SlideShare a Scribd company logo
1 of 32
Reduction in rejection due to sealing open by
50%.
Asia EIT Convention 2015
Project Name : To reduce sealing open rejection 1.3 % to 0.03 %
Date ( Revision by) :
Prepared By : KHUSHAL R. TALHAN
Approved By: AMOL KHANDAGALE
BUSINESS CASE :
OPPORTUNITY STATEMENT (HIGH LEVEL PROBLEM
STATEMENT )
Vishay componenets India pvt ltd, it is a
world largest manufacture of semiconductor
and passive components.
To improve the yield , rejection percentage ,and cost of poor quality.
.
DEFECT DEFINATION : metal is not fully covered entire area by plastic
film.otherwise plastic film is opening during next operation.
GOAL STATEMENT : PROJECT SCOPE
Reduce the rejection of sealing open and thread open of Film capacitor. Process start point : AT WINDING STAGE .
Expected Saving / Benefits
COST OF SAVING 1,60,16000
Process End Point : FINAL CONTROL INSPECTION STAGE
Project Plan : Team :
Task / Phase
Start Date End Date
Actual
Date Name Role
Commitme
nt
Define 07-Jan-14 22-Jan-14 22-Jan-14 KHUSHAL TALHAN DATA COLLECTION 95%
Measure 20-Feb-14 22-Feb-14 24-Feb-14 TANAJI PHALKE ACTION 99%
Analyse 10-Mar-14 28-Mar-14 30-Apr-14 RANJIT MALGAR MONITORING 99%
Improve
12-Apr-14 03-Apr-14 15-Apr-14 GANESH SATAV
HORIZONTAL
DEPLOYMENT. 99%
Control 06-May-14 22-May-14 30-May-14 AMAR JANGAM MONITORING 99%
TEAM / PROJECT
CHARTER
winding flattenin
g
interleavin
g
Metal
spray
waxin
g
deburringdetappin
g
Healing and
sorting
Final
control
Process Flow Diagram of
Capacitor
At this
stage
sealing
open is
detected
Defect
generation
stage
Initial
detection of
defect
SIX SIGMA DMAIC PHASE
Identify problem DEFINE
Practical Problem
MEASU
RE
Root cause
analysis
ANALYZ
E
Problem
solution
IMPROV
E
Problem control
CONTRO
L
Total Front End Yield in year 2013 – 92.1%
Breakage of 7.9% rejection
Mechanical defects : 4.12 %
Electrical defects :3.78 %
The process engineering dept has taken project of Electrical Defects
Focused on mechanical defects
1.
33
Why theme is selected ?
0.00
20.00
40.00
60.00
80.00
100.00
Reject.%
Break up of mechanical rejects in % 1.3
%
Cost of poor Quality
$
Issue No. of pieces
Scrapped in 2014
Sealing open 3.6 mln
Cost of poor quality = 3600000*5 RS = 1800000 RS
$ 494K
1. TURNOVER: RS 1993.4
MLN
2. PBT :RS 176.3 MLN
To improve film cap yield 85%
Dept action plan : Reduction in
rejection of sealing open issue by
50%
Linkage to quality Policy
Project leader
A.T.Khandagale
(Maint. Engineer)
T.M.Phalke
(Maint. Engineer)
K.R.Talhan
(Quality .Engineer)
G.B.Satav
(Jr.Maint. Engineer)
Malgar R.S.
(Prod. Operator)
 Assembly follow-up
 Defect mode
analysis
 Standardization
 Data collection
 Equipment
Improvement
 Result check
 Solution action
 Data collection
 Assembly follow-up
 Result check
 Horizontal deployment
 Data collection
 Routine Check
 Production trials
 Result check
Team Organization
No. of Meetings Held : 10
Meeting Calendar
Date 7.01.15 22.01.15 20.02.15 10.03.15 28.03.15 12.04.15 3.05.15 6.06.15 25.06.15 21.07.15
Meeting at
3.00 p.m.
Team
Attendanc
e
100% 100% 80% 100% 100% 80% 100% 100% 100% 100%
In that meeting we got root cause of sealing open
problem.
1. Data collection
2. Brainstorming
3. Pareto analysis
4. Ishikawa diagram
5. Why-Why analysis
6. Variable search( DOE)
Tools used to solve problem
Activity planning (Gantt) Chart
Activities Planned Responsibility Wk No. W1402 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44
Data collection of sealing
open issue
KHUSHAL
Planned
Actual
Analysis of available data Team
Planned
Actual
Action Plan as per
analysis
T.M.Phalke
Planned
Actual
Execution of actions Satav/Kulkarni
Planned
Actual
results confirmation on
machines.
KHUSHAL
Planned
Actual
Horizontal Deployments
on all machines groups,
Satav/Kulkarni.
Planned
Actual
Sealing Open
Define problem – Sealing open
Good
Bad
Bad
Flap open
Thread open
Rejection 30%
Rejection 70%
Measure problem – Sealing open
Sealing problem faced on winding stage
Following are the different winding machines and sealing open
percentage as per following
Rejection
of sealing
issue is
1.33%
Machine
Name
Present sealing
rejection
Present sealing Profile
Stella
Romeo
0.97 50% Land Sealing
Stella ERO 0.01 Cover film + 50% Land
VHW 0.05 Cover film + 50% Land
Ariane 0.2 50% Land Sealing
Cosmos 0.15 50% Land Sealing
AVM 0.04 50% Land Sealing
BC 2000 0.01 Cover film + 50% Land
From above study it is finalized that sealing open rejection on
stella Romeo machine
Data collection – Sealing open for
stella romeo m/cs
Date Machine No.
Foil
Micron
Sealing
temp
Sealing
Profile
Problem Observed Action taken
18.02.2014 Stella fl. 6e-5 12 310 Square Threads open Clean the pencil.
20.02.2014 Stella fl. 6e-9 6.2 290 Square Flap open Sealing not parallel so adjust grub screw.
22.02.2014 Stella fl. 6e-4 6.2 280 Square Threads open Sealing not parallel so adjust grub screw.
25.02.2014 Stella6e-1 6.2 280 Plain Flap open Clean the pencil and adjust the grub.
27.02.2014 Stella fl. 6e-2 12 320 Square Threads open Sealing not parallel so adjust grub screw.
02.03.2014 Stella fl. 6e-6 6.2 280 Square Threads open Reduce sealing temperature
04.03.2014 Stella fl. 6e-10 12 310 Square Threads open Sealing not parallel so adjust grub screw
05.03.2014 Stella fl. 6e-4 6.2 290 Square Flap open Sealing not parallel so adjust grub screw.
08.03.2014 Stella fl. 6e-5 12 310 Square Threads open Reduce sealing temperature
10.03.2014 Stella fl. 6e-11 12 320 Square Threads open Sealing not parallel so adjust grub screw.
11.03.2014 Stella fl. 6e-12 12 310 Square Threads open Clean the pencil and adjust the grub
13.03.2014 Stella 6e-5 6.2 280 Plain Flap open Sealing not parallel so adjust grub screw.
15.03.2014 Stella fl. 6e-9 6.2 280 Square Threads open Clean the pencil and adjust the grub
16.03.2014 Stella 6e-8 12 310 Plain Flap open Sealing not parallel so adjust grub screw.
17.03.2014 Stella fl. 6e-4 6.2 280 Square Threads open Clean the pencil and adjust the grub
19.03.2014 Stella fl. 6e-2 6.2 290 Square Threads open Clean the pencil and adjust the grub
21.03.2014 Stella fl. 6e-12 6.2 280 Square Threads open Reduce sealing temperature
Remark : Various trial conducted to find various causes of sealing open
fault,
no conclusion from trials.
Further analysis of sealing
open
Sr.No.
Types of
sealing open
Action taken to solve problem
1 Flap open Sealing not parallel so adjust grub screw.
2 Threads open
Clean sealing pencil
Set the temperature
Team decided to work initially on seal , flap open problem.
Why why Analysis of sealing flap open
Sealing pencil not parallel. Why ?
Grub Screw for parallel adjustment found loose. Why ?
After 1 week Compression spring pressure was getting
reduced at working temp. up to 350 °C . Why?
Present Compression spring material was
loosing properties at temp 350 °C.
Team Investigated and decided to replace material of
Grub screw and compression spring which can
sustain up to 600°C temperature.
Root
Cause of
the
Problem
Analysis of Comp. spring Material
Type of spring
material
Trial
Life of
spring(Spring
Length -14mm)
Not ok <10mm
Remark
Hard spring steel W1511
Not ok after one
week used
Not Suitable
Stainless steel spring
steel
W1512
Not ok after two
week used
Not Suitable
EN12070 W1512
Not ok after two
week used
Not Suitable
Inconel X750
Ni Cr 15 Fe 7 Ti Al W1514
OK even after 4
Week used(length
remain 14mm)
Suitable
Team decided to use material Inconel X750
Result after spring material
change
After changing compression spring – Sealing flap
open rejection is eliminated but sealing threads
open rejection is still 0.95% hence team decided to
study on threads open rejection
Horizontal deployment and standardization
Machines/Group
No. of Machines
Available
No .of Machines
Completed
Status
Stella Winding 46 46 Completed in week 1526
Standardization
Description
12 NC
Old New
Compression Spring 8203 110 32550 8203 110 32551
Sealing pencil compression spring replacement
frequency defined one year in Preventive Maintenance
Check sheet.
Sealing pencil spring drawing, stock no., changed in
Spare list..
Fishbone diagram – Sealing thread Open
Sealing
thread
Open
Untrained operator
Sealing pencil
not parallel
MAN
METHOD
MACHINE
Wrong
parameter
setting
WINDING
WINDING
Profile of
Sealing
pencil is
not ok
MATERIAL
FILM
No Method
for
inspection
Improper sealing
due to high speed
Sealing
open due to
low Temp
Sealing open
due to wrong
setting of
temp
Sealing
Pressure
not proper
Film MKT Film MKP
Film thickness
Solenoid
stroke not
standard
Compression
spring not ok
Serration
of sealing
pencil
worn out
Play in
Pencil
Guide way
Grub screw
loose
3
1
2
Sealing thread open – Ranking method
Variables Verification Data Influence
1) Sealing open due to wrong setting
of temp
Checked temperature and found range
280-320 in work instruction.
Yes
2)Serration of sealing pencil worn out
Verified and corrected during preventive
maintenance
No
3) Improper sealing due to high speed
Sealing speed is verified and found as per
instructions
No
4)Sealing pencil profile design is not
suitable.
Product observed under microscope
,spikes observed at non contact area of
pencil.
Yes
5)Film thickness
Difference in rejection quantity according to
film thickness
Yes
6)Play in Pencil Guide way Verified and corrected during preventive
maintenance
No
7) Solenoid stroke not standard Solenoid stroke length defined and Verified
during preventive maintenance
No
SR.NO. FACTOR DESCRIPTION LOW HIGH
1 Sealing temperature 280 320
2 Foil Thickness 6.2 12
3 Sealing profile(Land %) 50% 100%
From data analysis three parameters affects on sealing thread open
,Hence team decided variable search of these three parameters.
LAND
DEPTH
ROOT
SEALING PROFILE
Full Factorial Design
Factors: 3 Base Design: 3, 8
Runs: 16 Replicates: 2
PARETO ANALYSIS DOE
Remark: From above graph sealing land is significant paramet
MAIN EFFECT AND INTERACTION PLOT
REMARK : SEALING LAND IS
SIGNIFICANT ,NO INTERACTION IS
SIGNIFICANT
DESIGN OPTIMISER SETTING
REMARK : SEALING LAND SETTING 100%
AND SEALING TEMP IS CHANGED
ACCORDING TO FILM THIKNESS.
Before
SEALING PENCIL DRAWING
After
Land 50% Land 70%
Horizontal deployment and Standardization
Description
12 NC
Old New
Sealing Tip--Stella 7604 004 27691 7604 004 27692
Sealing Tip Left--Cosmos 7604 004 27671 7604 004 27672
Sealing Tip Right--Cosmos 7604 004 27681 7604 004 27682
Sealing Tip--Araine No 7615 511 00200
This change is regularized thru Change proposal no. : CP-L13084
Machines/Group
No. of
Machines
Available
No .of
Machines
Completed
Status
Stella winding 46 46 Completed 1539
AVM Machines 3 3 Completed 1540
3e-11e VHW
Group
16 16 Completed 1544
Ariane Group 8 8 Completed 1541
Cosmos Group 16 16 Completed1543
1.33
0.34
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1 2
sealing open
sealing open
Target Achievement
50
% 70
%
orignal
targe
t
achieved
RESULTS OF REJECTION
1.28%
0.72%
REMARK : AVERAGE REJECTION % FOR
SEAL OPEN IS REDUCED FROM 1.28% TO
0.35%
Cost of saving =Rs 1,60,16,000
Cost of Saving =0.99% reduction X 4 Mln X52 weeks X 5Rs
Results - saving
Thank you

More Related Content

Similar to sealing open project

VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBGVVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
Indrani7
 
Fall 2014 Co-op Rotation Summary
Fall 2014 Co-op Rotation SummaryFall 2014 Co-op Rotation Summary
Fall 2014 Co-op Rotation Summary
Ash Abel
 
Unlocking slide after flattening 5-20
Unlocking slide after flattening 5-20Unlocking slide after flattening 5-20
Unlocking slide after flattening 5-20
John Zill
 
Six Sigma Case Study
Six Sigma Case StudySix Sigma Case Study
Six Sigma Case Study
sanjay_asati
 
Final Review Elaine Mau Procter and Gamble
Final Review Elaine Mau Procter and GambleFinal Review Elaine Mau Procter and Gamble
Final Review Elaine Mau Procter and Gamble
Elaine Mau
 
GROUP PROJECT Mini open-ended project aerolab 1
GROUP PROJECT Mini open-ended project aerolab 1GROUP PROJECT Mini open-ended project aerolab 1
GROUP PROJECT Mini open-ended project aerolab 1
nikadam468
 
Minimization of the Casting Defects Using Taguchi’s Method
Minimization of the Casting Defects Using Taguchi’s MethodMinimization of the Casting Defects Using Taguchi’s Method
Minimization of the Casting Defects Using Taguchi’s Method
inventionjournals
 

Similar to sealing open project (20)

Sandeep six sigma ppt
Sandeep six sigma pptSandeep six sigma ppt
Sandeep six sigma ppt
 
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBGVVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
 
Defects Analysis and Optimization of Process Parameters using Taguchi Doe Tec...
Defects Analysis and Optimization of Process Parameters using Taguchi Doe Tec...Defects Analysis and Optimization of Process Parameters using Taguchi Doe Tec...
Defects Analysis and Optimization of Process Parameters using Taguchi Doe Tec...
 
170614. Annual Report Finish.pptx
170614.  Annual Report Finish.pptx170614.  Annual Report Finish.pptx
170614. Annual Report Finish.pptx
 
Enigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in indiaEnigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in india
 
Fall 2014 Co-op Rotation Summary
Fall 2014 Co-op Rotation SummaryFall 2014 Co-op Rotation Summary
Fall 2014 Co-op Rotation Summary
 
IRJET- Optimization of Process Parameter in Injection Moulding using Tagu...
IRJET-  	  Optimization of Process Parameter in Injection Moulding using Tagu...IRJET-  	  Optimization of Process Parameter in Injection Moulding using Tagu...
IRJET- Optimization of Process Parameter in Injection Moulding using Tagu...
 
Unlocking slide after flattening 5-20
Unlocking slide after flattening 5-20Unlocking slide after flattening 5-20
Unlocking slide after flattening 5-20
 
Six Sigma Case Study
Six Sigma Case StudySix Sigma Case Study
Six Sigma Case Study
 
CMA05MT900-A版承認書(FOR 訊舟)20090615
CMA05MT900-A版承認書(FOR 訊舟)20090615CMA05MT900-A版承認書(FOR 訊舟)20090615
CMA05MT900-A版承認書(FOR 訊舟)20090615
 
IRJET- Quantative Analysis of Undercut in PCM for SS304
IRJET- Quantative Analysis of Undercut in PCM for SS304IRJET- Quantative Analysis of Undercut in PCM for SS304
IRJET- Quantative Analysis of Undercut in PCM for SS304
 
PMS FY 22-23.pptx
PMS FY 22-23.pptxPMS FY 22-23.pptx
PMS FY 22-23.pptx
 
Final Review Elaine Mau Procter and Gamble
Final Review Elaine Mau Procter and GambleFinal Review Elaine Mau Procter and Gamble
Final Review Elaine Mau Procter and Gamble
 
June 15 presentation
June 15 presentationJune 15 presentation
June 15 presentation
 
IRJET- Effect of Injection Moulding Process Parameter on Warpage of using Tag...
IRJET- Effect of Injection Moulding Process Parameter on Warpage of using Tag...IRJET- Effect of Injection Moulding Process Parameter on Warpage of using Tag...
IRJET- Effect of Injection Moulding Process Parameter on Warpage of using Tag...
 
Composite failure analysis
Composite failure analysisComposite failure analysis
Composite failure analysis
 
ENHANCEMENT OF MOLD EFFICIENCY USING CONFORMAL COOLING
ENHANCEMENT OF MOLD EFFICIENCY USING CONFORMAL COOLINGENHANCEMENT OF MOLD EFFICIENCY USING CONFORMAL COOLING
ENHANCEMENT OF MOLD EFFICIENCY USING CONFORMAL COOLING
 
GROUP PROJECT Mini open-ended project aerolab 1
GROUP PROJECT Mini open-ended project aerolab 1GROUP PROJECT Mini open-ended project aerolab 1
GROUP PROJECT Mini open-ended project aerolab 1
 
New Honda Circle
New Honda Circle New Honda Circle
New Honda Circle
 
Minimization of the Casting Defects Using Taguchi’s Method
Minimization of the Casting Defects Using Taguchi’s MethodMinimization of the Casting Defects Using Taguchi’s Method
Minimization of the Casting Defects Using Taguchi’s Method
 

sealing open project

  • 1. Reduction in rejection due to sealing open by 50%. Asia EIT Convention 2015
  • 2. Project Name : To reduce sealing open rejection 1.3 % to 0.03 % Date ( Revision by) : Prepared By : KHUSHAL R. TALHAN Approved By: AMOL KHANDAGALE BUSINESS CASE : OPPORTUNITY STATEMENT (HIGH LEVEL PROBLEM STATEMENT ) Vishay componenets India pvt ltd, it is a world largest manufacture of semiconductor and passive components. To improve the yield , rejection percentage ,and cost of poor quality. . DEFECT DEFINATION : metal is not fully covered entire area by plastic film.otherwise plastic film is opening during next operation. GOAL STATEMENT : PROJECT SCOPE Reduce the rejection of sealing open and thread open of Film capacitor. Process start point : AT WINDING STAGE . Expected Saving / Benefits COST OF SAVING 1,60,16000 Process End Point : FINAL CONTROL INSPECTION STAGE Project Plan : Team : Task / Phase Start Date End Date Actual Date Name Role Commitme nt Define 07-Jan-14 22-Jan-14 22-Jan-14 KHUSHAL TALHAN DATA COLLECTION 95% Measure 20-Feb-14 22-Feb-14 24-Feb-14 TANAJI PHALKE ACTION 99% Analyse 10-Mar-14 28-Mar-14 30-Apr-14 RANJIT MALGAR MONITORING 99% Improve 12-Apr-14 03-Apr-14 15-Apr-14 GANESH SATAV HORIZONTAL DEPLOYMENT. 99% Control 06-May-14 22-May-14 30-May-14 AMAR JANGAM MONITORING 99% TEAM / PROJECT CHARTER
  • 3. winding flattenin g interleavin g Metal spray waxin g deburringdetappin g Healing and sorting Final control Process Flow Diagram of Capacitor At this stage sealing open is detected Defect generation stage Initial detection of defect
  • 4. SIX SIGMA DMAIC PHASE Identify problem DEFINE Practical Problem MEASU RE Root cause analysis ANALYZ E Problem solution IMPROV E Problem control CONTRO L
  • 5. Total Front End Yield in year 2013 – 92.1% Breakage of 7.9% rejection Mechanical defects : 4.12 % Electrical defects :3.78 % The process engineering dept has taken project of Electrical Defects Focused on mechanical defects 1. 33 Why theme is selected ? 0.00 20.00 40.00 60.00 80.00 100.00 Reject.% Break up of mechanical rejects in % 1.3 %
  • 6. Cost of poor Quality $ Issue No. of pieces Scrapped in 2014 Sealing open 3.6 mln Cost of poor quality = 3600000*5 RS = 1800000 RS $ 494K
  • 7. 1. TURNOVER: RS 1993.4 MLN 2. PBT :RS 176.3 MLN To improve film cap yield 85% Dept action plan : Reduction in rejection of sealing open issue by 50% Linkage to quality Policy
  • 8. Project leader A.T.Khandagale (Maint. Engineer) T.M.Phalke (Maint. Engineer) K.R.Talhan (Quality .Engineer) G.B.Satav (Jr.Maint. Engineer) Malgar R.S. (Prod. Operator)  Assembly follow-up  Defect mode analysis  Standardization  Data collection  Equipment Improvement  Result check  Solution action  Data collection  Assembly follow-up  Result check  Horizontal deployment  Data collection  Routine Check  Production trials  Result check Team Organization
  • 9. No. of Meetings Held : 10 Meeting Calendar Date 7.01.15 22.01.15 20.02.15 10.03.15 28.03.15 12.04.15 3.05.15 6.06.15 25.06.15 21.07.15 Meeting at 3.00 p.m. Team Attendanc e 100% 100% 80% 100% 100% 80% 100% 100% 100% 100% In that meeting we got root cause of sealing open problem.
  • 10. 1. Data collection 2. Brainstorming 3. Pareto analysis 4. Ishikawa diagram 5. Why-Why analysis 6. Variable search( DOE) Tools used to solve problem
  • 11. Activity planning (Gantt) Chart Activities Planned Responsibility Wk No. W1402 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 Data collection of sealing open issue KHUSHAL Planned Actual Analysis of available data Team Planned Actual Action Plan as per analysis T.M.Phalke Planned Actual Execution of actions Satav/Kulkarni Planned Actual results confirmation on machines. KHUSHAL Planned Actual Horizontal Deployments on all machines groups, Satav/Kulkarni. Planned Actual
  • 13. Define problem – Sealing open Good Bad Bad Flap open Thread open Rejection 30% Rejection 70%
  • 14. Measure problem – Sealing open Sealing problem faced on winding stage Following are the different winding machines and sealing open percentage as per following Rejection of sealing issue is 1.33% Machine Name Present sealing rejection Present sealing Profile Stella Romeo 0.97 50% Land Sealing Stella ERO 0.01 Cover film + 50% Land VHW 0.05 Cover film + 50% Land Ariane 0.2 50% Land Sealing Cosmos 0.15 50% Land Sealing AVM 0.04 50% Land Sealing BC 2000 0.01 Cover film + 50% Land From above study it is finalized that sealing open rejection on stella Romeo machine
  • 15. Data collection – Sealing open for stella romeo m/cs Date Machine No. Foil Micron Sealing temp Sealing Profile Problem Observed Action taken 18.02.2014 Stella fl. 6e-5 12 310 Square Threads open Clean the pencil. 20.02.2014 Stella fl. 6e-9 6.2 290 Square Flap open Sealing not parallel so adjust grub screw. 22.02.2014 Stella fl. 6e-4 6.2 280 Square Threads open Sealing not parallel so adjust grub screw. 25.02.2014 Stella6e-1 6.2 280 Plain Flap open Clean the pencil and adjust the grub. 27.02.2014 Stella fl. 6e-2 12 320 Square Threads open Sealing not parallel so adjust grub screw. 02.03.2014 Stella fl. 6e-6 6.2 280 Square Threads open Reduce sealing temperature 04.03.2014 Stella fl. 6e-10 12 310 Square Threads open Sealing not parallel so adjust grub screw 05.03.2014 Stella fl. 6e-4 6.2 290 Square Flap open Sealing not parallel so adjust grub screw. 08.03.2014 Stella fl. 6e-5 12 310 Square Threads open Reduce sealing temperature 10.03.2014 Stella fl. 6e-11 12 320 Square Threads open Sealing not parallel so adjust grub screw. 11.03.2014 Stella fl. 6e-12 12 310 Square Threads open Clean the pencil and adjust the grub 13.03.2014 Stella 6e-5 6.2 280 Plain Flap open Sealing not parallel so adjust grub screw. 15.03.2014 Stella fl. 6e-9 6.2 280 Square Threads open Clean the pencil and adjust the grub 16.03.2014 Stella 6e-8 12 310 Plain Flap open Sealing not parallel so adjust grub screw. 17.03.2014 Stella fl. 6e-4 6.2 280 Square Threads open Clean the pencil and adjust the grub 19.03.2014 Stella fl. 6e-2 6.2 290 Square Threads open Clean the pencil and adjust the grub 21.03.2014 Stella fl. 6e-12 6.2 280 Square Threads open Reduce sealing temperature Remark : Various trial conducted to find various causes of sealing open fault, no conclusion from trials.
  • 16. Further analysis of sealing open Sr.No. Types of sealing open Action taken to solve problem 1 Flap open Sealing not parallel so adjust grub screw. 2 Threads open Clean sealing pencil Set the temperature Team decided to work initially on seal , flap open problem.
  • 17. Why why Analysis of sealing flap open Sealing pencil not parallel. Why ? Grub Screw for parallel adjustment found loose. Why ? After 1 week Compression spring pressure was getting reduced at working temp. up to 350 °C . Why? Present Compression spring material was loosing properties at temp 350 °C. Team Investigated and decided to replace material of Grub screw and compression spring which can sustain up to 600°C temperature. Root Cause of the Problem
  • 18. Analysis of Comp. spring Material Type of spring material Trial Life of spring(Spring Length -14mm) Not ok <10mm Remark Hard spring steel W1511 Not ok after one week used Not Suitable Stainless steel spring steel W1512 Not ok after two week used Not Suitable EN12070 W1512 Not ok after two week used Not Suitable Inconel X750 Ni Cr 15 Fe 7 Ti Al W1514 OK even after 4 Week used(length remain 14mm) Suitable Team decided to use material Inconel X750
  • 19. Result after spring material change After changing compression spring – Sealing flap open rejection is eliminated but sealing threads open rejection is still 0.95% hence team decided to study on threads open rejection
  • 20. Horizontal deployment and standardization Machines/Group No. of Machines Available No .of Machines Completed Status Stella Winding 46 46 Completed in week 1526 Standardization Description 12 NC Old New Compression Spring 8203 110 32550 8203 110 32551 Sealing pencil compression spring replacement frequency defined one year in Preventive Maintenance Check sheet. Sealing pencil spring drawing, stock no., changed in Spare list..
  • 21. Fishbone diagram – Sealing thread Open Sealing thread Open Untrained operator Sealing pencil not parallel MAN METHOD MACHINE Wrong parameter setting WINDING WINDING Profile of Sealing pencil is not ok MATERIAL FILM No Method for inspection Improper sealing due to high speed Sealing open due to low Temp Sealing open due to wrong setting of temp Sealing Pressure not proper Film MKT Film MKP Film thickness Solenoid stroke not standard Compression spring not ok Serration of sealing pencil worn out Play in Pencil Guide way Grub screw loose 3 1 2
  • 22. Sealing thread open – Ranking method Variables Verification Data Influence 1) Sealing open due to wrong setting of temp Checked temperature and found range 280-320 in work instruction. Yes 2)Serration of sealing pencil worn out Verified and corrected during preventive maintenance No 3) Improper sealing due to high speed Sealing speed is verified and found as per instructions No 4)Sealing pencil profile design is not suitable. Product observed under microscope ,spikes observed at non contact area of pencil. Yes 5)Film thickness Difference in rejection quantity according to film thickness Yes 6)Play in Pencil Guide way Verified and corrected during preventive maintenance No 7) Solenoid stroke not standard Solenoid stroke length defined and Verified during preventive maintenance No
  • 23. SR.NO. FACTOR DESCRIPTION LOW HIGH 1 Sealing temperature 280 320 2 Foil Thickness 6.2 12 3 Sealing profile(Land %) 50% 100% From data analysis three parameters affects on sealing thread open ,Hence team decided variable search of these three parameters. LAND DEPTH ROOT SEALING PROFILE Full Factorial Design Factors: 3 Base Design: 3, 8 Runs: 16 Replicates: 2
  • 24. PARETO ANALYSIS DOE Remark: From above graph sealing land is significant paramet
  • 25. MAIN EFFECT AND INTERACTION PLOT REMARK : SEALING LAND IS SIGNIFICANT ,NO INTERACTION IS SIGNIFICANT
  • 26. DESIGN OPTIMISER SETTING REMARK : SEALING LAND SETTING 100% AND SEALING TEMP IS CHANGED ACCORDING TO FILM THIKNESS.
  • 28. Horizontal deployment and Standardization Description 12 NC Old New Sealing Tip--Stella 7604 004 27691 7604 004 27692 Sealing Tip Left--Cosmos 7604 004 27671 7604 004 27672 Sealing Tip Right--Cosmos 7604 004 27681 7604 004 27682 Sealing Tip--Araine No 7615 511 00200 This change is regularized thru Change proposal no. : CP-L13084 Machines/Group No. of Machines Available No .of Machines Completed Status Stella winding 46 46 Completed 1539 AVM Machines 3 3 Completed 1540 3e-11e VHW Group 16 16 Completed 1544 Ariane Group 8 8 Completed 1541 Cosmos Group 16 16 Completed1543
  • 29. 1.33 0.34 0 0.2 0.4 0.6 0.8 1 1.2 1.4 1 2 sealing open sealing open Target Achievement 50 % 70 % orignal targe t achieved
  • 30. RESULTS OF REJECTION 1.28% 0.72% REMARK : AVERAGE REJECTION % FOR SEAL OPEN IS REDUCED FROM 1.28% TO 0.35%
  • 31. Cost of saving =Rs 1,60,16,000 Cost of Saving =0.99% reduction X 4 Mln X52 weeks X 5Rs Results - saving