PROJ598—Contract and Procurement Management
RFP Template:
Template notes:
The formats of RFPs used by companies and government
agencies are seldom the same. The organization of the technical,
management, and commercial information included in RFPs
varies. There are six commonly used sections of information
that procurement groups include in RFPs. We will use these six
sections as a template for your RFPs.
1. Instructions to Bidders
2. Description of Work
3. Proposal
4. Specifications and Drawings
5. Special Conditions
6. General Conditions and Contract Agreement
The Instructions to Bidders section provides sufficient
information to bidders to allow them to prepare a responsive bid
proposal. Most of this information is not required in the final
contract for the work. The information in the Description of
Work, Proposal, Specifications and Drawings, Special
Conditions, and the General Conditions and Contract Agreement
sections is included in the final contract for the work. The
remainder of this template discusses each of these sections
included in RFPs.
Also, you will want to delete the description information (in
blue) after you have added your data under each section of the
template.
How to Make Sure You are Writing a Comprehensive RFP
The RFP should provide sufficient information for a bidder to
prepare a bid proposal that is responsive to each of the
technical, management, and commercial requirements specified
in the RFP.
The RFP should provide the necessary information concerning
contract requirements. When the information from the
successful bid proposal is combined with the requirements in
the RFP, all of the information required to prepare a contract
for the work should be available.
The management requirement in the RFP should define how the
contract work will be managed by the owner and the contractor.
Request for Proposal
Template
Name of the RFP topic you chose.
Name of your company (optional)
Company address (optional)
Company phone (optional)
Distribution list (optional)
Your name
Your e-mail address
PM598—Current term
TABLE OF CONTENTS
1. INSTRUCTIONS TO BIDDERS
..
9
1.1. General Description of Work
.
9
1.2. What Must Be Included with Bid
.
9
1.3. Schedule of Bid Period Activities
.
9
1.4. Location of Work
.
10
1.5. Pre-Bid Meeting
.
10
1.6. Owner Contact for Questions
.
10
1.7. Pre-Award Surveys
.
10
1.8. Sealed Bid Requirements
.
10
1.9. Basis for Bid Evaluation
..
11
1.10. Ethical Standards
.
11
1.11. Responsibility for Surety Bonds
.
11
1.12. Proposal Format
11
1.13. List of Bidders
.
11
1.14. Letter of Acknowledgment
11
2. DESCRIPTION OF WORK
..
12
2.1. Engineering Contracts
.
12
2.2. Construction Contracts
.
13
3. PROPOSAL
..
13
3.1. Breakdown of Bid Price
.
14
3.2. Revisions and Extra Work
.
14
3.3. Escalation Formulas
.
14
3.4. Scheduled Completion Dates
.
14
3.5. List of Subcontractors
.
14
3.6. Key Supplier or Contractor Personnel
14
3.7. Length of Time Bid Is Valid
.
14
3.8. List of Bid Document Addenda Reviewed by Bidder
14
3.9. Notice of Conflicts or Errors in Bid Documents
.
14
3.10. Clarifications of Bids
.
15
3.11. Bidder Signature
.
15
4. SPECIFICATIONS AND DRAWINGS
..
15
5. SPECIAL CONDITIONS
..
15
6. GENERAL CONDITIONS AND CONTRACT AGREEMENTS
..
16
Appendix A
..
17
Appendix B
..
18
Supplier/Bidder List
18
Note: Click somewhere within your table of contents, press F9,
select the “update entire table” radio button, and click “OK” to
refresh it automatically.
1. INSTRUCTIONS TO BIDDERS
The Instructions to Bidders section contains the information
that a bidder requires to prepare a bid proposal that is
responsive to each of the requirements that are included in other
sections of the RFP. Certain RFPs provide this information in
an Invitation to Bid letter as well as in the Instructions to
Bidders. The following sections discuss common items that are
included, in Instructions to Bidders (referred to as Instructions).
1.1. General Description of Work
The Instructions provide a general description of the work
covered by the contract. If there are detailed Description of
Work and Specifications and Drawings sections included in the
RFP, these sections are referenced in the general description of
the work.
1.2. What Must Be Included with Bid
To properly evaluate the bid proposals when they are received,
all of the information requested in the RFP must be provided by
the bidders. Since several sections of the RFP may require that
bidders submit specific information, the instructions summarize
the specific information that must be submitted with the bids.
Much of the specific information that is required from bidders
is addressed in the Proposal section. The technical
specifications in the RFP may require that bidders submit
certain technical data and procedures with their bid proposals.
The management requirements in the Special Conditions may
specify that bidders submit information such as quality, safety,
environmental, and schedule program descriptions. The
commercial requirements can define financial or insurance
documents that must be submitted by the bidders.
1.3. Schedule of Bid Period Activities
The Instructions define the date when bids are due. Many RFPs
provide the specific time of day that bids must be received.
Most companies will not accept bids after the due date. If a
bidder notifies an owner in advance that it cannot meet the
specified bid submittal date, an owner may extend the deadline
for all bidders. Continued extensions of the due dates for bid
proposals cause confusion among the bidders and hard feelings
on the part of the bidders that complete their proposals on time.
The Instructions should clearly define the owner's position on
receiving bids after the due date in the RFP. The Instructions
specify the location where bid proposals will be received by an
owner as well as the due date.
It is helpful to provide the bidders with an estimate of the date
when the contract will be awarded. This date is consistent with
project schedule requirements. Providing this date in the
Instructions gives the bidders an indication of when contract
work will begin and establishes the completion date for the
project groups responsible for evaluating the bids for the
contract.
If there are specific meetings scheduled during the bid
preparation period, the dates for these meetings are defined in
the Instructions. For example, there may be a pre-bid meeting to
explain the RFP and answer bidder questions. The owner may
also want to schedule project site visits and meetings with
specific bidders to review their technical and management
capabilities.
1.4. Location of Work
The Instructions give the location of the project site. Material
and equipment contract bidders need this information to
determine shipping costs. If shipments must be made to a
storage facility not at the project site, the Instructions provide
the location of the storage facility. Service contract bidders may
need to visit the site to obtain information necessary to
complete their bid proposals. The Instructions provide
information on how site visits are arranged with an owner. If
the project site is in a remote location, the Instructions provide
directions on how to get to the site.
1.5. Pre-Bid Meeting
Pre-bid meetings can be held after the RFPs are issued and prior
to the bid due date. Pre-bid meetings may be referred to with
other titles in RFPs, such as a pre-proposal conference in
government RFPs. If an owner intends to have a pre-bid
meeting, the Instructions provide the location, date, and time of
the meeting. The Instructions may also describe the purpose of
the meeting and how answers to questions from bidders will be
handled. The answers to the questions from bidders are
normally handled in a formal manner since they are a
supplement to the information provided in the RFP.
1.6. Owner Contact for Questions
It is important that an owner designate one individual to act as
the contact person for questions from bidders during the bid
period. This organizational approach assures that questions are
handled in a consistent manner and that all bidders receive the
same answers to questions. The answers to individual questions
from bidders during the bid period that are not responded to at a
pre-bid meeting are also important supplemental information to
the original RFP. The procurement group representative
assigned to a contract is often the designated contact person for
an owner. The Instructions specify the name of the person in the
owner's organization that is responsible for responding to bidder
questions. The Instructions also specify the telephone number
and address of the contact person. The Instructions define the
procedure that will be used for providing answers to all bidders
when one bidder asks a question concerning requirements in the
RFP.
1.7. Pre-Award Surveys
Certain owners perform pre-award surveys of specific bidders to
obtain information on technical and management capabilities.
These surveys are performed after the RFP is issued to the
bidders and prior to award. The surveys can require detailed
presentations from bidders regarding the technical and
management approaches that they will take on a contract. The
Instructions inform the bidders of the subjects that are covered
at these meetings. The surveys are usually conducted at the
bidder's facility since the adequacy of a bidder's facility is part
of the survey. The timing of a pre-award survey is established
on an individual bidder basis.
1.8. Sealed Bid Requirements
Many RFPs require that bid proposals are sealed when
submitted to an owner. This provides a measure of security that
bids have not been altered after they were prepared. The
Instructions define the sealed bid requirements. Requirements
for addressing the bids to the proper party are defined in the
Instructions. If the bids are not required to be sealed, the
Instructions address the acceptability of telegraphic and
facsimile bid proposals and bid proposal modifications. The
Instructions specify the number of copies of bid proposals that
are required.
1.9. Basis for Bid Evaluation
There are advantages in defining the basis that an owner will
use in evaluating bid proposals. If an owner intends to give
significant weight in its bid evaluation to factors such as
technical, quality and schedule control capability as well as
quoted prices, the bidders should be aware of this fact.
This gives them the opportunity to emphasize the strengths of
their technical and management programs. They may propose
stronger programs in these areas if they believe that this will
improve their chances of contract award. The Instructions
should define the basis that an owner will use to evaluate the
bidders for contract work.
1.10. Ethical Standards
Many owners include ethical standards that the owner and the
supplier or contractors are required to follow in their
relationships with one another prior to and after the award of a
contract in the Instructions. These standards often come from
corporate procurement policies. They include such item
restrictions on gifts and entertainment from suppliers and
contractors to owner personnel.
1.11. Responsibility for Surety Bonds
If another section of the RFP does not specify the exact
requirements for surety bonds for a contract, the Instructions
clarify the types of bonds required and the cost responsibility
for providing the bonds.
1.12. Proposal Format
If the RFP requires that bidders prepare detailed proposals
describing how they will accomplish contract work activities,
the Instructions define the format required for the proposals.
Limits may be placed on the length of different sections in the
proposal to ensure that overly lengthy proposals are not
received from bidders.
1.13. List of Bidders
Many RFPs include a list of the companies in the Instructions
section that have been asked to bid on the contract. This
approach has the advantage of making the bidders aware that
they are involved in a competitive bidding process.
Note: A place is provided in Appendix B for a detailed list of
bidders.
1.14. Letter of Acknowledgment
It is important that procurement groups receive feedback as
early as possible from companies that receive RFPs regarding
their intent to bid the work. If one or more companies on the list
of bidders for a contract decline to bid, there may be
insufficient bidders to satisfy competitive bidding requirements.
It may be necessary to send RFPs to additional bidders to obtain
the desired number of bid proposals. To obtain this feedback in
a timely manner, the Instructions often include a Letter of
Acknowledgment that requires bidders to state whether they
intend to submit bid proposals.
2. DESCRIPTION OF WORK
Service contracts require a Description of Work in the RFPs.
Certain large engineered materials and equipment contracts will
also require Description of Work sections in their RFPs. The
Description of Work has other titles such as Statement of Work
or Scope of Work in RFPs used by different companies and
government agencies. Other companies include the Description
of Work in the technical specifications for a contract.
The purpose of the Description of Work in the RFP is to define
the scope of work for a
contract. Other sections of the RFP for a contract such as the
Specifications and Drawings and the Special Conditions also
provide information that describes the work scope for bidders.
The Description of Work references the other RFP sections as
required.
2.1. Engineering Contracts
The Description for an engineering contract RFP contains an
overview of the technical features of a project. Other general
information such as the location of the project, existing
facilities at the project site, and responsibility for licensing and
permits is defined. If there is more than one engineering
contractor on a project, the scopes of the other engineering
contracts are defined in sufficient detail for the bidder to
understand its role in the design of a project.
If there is a performance specification in the engineering
contract RFP, the Description references the specification for
details concerning the technical requirements for the design of
the project. If there is not a performance specification included
in the RFP, the Description contains the owner's design
performance requirements. If the performance specification
includes design areas that are not in the scope of an engineering
contract, the Description explains which items in the
performance specification apply to the contract.
The division of responsibility between the owner and the
engineering contractor is explained in the Description. If an
owner intends to perform design functions such as establishing
design criteria for certain systems, these functions are defined.
The division of responsibility indicates which design documents
and procedures produced by the engineering contractor require
owner
approval. The division of responsibility also establishes the
materials and equipment that are procured by the owner and
those that are procured by the engineering contractor. The
division of responsibility defines whether the engineering
contractor or a supplier is responsible for the detailed design of
engineered materials.
The type and duration of the support that the engineering
contractor is required to provide to other project groups, such as
licensing, procurement, construction or manufacturing, and
testing, is addressed in the Description. If the engineering
contractor is required to provide liaison personnel at the project
site to clarify design requirements, this program is defined in
the Description.
The quality, schedule, cost, and other management programs
required to manage the engineering contract work can be
defined in the Description. An alternative approach is to include
the management requirements in the Special Conditions. It is
not significant which section of the RFP includes the
management requirements as long as they are well defined.
2.2. Construction Contracts
The Description for a construction contract RFP contains an
overview of the technical features of a project. It also provides
the location of the work, existing facilities at the project site,
and the responsibility for obtaining permits and licenses for a
project. If there are multiple construction contractors working
on the project, the scope of work of each construction
contractor is described in the Description.
If the construction contract pricing approach is fixed price or
unit price, there is a separate section of the RFP that contains
technical specifications and drawings. The construction
contractor's responsibilities for performing the work in these
specifications and drawings are defined in the Description. In
cases where the specifications and drawings include work
performed by more than one contractor, the specific
responsibilities of each contractor are defined in the
Description. If the specifications and drawings are not complete
when the RFP is issued, the degree of completion is defined in
the Description.
The division of responsibility between an owner and a
construction contractor is defined in the description. If the
construction contractor will be responsible for detailed design
functions, these functions are delineated in the division of
responsibility. The division of responsibility specifies the
materials and equipment that are furnished to a contractor by an
owner. It also specifies the materials and equipment that are
procured and installed by the contractor. The division of
responsibility defines the responsibility for testing the systems
and components installed by a contractor.
The construction contractor's responsibilities for providing
services such as clean up, scaffolding, temporary office
buildings, warehousing, temporary electrical, temporary heat,
security, and construction equipment are described in the
Description. If an owner elects to provide services to a
construction contractor, the services are defined in the
Description.
The support that a construction contractor is required to provide
to other project groups is defined in the Instructions. The
contractor can be required to provide as built drawings to the
engineering group for final design validation. The contractor
may have to provide construction personnel to the testing group
to support testing activities. The contractor can be responsible
for providing scaffolding for access for inspections by owner
quality personnel.
The quality, schedule, cost, safety, environmental, and other
management programs required to control the construction
contract work can be addressed in the Description. They can
also be addressed in the Special Conditions.
3. PROPOSAL
The Proposal section of the RFP contains all of the pricing
information required from bidders to allow an owner to evaluate
the costs of the bids. It can also define technical and
management information that is required from the bidders. The
Proposal section of the RFP can have different titles in the RFPs
issued by different companies. Certain companies call the
Proposal section a Bid Form.
3.1. Breakdown of Bid Price
It is important that the bidder understand the scope of work that
is covered by each requested bid price item. It is helpful to
reference the Description of Work and the Specifications and
Drawings sections of the RFP in defining the scope of work for
each bid price item.
3.2. Revisions and Extra Work
If unit prices are feasible for extra work, the Proposal specifies
the unit prices required. If extra work will be handled on a
reimbursable basis, the Proposal can request cost limits for the
reimbursable work.
3.3. Escalation Formulas
If the owner is requesting fixed price bids subject to escalation
of labor and material costs, the Proposal requests the formulas
that will be applied to current labor and material prices to
determine escalation costs. The structure of these formulas can
significantly impact the cost of a contract.
3.4. Scheduled Completion Dates
If an owner wants a bidder to provide schedule dates for key
contract activities, the Proposal lists the key schedule activities
and requests that the contractor provide the dates. Start and
completion dates for key contract schedule activities may be
requested.
3.5. List of Subcontractors
The Proposal section provides space for bidders to list the
subcontractors that they intend to use to perform the contract
work. In addition to the names of subcontract firms, bidders
should provide descriptions of the subcontractor work scopes,
subcontractor experience, location of subcontractor offices, and
telephone numbers.
3.6. Key Supplier or Contractor Personnel
The Proposal requires that a supplier or a contractor name the
person that will be in charge of the contract work and will be
the primary contact for an owner. The names of other key
personnel can be requested in the Proposal section.
3.7. Length of Time Bid Is Valid
If there is a possibility that the award of a contract will not
occur until a significant period of time after bids are received,
the Proposal requests the length of time that a bid is valid after
receipt by an owner.
3.8. List of Bid Document Addenda Reviewed by Bidder
If there are bid document addenda issued after the RFP is
issued, the Proposal section requests that bidders list the
addenda that they have reviewed. This procedure ensures that
all bidders have reviewed the necessary documents.
3.9. Notice of Conflicts or Errors in Bid Documents
Requesting that bidders formally notify an owner of conflicts or
errors in bid documents provides a formal means of
communicating conflicts and errors. The errors can be corrected
prior to the start of contract work.
3.10. Clarifications of Bids
Certain Proposal sections provide space for a bidder to state any
clarifications or exceptions to its bid. Although the intent of the
RFP is to define the work scope in a manner that eliminates the
need for clarifications and exceptions, there may be items that
are not clear that should be addressed. Excessive clarifications
or exceptions may cause a bid proposal to be rejected.
3.11. Bidder Signature
The Proposal contains space for the supplier or the contractor to
sign its completed Proposal. It also includes the date the
Proposal is signed, the title of the person signing, and any
required identification numbers or license numbers.
4. SPECIFICATIONS AND DRAWINGS
Specifications and Drawings sections are required for RFPs for
fixed and unit price contracts. They are also required for target
price and reimbursable with incentive fee contracts since they
define the basis of targets and incentive fees. Depending upon
how the contracts are scoped on a project, the specifications and
drawings included in the RFP may or may not relate only to the
contract for which the RFP is prepared. The Description of
Work explains which portions of the specifications and
drawings relate to a particular contract. In some cases, the
specifications and drawings are marked up to define contract
work scopes.
Service contracts usually require a Description of Work in
addition to the Specifications and Drawings in the RFP to
clarify the work activities that are the responsibility of a
contractor. Many engineered materials and equipment contracts
do not require extensive Description of Work sections since all
necessary information for the bidders is included in the
Specifications and Drawings.
Note: Don’t spend too much time creating drawings or
specifications. Simply cut and paste a picture from the internet
and describe it here.
5. SPECIAL CONDITIONS
The Special Conditions section of the RFP includes all of the
management requirements and any other specific contract
requirements. The Special Conditions section usually does not
address the technical requirements for a project.
The management requirements for RFP's are prepared by several
different project groups as discussed previously. The
procurement group receives the management requirements for
each contract from these groups. In many cases the language of
the management requirements for different contracts can be
similar. The procurement group works with the other project
groups to determine the extent that management clauses can be
standardized in the Special Conditions. Important management
requirements for a specific contract should not be omitted from
the RFP for the sake of standardization.
Certain RFPs include the Special Conditions information in the
Description of Work section. This eliminates the need for the
Special Conditions. As long as the management requirements
are well defined, it makes little difference if they are included
in the Description of Work or the Special Conditions.
Many RFPs do not adequately define all of the necessary
management requirements for a contract. Inadequate definition
of management requirements can lead to poor management of a
contract. Project management has the overall responsibility for
assuring that RFP's adequately define management
requirements. It is helpful to include all of the management
requirements for a particular area such as control of quality in
one part of the RFP. If the quality requirements are contained in
different sections in the RFP, it can be difficult to determine if
the necessary quality requirements are all included in the RFP.
6. GENERAL CONDITIONS AND CONTRACT AGREEMENTS
The General Conditions section of the RFP contains the
commercial requirements for a contract. Many of these
commercial terms cover situations, such as changes to the
original contract, technical and management requirements, or
cases in which the contractor does not perform in accordance
with these requirements. Other commercial clauses cover terms
of payment, invoicing, and responsibility for tax payments.
Since the procurement group is responsible for preparing these
commercial terms with assistance from the legal group, the
procurement group can prepare the General Conditions section
of the RFP with relatively little input from other project groups.
Many RFPs contain a Contract Agreement section in addition to
the General Conditions. The purpose of including the Contract
Agreement section in the RFP is to show the bidders the
contract format that will be used if they are awarded the
contract. Contract Agreements contain commercial clauses that
are very similar to the clauses normally included in the General
Conditions. The Contract Agreement usually includes the
General Conditions, Description of Work, Proposal,
Specifications and Drawings, and Special Conditions sections in
the contract by referencing these documents. This means that
the requirements of all of these sections are a part of the
contract. It is not significant which commercial requirements
are included in the Contract Agreement and which requirements
are included in the General Conditions since both sections are
included in a signed contract.
Appendix A
Acknowledgment Letter for bid no. ______
(RFP Description)
(Project Description)
Attention: ___________________________
Date:________________
(contact representative)
Receipt of the above captioned Request for Proposal is hereby
acknowledged with the following comments:
£
We will submit a bid on or before
______________________
£
We will not submit a bid for the following reasons:
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
___________________________________________
__________________________ has been assigned to be the
primary contact person for the bid submission process.
The contact telephone, fax, and e-mail are as follows.
Telephone
________________________________
Fax
________________________________
E-mail
________________________________
Designated
Officer
________________________________
Title
________________________________
Address
________________________________
________________________________
Appendix B
Supplier/Bidder List
Supplier/Bidder
Contact #
How I chose these potential suppliers:
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
__________________________________________

More Related Content

Similar to PROJ598—Contract and Procurement ManagementRFP Templat.docx

How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docx
How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docxHow to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docx
How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docxpooleavelina
 
Proposal and Bid Management Terms.pptx
Proposal and Bid Management  Terms.pptxProposal and Bid Management  Terms.pptx
Proposal and Bid Management Terms.pptxNavas Kilikkottu
 
RFP execution a practical guideline to improve selection process
RFP execution a practical guideline to improve selection processRFP execution a practical guideline to improve selection process
RFP execution a practical guideline to improve selection processMario Navarro
 
Social Media Consulting Services RFP
Social Media Consulting Services RFPSocial Media Consulting Services RFP
Social Media Consulting Services RFPDemand Metric
 
Advertising Agency RFP Template
Advertising Agency RFP Template Advertising Agency RFP Template
Advertising Agency RFP Template Demand Metric
 
CRM Consulting Services RFP
CRM Consulting Services RFPCRM Consulting Services RFP
CRM Consulting Services RFPDemand Metric
 
Your-22-Step-Guide-to-the-RFP-Process.pdf
Your-22-Step-Guide-to-the-RFP-Process.pdfYour-22-Step-Guide-to-the-RFP-Process.pdf
Your-22-Step-Guide-to-the-RFP-Process.pdfPushkarP2
 
C:\Users\Michele Roth\Documents\Hrd 870 Bronack\Hrd870grouppppresentationfinal
C:\Users\Michele Roth\Documents\Hrd 870 Bronack\Hrd870grouppppresentationfinalC:\Users\Michele Roth\Documents\Hrd 870 Bronack\Hrd870grouppppresentationfinal
C:\Users\Michele Roth\Documents\Hrd 870 Bronack\Hrd870grouppppresentationfinalMichele Roth
 
Hrd870grouppppresentationfinal
Hrd870grouppppresentationfinalHrd870grouppppresentationfinal
Hrd870grouppppresentationfinalMichele Roth
 
RFQ-RFP Best Practices Workshop Jan2012.ppt
RFQ-RFP Best Practices Workshop Jan2012.pptRFQ-RFP Best Practices Workshop Jan2012.ppt
RFQ-RFP Best Practices Workshop Jan2012.pptAravindReddyKetham1
 
Marketing Automation Consulting RFP
Marketing Automation Consulting RFPMarketing Automation Consulting RFP
Marketing Automation Consulting RFPDemand Metric
 
Public Relations Agency RFP
Public Relations Agency RFPPublic Relations Agency RFP
Public Relations Agency RFPDemand Metric
 
Business negotiations for purchasing and supply chain management
Business negotiations for purchasing and supply chain managementBusiness negotiations for purchasing and supply chain management
Business negotiations for purchasing and supply chain managementSajeena Justin
 
Tender and tender document
Tender and tender documentTender and tender document
Tender and tender documentAkshataFarakate
 
Procurement seminar
Procurement seminarProcurement seminar
Procurement seminarshabbirjaved
 
LMS RFP Template / Sample
LMS RFP Template / SampleLMS RFP Template / Sample
LMS RFP Template / SampleParadiso LMS
 
Real Stories from the RFP Process
Real Stories from the RFP ProcessReal Stories from the RFP Process
Real Stories from the RFP Processrshonerd
 

Similar to PROJ598—Contract and Procurement ManagementRFP Templat.docx (20)

How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docx
How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docxHow to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docx
How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docx
 
Evaluation Training Guide
Evaluation Training GuideEvaluation Training Guide
Evaluation Training Guide
 
IT Service Desk Software RFP Template
IT Service Desk Software RFP TemplateIT Service Desk Software RFP Template
IT Service Desk Software RFP Template
 
Proposal and Bid Management Terms.pptx
Proposal and Bid Management  Terms.pptxProposal and Bid Management  Terms.pptx
Proposal and Bid Management Terms.pptx
 
RFP execution a practical guideline to improve selection process
RFP execution a practical guideline to improve selection processRFP execution a practical guideline to improve selection process
RFP execution a practical guideline to improve selection process
 
Social Media Consulting Services RFP
Social Media Consulting Services RFPSocial Media Consulting Services RFP
Social Media Consulting Services RFP
 
Advertising Agency RFP Template
Advertising Agency RFP Template Advertising Agency RFP Template
Advertising Agency RFP Template
 
CRM Consulting Services RFP
CRM Consulting Services RFPCRM Consulting Services RFP
CRM Consulting Services RFP
 
Your-22-Step-Guide-to-the-RFP-Process.pdf
Your-22-Step-Guide-to-the-RFP-Process.pdfYour-22-Step-Guide-to-the-RFP-Process.pdf
Your-22-Step-Guide-to-the-RFP-Process.pdf
 
C:\Users\Michele Roth\Documents\Hrd 870 Bronack\Hrd870grouppppresentationfinal
C:\Users\Michele Roth\Documents\Hrd 870 Bronack\Hrd870grouppppresentationfinalC:\Users\Michele Roth\Documents\Hrd 870 Bronack\Hrd870grouppppresentationfinal
C:\Users\Michele Roth\Documents\Hrd 870 Bronack\Hrd870grouppppresentationfinal
 
Hrd870grouppppresentationfinal
Hrd870grouppppresentationfinalHrd870grouppppresentationfinal
Hrd870grouppppresentationfinal
 
RFQ-RFP Best Practices Workshop Jan2012.ppt
RFQ-RFP Best Practices Workshop Jan2012.pptRFQ-RFP Best Practices Workshop Jan2012.ppt
RFQ-RFP Best Practices Workshop Jan2012.ppt
 
Marketing Automation Consulting RFP
Marketing Automation Consulting RFPMarketing Automation Consulting RFP
Marketing Automation Consulting RFP
 
Public Relations Agency RFP
Public Relations Agency RFPPublic Relations Agency RFP
Public Relations Agency RFP
 
Business negotiations for purchasing and supply chain management
Business negotiations for purchasing and supply chain managementBusiness negotiations for purchasing and supply chain management
Business negotiations for purchasing and supply chain management
 
Tender and tender document
Tender and tender documentTender and tender document
Tender and tender document
 
Chapter -Two (3).pdf
Chapter -Two (3).pdfChapter -Two (3).pdf
Chapter -Two (3).pdf
 
Procurement seminar
Procurement seminarProcurement seminar
Procurement seminar
 
LMS RFP Template / Sample
LMS RFP Template / SampleLMS RFP Template / Sample
LMS RFP Template / Sample
 
Real Stories from the RFP Process
Real Stories from the RFP ProcessReal Stories from the RFP Process
Real Stories from the RFP Process
 

More from leahlegrand

Q1-  Calculate the Sum, Wrapped Sum and Checksum from the follow.docx
Q1-  Calculate the Sum, Wrapped Sum and Checksum from the follow.docxQ1-  Calculate the Sum, Wrapped Sum and Checksum from the follow.docx
Q1-  Calculate the Sum, Wrapped Sum and Checksum from the follow.docxleahlegrand
 
Q1 Write a function in PHP that receives a number as an input.docx
Q1 Write a function in PHP that receives a number as an input.docxQ1 Write a function in PHP that receives a number as an input.docx
Q1 Write a function in PHP that receives a number as an input.docxleahlegrand
 
Q1. Discuss the civil liability of auditors to third parties under.docx
Q1. Discuss the civil liability of auditors to third parties under.docxQ1. Discuss the civil liability of auditors to third parties under.docx
Q1. Discuss the civil liability of auditors to third parties under.docxleahlegrand
 
Q1. Morocco has a flexible exchange rate regime. The demand for do.docx
Q1. Morocco has a flexible exchange rate regime. The demand for do.docxQ1. Morocco has a flexible exchange rate regime. The demand for do.docx
Q1. Morocco has a flexible exchange rate regime. The demand for do.docxleahlegrand
 
Q1- Why does a router normally have more than one interfaceQ2- .docx
Q1- Why does a router normally have more than one interfaceQ2- .docxQ1- Why does a router normally have more than one interfaceQ2- .docx
Q1- Why does a router normally have more than one interfaceQ2- .docxleahlegrand
 
Q.1selesct any current event .which level of government,federal or .docx
Q.1selesct any current event .which level of government,federal or .docxQ.1selesct any current event .which level of government,federal or .docx
Q.1selesct any current event .which level of government,federal or .docxleahlegrand
 
Q 2Researchers commonly consider the effects of their studies .docx
Q 2Researchers commonly consider the effects of their studies .docxQ 2Researchers commonly consider the effects of their studies .docx
Q 2Researchers commonly consider the effects of their studies .docxleahlegrand
 
Putin’s Plan – PBS frontline worldhttpwww.pbs.orgfro.docx
Putin’s Plan – PBS frontline worldhttpwww.pbs.orgfro.docxPutin’s Plan – PBS frontline worldhttpwww.pbs.orgfro.docx
Putin’s Plan – PBS frontline worldhttpwww.pbs.orgfro.docxleahlegrand
 
Put yourself in the shoes of a person living in Europe during the Mi.docx
Put yourself in the shoes of a person living in Europe during the Mi.docxPut yourself in the shoes of a person living in Europe during the Mi.docx
Put yourself in the shoes of a person living in Europe during the Mi.docxleahlegrand
 
Purpose The goal of this exercise is to observe a cultural scene.docx
Purpose The goal of this exercise is to observe a cultural scene.docxPurpose The goal of this exercise is to observe a cultural scene.docx
Purpose The goal of this exercise is to observe a cultural scene.docxleahlegrand
 
Q1 Describe the ways in which Elena challenges gender expectation f.docx
Q1 Describe the ways in which Elena challenges gender expectation f.docxQ1 Describe the ways in which Elena challenges gender expectation f.docx
Q1 Describe the ways in which Elena challenges gender expectation f.docxleahlegrand
 
Q 1Over the past 16 years, only two building permits for new h.docx
Q 1Over the past 16 years, only two building permits for new h.docxQ 1Over the past 16 years, only two building permits for new h.docx
Q 1Over the past 16 years, only two building permits for new h.docxleahlegrand
 
Q 2In qualitative studies, individual or institutional harm an.docx
Q 2In qualitative studies, individual or institutional harm an.docxQ 2In qualitative studies, individual or institutional harm an.docx
Q 2In qualitative studies, individual or institutional harm an.docxleahlegrand
 
Purpose This assignment gives you a chance to produce a scholar.docx
Purpose This assignment gives you a chance to produce a scholar.docxPurpose This assignment gives you a chance to produce a scholar.docx
Purpose This assignment gives you a chance to produce a scholar.docxleahlegrand
 
PurposeThe purpose of this assignment is to provide the student .docx
PurposeThe purpose of this assignment is to provide the student .docxPurposeThe purpose of this assignment is to provide the student .docx
PurposeThe purpose of this assignment is to provide the student .docxleahlegrand
 
PurposeTo assess your ability toDescribe technologies that unde.docx
PurposeTo assess your ability toDescribe technologies that unde.docxPurposeTo assess your ability toDescribe technologies that unde.docx
PurposeTo assess your ability toDescribe technologies that unde.docxleahlegrand
 
Purpose The purpose of Draft 3 is to build upon Draft 2 and.docx
Purpose The purpose of Draft 3 is to build upon Draft 2 and.docxPurpose The purpose of Draft 3 is to build upon Draft 2 and.docx
Purpose The purpose of Draft 3 is to build upon Draft 2 and.docxleahlegrand
 
Purpose of the paper is to examine the issues related to corrections.docx
Purpose of the paper is to examine the issues related to corrections.docxPurpose of the paper is to examine the issues related to corrections.docx
Purpose of the paper is to examine the issues related to corrections.docxleahlegrand
 
Public speaking is different from conversation. Explain differences.docx
Public speaking is different from conversation. Explain differences.docxPublic speaking is different from conversation. Explain differences.docx
Public speaking is different from conversation. Explain differences.docxleahlegrand
 
Published on The Root (httpwww.theroot.com) ! Why I A.docx
Published on The Root (httpwww.theroot.com) ! Why I A.docxPublished on The Root (httpwww.theroot.com) ! Why I A.docx
Published on The Root (httpwww.theroot.com) ! Why I A.docxleahlegrand
 

More from leahlegrand (20)

Q1-  Calculate the Sum, Wrapped Sum and Checksum from the follow.docx
Q1-  Calculate the Sum, Wrapped Sum and Checksum from the follow.docxQ1-  Calculate the Sum, Wrapped Sum and Checksum from the follow.docx
Q1-  Calculate the Sum, Wrapped Sum and Checksum from the follow.docx
 
Q1 Write a function in PHP that receives a number as an input.docx
Q1 Write a function in PHP that receives a number as an input.docxQ1 Write a function in PHP that receives a number as an input.docx
Q1 Write a function in PHP that receives a number as an input.docx
 
Q1. Discuss the civil liability of auditors to third parties under.docx
Q1. Discuss the civil liability of auditors to third parties under.docxQ1. Discuss the civil liability of auditors to third parties under.docx
Q1. Discuss the civil liability of auditors to third parties under.docx
 
Q1. Morocco has a flexible exchange rate regime. The demand for do.docx
Q1. Morocco has a flexible exchange rate regime. The demand for do.docxQ1. Morocco has a flexible exchange rate regime. The demand for do.docx
Q1. Morocco has a flexible exchange rate regime. The demand for do.docx
 
Q1- Why does a router normally have more than one interfaceQ2- .docx
Q1- Why does a router normally have more than one interfaceQ2- .docxQ1- Why does a router normally have more than one interfaceQ2- .docx
Q1- Why does a router normally have more than one interfaceQ2- .docx
 
Q.1selesct any current event .which level of government,federal or .docx
Q.1selesct any current event .which level of government,federal or .docxQ.1selesct any current event .which level of government,federal or .docx
Q.1selesct any current event .which level of government,federal or .docx
 
Q 2Researchers commonly consider the effects of their studies .docx
Q 2Researchers commonly consider the effects of their studies .docxQ 2Researchers commonly consider the effects of their studies .docx
Q 2Researchers commonly consider the effects of their studies .docx
 
Putin’s Plan – PBS frontline worldhttpwww.pbs.orgfro.docx
Putin’s Plan – PBS frontline worldhttpwww.pbs.orgfro.docxPutin’s Plan – PBS frontline worldhttpwww.pbs.orgfro.docx
Putin’s Plan – PBS frontline worldhttpwww.pbs.orgfro.docx
 
Put yourself in the shoes of a person living in Europe during the Mi.docx
Put yourself in the shoes of a person living in Europe during the Mi.docxPut yourself in the shoes of a person living in Europe during the Mi.docx
Put yourself in the shoes of a person living in Europe during the Mi.docx
 
Purpose The goal of this exercise is to observe a cultural scene.docx
Purpose The goal of this exercise is to observe a cultural scene.docxPurpose The goal of this exercise is to observe a cultural scene.docx
Purpose The goal of this exercise is to observe a cultural scene.docx
 
Q1 Describe the ways in which Elena challenges gender expectation f.docx
Q1 Describe the ways in which Elena challenges gender expectation f.docxQ1 Describe the ways in which Elena challenges gender expectation f.docx
Q1 Describe the ways in which Elena challenges gender expectation f.docx
 
Q 1Over the past 16 years, only two building permits for new h.docx
Q 1Over the past 16 years, only two building permits for new h.docxQ 1Over the past 16 years, only two building permits for new h.docx
Q 1Over the past 16 years, only two building permits for new h.docx
 
Q 2In qualitative studies, individual or institutional harm an.docx
Q 2In qualitative studies, individual or institutional harm an.docxQ 2In qualitative studies, individual or institutional harm an.docx
Q 2In qualitative studies, individual or institutional harm an.docx
 
Purpose This assignment gives you a chance to produce a scholar.docx
Purpose This assignment gives you a chance to produce a scholar.docxPurpose This assignment gives you a chance to produce a scholar.docx
Purpose This assignment gives you a chance to produce a scholar.docx
 
PurposeThe purpose of this assignment is to provide the student .docx
PurposeThe purpose of this assignment is to provide the student .docxPurposeThe purpose of this assignment is to provide the student .docx
PurposeThe purpose of this assignment is to provide the student .docx
 
PurposeTo assess your ability toDescribe technologies that unde.docx
PurposeTo assess your ability toDescribe technologies that unde.docxPurposeTo assess your ability toDescribe technologies that unde.docx
PurposeTo assess your ability toDescribe technologies that unde.docx
 
Purpose The purpose of Draft 3 is to build upon Draft 2 and.docx
Purpose The purpose of Draft 3 is to build upon Draft 2 and.docxPurpose The purpose of Draft 3 is to build upon Draft 2 and.docx
Purpose The purpose of Draft 3 is to build upon Draft 2 and.docx
 
Purpose of the paper is to examine the issues related to corrections.docx
Purpose of the paper is to examine the issues related to corrections.docxPurpose of the paper is to examine the issues related to corrections.docx
Purpose of the paper is to examine the issues related to corrections.docx
 
Public speaking is different from conversation. Explain differences.docx
Public speaking is different from conversation. Explain differences.docxPublic speaking is different from conversation. Explain differences.docx
Public speaking is different from conversation. Explain differences.docx
 
Published on The Root (httpwww.theroot.com) ! Why I A.docx
Published on The Root (httpwww.theroot.com) ! Why I A.docxPublished on The Root (httpwww.theroot.com) ! Why I A.docx
Published on The Root (httpwww.theroot.com) ! Why I A.docx
 

Recently uploaded

Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 

Recently uploaded (20)

TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 

PROJ598—Contract and Procurement ManagementRFP Templat.docx

  • 1. PROJ598—Contract and Procurement Management RFP Template: Template notes: The formats of RFPs used by companies and government agencies are seldom the same. The organization of the technical, management, and commercial information included in RFPs varies. There are six commonly used sections of information that procurement groups include in RFPs. We will use these six sections as a template for your RFPs. 1. Instructions to Bidders 2. Description of Work 3. Proposal 4. Specifications and Drawings 5. Special Conditions 6. General Conditions and Contract Agreement
  • 2. The Instructions to Bidders section provides sufficient information to bidders to allow them to prepare a responsive bid proposal. Most of this information is not required in the final contract for the work. The information in the Description of Work, Proposal, Specifications and Drawings, Special Conditions, and the General Conditions and Contract Agreement sections is included in the final contract for the work. The remainder of this template discusses each of these sections included in RFPs. Also, you will want to delete the description information (in blue) after you have added your data under each section of the template. How to Make Sure You are Writing a Comprehensive RFP The RFP should provide sufficient information for a bidder to prepare a bid proposal that is responsive to each of the technical, management, and commercial requirements specified in the RFP. The RFP should provide the necessary information concerning contract requirements. When the information from the successful bid proposal is combined with the requirements in the RFP, all of the information required to prepare a contract for the work should be available. The management requirement in the RFP should define how the contract work will be managed by the owner and the contractor.
  • 3. Request for Proposal Template Name of the RFP topic you chose. Name of your company (optional) Company address (optional) Company phone (optional) Distribution list (optional) Your name Your e-mail address
  • 4. PM598—Current term TABLE OF CONTENTS 1. INSTRUCTIONS TO BIDDERS .. 9 1.1. General Description of Work . 9 1.2. What Must Be Included with Bid . 9 1.3. Schedule of Bid Period Activities . 9 1.4. Location of Work . 10 1.5. Pre-Bid Meeting . 10 1.6. Owner Contact for Questions . 10
  • 5. 1.7. Pre-Award Surveys . 10 1.8. Sealed Bid Requirements . 10 1.9. Basis for Bid Evaluation .. 11 1.10. Ethical Standards . 11 1.11. Responsibility for Surety Bonds . 11 1.12. Proposal Format 11 1.13. List of Bidders . 11 1.14. Letter of Acknowledgment 11 2. DESCRIPTION OF WORK .. 12 2.1. Engineering Contracts .
  • 6. 12 2.2. Construction Contracts . 13 3. PROPOSAL .. 13 3.1. Breakdown of Bid Price . 14 3.2. Revisions and Extra Work . 14 3.3. Escalation Formulas . 14 3.4. Scheduled Completion Dates . 14 3.5. List of Subcontractors . 14 3.6. Key Supplier or Contractor Personnel 14 3.7. Length of Time Bid Is Valid . 14
  • 7. 3.8. List of Bid Document Addenda Reviewed by Bidder 14 3.9. Notice of Conflicts or Errors in Bid Documents . 14 3.10. Clarifications of Bids . 15 3.11. Bidder Signature . 15 4. SPECIFICATIONS AND DRAWINGS .. 15 5. SPECIAL CONDITIONS .. 15 6. GENERAL CONDITIONS AND CONTRACT AGREEMENTS .. 16 Appendix A .. 17 Appendix B .. 18
  • 8. Supplier/Bidder List 18 Note: Click somewhere within your table of contents, press F9, select the “update entire table” radio button, and click “OK” to refresh it automatically. 1. INSTRUCTIONS TO BIDDERS The Instructions to Bidders section contains the information that a bidder requires to prepare a bid proposal that is responsive to each of the requirements that are included in other sections of the RFP. Certain RFPs provide this information in an Invitation to Bid letter as well as in the Instructions to Bidders. The following sections discuss common items that are included, in Instructions to Bidders (referred to as Instructions). 1.1. General Description of Work The Instructions provide a general description of the work covered by the contract. If there are detailed Description of Work and Specifications and Drawings sections included in the RFP, these sections are referenced in the general description of the work. 1.2. What Must Be Included with Bid To properly evaluate the bid proposals when they are received,
  • 9. all of the information requested in the RFP must be provided by the bidders. Since several sections of the RFP may require that bidders submit specific information, the instructions summarize the specific information that must be submitted with the bids. Much of the specific information that is required from bidders is addressed in the Proposal section. The technical specifications in the RFP may require that bidders submit certain technical data and procedures with their bid proposals. The management requirements in the Special Conditions may specify that bidders submit information such as quality, safety, environmental, and schedule program descriptions. The commercial requirements can define financial or insurance documents that must be submitted by the bidders. 1.3. Schedule of Bid Period Activities The Instructions define the date when bids are due. Many RFPs provide the specific time of day that bids must be received. Most companies will not accept bids after the due date. If a bidder notifies an owner in advance that it cannot meet the specified bid submittal date, an owner may extend the deadline for all bidders. Continued extensions of the due dates for bid proposals cause confusion among the bidders and hard feelings on the part of the bidders that complete their proposals on time. The Instructions should clearly define the owner's position on receiving bids after the due date in the RFP. The Instructions specify the location where bid proposals will be received by an owner as well as the due date. It is helpful to provide the bidders with an estimate of the date when the contract will be awarded. This date is consistent with project schedule requirements. Providing this date in the Instructions gives the bidders an indication of when contract work will begin and establishes the completion date for the
  • 10. project groups responsible for evaluating the bids for the contract. If there are specific meetings scheduled during the bid preparation period, the dates for these meetings are defined in the Instructions. For example, there may be a pre-bid meeting to explain the RFP and answer bidder questions. The owner may also want to schedule project site visits and meetings with specific bidders to review their technical and management capabilities. 1.4. Location of Work The Instructions give the location of the project site. Material and equipment contract bidders need this information to determine shipping costs. If shipments must be made to a storage facility not at the project site, the Instructions provide the location of the storage facility. Service contract bidders may need to visit the site to obtain information necessary to complete their bid proposals. The Instructions provide information on how site visits are arranged with an owner. If the project site is in a remote location, the Instructions provide directions on how to get to the site. 1.5. Pre-Bid Meeting Pre-bid meetings can be held after the RFPs are issued and prior to the bid due date. Pre-bid meetings may be referred to with other titles in RFPs, such as a pre-proposal conference in government RFPs. If an owner intends to have a pre-bid meeting, the Instructions provide the location, date, and time of the meeting. The Instructions may also describe the purpose of the meeting and how answers to questions from bidders will be handled. The answers to the questions from bidders are
  • 11. normally handled in a formal manner since they are a supplement to the information provided in the RFP. 1.6. Owner Contact for Questions It is important that an owner designate one individual to act as the contact person for questions from bidders during the bid period. This organizational approach assures that questions are handled in a consistent manner and that all bidders receive the same answers to questions. The answers to individual questions from bidders during the bid period that are not responded to at a pre-bid meeting are also important supplemental information to the original RFP. The procurement group representative assigned to a contract is often the designated contact person for an owner. The Instructions specify the name of the person in the owner's organization that is responsible for responding to bidder questions. The Instructions also specify the telephone number and address of the contact person. The Instructions define the procedure that will be used for providing answers to all bidders when one bidder asks a question concerning requirements in the RFP. 1.7. Pre-Award Surveys Certain owners perform pre-award surveys of specific bidders to obtain information on technical and management capabilities. These surveys are performed after the RFP is issued to the bidders and prior to award. The surveys can require detailed presentations from bidders regarding the technical and management approaches that they will take on a contract. The Instructions inform the bidders of the subjects that are covered at these meetings. The surveys are usually conducted at the bidder's facility since the adequacy of a bidder's facility is part of the survey. The timing of a pre-award survey is established on an individual bidder basis.
  • 12. 1.8. Sealed Bid Requirements Many RFPs require that bid proposals are sealed when submitted to an owner. This provides a measure of security that bids have not been altered after they were prepared. The Instructions define the sealed bid requirements. Requirements for addressing the bids to the proper party are defined in the Instructions. If the bids are not required to be sealed, the Instructions address the acceptability of telegraphic and facsimile bid proposals and bid proposal modifications. The Instructions specify the number of copies of bid proposals that are required. 1.9. Basis for Bid Evaluation There are advantages in defining the basis that an owner will use in evaluating bid proposals. If an owner intends to give significant weight in its bid evaluation to factors such as technical, quality and schedule control capability as well as quoted prices, the bidders should be aware of this fact. This gives them the opportunity to emphasize the strengths of their technical and management programs. They may propose stronger programs in these areas if they believe that this will improve their chances of contract award. The Instructions should define the basis that an owner will use to evaluate the bidders for contract work. 1.10. Ethical Standards Many owners include ethical standards that the owner and the supplier or contractors are required to follow in their relationships with one another prior to and after the award of a contract in the Instructions. These standards often come from
  • 13. corporate procurement policies. They include such item restrictions on gifts and entertainment from suppliers and contractors to owner personnel. 1.11. Responsibility for Surety Bonds If another section of the RFP does not specify the exact requirements for surety bonds for a contract, the Instructions clarify the types of bonds required and the cost responsibility for providing the bonds. 1.12. Proposal Format If the RFP requires that bidders prepare detailed proposals describing how they will accomplish contract work activities, the Instructions define the format required for the proposals. Limits may be placed on the length of different sections in the proposal to ensure that overly lengthy proposals are not received from bidders. 1.13. List of Bidders Many RFPs include a list of the companies in the Instructions section that have been asked to bid on the contract. This approach has the advantage of making the bidders aware that they are involved in a competitive bidding process. Note: A place is provided in Appendix B for a detailed list of bidders. 1.14. Letter of Acknowledgment
  • 14. It is important that procurement groups receive feedback as early as possible from companies that receive RFPs regarding their intent to bid the work. If one or more companies on the list of bidders for a contract decline to bid, there may be insufficient bidders to satisfy competitive bidding requirements. It may be necessary to send RFPs to additional bidders to obtain the desired number of bid proposals. To obtain this feedback in a timely manner, the Instructions often include a Letter of Acknowledgment that requires bidders to state whether they intend to submit bid proposals. 2. DESCRIPTION OF WORK Service contracts require a Description of Work in the RFPs. Certain large engineered materials and equipment contracts will also require Description of Work sections in their RFPs. The Description of Work has other titles such as Statement of Work or Scope of Work in RFPs used by different companies and government agencies. Other companies include the Description of Work in the technical specifications for a contract. The purpose of the Description of Work in the RFP is to define the scope of work for a contract. Other sections of the RFP for a contract such as the Specifications and Drawings and the Special Conditions also provide information that describes the work scope for bidders. The Description of Work references the other RFP sections as required. 2.1. Engineering Contracts The Description for an engineering contract RFP contains an
  • 15. overview of the technical features of a project. Other general information such as the location of the project, existing facilities at the project site, and responsibility for licensing and permits is defined. If there is more than one engineering contractor on a project, the scopes of the other engineering contracts are defined in sufficient detail for the bidder to understand its role in the design of a project. If there is a performance specification in the engineering contract RFP, the Description references the specification for details concerning the technical requirements for the design of the project. If there is not a performance specification included in the RFP, the Description contains the owner's design performance requirements. If the performance specification includes design areas that are not in the scope of an engineering contract, the Description explains which items in the performance specification apply to the contract. The division of responsibility between the owner and the engineering contractor is explained in the Description. If an owner intends to perform design functions such as establishing design criteria for certain systems, these functions are defined. The division of responsibility indicates which design documents and procedures produced by the engineering contractor require owner approval. The division of responsibility also establishes the materials and equipment that are procured by the owner and those that are procured by the engineering contractor. The division of responsibility defines whether the engineering contractor or a supplier is responsible for the detailed design of engineered materials.
  • 16. The type and duration of the support that the engineering contractor is required to provide to other project groups, such as licensing, procurement, construction or manufacturing, and testing, is addressed in the Description. If the engineering contractor is required to provide liaison personnel at the project site to clarify design requirements, this program is defined in the Description. The quality, schedule, cost, and other management programs required to manage the engineering contract work can be defined in the Description. An alternative approach is to include the management requirements in the Special Conditions. It is not significant which section of the RFP includes the management requirements as long as they are well defined. 2.2. Construction Contracts The Description for a construction contract RFP contains an overview of the technical features of a project. It also provides the location of the work, existing facilities at the project site, and the responsibility for obtaining permits and licenses for a project. If there are multiple construction contractors working on the project, the scope of work of each construction contractor is described in the Description. If the construction contract pricing approach is fixed price or unit price, there is a separate section of the RFP that contains technical specifications and drawings. The construction contractor's responsibilities for performing the work in these specifications and drawings are defined in the Description. In
  • 17. cases where the specifications and drawings include work performed by more than one contractor, the specific responsibilities of each contractor are defined in the Description. If the specifications and drawings are not complete when the RFP is issued, the degree of completion is defined in the Description. The division of responsibility between an owner and a construction contractor is defined in the description. If the construction contractor will be responsible for detailed design functions, these functions are delineated in the division of responsibility. The division of responsibility specifies the materials and equipment that are furnished to a contractor by an owner. It also specifies the materials and equipment that are procured and installed by the contractor. The division of responsibility defines the responsibility for testing the systems and components installed by a contractor. The construction contractor's responsibilities for providing services such as clean up, scaffolding, temporary office buildings, warehousing, temporary electrical, temporary heat, security, and construction equipment are described in the Description. If an owner elects to provide services to a construction contractor, the services are defined in the Description. The support that a construction contractor is required to provide to other project groups is defined in the Instructions. The contractor can be required to provide as built drawings to the engineering group for final design validation. The contractor
  • 18. may have to provide construction personnel to the testing group to support testing activities. The contractor can be responsible for providing scaffolding for access for inspections by owner quality personnel. The quality, schedule, cost, safety, environmental, and other management programs required to control the construction contract work can be addressed in the Description. They can also be addressed in the Special Conditions. 3. PROPOSAL The Proposal section of the RFP contains all of the pricing information required from bidders to allow an owner to evaluate the costs of the bids. It can also define technical and management information that is required from the bidders. The Proposal section of the RFP can have different titles in the RFPs issued by different companies. Certain companies call the Proposal section a Bid Form. 3.1. Breakdown of Bid Price It is important that the bidder understand the scope of work that is covered by each requested bid price item. It is helpful to reference the Description of Work and the Specifications and Drawings sections of the RFP in defining the scope of work for each bid price item. 3.2. Revisions and Extra Work If unit prices are feasible for extra work, the Proposal specifies the unit prices required. If extra work will be handled on a reimbursable basis, the Proposal can request cost limits for the reimbursable work.
  • 19. 3.3. Escalation Formulas If the owner is requesting fixed price bids subject to escalation of labor and material costs, the Proposal requests the formulas that will be applied to current labor and material prices to determine escalation costs. The structure of these formulas can significantly impact the cost of a contract. 3.4. Scheduled Completion Dates If an owner wants a bidder to provide schedule dates for key contract activities, the Proposal lists the key schedule activities and requests that the contractor provide the dates. Start and completion dates for key contract schedule activities may be requested. 3.5. List of Subcontractors The Proposal section provides space for bidders to list the subcontractors that they intend to use to perform the contract work. In addition to the names of subcontract firms, bidders should provide descriptions of the subcontractor work scopes, subcontractor experience, location of subcontractor offices, and telephone numbers. 3.6. Key Supplier or Contractor Personnel The Proposal requires that a supplier or a contractor name the person that will be in charge of the contract work and will be the primary contact for an owner. The names of other key personnel can be requested in the Proposal section. 3.7. Length of Time Bid Is Valid If there is a possibility that the award of a contract will not
  • 20. occur until a significant period of time after bids are received, the Proposal requests the length of time that a bid is valid after receipt by an owner. 3.8. List of Bid Document Addenda Reviewed by Bidder If there are bid document addenda issued after the RFP is issued, the Proposal section requests that bidders list the addenda that they have reviewed. This procedure ensures that all bidders have reviewed the necessary documents. 3.9. Notice of Conflicts or Errors in Bid Documents Requesting that bidders formally notify an owner of conflicts or errors in bid documents provides a formal means of communicating conflicts and errors. The errors can be corrected prior to the start of contract work. 3.10. Clarifications of Bids Certain Proposal sections provide space for a bidder to state any clarifications or exceptions to its bid. Although the intent of the RFP is to define the work scope in a manner that eliminates the need for clarifications and exceptions, there may be items that are not clear that should be addressed. Excessive clarifications or exceptions may cause a bid proposal to be rejected. 3.11. Bidder Signature The Proposal contains space for the supplier or the contractor to sign its completed Proposal. It also includes the date the Proposal is signed, the title of the person signing, and any required identification numbers or license numbers. 4. SPECIFICATIONS AND DRAWINGS
  • 21. Specifications and Drawings sections are required for RFPs for fixed and unit price contracts. They are also required for target price and reimbursable with incentive fee contracts since they define the basis of targets and incentive fees. Depending upon how the contracts are scoped on a project, the specifications and drawings included in the RFP may or may not relate only to the contract for which the RFP is prepared. The Description of Work explains which portions of the specifications and drawings relate to a particular contract. In some cases, the specifications and drawings are marked up to define contract work scopes. Service contracts usually require a Description of Work in addition to the Specifications and Drawings in the RFP to clarify the work activities that are the responsibility of a contractor. Many engineered materials and equipment contracts do not require extensive Description of Work sections since all necessary information for the bidders is included in the Specifications and Drawings. Note: Don’t spend too much time creating drawings or specifications. Simply cut and paste a picture from the internet and describe it here. 5. SPECIAL CONDITIONS The Special Conditions section of the RFP includes all of the management requirements and any other specific contract requirements. The Special Conditions section usually does not address the technical requirements for a project.
  • 22. The management requirements for RFP's are prepared by several different project groups as discussed previously. The procurement group receives the management requirements for each contract from these groups. In many cases the language of the management requirements for different contracts can be similar. The procurement group works with the other project groups to determine the extent that management clauses can be standardized in the Special Conditions. Important management requirements for a specific contract should not be omitted from the RFP for the sake of standardization. Certain RFPs include the Special Conditions information in the Description of Work section. This eliminates the need for the Special Conditions. As long as the management requirements are well defined, it makes little difference if they are included in the Description of Work or the Special Conditions. Many RFPs do not adequately define all of the necessary management requirements for a contract. Inadequate definition of management requirements can lead to poor management of a contract. Project management has the overall responsibility for assuring that RFP's adequately define management requirements. It is helpful to include all of the management requirements for a particular area such as control of quality in one part of the RFP. If the quality requirements are contained in different sections in the RFP, it can be difficult to determine if the necessary quality requirements are all included in the RFP. 6. GENERAL CONDITIONS AND CONTRACT AGREEMENTS The General Conditions section of the RFP contains the
  • 23. commercial requirements for a contract. Many of these commercial terms cover situations, such as changes to the original contract, technical and management requirements, or cases in which the contractor does not perform in accordance with these requirements. Other commercial clauses cover terms of payment, invoicing, and responsibility for tax payments. Since the procurement group is responsible for preparing these commercial terms with assistance from the legal group, the procurement group can prepare the General Conditions section of the RFP with relatively little input from other project groups. Many RFPs contain a Contract Agreement section in addition to the General Conditions. The purpose of including the Contract Agreement section in the RFP is to show the bidders the contract format that will be used if they are awarded the contract. Contract Agreements contain commercial clauses that are very similar to the clauses normally included in the General Conditions. The Contract Agreement usually includes the General Conditions, Description of Work, Proposal, Specifications and Drawings, and Special Conditions sections in the contract by referencing these documents. This means that the requirements of all of these sections are a part of the contract. It is not significant which commercial requirements are included in the Contract Agreement and which requirements are included in the General Conditions since both sections are included in a signed contract. Appendix A Acknowledgment Letter for bid no. ______ (RFP Description)
  • 24. (Project Description) Attention: ___________________________ Date:________________ (contact representative) Receipt of the above captioned Request for Proposal is hereby acknowledged with the following comments: £ We will submit a bid on or before ______________________ £ We will not submit a bid for the following reasons: _____________________________________________________ _____________________________________________________ _____________________________________________________ _____________________________________________________ ___________________________________________
  • 25. __________________________ has been assigned to be the primary contact person for the bid submission process. The contact telephone, fax, and e-mail are as follows. Telephone ________________________________ Fax ________________________________ E-mail ________________________________ Designated Officer ________________________________ Title ________________________________ Address ________________________________
  • 26. ________________________________ Appendix B Supplier/Bidder List Supplier/Bidder Contact # How I chose these potential suppliers: _____________________________________________________ _____________________________________________________ _____________________________________________________ _____________________________________________________ _____________________________________________________ _____________________________________________________ _____________________________________________________ _____________________________________________________ _____________________________________________________ _____________________________________________________ _____________________________________________________ _____________________________________________________