The document summarizes an event being held at Brompton Cemetery on June 17th about the Parks for People programme. It includes an agenda with presentations from Heritage Lottery Fund and others on topics like assessing cemetery projects and the importance of burial grounds for natural heritage. The programme aims to conserve existing heritage in designed parks and cemeteries, with £30m available annually. Cemeteries are eligible for funding, but projects must achieve outcomes like developing skills, learning about heritage, and improving the local community. A master plan approach is encouraged.
3. Brompton Cemetery Event 17 June 2014
Time Presentation Speaker
10.45am Tea & Coffee available
11.00am Introduction to day Norma Pearson
Heritage Lottery Fund
11.15am Guided Tour of Brompton Cemetery Robert Stephenson
Friends of Brompton
Cemetery
12.15pm Parks for People programme:
Policy Perspective
Lucy Hares
Heritage Lottery Fund
12.30pm Lunch and Networking
4. Brompton Cemetery Event 17 June 2014
Time Presentation Speaker
2pm Parks For People: Assessing Officer’s
Perspective
Jane Stancliffe
Heritage Lottery Fund
2.15pm Questions and Group Discussion
2.45pm Tea & Coffee
3pm The Importance of Burial Grounds for Natural
Heritage
Harriet Carty
Caring for God’s acre
3.20pm Business of cemeteries: Graves Gary Burks
City of London Cemetery and
Crematorium (City Corporation)
3.40pm Cemeteries: built heritage at risk Rebecca Barrett
English Heritage
4pm Group discussions
4.30pm Conclusions and Next Steps
7. The programme’s priority is to conserve the existing
heritage of a designed park or cemetery
HLF and BIG dedicated budget for Parks for People
programme is £30m per year for England.
Same application process:
Application dates: 28 February for decision in June
31 August for decision in December
Parks for People programme
8. ➜ Two round process with a development phase
➜ Development phase 24 months
➜ Three month assessment time
➜ Projects compete nationally
• Project enquiry form
Application Process
9. ➜ Lower grant threshold – £100,000 to £5m
Cemeteries are included in the programme➜
Expectation that Friends/ user group/ local community are already➜
involved in the management of the park or cemetery prior to application
Tell us about the need:➜
No LA greenspace strategy required but application should
show why park/cemetery restoration is a priority at this time.
You will need to tell us the number of visitors, trainees and volunteers.➜
Achieve outcomes➜
Park-specific essential reading available for applicants online.➜
Parks for People
~ programme features
10. • HLF interested in cemeteries as designed
landscapes, rather than funding organically
developed churchyards.
• HLF can fund work to privately owned memorials but
it can’t be the main focus of the project
• Can’t just restore a historic chapel in the centre of the
site; should still take a master plan approach and
incorporate a variety of capital work and activities.
• How to offer good quality activities and public spaces
with limited amenities, and without offending
sensitivities?
Key Issues for Cemeteries
11. We describe the differences that we want to make to heritage, people
and communities as ‘outcomes.’
Projects need to achieve all ten outcomes. We anticipate that your
project will contribute to some more than others.
Heritage will be:
better managed (weighted)➜
in better condition➜
better interpreted and explained➜
better identified and recorded➜
We value the ‘weighted’ outcomes the most
Parks for People Outcomes
12. People will have:
Developed skills (weighted)➜
Learned about heritage➜
Volunteered time➜
For communities:
The local area/community will be a better place to work, live or visit➜
(weighted)
Negative environmental impacts will be reduced➜
More people and a wider range of people will have engaged with➜
heritage
Outcomes will be assessed in these three groupings.
Parks for People Outcomes
13. • Developing skills
• Demonstrating the difference funding will make
• Master plan for the whole site – long term vision
• Delivering the project at the right time (why now?)
• Long term management and maintenance resources
• Consultation - strong stakeholder / community
actively engaged
• Capacity and capability of organisation
• Cultural change within an organisation
• High quality project team
• Governance of project and organisation
What makes a good Parks Project for HLF?
Editor's Notes
Yes
Yes
Yes
Yes
Yes
HLF website – How to Apply – Pick a programme - Parks for People
HLF and BIG £100m for 3 years UPDATE