Building History
1982 - Original building completed by Developer – Mission Viejo
1986 - Addition - Gym
2001 - Addition of Cardio & Weight Area $6.2M
2013 - Men’s and Women’s Showers Renovated $80K
- McKinstry Energy Saving Project $1.0M
2015 - Gym and Racquetball Flooring replaced $156K
- Racquetball Court Renovation – Ongoing $23K/court
3. PLANNING PROCESS
Goal: Collect suggestions for improving facilities
Identify future capital needs
Facilities Focus Group – Delegates & Members invited – June 2014
• Improve Northridge Entrance and Lobby Areas
• Replace Northridge Gym Floor
• Refurbish Northridge Racquetball Courts
Frequent Users Survey – All Facilities – June 2014
• 72% - Northridge should be 1st Rec. Center to be updated & remodeled - 267 Surveys
• 94% - Facebook Survey also agreed - 71 Surveys
4. SPACE PLANNING PROJECT
August 2015 – March 2016
• Barker Rinker Seacat - Nat’l. Architectural Consultant
• Examined usage data (Open to Close) – (All facilities)
• Take a fresh look at space utilization
• Resource document (64 pages)
• Staff tied findings into proposed improvements for Northridge
• Improvements tested for feasibility
NORTHRIDGE RENOVATION CONCEPT PLAN
• Populous - Int’l. Award Winning Sports Facility Design Firm
• Staff & Board Input - Developed Concept Plan.
5.
6.
7.
8.
9.
10. NEXT STEPS
FOR 2017 COMPLETION
• Proposed Concept Plan on the website for Delegate/Member review.
• Public comment sent to Annie avincent@hrcaonline.org
• Staff to review suggestions / comments
• July 2016 - Delegate Update - Request approval to move forward
• July 2016 - RFP’s to Architects and Contractors
• August – Begin Design Process
• November – Budget Approval
• April 2017 - Begin Construction
• Oct. – Nov. - Complete Construction