign responsibility for collecting 
information to be communicated. 
5. Identify the best media and methods to communicate. Stakeholders may 
absorb information in different ways. 
6. Identify key information that needs to be communicated regularly. 
7. Define when and how communications will be provided. 
8. Document any required approval process needed for any of the 
communications. 
9. Assign responsibilities for creating and delivering the various types of 
communications. 
10. Identify communication triggers, such as key 
Notebook Overview 4
Project Management Fundamentals Workshop 
events/milestones/deliverable dates. 
11. Define a process for handling ad hoc communications the project is likely 
to encounter. 
12. Develop a library of project information, and assign responsibilities for its 
maintenance. 
13. Create internal and external feedback loops to evaluate the effectiveness of 
communications. 
14. Schedule the work of communications and related triggers into the project 
schedule to ensure they are part of the overall plan. 
15. Define a process for updating/changing the Communications Plan. 
View a communication plan template. 
Notebook Overview 5
Project Management Fundamentals Workshop 
Core Project Team Analysis 
What? 
A technique for identifying the key members of the team. It can also be used to 
negotiate with functional managers for resources and general project support. 
When? 
Ɣ During the definition phase to identify the key members of the project 
team. 
Ɣ During the planning phase to refine the makeup of the team. 
How? 
1. Determine the major tasks that will have to be accomplished. 
2. Determine which functional areas will most likely be affected by the 
project, i.e., those functional areas possessing the skills to accomplish part 
of the project. You should also determine who will be affected in a less 
direct way, such as customer service representatives. 
Note: Those who are not directly affected at the beginning of a project 
may be the ultimate users of the final product, and therefore, may have 
valuable insight for the definition and planning stages. 
3. Determine the expertise required for the project. 
4. Determine key people with the requisite expertise to form the core of the 
team. 
View a core project team analysis template. 
Notebook Overview 6
Project Management Fundamentals Workshop 
Cost/Benefit Analysis 
What? 
A technique to determining if the benefits outweigh the costs of a project. 
When? 
During all phases of the project. 
Ɣ When you are determining whether to pursue a project. 
Ɣ During the prioritization of corporate projects. 
Ɣ Anytime there is a question about the relative benefit/cost of a project. 
How? 
1. Estimate by year all the costs of the project including: 
x Development 
x Labor 
x Capital investment 
x Cost of maintenance 
x Cost of operation 
2. Estimate the benefits of the project by putting dollar values on the 
following (by year): 
x Expected profits as a result of implementing the project. 
x Cost avoidance or savings in operating and maintenance costs 
because of having the new project in place. 
x Cost savings because of increased efficiency or speed. 
x Cost savings as a result of reduced labor if applicable. 
3. Determine the break-even point. 
4. Read the difference between the total benefits line and the total costs line. 
View a cost/benefit analysis worksheet. 
Notebook Overview 7
Project Management Fundamentals Workshop 
Critical Requirements Checklist 
What? 
A checklist to aid in identifying all of the requirements of a project. 
When? 
During the definition and start-up phase to identify the project requirements, 
scope, and objectives. 
How? 
1. Complete a cost/benefit analysis. 
2. Determine the specific outcomes, success factors, goals, and objectives of 
the project. 
3. Identify any the legal requirements and/or mandates. 
4. Determine the structure and organization of the project. 
5. Identify important tasks and milestones of the project and their schedule. 
6. Identify the types of personnel schedules needed and how will they be 
used. 
7. Determine the distribution of other resources (budget, equipment, 
materials, facilities) among the various tasks. 
8. Determine how the key elements of the project (cost, performance, and 
schedule) will be estimated and controlled. 
9. Identify potential problems and risk areas involved in carrying out the 
project and a plan to resolve or reduce them. 
View a critical requirements checklist. 
Notebook Overview 8
Project Management Fundamentals Workshop 
Final Report 
What? 
A reporting technique to document information contained in the project plan, 
appropriate documentation of the post-implementation review meeting, lessons 
learned, and the budget, schedules, change orders, and updates. 
When? 
After the completion and delivery of the project. It is the last activity in the project 
completion phase. 
How? 
1. Gather all data that have been generated during the life of the project. 
2. Develop a report using the format on the following page. 
3. Schedule a post-implementation review using the report data for a 
debriefing guide. 
4. Distribute the Post-Implementation Review Report to appropriate 
stakeholders/customer representatives. 
View a final report template. 
Notebook Overview 9
Project Management Fundamentals Workshop 
Kick-Off Meeting 
What? 
The kick-off meeting 
Ɣ Provides a briefing of the culmination of all the information gained 
through the other activities. 
Ɣ Provides a chance to discuss any potential trouble spots of the project or 
information that is still missing. 
Ɣ Gives the project manager the opportunity to gain buy-in from all team 
members. 
When? 
During the project planning phase. This is the last activity in the project planning 
phase. 
How? 
1. Create an agenda. 
2. Provide an overview of the project. 
3. Discuss the project requirements and process. 
4. Conduct team building activities. 
5. Discuss general issues encountered by project team. 
6. Clarify next steps. 
View a kick-off meeting checklist. 
Notebook Overview 10
Project Management Fundamentals Workshop 
Lessons Learned 
What? 
Document that stores what was done right, wrong, and what would be done 
differently. It identifies the cause of variances, the reason for the corrective action, 
and any other lessons learned. 
When? 
Documentation of lessons learned should begin in the project implementation and 
control phase and continue through the project completion phase. 
How? 
1. Maintain a lessons learned log throughout the life of the project. 
2. Capture lessons learned as close as possible to the learning opportunity 
(e.g., after an issue has been resolved, change in scope has occurred, or a 
risk has been mitigated). 
3. Review lessons learned as part of Risk Management. 
4. Identify project management processes that can be improved as a result of 
lessons learned and make the improvements. 
5. Summarize lessons learned in the Final Report. 
View a lessons learned checklist. 
Notebook Overview 11
Project Management Fundamentals Workshop 
Milestone Chart 
What? 
A summary-level schedule that identifies key points in the project’s life span used 
to keep stakeholders informed of project progress and to alert them to schedule 
slippage. It displays the high-level picture of a project’s scheduled and actual 
milestone start and completion dates. 
When? 
During the project implementation and control phase to track milestone activity. 
Ɣ To provide a broad-brush picture of the project’s progress. 
Ɣ For an approval process. 
Note: If all the key events are going to be on the Gantt Chart, then the milestone 
tracking can be done directly from the Gantt Chart. 
How? 
Fill in the blanks by recording key events that are identified as milestones or that 
need approval before the project can proceed. Include key task events as well as 
events that have to be tracked for other than project progress, i.e., those events 
that senior management has identified for special review. 
View a milestone chart template. 
Notebook Overview 12
Project Management Fundamentals Workshop 
Network Diagram 
What? 
A schematic display of task interdependencies that displays the relationships of 
project activities chronologically from left to right. The diagram uses project logic 
and critical path activities. 
When? 
During the project planning phase: 
Ɣ After completing the WBS. 
Ɣ Prior to completing the critical path. 
How? 
1. Using the WBS, place the subtasks in the order in which they should be 
completed. 
2. Identify concurrent tasks by rearranging them so that concurrent tasks 
align vertically. 
3. Identify interdependencies among tasks. 
View a network diagram sample. 
Notebook Overview 13
Project Management Fundamentals Workshop 
Post-Implementation Review Meeting 
What? 
A meeting with the project team to review the entire project for what went well, 
what did not go well, and how to perform tasks more effectively or efficiently in 
the future. This meeting is also called the project review meeting. 
When? 
After the completion and delivery of the project. It is the second to last activity to 
be completed in this phase. 
How? 
1. Gather all data that have been generated during the life of the project. 
2. Develop an agenda using the format on the following page. 
3. Schedule a post-implementation review with the entire project team. 
View post-implementation review meeting agenda. 
Notebook Overview 14
Project Management Fundamentals Workshop 
Project Charter 
What? 
Ɣ The project charter states the business case for and the goal of the 
project. 
Ɣ Each primary stakeholder should sign the charter as approval and 
support for the project. 
Ɣ The project charter lists the project manager and/or management team. 
Ɣ The charter should also include the initial time, cost, and performance 
requirements for the outcome. 
When? 
The project sponsor generally provides the project charter before or very early in 
the project definition and start-up phase. 
How? 
Use the project charter to: 
Ɣ Identify the problem statement. 
Ɣ Determine the project goal. 
Ɣ Determine the scope. 
Ɣ Identify the project requirements. 
View a sample project charter. 
Notebook Overview 15
Project Management Fundamentals Workshop 
Project Scoping Meeting 
What? 
A meeting to determine the availability of potential resources to gain early 
stakeholder buy-in and clarify or confirm the project goals and requirements. 
When? 
During the project definition and start-up phase. 
How? 
1. Review the project goals and requirements. 
2. Discuss the high-level benefits. 
3. Determine potential high-level risks. 
4. Confirm resource appropriateness for project and availability. 
5. Clarify or confirm stakeholder membership. 
6. Review the critical requirements of the project. 
7. Review project charter. 
View a project scoping meeting agenda template. 
Notebook Overview 16
Project Management Fundamentals Workshop 
Risk Assessment Chart 
What? 
A simple technique that helps to minimize surprises which can occur during the 
life of a project. This chart is designed to help the project team think through the 
potential risks or problems related to the three main project parameters of time, 
cost, and scope/quality; identify the potential problem; recognize the problem if it 
occurs; and decide on the course of action. 
When? 
Anytime you want to identify and plan for potential problems. 
How? 
1. Brainstorm with the project team members or other knowledgeable people 
who have been a part of a similar project to identify potential problems. 
2. Fill in the Risk Assessment Chart to identify the problem, how and when 
the problem will surface, and what the alternative action will be. 
3. Collect all the Risk Assessment Charts and make copies of them available 
to each team member. 
4. If a potential problem is identified that is out of the sphere of the project 
manager’s control, provide a copy to the effected person or function and 
establish a monitoring system that will ensure the problem is corrected if it 
occurs. 
View a risk assessment chart tool/template. 
Notebook Overview 17
Project Management Fundamentals Workshop 
Risk Management Plan 
What? 
A systematic approach to manage risks that includes: 
Ɣ Identifying the risk 
Ɣ Assessing the risk’s impact 
Ɣ Responding to the risk 
Ɣ Monitoring and controlling the 
When? 
During the project implementation and control phase. 
How? 
1. Identify and describe the risk Ɇ A risk ID similar to a task ID allows the 
risk to be tracked and monitored. 
2. Assess the risk’s impact Ɇ A probability/impact matrix categorizes risks 
based on the probability to occur and the impact if or when it does. 
Typically, this is expressed as “High/High” to “Low/Low.” 
3. Respond to the risk – Risk response represents your desired general action 
when faced with that risk. Typical responses include avoid, accept, 
mitigate, or transfer. 
4. Monitor and Control the risk – This involves documenting all aspects of 
the risks including the resolution decision. 
View a risk management plan tool/template. 
Notebook Overview 18
Project Management Fundamentals Workshop 
Stakeholder Analysis 
What? 
A technique for identifying the parties-at-interest in a project. These are the people 
who have a vital concern for the success of the project because it directly impacts 
their function. 
When? 
Ɣ During the definition and start-up and planning phases to identify the 
stakeholders and to determine what level and type of involvement each 
should have. 
Ɣ During the life of the project to ensure that all parties-at-interest 
are being involved appropriately in the project. 
How? 
1. List the significant stakeholders. 
2. Identify if the listed people or groups will resist the project (-), support the 
project (+), or be neutral (0). 
3. Describe the reason for each stakeholder’s position. 
4. Identify any strategy or action you can take to maintain support, increase 
support, or overcome resistance. 
View a stakeholder analysis tool/template. 
Notebook Overview 19
Project Management Fundamentals Workshop 
Task Responsibility Matrix 
What? 
A list of resources and their assigned tasks. Completing the task responsibility 
matrix helps to ensure the right number of the right resources are available at the 
right time. 
When? 
During the project planning phase, immediately after identifying the tasks in the 
WBS. 
How? 
After identify the project tasks: 
1. Enter the WBS # in the task ID column of the matrix. 
2. Enter a task description for each task ID. 
3. Determine and enter the team member responsible for each identified task 
and his or her title (e.g., P for programmer). 
4. Determine the time to complete the task and enter it below the responsible 
team member’s name. 
View a task responsibility matrix tool. 
Notebook Overview 20
Project Management Fundamentals Workshop 
Work Breakdown Structure (WBS) 
What? 
A detailed list of project elements organized by deliverables. Each descending level 
of the list represents a more detailed definition of the work to be completed. The 
total listing defines the overall scope of the project. It acts as the vehicle for 
breaking down the work into smaller elements, providing a greater probability that 
every major and minor activity will be accounted for. 
When? 
Ɣ During the definition and start-up phase as a top-level view of the 
project’s resource requirements. 
Ɣ During the planning phase to refine the project resource requirements 
and budget, develop the Task Responsibility Matrix, and assign task 
responsibility. 
Ɣ During the implementation and control phase to monitor the project’s 
progress. 
Ɣ During the completion phase to assess if all the requirements have been 
accomplished. 
How? 
1. Subdivide the total effort into discrete and logical sub-elements. A good 
approach is to view the subdivision process as a flow chart of the project 
from the whole to each succeeding lower level. 
2. Check the proposed WBS elements for completeness, compatibility, and 
continuity. 
3. Determine that the WBS satisfies all the project requirements. 
4. Double check to determine if the WBS provides for logical subdivision of 
all project work. 
5. Establish assignment of responsibilities for all identified effort to specific 
organizations. 
6. Check the proposed WBS against the reporting requirements of the 
organizations involved. 
Note: The two most common ways to construct a WBS are the Indentured 
Structure and the Graphical Tree Diagram Structure. 
View a WBS template, WBS formats, or WBS samples. 
Notebook Overview 21
Project Management Fundamentals Workshop 
Notebook Tools and Templates 22 
Action Plan Template 
Status 
Notes 
Comp. 
Date 
Start 
Date 
Person(s) 
Responsible 
* = Primary 
Action Plan 
PROJECT: 
PERSON RESPONSIBLE: 
START DATE: 
COMPLETION DATE: 
Steps to be 
Taken
Project Management Fundamentals Workshop 
Communications Plan Template 
Audiences 
Activity or 
Event 
When Method Person 
Responsible 
Sponsor Project 
Team 
Other 
Project Kickoff Project start 
(include date 
when planned) 
Meeting Project manager Approve Receive 
Project Plan Start and updates Document 
Team Meetings Weekly Document 
minutes project 
portal 
Major Milestone 
Announcements 
As completed Email 
Project Closeout 
Report 
End of project Document 
Notebook Tools and Templates 23
Project Management Fundamentals Workshop 
Core Project Team Analysis Template 
Project: Directly Impacted Indirectly Impacted 
General Project Task Organizational Area(s) Organizational Area(s) 
Notebook Tools and Templates 24
Project Management Fundamentals Workshop 
Cost/Benefit Analysis Worksheet 
BENEFITS 
Effect of New System on Annual Profits Present System (a) Proposed System (b) b-a 
A. Estimated Profit .................................. 
B. Total Difference in Estimated Profit .......................................................................................... 
Effect of New System on Annual Operating Expenses Present 
System 
Proposed 
System 
Annual 
Expense 
Decrease 
C. Equipment Rental ..................................................... $ $ $ 
D. Equipment Maintenance .......................................... 
E. Personnel (Include Benefits) .................................... 
F. Other Expenses (Specify) ......................................... 
1. ....................................………………………………. 
2. .........................................…………………………… 
3. .............................................................................…. 
G. Total Expense Decrease ...........................................................................................……...... $ 
H. Total Benefits (B + G) ...................................................................................................……... $ 
COSTS 
Initial Investment Days of Labor Dollars 
I. Labor (By Labor Category) Development Implementation Salary/Day Total $s 
1. ........................………………… 
2. ....................……………………. 
3. ...................…………………….. 
4. ................................…………… 
5. Other Labor ………………….. 
J. Total Labor Expense ...........................................................................................................……...... 
Dollars 
K. Capital Equipment/Setup/Testing Development Implementation Total 
1. Facilities 
2. Computers 
3. Furniture 
4. Equipment Installation/Setup 
5. Equipment Testing 
6. Other 
L. Total Capital Equipment Expense .....................................................................................….......... $ 
Dollars 
M. Other Expenses Development Implementation Total 
1. Training 
2. Supplies 
3. Travel 
4. Consultants 
5. Miscellaneous 
N. Total Other Expenses..................................................................................................................... $ 
O. Total Costs (J + L + N) ..............................................................................................................… $ 
Total Benefit/Cost = H - O = _____________________ Estimated Break-Even Period: Year ____ 
Notebook Tools and Templates 25
Project Management Fundamentals Workshop 
Critical Requirements Checklist 
Asked Question Answer 
… What are the specific outcomes, success 
factors, goals, and objectives of this project? 
… What are the legal requirements and/or 
mandates, if any? 
… How is the project going to be structured and 
organized? 
… What are the important tasks and milestones 
of the project, and how should they be 
scheduled? 
… What types of personnel are needed, and 
how will they be used? 
… How are other resources (budget, 
equipment, materials, facilities) going to be 
distributed among the various tasks? 
… How will the key elements of the project 
(cost, performance, and schedule) be 
estimated and controlled? What tools will be 
used? 
… What are the potential problems and risk 
areas involved in carrying out the project, 
and how will they be handled? 
… What are the costs/benefits of this project? 
Notebook Tools and Templates 26
Project Management Fundamentals Workshop 
Final Report Template 
Executive Summary 
1.0 Introduction 
2.0 Project Review 
Project Objectives 
Project Approach 
Project Management and Planning 
Technology 
Project Deliverables 
Quality and Process Issues 
Resource Utilization 
Roles and Responsibilities 
Problems/Changes Encountered and Solutions Effected 
3.0 Lessons Learned 
Appendix A: Post-implementation Review Session 
Notebook Tools and Templates 27
Project Management Fundamentals Workshop 
Kick-Off Meeting Checklist 
… PROVIDE AN OVERVIEW OF THE PROJECT 
x Give background information of the project. 
x Describe project goals. 
x Explain how and why project team members were selected. 
x Explain role of stakeholders and functional managers. 
… DISCUSS PROJECT REQUIREMENTS AND PROCESSES 
x Discuss tentative schedule and budget. 
x Describe project outcomes or end results, objectives, and success criteria. 
x Discuss administrative issues and needs. 
x Discuss data collection and analysis process. 
x Identify the decision-making process. 
x Identify required documentation. 
x Discuss how the team members will communicate with each other and to the 
larger organization. 
x Discuss project evaluation processes. 
For the first “team members only” meeting, include the following: 
… CONDUCT TEAM BUILDING ACTIVITIES 
x Ask team members to introduce themselves and share their experiences 
working on projects. 
x As a team, set ground rules for how everyone will work together. 
x Discuss the value of individual differences and how each team member brings 
his/her unique contribution. 
x Identify expectations team members have for the team and for each other. 
… DISCUSS GENERAL ISSUES ENCOUNTERED BY PROJECT TEAMS 
x Discuss the pull between “back home” and project assignments. 
x Discuss team members’ conflicting loyalties. 
x Discuss predisposition toward solutions and using the problem-solving model to 
avoid this. 
x Identify “us” versus “them” thinking within and outside the team. 
x Discuss project activities as iterative processes. 
x Discuss the importance of attending to team processes. 
… CLARIFY NEXT STEPS 
Notebook Tools and Templates 28
Project Management Fundamentals Workshop 
Lessons Learned Checklist 
… Have you identified sources of lessons learned to review before the start of the 
project (Post Implementation Reports, logs, databases, etc.)? 
… Are you logging lessons learned throughout the entire life of the project? 
… Have you clearly documented lessons learned and resolutions for the Post 
Implementation Report? 
… Are you implementing improvements learned from previous lessons in current and 
future projects? 
… Are you reviewing lessons learned to help with resolution of similar issues? 
… Did you review lessons learned as part of Risk Management? 
… Are you making improvements to project management processes as a result of using 
lessons learned? 
Notebook Tools and Templates 29
Project Management Fundamentals Workshop 
Milestone Chart Template 
Milestone Scheduled 
Start 
Actual 
Start 
Scheduled 
Completion 
Actual 
Completion 
Notebook Tools and Templates 30
Project Management Fundamentals Workshop 
Network Diagram Sample 
TaskID: 2.2.2 The Big Move Duration: 8 hours 
Task Name: Packing personal office items 
Notes: 
Time allotted equals one business day. Task can be 
accomplished around work schedule during this time. Labeled 
boxes will be needed prior to the start of this task. 
Status: Not Started 25% 50% 75% Completed 
Resource: Facility management, employees Dep: 1.3.4 
Notebook Tools and Templates 31
Project Management Fundamentals Workshop 
Post-Implementation Review Meeting Agenda 
Agenda 
1. Review of project objectives and the project approach 
2. Review of the planning process and project management 
3. Review of the project milestones and deliverables 
4. Identification of successful project elements 
5. Identification of and review of the quality, cost, time, performance, and process 
issues 
6. Review of the resource utilization and roles and responsibilities 
7. Identification and review of the problems/changes encountered and their 
solutions 
8. Discussion and documentation of lessons learned 
9. Recognition of and rewards for the project team and team members 
Notebook Tools and Templates 32
Project Management Fundamentals Workshop 
Project Charter Sample 
Biometric Support Center (BSC) Training Review Team 
Charter Objectives 
0.1 Purpose of the Charter 
This charter establishes the United States Visitor and Immigrant Status Indicator Technology (US-VISIT) 
Biometric Support Center (BSC) Training Review Team and defines the mission, authority, 
responsibilities, membership, meeting schedule, and decision-making process. The LearningWorks 
Project Manager (LWPM) is responsible for the development, implementation, and maintenance of 
this charter. Any questions or suggestions for improvement of this charter should be directed to the 
LWPM. 
0.2 Mission 
The mission of the BSC training review team is to develop materials that will increase the awareness 
by local law enforcement and other criminal justice agencies of the functions and services available 
through the BSC. To accomplish this mission, the BSC training review team will perform the 
following: 
x Recommend the content to be included in any products 
x Ensure that the content accurately reflects the viewpoints of the organizations represented 
x Review products and provide comments in a timely manner 
0.3 Specific Efforts 
0.3.1 Project Friction Ridge Brochure 
The Biometric Support Initiative (recently coined Project Friction Ridge) seeks to address the needs 
of local law enforcement through the creation of a brochure. This brochure will reflect the Project 
Friction Ridge-shared initiative and will showcase both the BSC and Immigration and Customs 
Enforcement (ICE). 
0.3.2 Biometric Support Center eCard 
The BSC eCard is currently being developed to educate local and international law enforcement 
organizations about BSC capabilities. While this tool is considered a training tool, it may also 
function as a mechanism for promoting BSC services and Department of Homeland Security (DHS) 
agencies who work in conjunction with the BSC. 
0.3.3 Train-the-Trainer Course 
A one-day Train-the-Trainer (TTT) course will be developed and presented to 26 ICE Special 
Agents in Charge (SAC). These agents will tour BSC facilities and learn to present a course on the 
BSC and the ICE Compliance Enforcement Unit (CEU) to local and state law enforcement 
agencies. 
Notebook Tools and Templates 33
Project Management Fundamentals Workshop 
1. Roles and Responsibilities 
1.1 Development and Review Process 
1. The LearningWorks training team will develop materials with the input of BSC training 
review team members. 
2. The BSC training review team will meet to discuss the materials and any immediate changes. 
3. The draft material will be provided to the BSC training review team for review and 
comments. 
4. The comments provided by individual BSC training review team members should be 
complete and reflect the viewpoints of the respective organization. 
5. The BSC training review team will meet to discuss the comments. 
6. Comments accepted by all of the BSC training review team members will be incorporated 
into the material by the LearningWorks training team. 
7. Issues that cannot be resolved by the BSC training review team shall be elevated to the BSC 
program manager. 
8. The LearningWorks training team will revise draft materials. 
9. The BSC program manager will approve the final product. 
1.2 Responsibilities 
x The BSC program manager has the final say on all products. 
x The BSC Designated Authorizing Authority (DAA) has responsibility for approving or 
disapproving a recommended disposition for all proposed changes submitted to the BSC 
training review team at its level of authority. 
x An issue that cannot be resolved by the BSC training review team shall be elevated to the 
BSC program manager. 
x Individual BSC training review team standing members are responsible for attending all 
meetings and are assigned the responsibility of providing advice and counsel to the LWPM 
and the BSC DAA on proposed changes. 
x The LWPM will be responsible for leading meetings, maintaining schedules, and 
coordinating between organizations and agencies. 
x The LearningWorks training team will be responsible for all development of training 
materials as well as conducting any training events. 
x The BSC training review team standing members are responsible for providing technical, 
managerial, and administrative guidance on issues brought for review. 
x This is a joint effort; therefore, representatives from each organization are responsible for 
ensuring that their organization tries to restrict review cycles to the available timeframes. 
Any indication that conflicts are preventing the representatives from promoting their 
materials should be addressed to the LWPM so that the schedule can be updated, and to the 
BSC training review team to determine the effect on the schedule. 
Notebook Tools and Templates 34
Project Management Fundamentals Workshop 
x US-VISIT Outreach (Outreach) will review materials to make suggestions regarding content 
and to keep all materials in alignment with the US-VISIT style guidelines. 
1.3 Project-specific Responsibilities 
1.3.1 Project Friction Ridge Brochure 
Since Project Friction Ridge promotes a blending of BSC and ICE support, this effort will include 
more extensive input from the ICE representatives than will be needed for the other efforts. 
Therefore, the schedule will reflect these needs. Ten working days will be provided to the ICE 
organization for review cycles, instead of the standard five working days. 
1.3.2 Biometric Support Center eCard 
The BSC eCard is a mechanism to educate prospective organizations which may interface with the 
BSC about its services. The eCard will be used to both educate and promote the BSC. 
Outreach will be an integral member of this effort. ICE representatives will have a subject matter 
expert (SME) role in this effort to ensure that any references to ICE and BSC interaction accurately 
reflect the organizations’ partnership. 
1.3.3 Train-the-Trainer Course 
The TTT course will be developed to support ICE SAC agents by providing a tour of BSC facilities 
and a training session on the BSC/ICE CEU program to be taught to local and state law 
enforcement agencies. This effort will require ICE representatives to speak the language and 
understand the mentality of their peers to ensure optimum learning. Outreach will review materials 
to make suggestions on content and to keep all materials in alignment with the US-VISIT style 
guidelines. 
1.4 Membership 
The membership of the BSC training review team is comprised of standing members who are 
program representatives and ad hoc participants who are SMEs or stakeholders in a proposed 
change. 
1.4.1 Permanent Members 
The BSC training review team consists of a program owner and standing members. 
1.4.1.1 Program Owner 
The program owner of the BSC training review team is the BSC program manager. 
1.4.1.2 Standing Members 
Standing members provide advice and counsel to the program owner by reviewing all materials 
presented to the BSC training review team. Standing members include the following: 
1. BSC DAA 
2. LearningWorks Program Manager 
3. LearningWorks Deputy Program Manager 
4. LWPM 
5. BSC Representatives 
6. LearningWorks Training Representatives 
Notebook Tools and Templates 35
Project Management Fundamentals Workshop 
7. Outreach Representatives 
8. ICE Representatives 
1.4.2 Effort-driven Membership 
There are three efforts associated with the current requirements for the BSC training review team; 
therefore, members may change from effort to effort. However, representatives from all 
organizations are encouraged to participate in all efforts. 
1.4.3 Ad Hoc Members 
Ad hoc participants may attend meetings when invited by a permanent member. An ad hoc 
participant may be a stakeholder and may attend a meeting when a proposed issue in which he or 
she has a stake is on the agenda. 
2. Meeting and Review Schedule 
The BSC training review team will meet as scheduled to determine the disposition of pending 
change requests and to review draft documentation. 
The BSC training review team may convene on an ad hoc basis under the following circumstances: 
x When a proposed change requires disposition before the next scheduled meeting 
x As requested by the sponsor of a change 
3. Concurrence 
I understand that I (or a representative from my organization) am responsible for attending all review 
meetings; assisting the BSC program manager with understanding the issues involved in each 
proposed change or authority issue presented to the BSC training review team; representing the 
interests of my organization; and providing technical, managerial, and administrative guidance on 
issues brought before the BSC training review team. 
Program Manager: John Smith 
Date 
BSC DAA: Paul Dodson 
Date 
LearningWorks Program Manager: Ryan Patrick 
Date 
Outreach Representative: Irina Roumiantseva 
Date 
ICE Representative: Tony Nelson 
Date 
Notebook Tools and Templates 36
Project Management Fundamentals Workshop 
Project Scoping Meeting Agenda Template 
Project Review Briefing Elements: 
ƒ Project Goal 
ƒ Project Requirements (Cost, Time, Scope/Quality): 
Project Discussion Areas: 
ƒ High-level objectives 
ƒ Cost/Benefit analysis 
ƒ Potential risks 
ƒ Core team analysis 
ƒ Stakeholder analysis 
ƒ Any remaining questions on the Critical Requirements Checklist 
Notebook Tools and Templates 37
Project Management Fundamentals Workshop 
Risk Assessment Chart Tool/Template 
Project 
Parameter 
Potential 
Problem 
When and 
How 
It Could Occur 
Probability of 
Occurrence and 
Impact 
Alternative 
Action 
Quality 
Budget 
Schedule 
Notebook Tools and Templates 38
Project Management Fundamentals Workshop 
Risk Management Plan Tool/Template 
Project 
Parameter 
Description Assessment 
Freq./Impact 
Response Documentation 
Quality 
Budget 
Schedule 
Notebook Tools and Templates 39
Project Management Fundamentals Workshop 
Stakeholder Analysis Tool/Template 
Stakeholders Position 
+ - 0 
Reason for 
Position 
Strategy 
Help Desk 
Manager 
IT Manager 
Union 
Representative 
Program Manager 
Notebook Tools and Templates 40
Project Management Fundamentals Workshop 
Task Responsibility Matrix Tool/Template 
Project: Claims Course 
Task ID 
Task 
(WBS #) 
Description 
Team Member 
Responsible/Duration 
1.1 Technology Survey J. Small – P 
6 weeks 
1.2.1 Computer Proposal 
Request 
J. Small – P 
4 weeks 
M. Byte – S 
2 weeks 
1.2.2 Evaluate Proposals J. Small – P 
2 weeks 
M. Byte – S 
2 weeks 
1.2.3 Award Contract P. Mason 
1 week 
1.3.1 Assemble System M. Byte 
Lead 
Vendor – P 
4 weeks 
1.3.3 Install/Test 
Computer 
M. Byte 
Lead 
Vendor – P 
4 weeks 
1.3.4 Network Terminals/ 
Test 
D. Reed – P 
2 weeks 
M. Byte – S 
1.4.1 Conduct Training 
Needs Assessment 
Berlitz – P 
4 weeks 
1.4.2 Design Training 
Course 
Berlitz – P 
1 week 
De Zeiner – S 
1 week 
1.4.3 Review and 
Approve Design 
Team to be appointed 
1 week 
1.4.4 Develop Course Berlitz – P 
2 weeks 
De Zeiner – S 
1.4.5 Review and 
Approve Course 
Team to be appointed 
1 week 
1.4.6 Publish Course Berlitz 
Lead 
Publishing Department 
1 week 
1.4.8 Train Claims 
Department 
Berlitz ? 
4 weeks 
Sylvan ? 
Legend: P = Prime Note: Write in the name of the person responsible for the task and 
S = Support indicate whether role is primary (P) or supporting (S). 
Notebook Tools and Templates 41
Project Management Fundamentals Workshop 
Work Breakdown Structure (WBS) Template 
Work Breakdown Structure 
Project: New Application Development and Integration 
Phase Task SubTask SubTask 
Start 
Date 
End 
Date Duration Depend. Resource 
1.0 Analysis 
1.1 First level 
task 
1.1.1 2nd Level 
Task 
1.1.1.1 Third Level Task 
Milestone 1.0 ¡ ¡ ¡ ¡ ¡ 
2.0 Design 
Milestone 2.0 ¡ ¡ ¡ ¡ ¡ 
Notebook Tools and Templates 42
Project Management Fundamentals Workshop 
Work Breakdown Structure 
Project: New Application Development and Integration 
Phase Task SubTask SubTask 
Start 
Date 
End 
Date Duration Depend. Resource 
3.0 Development 
4.0 Implementation 
5.0 Evaluation 
Notebook Tools and Templates 43
Project Management Fundamentals Workshop 
Work Breakdown Structure (WBS) Formats 
INDENTURED STRUCTURE WBS 
Level Description 
1 Project Name 
2 Major Project Elements 
3 Major Element Tasks 
4 Subtask 
5 Work Package 
TREE DIAGRAM STRUCTURE WBS 
PROJECT NAME 
Major Project 
Elements 
Major Project 
Elements 
Major Project 
Elements 
Task Task Task 
Subtask Subtask 
Notebook Tools and Templates 44
Project Management Fundamentals Workshop 
Work Breakdown Structure (WBS) Samples 
Indentured Structure 
1.0 Training Analysis and Development of Training Center 
1.1 Assess Training Needs 
1.1.1 Survey Instructors 
1.1.1.1 Make Student Throughput Chart 
1.1.1.2 Determine Types and Numbers of Courses Taught 
1.1.1.3 Assess Instructors’ Experience With AV Equip. 
1.1.1.3.1 Determine Instructors’ AV Preferences 
1.1.1.4 Determine Equipment Needs per Classroom 
1.2 Design and Layout Classrooms 
1.2.1 Obtain Engineering Drawings 
1.2.2 Draw Aids and Desks to Scale 
1.2.2.1 Sketch Various Room Arrangements 
1.3 Survey Available Technology 
1.3.1 Survey Vendors for State-of-the-art Equipment 
1.3.2 Cost/Benefit/Trade-Off Analysis 
1.4 Classroom/Teaching Aid Equipment 
1.4.1 Issue Request for Proposal (RFP) 
1.4.1.1 Prepare RFP/Equipment Specifications 
1.4.2 Evaluate Proposals 
1.4.2.1 Determine winner(s) 
1.4.3 Issue Contract(s) 
1.5 Install Equipment 
1.6 Program Support 
1.6.1 Project Management 
1.6.1.1 Clerical Support 
1.6.2 ODCs (Other Direct Costs) 
1.6.2.1 Consultants 
1.6.2.2 Marketing Support 
1.6.2.3 RFP Publication/Binders/Paper 
1.6.2.4 Copying 
Notebook Tools and Templates 45
Project Management Fundamentals Workshop 
Work Breakdown Structure (WBS) Samples 
Tree Diagram Structure 
Level 1 
Level 2 
Level 3 
Level 4 
Level 5 
Training Analysis 
and Development 
of Training Center 
Assess Training 
Needs 
Survey 
Instructors 
Determine 
Types and 
Numbers of 
Courses Taught 
Assess 
Instructors’ 
Experience 
Design and 
Layout 
Classrooms 
Obtain 
Engineering 
Drawings 
Determine 
Equipment 
Needs per 
Classroom 
Determine 
Instructors’ 
Preferences 
Draw Aids 
and Desks 
to Scale 
Sketch Various 
Room 
Arrangements 
Make 
Student 
Throughput 
Chart 
Notebook Tools and Templates 46

More Related Content

What's hot

Project manager project-plan-template-cm
Project manager project-plan-template-cmProject manager project-plan-template-cm
Project manager project-plan-template-cmPrasad Reddy
 
Scope Management Powerpoint Presentation Slides
Scope Management Powerpoint Presentation SlidesScope Management Powerpoint Presentation Slides
Scope Management Powerpoint Presentation SlidesSlideTeam
 
Project Management Plan Template
Project Management Plan TemplateProject Management Plan Template
Project Management Plan TemplateSimplilearn
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsJacobs Engineering
 
Software Project Management: Project Planning
Software Project Management: Project PlanningSoftware Project Management: Project Planning
Software Project Management: Project PlanningMinhas Kamal
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management MethodologyC.Y Wong
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsOxfordCambridge
 
Project Management Life Cycle Methodology PowerPoint Presentation Slides
Project Management Life Cycle Methodology PowerPoint Presentation Slides Project Management Life Cycle Methodology PowerPoint Presentation Slides
Project Management Life Cycle Methodology PowerPoint Presentation Slides SlideTeam
 
Project Management Steps And Process Powerpoint Presentation Slide
Project Management Steps And Process Powerpoint Presentation SlideProject Management Steps And Process Powerpoint Presentation Slide
Project Management Steps And Process Powerpoint Presentation SlideSlideTeam
 
Project Cost Estimation Methods PowerPoint Presentation Slides
Project Cost Estimation Methods PowerPoint Presentation Slides Project Cost Estimation Methods PowerPoint Presentation Slides
Project Cost Estimation Methods PowerPoint Presentation Slides SlideTeam
 
4-0 PROJECT EXECUTION AND CONTROL
4-0 PROJECT EXECUTION AND CONTROL4-0 PROJECT EXECUTION AND CONTROL
4-0 PROJECT EXECUTION AND CONTROLpmSPECFramework
 
Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter TemplateNaseer Muhammud
 
Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)stakeholdermap
 
Roles and-responsibilities-project manager
Roles and-responsibilities-project managerRoles and-responsibilities-project manager
Roles and-responsibilities-project managerobsession56
 
4 steps to perfect project planning
4 steps to perfect project planning4 steps to perfect project planning
4 steps to perfect project planningjosephb987
 

What's hot (20)

Project manager project-plan-template-cm
Project manager project-plan-template-cmProject manager project-plan-template-cm
Project manager project-plan-template-cm
 
Project Charter
Project CharterProject Charter
Project Charter
 
Scope Management Powerpoint Presentation Slides
Scope Management Powerpoint Presentation SlidesScope Management Powerpoint Presentation Slides
Scope Management Powerpoint Presentation Slides
 
Walking Through Your Project Proposal
Walking Through Your Project ProposalWalking Through Your Project Proposal
Walking Through Your Project Proposal
 
Project Management Plan Template
Project Management Plan TemplateProject Management Plan Template
Project Management Plan Template
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
 
Software Project Management: Project Planning
Software Project Management: Project PlanningSoftware Project Management: Project Planning
Software Project Management: Project Planning
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management Methodology
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Project Management Life Cycle Methodology PowerPoint Presentation Slides
Project Management Life Cycle Methodology PowerPoint Presentation Slides Project Management Life Cycle Methodology PowerPoint Presentation Slides
Project Management Life Cycle Methodology PowerPoint Presentation Slides
 
Project Management Steps And Process Powerpoint Presentation Slide
Project Management Steps And Process Powerpoint Presentation SlideProject Management Steps And Process Powerpoint Presentation Slide
Project Management Steps And Process Powerpoint Presentation Slide
 
Project Cost Estimation Methods PowerPoint Presentation Slides
Project Cost Estimation Methods PowerPoint Presentation Slides Project Cost Estimation Methods PowerPoint Presentation Slides
Project Cost Estimation Methods PowerPoint Presentation Slides
 
4-0 PROJECT EXECUTION AND CONTROL
4-0 PROJECT EXECUTION AND CONTROL4-0 PROJECT EXECUTION AND CONTROL
4-0 PROJECT EXECUTION AND CONTROL
 
Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter Template
 
Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)
 
Roles and-responsibilities-project manager
Roles and-responsibilities-project managerRoles and-responsibilities-project manager
Roles and-responsibilities-project manager
 
The role of the project manager
The role of the project managerThe role of the project manager
The role of the project manager
 
4 steps to perfect project planning
4 steps to perfect project planning4 steps to perfect project planning
4 steps to perfect project planning
 
Project management
Project managementProject management
Project management
 

Viewers also liked

Cafe construction project report
Cafe construction project reportCafe construction project report
Cafe construction project reportHagi Sahib
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.Hagi Sahib
 
Orgb Team Charter[1]
Orgb   Team Charter[1]Orgb   Team Charter[1]
Orgb Team Charter[1]guest30696ca8
 
Board of advisors sample charter and advisor role description
Board of advisors   sample charter and advisor role descriptionBoard of advisors   sample charter and advisor role description
Board of advisors sample charter and advisor role descriptionDave Litwiller
 
Final project report format
Final project report formatFinal project report format
Final project report formatMasud Sarkar
 
Project Management Plan - Cafe Au Lait.PDF
Project Management Plan - Cafe Au Lait.PDFProject Management Plan - Cafe Au Lait.PDF
Project Management Plan - Cafe Au Lait.PDFGeoff Penhorwood
 
Restaurant project
Restaurant projectRestaurant project
Restaurant projectArun Kabra
 
Sample project -Marketing Management
Sample project -Marketing Management Sample project -Marketing Management
Sample project -Marketing Management Mamta Narula
 
Fdrg bcn-015 - m icf project plan (june 2014)
Fdrg bcn-015 - m icf project plan (june 2014)Fdrg bcn-015 - m icf project plan (june 2014)
Fdrg bcn-015 - m icf project plan (june 2014)Stefanus Snyman
 
2008 Debrief Form
2008 Debrief Form2008 Debrief Form
2008 Debrief FormUSCGA
 
IIBA Facilitation Skills for Business Analysis v3
IIBA Facilitation Skills for Business Analysis v3IIBA Facilitation Skills for Business Analysis v3
IIBA Facilitation Skills for Business Analysis v3Rick Walters
 
The Project Café published
The Project Café publishedThe Project Café published
The Project Café publishedVishanka Gandhi
 
Employee Communications Focus Group Protocol
Employee Communications Focus Group ProtocolEmployee Communications Focus Group Protocol
Employee Communications Focus Group ProtocolShel Holtz
 
It's Not Your Fault - Blameless Post-mortems
It's Not Your Fault - Blameless Post-mortemsIt's Not Your Fault - Blameless Post-mortems
It's Not Your Fault - Blameless Post-mortemsJason Hand
 
Cafe on Wheels Project model
Cafe on Wheels Project modelCafe on Wheels Project model
Cafe on Wheels Project modelTambeAnagha
 
Work sample first grade detective descriptives writing workshop tasha grant
Work sample first grade detective descriptives writing workshop tasha grantWork sample first grade detective descriptives writing workshop tasha grant
Work sample first grade detective descriptives writing workshop tasha grantTasha Grant
 
Inception workshop - Kickstarting an Agile project in style
Inception workshop - Kickstarting an Agile project in styleInception workshop - Kickstarting an Agile project in style
Inception workshop - Kickstarting an Agile project in styleJenny Wong
 
Communicating meaning and purpose of spatio-temporal data analysis (master's ...
Communicating meaning and purpose of spatio-temporal data analysis (master's ...Communicating meaning and purpose of spatio-temporal data analysis (master's ...
Communicating meaning and purpose of spatio-temporal data analysis (master's ...Matthias Hinz
 

Viewers also liked (20)

Cafe construction project report
Cafe construction project reportCafe construction project report
Cafe construction project report
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.
 
Orgb Team Charter[1]
Orgb   Team Charter[1]Orgb   Team Charter[1]
Orgb Team Charter[1]
 
Board of advisors sample charter and advisor role description
Board of advisors   sample charter and advisor role descriptionBoard of advisors   sample charter and advisor role description
Board of advisors sample charter and advisor role description
 
Final project report format
Final project report formatFinal project report format
Final project report format
 
Project Management Plan - Cafe Au Lait.PDF
Project Management Plan - Cafe Au Lait.PDFProject Management Plan - Cafe Au Lait.PDF
Project Management Plan - Cafe Au Lait.PDF
 
Restaurant project
Restaurant projectRestaurant project
Restaurant project
 
Sample project -Marketing Management
Sample project -Marketing Management Sample project -Marketing Management
Sample project -Marketing Management
 
Fdrg bcn-015 - m icf project plan (june 2014)
Fdrg bcn-015 - m icf project plan (june 2014)Fdrg bcn-015 - m icf project plan (june 2014)
Fdrg bcn-015 - m icf project plan (june 2014)
 
2008 Debrief Form
2008 Debrief Form2008 Debrief Form
2008 Debrief Form
 
Team Charter
Team Charter Team Charter
Team Charter
 
IIBA Facilitation Skills for Business Analysis v3
IIBA Facilitation Skills for Business Analysis v3IIBA Facilitation Skills for Business Analysis v3
IIBA Facilitation Skills for Business Analysis v3
 
The Project Café published
The Project Café publishedThe Project Café published
The Project Café published
 
Employee Communications Focus Group Protocol
Employee Communications Focus Group ProtocolEmployee Communications Focus Group Protocol
Employee Communications Focus Group Protocol
 
It's Not Your Fault - Blameless Post-mortems
It's Not Your Fault - Blameless Post-mortemsIt's Not Your Fault - Blameless Post-mortems
It's Not Your Fault - Blameless Post-mortems
 
Cafe on Wheels Project model
Cafe on Wheels Project modelCafe on Wheels Project model
Cafe on Wheels Project model
 
Work sample first grade detective descriptives writing workshop tasha grant
Work sample first grade detective descriptives writing workshop tasha grantWork sample first grade detective descriptives writing workshop tasha grant
Work sample first grade detective descriptives writing workshop tasha grant
 
Elmaddah course list
Elmaddah course listElmaddah course list
Elmaddah course list
 
Inception workshop - Kickstarting an Agile project in style
Inception workshop - Kickstarting an Agile project in styleInception workshop - Kickstarting an Agile project in style
Inception workshop - Kickstarting an Agile project in style
 
Communicating meaning and purpose of spatio-temporal data analysis (master's ...
Communicating meaning and purpose of spatio-temporal data analysis (master's ...Communicating meaning and purpose of spatio-temporal data analysis (master's ...
Communicating meaning and purpose of spatio-temporal data analysis (master's ...
 

Similar to Project Management Sample

Proposed project plan template
Proposed project plan templateProposed project plan template
Proposed project plan templateMichelle Joja
 
Project management slide show
Project management slide showProject management slide show
Project management slide showTanvir Anwar
 
Project management slides
Project management slidesProject management slides
Project management slidesoswaldo79
 
Project management
Project managementProject management
Project managementArnab Ghosh
 
This unit forms part of the following qualification BSB50420
This unit forms part of the following qualification BSB50420 This unit forms part of the following qualification BSB50420
This unit forms part of the following qualification BSB50420 TakishaPeck109
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practicekrunalchem
 
Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 NotesSamarthVarpe
 
Project Preparation and Management
Project Preparation and ManagementProject Preparation and Management
Project Preparation and ManagementGBPUA&T, Pantnagar
 
Project planning
Project planningProject planning
Project planningShaikh Zain
 
The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkitsIT-Toolkits.org
 
4. Proper planning of a software project unless the project is trivia.pdf
4. Proper planning of a software project unless the project is trivia.pdf4. Proper planning of a software project unless the project is trivia.pdf
4. Proper planning of a software project unless the project is trivia.pdfeyevisioncare1
 
System Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptSystem Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptAynetuTerefe2
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdfSurashmie Kaalmegh
 
software (1).pptx
software (1).pptxsoftware (1).pptx
software (1).pptxayanadamtew
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptxAtulBhagwat6
 

Similar to Project Management Sample (20)

Systematic Innovation
Systematic InnovationSystematic Innovation
Systematic Innovation
 
Proposed project plan template
Proposed project plan templateProposed project plan template
Proposed project plan template
 
Project management slide show
Project management slide showProject management slide show
Project management slide show
 
Project management slides
Project management slidesProject management slides
Project management slides
 
grp 9.pptx
grp 9.pptxgrp 9.pptx
grp 9.pptx
 
Project management
Project managementProject management
Project management
 
Planning skill.pdf
Planning skill.pdfPlanning skill.pdf
Planning skill.pdf
 
This unit forms part of the following qualification BSB50420
This unit forms part of the following qualification BSB50420 This unit forms part of the following qualification BSB50420
This unit forms part of the following qualification BSB50420
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practice
 
Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 Notes
 
Project Preparation and Management
Project Preparation and ManagementProject Preparation and Management
Project Preparation and Management
 
Project planning
Project planningProject planning
Project planning
 
The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkits
 
Project management
Project managementProject management
Project management
 
Communication 1
Communication 1Communication 1
Communication 1
 
4. Proper planning of a software project unless the project is trivia.pdf
4. Proper planning of a software project unless the project is trivia.pdf4. Proper planning of a software project unless the project is trivia.pdf
4. Proper planning of a software project unless the project is trivia.pdf
 
System Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptSystem Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).ppt
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
 
software (1).pptx
software (1).pptxsoftware (1).pptx
software (1).pptx
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptx
 

More from Lori Krein Studios

Career Planning and Development Participant Guide
Career Planning and Development Participant GuideCareer Planning and Development Participant Guide
Career Planning and Development Participant GuideLori Krein Studios
 
Career Planning and Development class
Career Planning and Development classCareer Planning and Development class
Career Planning and Development classLori Krein Studios
 
Operational Leadership Power Point Sample
Operational Leadership Power Point SampleOperational Leadership Power Point Sample
Operational Leadership Power Point SampleLori Krein Studios
 
Operational Leadership Participant Guide Sample
Operational Leadership Participant Guide SampleOperational Leadership Participant Guide Sample
Operational Leadership Participant Guide SampleLori Krein Studios
 
Tv #4 how to create a collage landscape
Tv #4 how to create a collage landscapeTv #4 how to create a collage landscape
Tv #4 how to create a collage landscapeLori Krein Studios
 
Tv #5 tie dye peace sign collage
Tv #5 tie dye peace sign collageTv #5 tie dye peace sign collage
Tv #5 tie dye peace sign collageLori Krein Studios
 
Tv #8 friend assemblage with string
Tv #8 friend assemblage with stringTv #8 friend assemblage with string
Tv #8 friend assemblage with stringLori Krein Studios
 
How to Create an Assemblage with String
How to Create an Assemblage with StringHow to Create an Assemblage with String
How to Create an Assemblage with StringLori Krein Studios
 
Tv #20 simple house landscape with lokta paper
Tv #20 simple house landscape with lokta paperTv #20 simple house landscape with lokta paper
Tv #20 simple house landscape with lokta paperLori Krein Studios
 
Collage Techniques: "Painting with Paper"
Collage Techniques: "Painting with Paper"Collage Techniques: "Painting with Paper"
Collage Techniques: "Painting with Paper"Lori Krein Studios
 
Tv #3 How To Create A Tile Mosaic
Tv #3 How To Create A Tile MosaicTv #3 How To Create A Tile Mosaic
Tv #3 How To Create A Tile MosaicLori Krein Studios
 
Tv #2 How To Create An Eco Friendly Assemblage
Tv #2 How To Create An Eco Friendly AssemblageTv #2 How To Create An Eco Friendly Assemblage
Tv #2 How To Create An Eco Friendly AssemblageLori Krein Studios
 

More from Lori Krein Studios (20)

Expressive Art defined
Expressive Art definedExpressive Art defined
Expressive Art defined
 
Vision board
Vision boardVision board
Vision board
 
Career Planning and Development Participant Guide
Career Planning and Development Participant GuideCareer Planning and Development Participant Guide
Career Planning and Development Participant Guide
 
Career Planning and Development class
Career Planning and Development classCareer Planning and Development class
Career Planning and Development class
 
Operational Leadership Power Point Sample
Operational Leadership Power Point SampleOperational Leadership Power Point Sample
Operational Leadership Power Point Sample
 
Operational Leadership Participant Guide Sample
Operational Leadership Participant Guide SampleOperational Leadership Participant Guide Sample
Operational Leadership Participant Guide Sample
 
Tv #4 how to create a collage landscape
Tv #4 how to create a collage landscapeTv #4 how to create a collage landscape
Tv #4 how to create a collage landscape
 
Tv #5 tie dye peace sign collage
Tv #5 tie dye peace sign collageTv #5 tie dye peace sign collage
Tv #5 tie dye peace sign collage
 
Tv #6 decoupage vase
Tv #6 decoupage vaseTv #6 decoupage vase
Tv #6 decoupage vase
 
Tv #7 city scape
Tv #7 city scapeTv #7 city scape
Tv #7 city scape
 
Tv #11 solstice assemblage
Tv #11 solstice assemblageTv #11 solstice assemblage
Tv #11 solstice assemblage
 
Tv #8 friend assemblage with string
Tv #8 friend assemblage with stringTv #8 friend assemblage with string
Tv #8 friend assemblage with string
 
CityScape Collage Project
CityScape Collage ProjectCityScape Collage Project
CityScape Collage Project
 
How to Create an Assemblage with String
How to Create an Assemblage with StringHow to Create an Assemblage with String
How to Create an Assemblage with String
 
Tv #19 Simple Trees Collage
Tv #19 Simple Trees CollageTv #19 Simple Trees Collage
Tv #19 Simple Trees Collage
 
Tv #20 simple house landscape with lokta paper
Tv #20 simple house landscape with lokta paperTv #20 simple house landscape with lokta paper
Tv #20 simple house landscape with lokta paper
 
Collage Techniques: "Painting with Paper"
Collage Techniques: "Painting with Paper"Collage Techniques: "Painting with Paper"
Collage Techniques: "Painting with Paper"
 
Swan Day Details2010
Swan Day Details2010Swan Day Details2010
Swan Day Details2010
 
Tv #3 How To Create A Tile Mosaic
Tv #3 How To Create A Tile MosaicTv #3 How To Create A Tile Mosaic
Tv #3 How To Create A Tile Mosaic
 
Tv #2 How To Create An Eco Friendly Assemblage
Tv #2 How To Create An Eco Friendly AssemblageTv #2 How To Create An Eco Friendly Assemblage
Tv #2 How To Create An Eco Friendly Assemblage
 

Recently uploaded

WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)Delhi Call girls
 
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...poojakaurpk09
 
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)sonalinghatmal
 
Guide to a Winning Interview May 2024 for MCWN
Guide to a Winning Interview May 2024 for MCWNGuide to a Winning Interview May 2024 for MCWN
Guide to a Winning Interview May 2024 for MCWNBruce Bennett
 
Call Girls Devanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service B...
Call Girls Devanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service B...Call Girls Devanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service B...
Call Girls Devanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service B...amitlee9823
 
Personal Brand Exploration ppt.- Ronnie Jones
Personal Brand  Exploration ppt.- Ronnie JonesPersonal Brand  Exploration ppt.- Ronnie Jones
Personal Brand Exploration ppt.- Ronnie Jonesjonesyde302
 
Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...
Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...
Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...sonalitrivedi431
 
Call Girls Jayanagar Just Call 👗 9155563397 👗 Top Class Call Girl Service Ban...
Call Girls Jayanagar Just Call 👗 9155563397 👗 Top Class Call Girl Service Ban...Call Girls Jayanagar Just Call 👗 9155563397 👗 Top Class Call Girl Service Ban...
Call Girls Jayanagar Just Call 👗 9155563397 👗 Top Class Call Girl Service Ban...only4webmaster01
 
Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...amitlee9823
 
➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men 🔝bhavnagar🔝 Esc...
➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men  🔝bhavnagar🔝   Esc...➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men  🔝bhavnagar🔝   Esc...
➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men 🔝bhavnagar🔝 Esc...amitlee9823
 
Joshua Minker Brand Exploration Sports Broadcaster .pptx
Joshua Minker Brand Exploration Sports Broadcaster .pptxJoshua Minker Brand Exploration Sports Broadcaster .pptx
Joshua Minker Brand Exploration Sports Broadcaster .pptxsportsworldproductio
 
➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men 🔝Nandyal🔝 Escorts...
➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men  🔝Nandyal🔝   Escorts...➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men  🔝Nandyal🔝   Escorts...
➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men 🔝Nandyal🔝 Escorts...amitlee9823
 
Hot Call Girls |Delhi |Janakpuri ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Janakpuri ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Janakpuri ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Janakpuri ☎ 9711199171 Book Your One night Standkumarajju5765
 
Dombivli Call Girls, 9892124323, Kharghar Call Girls, chembur Call Girls, Vas...
Dombivli Call Girls, 9892124323, Kharghar Call Girls, chembur Call Girls, Vas...Dombivli Call Girls, 9892124323, Kharghar Call Girls, chembur Call Girls, Vas...
Dombivli Call Girls, 9892124323, Kharghar Call Girls, chembur Call Girls, Vas...Pooja Nehwal
 
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Sa...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Sa...Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Sa...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Sa...Pooja Nehwal
 
Miletti Gabriela_Vision Plan for artist Jahzel.pdf
Miletti Gabriela_Vision Plan for artist Jahzel.pdfMiletti Gabriela_Vision Plan for artist Jahzel.pdf
Miletti Gabriela_Vision Plan for artist Jahzel.pdfGabrielaMiletti
 
Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.GabrielaMiletti
 
Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...amitlee9823
 
Call Girls Hosur Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hosur Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hosur Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hosur Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...amitlee9823
 

Recently uploaded (20)

WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)
 
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
 
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)
 
Guide to a Winning Interview May 2024 for MCWN
Guide to a Winning Interview May 2024 for MCWNGuide to a Winning Interview May 2024 for MCWN
Guide to a Winning Interview May 2024 for MCWN
 
Call Girls Devanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service B...
Call Girls Devanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service B...Call Girls Devanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service B...
Call Girls Devanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service B...
 
Personal Brand Exploration ppt.- Ronnie Jones
Personal Brand  Exploration ppt.- Ronnie JonesPersonal Brand  Exploration ppt.- Ronnie Jones
Personal Brand Exploration ppt.- Ronnie Jones
 
Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...
Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...
Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...
 
Call Girls Jayanagar Just Call 👗 9155563397 👗 Top Class Call Girl Service Ban...
Call Girls Jayanagar Just Call 👗 9155563397 👗 Top Class Call Girl Service Ban...Call Girls Jayanagar Just Call 👗 9155563397 👗 Top Class Call Girl Service Ban...
Call Girls Jayanagar Just Call 👗 9155563397 👗 Top Class Call Girl Service Ban...
 
Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
 
➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men 🔝bhavnagar🔝 Esc...
➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men  🔝bhavnagar🔝   Esc...➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men  🔝bhavnagar🔝   Esc...
➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men 🔝bhavnagar🔝 Esc...
 
Joshua Minker Brand Exploration Sports Broadcaster .pptx
Joshua Minker Brand Exploration Sports Broadcaster .pptxJoshua Minker Brand Exploration Sports Broadcaster .pptx
Joshua Minker Brand Exploration Sports Broadcaster .pptx
 
➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men 🔝Nandyal🔝 Escorts...
➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men  🔝Nandyal🔝   Escorts...➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men  🔝Nandyal🔝   Escorts...
➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men 🔝Nandyal🔝 Escorts...
 
Hot Call Girls |Delhi |Janakpuri ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Janakpuri ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Janakpuri ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Janakpuri ☎ 9711199171 Book Your One night Stand
 
Dombivli Call Girls, 9892124323, Kharghar Call Girls, chembur Call Girls, Vas...
Dombivli Call Girls, 9892124323, Kharghar Call Girls, chembur Call Girls, Vas...Dombivli Call Girls, 9892124323, Kharghar Call Girls, chembur Call Girls, Vas...
Dombivli Call Girls, 9892124323, Kharghar Call Girls, chembur Call Girls, Vas...
 
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Sa...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Sa...Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Sa...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Sa...
 
Miletti Gabriela_Vision Plan for artist Jahzel.pdf
Miletti Gabriela_Vision Plan for artist Jahzel.pdfMiletti Gabriela_Vision Plan for artist Jahzel.pdf
Miletti Gabriela_Vision Plan for artist Jahzel.pdf
 
Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.
 
Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
 
Call Girls Hosur Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hosur Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hosur Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hosur Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
 

Project Management Sample

  • 1. Project Management Fundamentals Workshop Participant Notebook Notebook Overviews Action Plan............................................................................................................. 3 Communications Plan.............................................................................................. 4 Core Project Team Analysis ..................................................................................... 6 Cost/Benefit Analysis............................................................................................... 7 Critical Requirements Checklist ................................................................................ 8 Final Report ........................................................................................................... 9 Kick-Off Meeting ................................................................................................... 10 Lessons Learned................................................................................................... 11 Milestone Chart .................................................................................................... 12 Network Diagram.................................................................................................. 13 Post-Implementation Review Meeting..................................................................... 14 Project Charter ..................................................................................................... 15 Project Scoping Meeting ........................................................................................ 16 Risk Assessment Chart .......................................................................................... 17 Risk Management Plan .......................................................................................... 18 Stakeholder Analysis ............................................................................................. 19 Task Responsibility Matrix...................................................................................... 20 Work Breakdown Structure (WBS).......................................................................... 21
  • 2. Project Management Fundamentals Workshop Tools and Templates Action Plan Template ............................................................................................ 22 Communications Plan Template ............................................................................. 23 Core Project Team Analysis Template ..................................................................... 24 Cost/Benefit Analysis Worksheet ............................................................................ 25 Critical Requirements Checklist .............................................................................. 26 Final Report Template........................................................................................... 27 Kick-Off Meeting Checklist ..................................................................................... 28 Lessons Learned Checklist ..................................................................................... 29 Milestone Chart Template...................................................................................... 30 Network Diagram Sample ...................................................................................... 31 Post-Implementation Review Meeting Agenda......................................................... 32 Project Charter Sample ......................................................................................... 33 Project Scoping Meeting Agenda Template.............................................................. 37 Risk Assessment Chart Tool/Template .................................................................... 38 Risk Management Plan Tool/Template .................................................................... 39 Stakeholder Analysis Tool/Template ....................................................................... 40 Task Responsibility Matrix Tool/Template................................................................ 41 Work Breakdown Structure (WBS) Template ........................................................... 42 Work Breakdown Structure (WBS) Formats............................................................. 44 Work Breakdown Structure (WBS) Samples............................................................. 45
  • 3. Project Management Fundamentals Workshop Action Plan What? Document to establish and track action items or project steps including: Ɣ Agreements made during team meetings Ɣ Steps to be taken Ɣ Responsible team member(s) Ɣ Start and completion dates Ɣ Any clarifying notes Ɣ Status of action items When? During the project implementation and control phase. How? 1. Record the steps that need to be taken, who is responsible, start and completion dates, clarifying notes, and the status. 2. Update the status of the steps on a regular basis. 3. Use the information on the Action Plan for status reporting. View an action plan template. Notebook Overview 3
  • 4. Project Management Fundamentals Workshop Communications Plan What? Provides the process for documenting work performed during the project and the communication of this information to the project team and stakeholders. Note: Depending on the complexity or size of a project, other elements will also be included, such as multiple, concurrent work breakdown structures for large projects or contractual documents for projects that outsource tasks. When? During the project planning phase. How? 1. Create an agenda. 2. Identify the project audience(s). 3. Determine what stakeholders need, want, and expect to know, taking into consideration frequency and length of involvement of all stakeholders. 4. Identify information sources and assign responsibility for collecting information to be communicated. 5. Identify the best media and methods to communicate. Stakeholders may absorb information in different ways. 6. Identify key information that needs to be communicated regularly. 7. Define when and how communications will be provided. 8. Document any required approval process needed for any of the communications. 9. Assign responsibilities for creating and delivering the various types of communications. 10. Identify communication triggers, such as key Notebook Overview 4
  • 5. Project Management Fundamentals Workshop events/milestones/deliverable dates. 11. Define a process for handling ad hoc communications the project is likely to encounter. 12. Develop a library of project information, and assign responsibilities for its maintenance. 13. Create internal and external feedback loops to evaluate the effectiveness of communications. 14. Schedule the work of communications and related triggers into the project schedule to ensure they are part of the overall plan. 15. Define a process for updating/changing the Communications Plan. View a communication plan template. Notebook Overview 5
  • 6. Project Management Fundamentals Workshop Core Project Team Analysis What? A technique for identifying the key members of the team. It can also be used to negotiate with functional managers for resources and general project support. When? Ɣ During the definition phase to identify the key members of the project team. Ɣ During the planning phase to refine the makeup of the team. How? 1. Determine the major tasks that will have to be accomplished. 2. Determine which functional areas will most likely be affected by the project, i.e., those functional areas possessing the skills to accomplish part of the project. You should also determine who will be affected in a less direct way, such as customer service representatives. Note: Those who are not directly affected at the beginning of a project may be the ultimate users of the final product, and therefore, may have valuable insight for the definition and planning stages. 3. Determine the expertise required for the project. 4. Determine key people with the requisite expertise to form the core of the team. View a core project team analysis template. Notebook Overview 6
  • 7. Project Management Fundamentals Workshop Cost/Benefit Analysis What? A technique to determining if the benefits outweigh the costs of a project. When? During all phases of the project. Ɣ When you are determining whether to pursue a project. Ɣ During the prioritization of corporate projects. Ɣ Anytime there is a question about the relative benefit/cost of a project. How? 1. Estimate by year all the costs of the project including: x Development x Labor x Capital investment x Cost of maintenance x Cost of operation 2. Estimate the benefits of the project by putting dollar values on the following (by year): x Expected profits as a result of implementing the project. x Cost avoidance or savings in operating and maintenance costs because of having the new project in place. x Cost savings because of increased efficiency or speed. x Cost savings as a result of reduced labor if applicable. 3. Determine the break-even point. 4. Read the difference between the total benefits line and the total costs line. View a cost/benefit analysis worksheet. Notebook Overview 7
  • 8. Project Management Fundamentals Workshop Critical Requirements Checklist What? A checklist to aid in identifying all of the requirements of a project. When? During the definition and start-up phase to identify the project requirements, scope, and objectives. How? 1. Complete a cost/benefit analysis. 2. Determine the specific outcomes, success factors, goals, and objectives of the project. 3. Identify any the legal requirements and/or mandates. 4. Determine the structure and organization of the project. 5. Identify important tasks and milestones of the project and their schedule. 6. Identify the types of personnel schedules needed and how will they be used. 7. Determine the distribution of other resources (budget, equipment, materials, facilities) among the various tasks. 8. Determine how the key elements of the project (cost, performance, and schedule) will be estimated and controlled. 9. Identify potential problems and risk areas involved in carrying out the project and a plan to resolve or reduce them. View a critical requirements checklist. Notebook Overview 8
  • 9. Project Management Fundamentals Workshop Final Report What? A reporting technique to document information contained in the project plan, appropriate documentation of the post-implementation review meeting, lessons learned, and the budget, schedules, change orders, and updates. When? After the completion and delivery of the project. It is the last activity in the project completion phase. How? 1. Gather all data that have been generated during the life of the project. 2. Develop a report using the format on the following page. 3. Schedule a post-implementation review using the report data for a debriefing guide. 4. Distribute the Post-Implementation Review Report to appropriate stakeholders/customer representatives. View a final report template. Notebook Overview 9
  • 10. Project Management Fundamentals Workshop Kick-Off Meeting What? The kick-off meeting Ɣ Provides a briefing of the culmination of all the information gained through the other activities. Ɣ Provides a chance to discuss any potential trouble spots of the project or information that is still missing. Ɣ Gives the project manager the opportunity to gain buy-in from all team members. When? During the project planning phase. This is the last activity in the project planning phase. How? 1. Create an agenda. 2. Provide an overview of the project. 3. Discuss the project requirements and process. 4. Conduct team building activities. 5. Discuss general issues encountered by project team. 6. Clarify next steps. View a kick-off meeting checklist. Notebook Overview 10
  • 11. Project Management Fundamentals Workshop Lessons Learned What? Document that stores what was done right, wrong, and what would be done differently. It identifies the cause of variances, the reason for the corrective action, and any other lessons learned. When? Documentation of lessons learned should begin in the project implementation and control phase and continue through the project completion phase. How? 1. Maintain a lessons learned log throughout the life of the project. 2. Capture lessons learned as close as possible to the learning opportunity (e.g., after an issue has been resolved, change in scope has occurred, or a risk has been mitigated). 3. Review lessons learned as part of Risk Management. 4. Identify project management processes that can be improved as a result of lessons learned and make the improvements. 5. Summarize lessons learned in the Final Report. View a lessons learned checklist. Notebook Overview 11
  • 12. Project Management Fundamentals Workshop Milestone Chart What? A summary-level schedule that identifies key points in the project’s life span used to keep stakeholders informed of project progress and to alert them to schedule slippage. It displays the high-level picture of a project’s scheduled and actual milestone start and completion dates. When? During the project implementation and control phase to track milestone activity. Ɣ To provide a broad-brush picture of the project’s progress. Ɣ For an approval process. Note: If all the key events are going to be on the Gantt Chart, then the milestone tracking can be done directly from the Gantt Chart. How? Fill in the blanks by recording key events that are identified as milestones or that need approval before the project can proceed. Include key task events as well as events that have to be tracked for other than project progress, i.e., those events that senior management has identified for special review. View a milestone chart template. Notebook Overview 12
  • 13. Project Management Fundamentals Workshop Network Diagram What? A schematic display of task interdependencies that displays the relationships of project activities chronologically from left to right. The diagram uses project logic and critical path activities. When? During the project planning phase: Ɣ After completing the WBS. Ɣ Prior to completing the critical path. How? 1. Using the WBS, place the subtasks in the order in which they should be completed. 2. Identify concurrent tasks by rearranging them so that concurrent tasks align vertically. 3. Identify interdependencies among tasks. View a network diagram sample. Notebook Overview 13
  • 14. Project Management Fundamentals Workshop Post-Implementation Review Meeting What? A meeting with the project team to review the entire project for what went well, what did not go well, and how to perform tasks more effectively or efficiently in the future. This meeting is also called the project review meeting. When? After the completion and delivery of the project. It is the second to last activity to be completed in this phase. How? 1. Gather all data that have been generated during the life of the project. 2. Develop an agenda using the format on the following page. 3. Schedule a post-implementation review with the entire project team. View post-implementation review meeting agenda. Notebook Overview 14
  • 15. Project Management Fundamentals Workshop Project Charter What? Ɣ The project charter states the business case for and the goal of the project. Ɣ Each primary stakeholder should sign the charter as approval and support for the project. Ɣ The project charter lists the project manager and/or management team. Ɣ The charter should also include the initial time, cost, and performance requirements for the outcome. When? The project sponsor generally provides the project charter before or very early in the project definition and start-up phase. How? Use the project charter to: Ɣ Identify the problem statement. Ɣ Determine the project goal. Ɣ Determine the scope. Ɣ Identify the project requirements. View a sample project charter. Notebook Overview 15
  • 16. Project Management Fundamentals Workshop Project Scoping Meeting What? A meeting to determine the availability of potential resources to gain early stakeholder buy-in and clarify or confirm the project goals and requirements. When? During the project definition and start-up phase. How? 1. Review the project goals and requirements. 2. Discuss the high-level benefits. 3. Determine potential high-level risks. 4. Confirm resource appropriateness for project and availability. 5. Clarify or confirm stakeholder membership. 6. Review the critical requirements of the project. 7. Review project charter. View a project scoping meeting agenda template. Notebook Overview 16
  • 17. Project Management Fundamentals Workshop Risk Assessment Chart What? A simple technique that helps to minimize surprises which can occur during the life of a project. This chart is designed to help the project team think through the potential risks or problems related to the three main project parameters of time, cost, and scope/quality; identify the potential problem; recognize the problem if it occurs; and decide on the course of action. When? Anytime you want to identify and plan for potential problems. How? 1. Brainstorm with the project team members or other knowledgeable people who have been a part of a similar project to identify potential problems. 2. Fill in the Risk Assessment Chart to identify the problem, how and when the problem will surface, and what the alternative action will be. 3. Collect all the Risk Assessment Charts and make copies of them available to each team member. 4. If a potential problem is identified that is out of the sphere of the project manager’s control, provide a copy to the effected person or function and establish a monitoring system that will ensure the problem is corrected if it occurs. View a risk assessment chart tool/template. Notebook Overview 17
  • 18. Project Management Fundamentals Workshop Risk Management Plan What? A systematic approach to manage risks that includes: Ɣ Identifying the risk Ɣ Assessing the risk’s impact Ɣ Responding to the risk Ɣ Monitoring and controlling the When? During the project implementation and control phase. How? 1. Identify and describe the risk Ɇ A risk ID similar to a task ID allows the risk to be tracked and monitored. 2. Assess the risk’s impact Ɇ A probability/impact matrix categorizes risks based on the probability to occur and the impact if or when it does. Typically, this is expressed as “High/High” to “Low/Low.” 3. Respond to the risk – Risk response represents your desired general action when faced with that risk. Typical responses include avoid, accept, mitigate, or transfer. 4. Monitor and Control the risk – This involves documenting all aspects of the risks including the resolution decision. View a risk management plan tool/template. Notebook Overview 18
  • 19. Project Management Fundamentals Workshop Stakeholder Analysis What? A technique for identifying the parties-at-interest in a project. These are the people who have a vital concern for the success of the project because it directly impacts their function. When? Ɣ During the definition and start-up and planning phases to identify the stakeholders and to determine what level and type of involvement each should have. Ɣ During the life of the project to ensure that all parties-at-interest are being involved appropriately in the project. How? 1. List the significant stakeholders. 2. Identify if the listed people or groups will resist the project (-), support the project (+), or be neutral (0). 3. Describe the reason for each stakeholder’s position. 4. Identify any strategy or action you can take to maintain support, increase support, or overcome resistance. View a stakeholder analysis tool/template. Notebook Overview 19
  • 20. Project Management Fundamentals Workshop Task Responsibility Matrix What? A list of resources and their assigned tasks. Completing the task responsibility matrix helps to ensure the right number of the right resources are available at the right time. When? During the project planning phase, immediately after identifying the tasks in the WBS. How? After identify the project tasks: 1. Enter the WBS # in the task ID column of the matrix. 2. Enter a task description for each task ID. 3. Determine and enter the team member responsible for each identified task and his or her title (e.g., P for programmer). 4. Determine the time to complete the task and enter it below the responsible team member’s name. View a task responsibility matrix tool. Notebook Overview 20
  • 21. Project Management Fundamentals Workshop Work Breakdown Structure (WBS) What? A detailed list of project elements organized by deliverables. Each descending level of the list represents a more detailed definition of the work to be completed. The total listing defines the overall scope of the project. It acts as the vehicle for breaking down the work into smaller elements, providing a greater probability that every major and minor activity will be accounted for. When? Ɣ During the definition and start-up phase as a top-level view of the project’s resource requirements. Ɣ During the planning phase to refine the project resource requirements and budget, develop the Task Responsibility Matrix, and assign task responsibility. Ɣ During the implementation and control phase to monitor the project’s progress. Ɣ During the completion phase to assess if all the requirements have been accomplished. How? 1. Subdivide the total effort into discrete and logical sub-elements. A good approach is to view the subdivision process as a flow chart of the project from the whole to each succeeding lower level. 2. Check the proposed WBS elements for completeness, compatibility, and continuity. 3. Determine that the WBS satisfies all the project requirements. 4. Double check to determine if the WBS provides for logical subdivision of all project work. 5. Establish assignment of responsibilities for all identified effort to specific organizations. 6. Check the proposed WBS against the reporting requirements of the organizations involved. Note: The two most common ways to construct a WBS are the Indentured Structure and the Graphical Tree Diagram Structure. View a WBS template, WBS formats, or WBS samples. Notebook Overview 21
  • 22. Project Management Fundamentals Workshop Notebook Tools and Templates 22 Action Plan Template Status Notes Comp. Date Start Date Person(s) Responsible * = Primary Action Plan PROJECT: PERSON RESPONSIBLE: START DATE: COMPLETION DATE: Steps to be Taken
  • 23. Project Management Fundamentals Workshop Communications Plan Template Audiences Activity or Event When Method Person Responsible Sponsor Project Team Other Project Kickoff Project start (include date when planned) Meeting Project manager Approve Receive Project Plan Start and updates Document Team Meetings Weekly Document minutes project portal Major Milestone Announcements As completed Email Project Closeout Report End of project Document Notebook Tools and Templates 23
  • 24. Project Management Fundamentals Workshop Core Project Team Analysis Template Project: Directly Impacted Indirectly Impacted General Project Task Organizational Area(s) Organizational Area(s) Notebook Tools and Templates 24
  • 25. Project Management Fundamentals Workshop Cost/Benefit Analysis Worksheet BENEFITS Effect of New System on Annual Profits Present System (a) Proposed System (b) b-a A. Estimated Profit .................................. B. Total Difference in Estimated Profit .......................................................................................... Effect of New System on Annual Operating Expenses Present System Proposed System Annual Expense Decrease C. Equipment Rental ..................................................... $ $ $ D. Equipment Maintenance .......................................... E. Personnel (Include Benefits) .................................... F. Other Expenses (Specify) ......................................... 1. ....................................………………………………. 2. .........................................…………………………… 3. .............................................................................…. G. Total Expense Decrease ...........................................................................................……...... $ H. Total Benefits (B + G) ...................................................................................................……... $ COSTS Initial Investment Days of Labor Dollars I. Labor (By Labor Category) Development Implementation Salary/Day Total $s 1. ........................………………… 2. ....................……………………. 3. ...................…………………….. 4. ................................…………… 5. Other Labor ………………….. J. Total Labor Expense ...........................................................................................................……...... Dollars K. Capital Equipment/Setup/Testing Development Implementation Total 1. Facilities 2. Computers 3. Furniture 4. Equipment Installation/Setup 5. Equipment Testing 6. Other L. Total Capital Equipment Expense .....................................................................................….......... $ Dollars M. Other Expenses Development Implementation Total 1. Training 2. Supplies 3. Travel 4. Consultants 5. Miscellaneous N. Total Other Expenses..................................................................................................................... $ O. Total Costs (J + L + N) ..............................................................................................................… $ Total Benefit/Cost = H - O = _____________________ Estimated Break-Even Period: Year ____ Notebook Tools and Templates 25
  • 26. Project Management Fundamentals Workshop Critical Requirements Checklist Asked Question Answer … What are the specific outcomes, success factors, goals, and objectives of this project? … What are the legal requirements and/or mandates, if any? … How is the project going to be structured and organized? … What are the important tasks and milestones of the project, and how should they be scheduled? … What types of personnel are needed, and how will they be used? … How are other resources (budget, equipment, materials, facilities) going to be distributed among the various tasks? … How will the key elements of the project (cost, performance, and schedule) be estimated and controlled? What tools will be used? … What are the potential problems and risk areas involved in carrying out the project, and how will they be handled? … What are the costs/benefits of this project? Notebook Tools and Templates 26
  • 27. Project Management Fundamentals Workshop Final Report Template Executive Summary 1.0 Introduction 2.0 Project Review Project Objectives Project Approach Project Management and Planning Technology Project Deliverables Quality and Process Issues Resource Utilization Roles and Responsibilities Problems/Changes Encountered and Solutions Effected 3.0 Lessons Learned Appendix A: Post-implementation Review Session Notebook Tools and Templates 27
  • 28. Project Management Fundamentals Workshop Kick-Off Meeting Checklist … PROVIDE AN OVERVIEW OF THE PROJECT x Give background information of the project. x Describe project goals. x Explain how and why project team members were selected. x Explain role of stakeholders and functional managers. … DISCUSS PROJECT REQUIREMENTS AND PROCESSES x Discuss tentative schedule and budget. x Describe project outcomes or end results, objectives, and success criteria. x Discuss administrative issues and needs. x Discuss data collection and analysis process. x Identify the decision-making process. x Identify required documentation. x Discuss how the team members will communicate with each other and to the larger organization. x Discuss project evaluation processes. For the first “team members only” meeting, include the following: … CONDUCT TEAM BUILDING ACTIVITIES x Ask team members to introduce themselves and share their experiences working on projects. x As a team, set ground rules for how everyone will work together. x Discuss the value of individual differences and how each team member brings his/her unique contribution. x Identify expectations team members have for the team and for each other. … DISCUSS GENERAL ISSUES ENCOUNTERED BY PROJECT TEAMS x Discuss the pull between “back home” and project assignments. x Discuss team members’ conflicting loyalties. x Discuss predisposition toward solutions and using the problem-solving model to avoid this. x Identify “us” versus “them” thinking within and outside the team. x Discuss project activities as iterative processes. x Discuss the importance of attending to team processes. … CLARIFY NEXT STEPS Notebook Tools and Templates 28
  • 29. Project Management Fundamentals Workshop Lessons Learned Checklist … Have you identified sources of lessons learned to review before the start of the project (Post Implementation Reports, logs, databases, etc.)? … Are you logging lessons learned throughout the entire life of the project? … Have you clearly documented lessons learned and resolutions for the Post Implementation Report? … Are you implementing improvements learned from previous lessons in current and future projects? … Are you reviewing lessons learned to help with resolution of similar issues? … Did you review lessons learned as part of Risk Management? … Are you making improvements to project management processes as a result of using lessons learned? Notebook Tools and Templates 29
  • 30. Project Management Fundamentals Workshop Milestone Chart Template Milestone Scheduled Start Actual Start Scheduled Completion Actual Completion Notebook Tools and Templates 30
  • 31. Project Management Fundamentals Workshop Network Diagram Sample TaskID: 2.2.2 The Big Move Duration: 8 hours Task Name: Packing personal office items Notes: Time allotted equals one business day. Task can be accomplished around work schedule during this time. Labeled boxes will be needed prior to the start of this task. Status: Not Started 25% 50% 75% Completed Resource: Facility management, employees Dep: 1.3.4 Notebook Tools and Templates 31
  • 32. Project Management Fundamentals Workshop Post-Implementation Review Meeting Agenda Agenda 1. Review of project objectives and the project approach 2. Review of the planning process and project management 3. Review of the project milestones and deliverables 4. Identification of successful project elements 5. Identification of and review of the quality, cost, time, performance, and process issues 6. Review of the resource utilization and roles and responsibilities 7. Identification and review of the problems/changes encountered and their solutions 8. Discussion and documentation of lessons learned 9. Recognition of and rewards for the project team and team members Notebook Tools and Templates 32
  • 33. Project Management Fundamentals Workshop Project Charter Sample Biometric Support Center (BSC) Training Review Team Charter Objectives 0.1 Purpose of the Charter This charter establishes the United States Visitor and Immigrant Status Indicator Technology (US-VISIT) Biometric Support Center (BSC) Training Review Team and defines the mission, authority, responsibilities, membership, meeting schedule, and decision-making process. The LearningWorks Project Manager (LWPM) is responsible for the development, implementation, and maintenance of this charter. Any questions or suggestions for improvement of this charter should be directed to the LWPM. 0.2 Mission The mission of the BSC training review team is to develop materials that will increase the awareness by local law enforcement and other criminal justice agencies of the functions and services available through the BSC. To accomplish this mission, the BSC training review team will perform the following: x Recommend the content to be included in any products x Ensure that the content accurately reflects the viewpoints of the organizations represented x Review products and provide comments in a timely manner 0.3 Specific Efforts 0.3.1 Project Friction Ridge Brochure The Biometric Support Initiative (recently coined Project Friction Ridge) seeks to address the needs of local law enforcement through the creation of a brochure. This brochure will reflect the Project Friction Ridge-shared initiative and will showcase both the BSC and Immigration and Customs Enforcement (ICE). 0.3.2 Biometric Support Center eCard The BSC eCard is currently being developed to educate local and international law enforcement organizations about BSC capabilities. While this tool is considered a training tool, it may also function as a mechanism for promoting BSC services and Department of Homeland Security (DHS) agencies who work in conjunction with the BSC. 0.3.3 Train-the-Trainer Course A one-day Train-the-Trainer (TTT) course will be developed and presented to 26 ICE Special Agents in Charge (SAC). These agents will tour BSC facilities and learn to present a course on the BSC and the ICE Compliance Enforcement Unit (CEU) to local and state law enforcement agencies. Notebook Tools and Templates 33
  • 34. Project Management Fundamentals Workshop 1. Roles and Responsibilities 1.1 Development and Review Process 1. The LearningWorks training team will develop materials with the input of BSC training review team members. 2. The BSC training review team will meet to discuss the materials and any immediate changes. 3. The draft material will be provided to the BSC training review team for review and comments. 4. The comments provided by individual BSC training review team members should be complete and reflect the viewpoints of the respective organization. 5. The BSC training review team will meet to discuss the comments. 6. Comments accepted by all of the BSC training review team members will be incorporated into the material by the LearningWorks training team. 7. Issues that cannot be resolved by the BSC training review team shall be elevated to the BSC program manager. 8. The LearningWorks training team will revise draft materials. 9. The BSC program manager will approve the final product. 1.2 Responsibilities x The BSC program manager has the final say on all products. x The BSC Designated Authorizing Authority (DAA) has responsibility for approving or disapproving a recommended disposition for all proposed changes submitted to the BSC training review team at its level of authority. x An issue that cannot be resolved by the BSC training review team shall be elevated to the BSC program manager. x Individual BSC training review team standing members are responsible for attending all meetings and are assigned the responsibility of providing advice and counsel to the LWPM and the BSC DAA on proposed changes. x The LWPM will be responsible for leading meetings, maintaining schedules, and coordinating between organizations and agencies. x The LearningWorks training team will be responsible for all development of training materials as well as conducting any training events. x The BSC training review team standing members are responsible for providing technical, managerial, and administrative guidance on issues brought for review. x This is a joint effort; therefore, representatives from each organization are responsible for ensuring that their organization tries to restrict review cycles to the available timeframes. Any indication that conflicts are preventing the representatives from promoting their materials should be addressed to the LWPM so that the schedule can be updated, and to the BSC training review team to determine the effect on the schedule. Notebook Tools and Templates 34
  • 35. Project Management Fundamentals Workshop x US-VISIT Outreach (Outreach) will review materials to make suggestions regarding content and to keep all materials in alignment with the US-VISIT style guidelines. 1.3 Project-specific Responsibilities 1.3.1 Project Friction Ridge Brochure Since Project Friction Ridge promotes a blending of BSC and ICE support, this effort will include more extensive input from the ICE representatives than will be needed for the other efforts. Therefore, the schedule will reflect these needs. Ten working days will be provided to the ICE organization for review cycles, instead of the standard five working days. 1.3.2 Biometric Support Center eCard The BSC eCard is a mechanism to educate prospective organizations which may interface with the BSC about its services. The eCard will be used to both educate and promote the BSC. Outreach will be an integral member of this effort. ICE representatives will have a subject matter expert (SME) role in this effort to ensure that any references to ICE and BSC interaction accurately reflect the organizations’ partnership. 1.3.3 Train-the-Trainer Course The TTT course will be developed to support ICE SAC agents by providing a tour of BSC facilities and a training session on the BSC/ICE CEU program to be taught to local and state law enforcement agencies. This effort will require ICE representatives to speak the language and understand the mentality of their peers to ensure optimum learning. Outreach will review materials to make suggestions on content and to keep all materials in alignment with the US-VISIT style guidelines. 1.4 Membership The membership of the BSC training review team is comprised of standing members who are program representatives and ad hoc participants who are SMEs or stakeholders in a proposed change. 1.4.1 Permanent Members The BSC training review team consists of a program owner and standing members. 1.4.1.1 Program Owner The program owner of the BSC training review team is the BSC program manager. 1.4.1.2 Standing Members Standing members provide advice and counsel to the program owner by reviewing all materials presented to the BSC training review team. Standing members include the following: 1. BSC DAA 2. LearningWorks Program Manager 3. LearningWorks Deputy Program Manager 4. LWPM 5. BSC Representatives 6. LearningWorks Training Representatives Notebook Tools and Templates 35
  • 36. Project Management Fundamentals Workshop 7. Outreach Representatives 8. ICE Representatives 1.4.2 Effort-driven Membership There are three efforts associated with the current requirements for the BSC training review team; therefore, members may change from effort to effort. However, representatives from all organizations are encouraged to participate in all efforts. 1.4.3 Ad Hoc Members Ad hoc participants may attend meetings when invited by a permanent member. An ad hoc participant may be a stakeholder and may attend a meeting when a proposed issue in which he or she has a stake is on the agenda. 2. Meeting and Review Schedule The BSC training review team will meet as scheduled to determine the disposition of pending change requests and to review draft documentation. The BSC training review team may convene on an ad hoc basis under the following circumstances: x When a proposed change requires disposition before the next scheduled meeting x As requested by the sponsor of a change 3. Concurrence I understand that I (or a representative from my organization) am responsible for attending all review meetings; assisting the BSC program manager with understanding the issues involved in each proposed change or authority issue presented to the BSC training review team; representing the interests of my organization; and providing technical, managerial, and administrative guidance on issues brought before the BSC training review team. Program Manager: John Smith Date BSC DAA: Paul Dodson Date LearningWorks Program Manager: Ryan Patrick Date Outreach Representative: Irina Roumiantseva Date ICE Representative: Tony Nelson Date Notebook Tools and Templates 36
  • 37. Project Management Fundamentals Workshop Project Scoping Meeting Agenda Template Project Review Briefing Elements: ƒ Project Goal ƒ Project Requirements (Cost, Time, Scope/Quality): Project Discussion Areas: ƒ High-level objectives ƒ Cost/Benefit analysis ƒ Potential risks ƒ Core team analysis ƒ Stakeholder analysis ƒ Any remaining questions on the Critical Requirements Checklist Notebook Tools and Templates 37
  • 38. Project Management Fundamentals Workshop Risk Assessment Chart Tool/Template Project Parameter Potential Problem When and How It Could Occur Probability of Occurrence and Impact Alternative Action Quality Budget Schedule Notebook Tools and Templates 38
  • 39. Project Management Fundamentals Workshop Risk Management Plan Tool/Template Project Parameter Description Assessment Freq./Impact Response Documentation Quality Budget Schedule Notebook Tools and Templates 39
  • 40. Project Management Fundamentals Workshop Stakeholder Analysis Tool/Template Stakeholders Position + - 0 Reason for Position Strategy Help Desk Manager IT Manager Union Representative Program Manager Notebook Tools and Templates 40
  • 41. Project Management Fundamentals Workshop Task Responsibility Matrix Tool/Template Project: Claims Course Task ID Task (WBS #) Description Team Member Responsible/Duration 1.1 Technology Survey J. Small – P 6 weeks 1.2.1 Computer Proposal Request J. Small – P 4 weeks M. Byte – S 2 weeks 1.2.2 Evaluate Proposals J. Small – P 2 weeks M. Byte – S 2 weeks 1.2.3 Award Contract P. Mason 1 week 1.3.1 Assemble System M. Byte Lead Vendor – P 4 weeks 1.3.3 Install/Test Computer M. Byte Lead Vendor – P 4 weeks 1.3.4 Network Terminals/ Test D. Reed – P 2 weeks M. Byte – S 1.4.1 Conduct Training Needs Assessment Berlitz – P 4 weeks 1.4.2 Design Training Course Berlitz – P 1 week De Zeiner – S 1 week 1.4.3 Review and Approve Design Team to be appointed 1 week 1.4.4 Develop Course Berlitz – P 2 weeks De Zeiner – S 1.4.5 Review and Approve Course Team to be appointed 1 week 1.4.6 Publish Course Berlitz Lead Publishing Department 1 week 1.4.8 Train Claims Department Berlitz ? 4 weeks Sylvan ? Legend: P = Prime Note: Write in the name of the person responsible for the task and S = Support indicate whether role is primary (P) or supporting (S). Notebook Tools and Templates 41
  • 42. Project Management Fundamentals Workshop Work Breakdown Structure (WBS) Template Work Breakdown Structure Project: New Application Development and Integration Phase Task SubTask SubTask Start Date End Date Duration Depend. Resource 1.0 Analysis 1.1 First level task 1.1.1 2nd Level Task 1.1.1.1 Third Level Task Milestone 1.0 ¡ ¡ ¡ ¡ ¡ 2.0 Design Milestone 2.0 ¡ ¡ ¡ ¡ ¡ Notebook Tools and Templates 42
  • 43. Project Management Fundamentals Workshop Work Breakdown Structure Project: New Application Development and Integration Phase Task SubTask SubTask Start Date End Date Duration Depend. Resource 3.0 Development 4.0 Implementation 5.0 Evaluation Notebook Tools and Templates 43
  • 44. Project Management Fundamentals Workshop Work Breakdown Structure (WBS) Formats INDENTURED STRUCTURE WBS Level Description 1 Project Name 2 Major Project Elements 3 Major Element Tasks 4 Subtask 5 Work Package TREE DIAGRAM STRUCTURE WBS PROJECT NAME Major Project Elements Major Project Elements Major Project Elements Task Task Task Subtask Subtask Notebook Tools and Templates 44
  • 45. Project Management Fundamentals Workshop Work Breakdown Structure (WBS) Samples Indentured Structure 1.0 Training Analysis and Development of Training Center 1.1 Assess Training Needs 1.1.1 Survey Instructors 1.1.1.1 Make Student Throughput Chart 1.1.1.2 Determine Types and Numbers of Courses Taught 1.1.1.3 Assess Instructors’ Experience With AV Equip. 1.1.1.3.1 Determine Instructors’ AV Preferences 1.1.1.4 Determine Equipment Needs per Classroom 1.2 Design and Layout Classrooms 1.2.1 Obtain Engineering Drawings 1.2.2 Draw Aids and Desks to Scale 1.2.2.1 Sketch Various Room Arrangements 1.3 Survey Available Technology 1.3.1 Survey Vendors for State-of-the-art Equipment 1.3.2 Cost/Benefit/Trade-Off Analysis 1.4 Classroom/Teaching Aid Equipment 1.4.1 Issue Request for Proposal (RFP) 1.4.1.1 Prepare RFP/Equipment Specifications 1.4.2 Evaluate Proposals 1.4.2.1 Determine winner(s) 1.4.3 Issue Contract(s) 1.5 Install Equipment 1.6 Program Support 1.6.1 Project Management 1.6.1.1 Clerical Support 1.6.2 ODCs (Other Direct Costs) 1.6.2.1 Consultants 1.6.2.2 Marketing Support 1.6.2.3 RFP Publication/Binders/Paper 1.6.2.4 Copying Notebook Tools and Templates 45
  • 46. Project Management Fundamentals Workshop Work Breakdown Structure (WBS) Samples Tree Diagram Structure Level 1 Level 2 Level 3 Level 4 Level 5 Training Analysis and Development of Training Center Assess Training Needs Survey Instructors Determine Types and Numbers of Courses Taught Assess Instructors’ Experience Design and Layout Classrooms Obtain Engineering Drawings Determine Equipment Needs per Classroom Determine Instructors’ Preferences Draw Aids and Desks to Scale Sketch Various Room Arrangements Make Student Throughput Chart Notebook Tools and Templates 46