5. 5
Location
Qatar, Al Khalij field
Total E&P Qatar
The facility consist of 8 not-normally-
manned platforms:
• 4 drilling platforms (DP1/2/3/4),
• 3 wellhead platforms (WP1/2/3), WP3
dedicated to the water injection only) and,
• 1 production platform PP1.
7. 7
Project Rationale
Increasing future water-cuts, limiting production on WP1-WP2-DP1 in particular:
1. Insufficient pipeline capacity (to Halul Island)
2. No extra capacity at process platform PP1
Water re-injection to increase oil production on WP1-WP2-DP1.
• Local water removal on DP1 required
• Re-injecting dissolved gases to improve emissions
8. 8
Challenges
DP1 was originally designed as a drilling / wellhead platform:
1. Installing a remotely operated package on DP1
2. No space available, resulting in a dedicated cantilever with consequent weight restrictions
Conventional solutions not feasible; new concept / technology required
11. 11
Process Package
Full automated for remote control
Full rated 1500#
Target water removal 90%
• Design: ASME B31.3 (pipe spec.)
• Material: Duplex
• Weight: 70 ton
• Size: 7.5m x 3.2m x 6.3m
13. 13
TechnipFMC InLine DeWaterer
• Joint development by Equinor/Statoil and
TechnipFMC
• Bulk oil removal
• Can be used as first step in produced water
treatment system
• Gas tolerant (up to 30% GVF)
• Oil content in: < 50%
• Typical outlet quality: 500-5000 ppm
• Pressure drop water outlet typically ~2 bar
Technology
14. 14
Statoil flow loop Porsgrunn
Simulated field conditions
Off-shore test Gullfaks C
Successful test at real conditions
Full scale test
Multiple liners
with gas
Maturity
Laboratory tests
Model fluids
Time
Technology - History
Heavy oil testing
Porsgrunn, for
Perigrino
Multiple real
field
applications
16. 16
Control, automation and monitoring
• Reject control using a CV on the oil outlet
(differential pressure ratio set-point)
• Turndown through actuated valves,
automated through downstream flow
meters (in addition to differential
pressure)
• Online oil in water analyzer on combined
water outlet
19. 19
Commissioning
• Unit was operating fully automatic with
good water quality within 1 week of first
startup
• Unit operated for several months with
good results
CONFIDENTIAL
20. 20
Troubleshooting & Experience
• After an unplanned shutdown, of aroud 2 weeks, the unit experienced mal-performance at
restart
• TechnipFMC and Total had to troubleshoot the unit, during which overall operations were
made more stable – intially flow from the wells was unstable. Flow stabilized after around
10 days, the unit then performed adequately, in a stable manner
• Online oil in water analysis is very challenging for the operating conditions experienced,
optimization is ongoing
CONFIDENTIAL
21. 21
Performance Testing
After troubleshooting unit operated in a
stable manner and performance testing was
conducted.
Contract was based on achieving the stated
performance. Results from performance
testing:
450 ppm best stable performance achieved
<1000 ppm on average
Unit has performed in a stable manner since,
achieving 400-700 ppm for close to one year
CONFIDENTIAL
Total E&P Qatar (TEPQ) operates oil production / processing facility at Al Khalij field located offshore Qatar 110 km from shore and 40 km N-E of Halul island in Arabian Gulf.
Wellhead platforms (WP) and drilling platforms are quite similar; basically smaller with fewer slots.
Processing facilities are minimal, typically consisting of manifolds, chemical injection skids, drains and vent systems, and instruments & controls.
The production platform (PP1) is a process platform, connected to DP2 by a bridge, and gathers production from DP2, DP3, WP3 and DP4. Oil, gas and water bulk separation is done on PP1;
Oil and gas streams are exported via the 20” pipeline to Halul.
Water is send to DP3 for injection and to water treatment unit, then toward WP3 for water injection.
Production from WP1 and WP2 is sent to DP1 platform from which oil, gas and water are directly sent to Halul, without any separation, via the 12” pipeline DP1-Halul.
In between these two axes, there is a 12” pipeline linking DP1 and PP1 that can be used on both directions.
39 000 – 88 0000 BWPD,
80-96% Water-cut
Up to 15% GVF
Target 500 ppm v/v and max 1000 ppm v/v OiW
Remove as much water as possible
Full automated and remotely controlled (UWP)
Full rated 1500#
6'' prototypes were tested in Arnhem in 2009. The best perfroming configurations were then tested in Porsgrunn (Norway). Cooperation between FMC and Statoil
FAT in 2009 in Arnhem for Petrobras InLine 3-phase separation skid. FMC Ref. P07-10049
In 2010 design improvement test programm in Arnhem and then in Porsgrunn
In Dec 2010 offshore testing at Gulfaks C (Statoil)
In 2011 heavy oil testing in Horten, Norway. Joint activity with NOFO and Statoil. FMC Ref.P 11-01051
In summer 2012 full scale (multiple liners) qualification testing in Drammen (Norway). Joint activity with Statoil
In 2012 very heavy oil testing in Porsgrunn by Statoil
Oil continuous testing in Arnhem by FMC, 2011. FMC Ref.09-06058