SlideShare a Scribd company logo
Running head: CHANGE CONTROL
1Executive Summary
The Lewis project has exceeded its projected cost and the
project team is running behind on the project’s time. Frank’s
team has been overwhelmed with reporting requests coming in
from Lewis’ representatives and the company’s suppliers have
affected the project’s time by delivering some of the project
parts late. At the moment, the project cost is 30% more than the
project team expected and the project team seeks some solutions
to bring it back on track.
The project team suggests the implementation of change
controls that would ensure that the project’s scope is controlled
and the costs minimized and ensure that the project is
completed on time with all the deliverables achieved. The
project team suggests the implementation of some changes in
the project team’s communication processes and how
procurements are made in order to bring the project back on
track.
Keywords: scope, deliverables, project team.
Table of Contents
2Executive Summary
4Introduction
Processes Involved in Change
Request………………………………………………………………
……….............4
4Identified Project Issues
Control Change
Requests……….......................................................................
.............................6
8Conclusion
10References
Introduction
The Lewis project is lagging behind the project sponsor’s
expectations, as the project’s cost, time and deliverable goals
seem to be unattainable with the amount of time remaining. One
of the problems that can be noticed from the project is the fact
that the project was running way over the projected budget with
the project team estimating that the project would cost 30%
above the projected budget.
Besides that, the project had experienced some serious material
delays, as the procurement processes were quite inefficient and
expensive. The core purpose of this proposal document is to
come up with an in-depth analysis of the problems that are
affecting Frank’s effectiveness in handling the project and come
up with proposed changes that could be implemented to make
the project get back on track within the remaining project time.
Processes Involved in Change Request
Due to a failure of coming up with a concrete plan, the project
team has come up with the idea of submitting a request to deal
with the changes necessary to alter the project. There are certain
processes they will have to go through in order to help the
company to get back on track. The company needs to rework on
the purpose and objectives that were initially carried out by
Frank’s before the start of the project. As the cost and time of
the project was going way up beyond the expectations, Franks’
would need to look over the scope of the project. The change
request team then fills out the change request form in which
they would identify a proposed change and then justifies the
identified change. They would continue on to identify the
impacts of change on time, cost, schedule and on stakeholders
as well. After a complete working on this change, the
management would continue on to change the management roles
for example they would set the employees according to their
positions unlike before. The management would then submit the
change request, review the proposed changes and after that, if
approved, the request will be approved. Identified Project Issues
Communication Breakdown
The project team experienced some serious communication
issues in the course of the project, which made the Lewis
project, go out of scope. To start with, Frank’s project team
required its suppliers to have a meeting with them for every part
the company acquired from them. Initially, Frank normally held
meetings with suppliers for parts that were deemed complex and
had specific design requirements.
However, for this project, the team scheduled meetings with all
the suppliers for all the parts, even for small off-the-shelf parts
that didn’t need to be modified. The meetings were not
productive, as the project team and the suppliers discussed the
same things that were discussed in their project proposals. This
communication flaw led to time-wastage, as the team was
involved in time-wasting meetings instead of actually focusing
on the project.
Besides that, the Lewis representatives needed to hold update
meetings with Frank’s project team every week on Wednesday.
Although the motive was pure from Lewis, they didn’t need to
involve the whole project team. The project team felt
overwhelmed by these weekly meetings and even had to hold
internal meetings every Tuesday in order for them to be on the
same page on the Wednesday meetings. Therefore, the project
team focused more on the meetings than the actual project work,
leading to time wastage.
Apart from that, the Lewis team always wanted constant updates
from the Frank team, which made it difficult for the Frank team
to work effectively. For example, the Lewis team wanted
special reports from the procurement team every week, a move
that made it difficult for the project team to work effectively
when it comes to the issue of identifying and preventing
problems that were related to procurement of parts.
The communication updates needed by the Lewis team went
further until they had direct access to the project team members,
a scenario that was not supposed to occur at all, as both clients
had agreed before the commencement of the project. The
communication breakdown led to communication lapses, as
Frank’s upper project management team wasn’t looped in in
some of the direct communications that took place between the
project team and Lewis’ representatives.
Procurement Flaws
As mentioned in the previous section, the project team needed
to schedule meetings with potential vendors for all parts,
instead of doing so for complex parts only. Those unnecessary
meetings caused a lot of time wastages from both teams, as
nothing concrete was achieved from such meetings. Therefore,
if Frank’s project management team had just used their normal
procurement process, the project team would have had better
project progress than it is currently.
Besides that, Frank’s project management team did not manage
the process of acquiring project spare parts effectively. The
company usually required the vendors to have lists of spare
parts ready in the last three weeks of the scheduled delivery
(assuming the order was made fifteen weeks prior to the
delivery). The vendors would use that time to come up with
accurate lists of the supply parts and their proposed shelf life.
However, since the project didn’t have a lot of float time, the
acceleration of the spare part lists acquisition processes resulted
into the project becoming more expensive whenever the
engineers needed to make changes to the plant. These changes
were accompanied with different spare part lists, a process that
became too complex to manage forcing Frank’s project team to
bring a full-time spare parts coordinator into the project.
Lack of a Risk Management Plan
Frank’s project team didn’t come up with a proper risk
management plan to address the issues that would affect the
project. Frank’s project management team was used to
conducting projects that dealt with iron and steel or petroleum
products. However, for this project, the company had to work
with both teams in order to accomplish the project.
The project team did not foresee issues where the vendors
would face some bankruptcy issues, leading to late deliveries
and affecting the Lewis project deliverables. As a mitigation
plan, the procurement team could have come up with a list of
backup providers for parts in case the primary ones were unable
to deliver on time.
Operational Inefficiencies
The project team was involved in tasks that were affecting the
effectiveness of the whole project. For example, the use of
overqualified individuals for small project tasks in order to
impress Lewis’ representatives affected the overall project costs
and man-hours used in the project. Apart from that, the request
for frequent reports and meetings between the project
stakeholders affected the project team’s effectiveness in
general, which resulted in time wastage.
Besides that, the constant reshuffle of project team
representatives and constant addition of project team members
to the project, was a clear sign that the project team had some
serious operational flows. For example, the addition of a team
member to manage the spare parts acquisition process was a
clear indication of how the process was flawed. Control Change
Request
Basically, when there are some changes occurs in project then
project manager has to deal with it and its very hard to keep the
project on track therefore it is very important to follow good
clear processes to control the change as project can easily go
out of control like frank’s project. There are always three
components on baseline project plan which are
scope(deliverables), cost or budget, time (schedule) and quality
which is beginning of project. then company have to face with
many issues, risk which have direct impact on these three
components and change is required where all representative
made change request to control it and its impact on other
components. Then recommendation and suggestions or solution
are discovered for that change which is documented on change
request log including all changes occurs during the project with
description, date, impact on other component. Then change
management control board have to attend meeting periodically
to control, analyse, evaluate and manage those changes and
once they approved the change then only those changes are used
into the project plan which also include rebase line the project
plan. Therefore, this is basic things to do while controlling
change request in project (Project Management Videos 2013).
Proposed Scope Changes
To start with, the company has to ensure that it changes its
communication strategy with Lewis’ representatives. Frank
could ensure that the project managers are the only people who
would be in contact with Lewis’ representatives. Although the
client will not like the move, it would be necessary in order to
ensure that the assigned project team members focus on the
project tasks at hand, a move that would ensure that the project
costs and deliverables are met for the remaining part of the
project. Therefore, communications should be done on a high-
level basis and proper channels followed when the project team
is reporting to the project sponsor (Meredith, Mantel Jr &
Shafer, 2017).
Apart from that, the project team would need to streamline its
operations across all organizational levels. For example, the
number of trips taken by the project team to meet the project
sponsors should be minimized and replaced with other forms of
communication. Technology has provided us with an
opportunity to communicate more efficiently and channels such
as Skype, Slack or email could be used instead of having the
team make visits, a move that saves the project’s time and leads
to efficient allocation of resources, which ensures that the
project is completed on time (Meredith, Mantel Jr & Shafer,
2017).
Finally, the problem of having late delivery of project materials
could be resolved by having the suppliers make components
available within shorter turnaround times. For this change to be
accomplished, the procurement team would have to find other
suppliers to make the components available for the cases where
some of the suppliers have filed for bankruptcy. Besides that,
Frank’s team should ensure that Service Level Agreements are
signed with suppliers before they are awarded tenders for such
projects (Snyder, 2013).
This change would require the project team to change how it
manages its spare part lists, with the project team having to
revert to its initial plan of having suppliers making them
available when the components are delivered to the company’s
production plants. Besides that, the project team could also
ensure that suppliers work together in order to have the parts
meet their specific needs. Successful companies such as Boeing
are able to assemble parts from different suppliers such as Rolls
Royce who supply the company with jet engines and have them
designed according to the company’s specifications. Frank
could use this move would save the company a lot of money,
especially when making changes to the plant’s design and SLAs
would save the project’s time.
Conclusion
Different issues that have been caused by Lewis and Frank’s
representatives have affected the project scope. Some of the
issues have something to do with communication flaws,
operational issues and other issues that have been discussed in
the change control proposal. The issues discussed have made the
project lag behind and more expensive to implement and the
project team may not complete the project on time if the same
trend continues. Therefore, the purpose of the proposed changes
is to bring the project back on track, greatly minimize on the
project’s cost and time. Therefore, there’s a possibility that the
project may not be completed on time but the work rate would
greatly be improved. References
Harrison, F., & Lock, D. (2017). Advanced project management:
a structured approach. Routledge.
Heagney, J. (2016). Fundamentals of project management.
Amacom.
kerzner, H. (2017). Project management: a systems approach to
planning, scheduling, and controlling. John Wiley & Sons.
Meredith, J. R., Mantel Jr, S. J., & Shafer, S. M. (2017). Project
management: a managerial approach. John Wiley & Sons.
Project Management Videos. (2013). How to Control Change
Requests on a Project (Streaming video). Retrieved
from https://www.youtube.com/watch?v=WWdgFFVkPgA
Snyder, C. S. (2013). A project manager’s book of forms: A
companion to the PMBOK guide (2nd ed.). Indianapolis, IN:
Wiley Publishing.
RISK REGISTER (Snyder, 2013, P111).
Project Title: Date
Risk ID
Risk Statement
Probability
Impact
Score
Response
Scope/ Quality
Schedule/Cost
Revised Probability
Revised Impact
Revised Score
Responsible Party
Actions
Status
Comments
Scope/ Quality
Schedule/ Cost
PROBABILITY AND IMPACT MATRIX (Snyder, 2013, P118).
Project Title: Date Prepared:
Very High
High
Medium
Low
Very Low
Very Low
Low
Medium
High
Very High
It was Friday afternoon, a late November day in 2003, and Ron
Katz, a purchas-
ing agent for Robert L. Frank Construction, poured over the
latest earned value
measurement reports. The results kept pointing out the same
fact; the Lewis
project was seriously over budget. Man-hours expended to date
were running 30
percent over the projection and, despite this fact, the project
was not progressing
sufficiently to satisfy the customer. Material deliveries had
experienced several
slippages, and the unofficial indication from the project
scheduler was that, due
to delivery delays on several of the project’s key items, the
completion date of the
coal liquefaction pilot plant was no longer possible.
Katz was completely baffled. Each day for the past few months
as he
reviewed the daily printout of project time charges, he would
note that the pur-
chasing and expediting departments were working on the Lewis
project, even
though it was not an unusually large project, dollarwise, for
Frank. Two years ear-
lier, Frank was working on a $300 million contract, a $100
million contract and
a $50 million contract concurrently with the Frank Chicago
purchasing depart-
ment responsible for all the purchasing, inspection, and
expediting on all three
contracts. The Lewis project was the largest project in house
and was valued at
only $90 million. What made this project so different from
previous contracts and
caused such problems? There was little Katz felt that he could
do to correct the
situation. All that could be done was to understand what had
occurred in an effort
Robert L. Frank
Construction
Company
665
c17.qxd 12/21/12 7:00 PM Page 665
to prevent a recurrence. He began to write his man-hour report
for requested by
the project manager the next day.
COMPANY BACKGROUND
Robert L. Frank Construction Company was an engineering and
construction firm
serving the petroleum, petrochemical, chemical, iron and steel,
mining, pharma-
ceutical, and food-processing industries from its corporate
headquarters in
Chicago, Illinois, and its worldwide offices. Its services include
engineering, pur-
chasing, inspection, expediting, construction, and consultation.
Frank’s history began in 1947 when Robert L. Frank opened his
office. In
1955, a corporation was formed, and by 1960 the company had
completed con-
tracts for the majority of the American producers of iron and
steel. In 1962, an
event occurred that was to have a large impact on Frank’s
future. This was the
merger of Wilson Engineering Company, a successful refinery
concern, with
Robert L. Frank, now a highly successful iron and steel concern.
This merger
greatly expanded Frank’s scope of operations and brought with
it a strong period
of growth. Several offices were opened in the United States in
an effort to better
handle the increase in business. Future expansions and mergers
enlarged the
Frank organization to the point where it had fifteen offices or
subsidiaries located
throughout the United States and twenty offices worldwide.
Through its first
twenty years of operations, Frank had more than 2,500 contracts
for projects hav-
ing an erected value of over $1 billion.
Frank’s organizational structure has been well suited to the type
of work
undertaken. The projects Frank contracted for typically had a
time constraint, a
budget constraint, and a performance constraint. They all
involved an outside cus-
tomer such as a major petroleum company or a steel
manufacturer. Upon accep-
tance of a project, a project manager was chosen (and usually
identified in the
proposal). The project manager would head up the project
office, typically con-
sisting of the project manager, one to three project engineers, a
project control
manager, and the project secretaries. The project team also
included the necessary
functional personnel from the engineering, purchasing,
estimating, cost control,
and scheduling areas. Exhibit I is a simplified depiction. Of the
functional areas,
the purchasing department is somewhat unique in its
organizational structure. The
purchasing department is organized on a project management
basis much as the project as a whole would be organized.
Within the purchasing
department, each project had a project office that included a
project purchasing
agent, one or more project expeditors and a project purchasing
secretary. Within
the purchasing department the project purchasing agent had line
authority over
only the project expeditor(s) and project secretary. However,
for the project pur-
chasing agent to accomplish his goals, the various functions
within the purchasing
666 ROBERT L. FRANK CONSTRUCTION COMPANY
c17.qxd 12/21/12 7:00 PM Page 666
Exhibit I. Frank organization
VP Eng. VP Control VP Procurement
Purchasing
Project A
Project B
Project C
Mechanical Piping Electrical Civil Estimate Schedule
667
c17.qxd 12/21/12 7:00 PM Page 667
department had to commit sufficient resources. Exhibit II
illustrates the organi-
zation within the purchasing department.
HISTORY OF THE LEWIS PROJECT
Since 1998, the work backlog at Frank has been steadily
declining. The Rovery
Project, valued at $600 million, had increased company
employment sharply
since its inception in 1997. In fact, the engineering on the
Rovery project was
such a large undertaking that in addition to the Chicago office’s
participation, two
other U.S. offices, the Canadian office, and the Italian
subsidiary were heavily
involved. However, since the Rovery project completion in
2001, not enough new
668 ROBERT L. FRANK CONSTRUCTION COMPANY
Exhibit II. Frank purchasing organization
Mgr. Procurement
Mgr. Buying, Esp., Insp.
Project A
Project B
Project C
Admin. Assistant
Chief Inspector
InspectionMgr. Buying Mgr. Traffic Chief Expediter
Buying Traffic Expediting
Project D
Project E
c17.qxd 12/21/12 7:00 PM Page 668
work was received to support the work force thus necessitating
recent lay-offs of
engineers, including a few project engineers.
Company officials were very disturbed with the situation.
Frank’s company
policy was to “maintain an efficient organization of sufficient
size and resources,
and staffed by people with the necessary qualifications, to
execute projects
in any location for the industries served by Frank.” However,
the recent down-
turn in business meant that there was not enough work even
with the reduction in
employees. Further cutbacks would jeopardize Frank’s
prospects of obtaining
future large projects as prospective clients look to contractors
with a sufficient
staff of qualified people to accomplish their work. By contrast,
supporting
employees out of overhead was not the way to do business,
either. It became
increasingly important to “cut the fat out” of the proposals
being submitted for
possible projects. Despite this, new projects were few and far
between, and the
projects that were received were small in scope and dollar value
and therefore did
not provide work for very many employees.
When rumors of a possible construction project for a new coal
liquefaction
pilot plant started circulating, Frank officials were extremely
interested in bidding
for the work. It was an excellent prospect for two reasons.
Besides Frank’s des-
perate need for work, the Lewis chemical process used in the
pilot plant would
benefit Frank in the long run by the development of state-of-
the-art technology.
If the pilot plant project could be successfully executed, when it
came time to
construct the full-scale facility, Frank would have the inside
track as they had
already worked with the technology. The full-scale facility
offered prospects
exceeding the Rovery project, Frank’s largest project to date.
Top priority was
therefore put on obtaining the Lewis project. It was felt that
Frank had a slight
edge due to successful completion of a Lewis project six years
ago. The proposal
submitted to Lewis contained estimates for material costs, man-
hours, and the
fee. Any changes in scope after contract award would be
handled by change order
to the contract. Both Lewis and Frank had excellent scope
change control processes
as part of their configuration management plans. The functional
department
affected would submit an estimate of extra man-hours involved
to the project man-
ager, who would review the request and submit it to the client
for approval. Frank’s
preference was for cost-plus-fixed-fee contracts.
One of the unique aspects stated in the Lewis proposal was the
requirement
for participation by both of Frank Chicago’s operating
divisions. Previous Frank
contracts were well suited to either Frank’s Petroleum and
Chemical Division
(P & C) or the Iron and Steel Division (I & S). However, due to
the unusual chem-
ical process, one that starts with coal and ends up with a liquid
energy form, one
of the plant’s three units was well suited to the P & C Division
and one was well
suited to the I & S Division. The third unit was an off-site unit
and was not of par-
ticular engineering significance.
History of the Lewis Project 669
c17.qxd 12/21/12 7:00 PM Page 669
The award of the contract six weeks later led to expectations by
most Frank
personnel that the company’s future was back on track again.
The project began
inauspiciously. The project manager was a well-liked, easy-
going sort who had
been manager of several Frank projects. The project office
included three of
Frank’s most qualified project engineers.
In the purchasing department, the project purchasing agent
(PPA) assigned to
the project was Frank’s most experienced PPA. Bill Hall had
just completed his
assignment on the Rovery Project and had done well,
considering the magnitude
of the job. The project had its problems, but they were small in
comparison to the
achievements. He had alienated some of the departments
slightly but that was to
be expected. Purchasing upper management was somewhat
dissatisfied with him
in that, due to the size of the project, he didn’t always use the
normal Frank pur-
chasing methods; rather, he used whatever method he felt was in
the best interest
of the project. Also, after the Rovery project, a purchasing
upper management
reshuffling left him in the same position but with less power
and authority rather
than receiving a promotion he had felt he had earned. As a
result, he began to sub-
tly criticize the purchasing management. This action caused
upper management
to hold him in less than high regard but, at the time of the
Lewis Project, Hall was
the best person available.
Due to the lack of float in the schedule and the early field start
date, it was
necessary to fast start the Lewis Project. All major equipment
was to be pur-
chased within the first three months. This, with few exceptions,
was accom-
plished. The usual problems occurred such as late receipt of
requisition from
engineering and late receipt of bids from suppliers.
One of the unique aspects of the Lewis project was the
requirement for pur-
chase order award meetings with vendors. Typically, Frank
would hold award
meetings with vendors of major equipment such as reactors,
compressors, large
process towers, or large pumps. However, almost each time
Lewis approved pur-
chase of a mechanical item or vessel, it requested that the
vendor come in for a
meeting. Even if the order was for an on-the-shelf stock pump
or small drum or
tank, a meeting was held. Initially, the purchasing department
meeting attendees
included the project purchasing agent, the buyer, the manager of
the traffic depart-
ment, the chief expeditor, and the chief Inspector. Engineering
representatives
included the responsible engineer and one or two of the project
engineers. Other
Frank attendees were the project control manager and the
scheduler. Quite often,
these meetings would accomplish nothing except the reiteration
of what had been
included in the proposal or what could have been resolved with
a phone call or
even e-mail. The project purchasing agent was responsible for
issuing meeting
notes after each meeting.
One day at the end of the first three-month period, the top-
ranking Lewis rep-
resentative met with Larry Broyles, the Frank project manager.
670 ROBERT L. FRANK CONSTRUCTION COMPANY
c17.qxd 12/21/12 7:00 PM Page 670
Lewis rep: Larry, the project is progressing but I’m a little
concerned. We
don’t feel like we have our finger on the pulse of the project.
The information
we are getting is sketchy and untimely. What we would like to
do is meet with
Frank every Wednesday to review progress and resolve
problems.
Larry: I’d be more than happy to meet with any of the Lewis
people because
I think your request has a lot of merit.
Lewis rep: Well, Larry, what I had in mind was a meeting
between all the
Lewis people, yourself, your project office, the project
purchasing agent, his
assistant, and your scheduling and cost control people.
Larry: This sounds like a pretty involved meeting. We’re going
to tie up a lot
of our people for one full day a week. I’d like to scale this thing
down. Our pro-
posal took into consideration meetings, but not to the magnitude
we’re talking
about.
Lewis rep: Larry, I’m sorry but we’re footing the bill on this
project and
we’ve got to know what’s going on.
Larry: I’ll set it up for this coming Wednesday.
Lewis rep: Good.
The required personnel were informed by the project manager
that effective
immediately, meetings with the client would be held weekly.
However, Lewis was
dissatisfied with the results of the meetings, so the Frank
project manager
informed his people that a premeeting would be held each
Tuesday to prepare the
Frank portion of the Wednesday meeting. All of the Wednesday
participants
attended the Tuesday premeetings.
Lewis requests for additional special reports from the
purchasing department
were given into without comment. The project purchasing agent
and his assistants
(project started with one and expanded to four) were devoting a
great majority of
their time to special reports and putting out fires instead of
being able to track
progress and prevent problems. For example, recommended
spare parts lists were
normally required from vendors on all Frank projects. Lewis
was no exception.
However, after the project began, Lewis decided it wanted the
spare parts recom-
mendations early into the job. Usually, spare parts lists are left
for the end of an
order. For example, on a pump with fifteen-week delivery,
normally Frank would
pursue the recommended spare parts list three to four weeks
prior to shipment, as
it would tend to be more accurate. This improved accuracy was
due to the fact
that at this point in the order, all changes probably had been
made. In the case of
the Lewis project, spare parts recommendations had to be
expedited from the day
the material was released for fabrication. Changes could still be
made that could
dramatically affect the design of the pump. Thus, a change in
the pump after
receipt of the spare parts list would necessitate a new spare
parts list. The time
involved in this method of expediting the spare parts list was
much greater than the
History of the Lewis Project 671
c17.qxd 12/21/12 7:00 PM Page 671
time involved in the normal Frank method. Added to this
situation was Lewis’s
request for a fairly involved biweekly report on the status of
spare parts lists on
all the orders. In addition, a full time spare parts coordinator
was assigned to the
project.
The initial lines of communication between Frank and Lewis
were initially
well defined. The seven in-house Lewis representatives
occupied the area adja-
cent to the Frank project office (see Exhibit III). Initially, all
communications
from Lewis were channeled through the Frank project office to
the applicable
functional employee. In the case of the purchasing department,
the Frank project
office would channel Lewis requests through the purchasing
project office.
Responses or return communications followed the reverse route.
Soon the volume
of communications increased to the point where response time
was becoming
unacceptable. In several special cases, an effort was made to cut
this response time.
Larry Broyles told the Lewis team members to call or go see the
functional per-
son (i.e., buyer or engineer) for the answer. However, this
practice soon became
the rule rather than the exception. Initially, the project office
was kept informed
672 ROBERT L. FRANK CONSTRUCTION COMPANY
Exhibit III. Floor plan—Lewis project teams
Project
Manager
Assistant to
Project
Manager
Procurement
Advisor
Inspection
Coordinator
Vacant
Project
Control
Manager
Chief Project
Engineer
Project
Manager
Project
Engineer
Project
Engineer
Project
Engineer
Assistant
Project
Engineer
Engineer
Engineer
Cost
Control
Grey boxed text Indicates Lewis Personnel
Normal text Indicates Frank Personnel
c17.qxd 12/21/12 7:00 PM Page 672
of these conversations, but this soon stopped. The Lewis
personnel had integrated
themselves into the Frank organization to the point where they
became part of the
organization.
The project continued on, and numerous problems cropped up.
Vendors’
material delays occurred, companies with Frank purchase orders
went bankrupt,
and progress was not to Lewis’s satisfaction. Upper
management soon became aware
the problems on this project due to its sensitive nature, and the
Lewis project was
now receiving much more intense involvement by senior
management than it had
previously. Upper management sat in on the weekly meetings in
an attempt to
pacify Lewis. Further problems plagued the project. Purchasing
management, in
an attempt to placate Lewis, replaced the project purchasing
agent. Ron Katz, a
promising young MBA graduate, had five years of experience as
an assistant to
several of the project purchasing agents. He was most recently a
project purchas-
ing agent on a fairly small project that had been very
successful. It was thought
by purchasing upper management that this move was a good
one, for two reasons.
First, it would remove Bill Hall from the project as PPA.
Second, by appointing
Ron Katz, Lewis would be pacified, as Katz was a promising
talent with a suc-
cessful project under his belt.
However, the project under direction of Katz still experienced
problems in
the purchasing area. Revisions by engineering to material
already on order caused
serious delivery delays. Recently requisitioned material could
not be located with
an acceptable delivery promise. Katz and purchasing upper
management, in an
attempt to improve the situation, assigned more personnel to the
project, personnel
that were more qualified than the positions dictated. Buyers and
upper-level pur-
chasing officials were sent on trips to vendors’ facilities that
were normally han-
dled by traveling expediters. In the last week the Lewis
representative met with
the project manager, Broyles:
Lewis rep: Larry, I’ve been reviewing these man-hour
expenditures, and I’m
disturbed by them.
Larry: Why’s that?
Lewis rep: The man-hour expenditures are far outrunning
project progress.
Three months ago, you reported that the project completion
percentage was 30
percent, but according to my calculations, we’ve used 47
percent of the man
hours. Last month you reported 40 percent project completion
and I show a 60
percent expenditure of man-hours.
Larry: Well, as you know, due to problems with vendors’
deliveries, we’ve
really had to expedite intensively to try to bring them back in
line.
Lewis rep: Larry, I’m being closely watched by my people on
this project,
and a cost or schedule overrun not only makes Frank look bad,
it makes me
look bad.
Larry: Where do we go from here?
History of the Lewis Project 673
c17.qxd 12/21/12 7:00 PM Page 673
Lewis rep: What I want is an estimate from your people on what
is left, man-
hour wise. Then I can sit down with my people and see where
we are.
Larry: I’ll have something for you the day after tomorrow.
Lewis rep: Good.
The functional areas were requested to provide this information,
which was
reviewed and combined by the project manager and submitted to
Lewis for
approval. Lewis’s reaction was unpleasant, to say the least. The
estimated man-
hours in the proposal were now insufficient. The revised
estimate was for almost
40 percent over the proposal. The Lewis representative
immediately demanded an
extensive report on the requested increase. In response to this,
the project man-
ager requested man-hour breakdowns from the functional areas.
Purchasing was
told to do a purchase order by purchase order breakdown of
expediting and
inspection man-hours. The buying section had to break down the
estimate of the
man-hours needed to purchase each requisition, many of which
were not even
issued. Things appeared to have gone from bad to worse.
674 ROBERT L. FRANK CONSTRUCTION COMPANY
c17.qxd 12/21/12 7:00 PM Page 674

More Related Content

Similar to Running head CHANGE CONTROL1Executive SummaryThe Lewis .docx

Project management
Project managementProject management
Project management
swapna pattem
 
How Scope Creep Negatively Impacts Project Success (& How to Fix It)
How Scope Creep Negatively Impacts Project Success (& How to Fix It)How Scope Creep Negatively Impacts Project Success (& How to Fix It)
How Scope Creep Negatively Impacts Project Success (& How to Fix It)
QuekelsBaro
 
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfImpact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
saikumarmba2023
 
Project typed
Project typedProject typed
Project typed
Rahul
 
Project Tracking and Scope Management
Project Tracking and Scope ManagementProject Tracking and Scope Management
Project Tracking and Scope ManagementTalha Siddiqui
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s Methodology
EPC Group
 
challenges of highway projects in India
challenges of highway projects in Indiachallenges of highway projects in India
challenges of highway projects in IndiaSanjay Kedia
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
S. Sathishkumar
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
SHAZEBALIKHAN1
 
Planning skill.pdf
Planning skill.pdfPlanning skill.pdf
Planning skill.pdf
abdelazizfarag1
 
Work breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxWork breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docx
ericbrooks84875
 
Lec 08 project scope_management
Lec 08 project scope_managementLec 08 project scope_management
Lec 08 project scope_management
SAJID ALI RUK
 
integration management
 integration management integration management
integration management
saiftahlawi1
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project ManagementMostafa Ewees
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
Jamil Faraj , PMP
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
Jamil Faraj , PMP
 
Pmp4
Pmp4Pmp4
Sas Presentation
Sas PresentationSas Presentation
Sas Presentationpats384888
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planningYasirHamour
 

Similar to Running head CHANGE CONTROL1Executive SummaryThe Lewis .docx (20)

Project management
Project managementProject management
Project management
 
How Scope Creep Negatively Impacts Project Success (& How to Fix It)
How Scope Creep Negatively Impacts Project Success (& How to Fix It)How Scope Creep Negatively Impacts Project Success (& How to Fix It)
How Scope Creep Negatively Impacts Project Success (& How to Fix It)
 
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdfImpact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
 
Project typed
Project typedProject typed
Project typed
 
Project Tracking and Scope Management
Project Tracking and Scope ManagementProject Tracking and Scope Management
Project Tracking and Scope Management
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s Methodology
 
challenges of highway projects in India
challenges of highway projects in Indiachallenges of highway projects in India
challenges of highway projects in India
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
Planning skill.pdf
Planning skill.pdfPlanning skill.pdf
Planning skill.pdf
 
Work breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxWork breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docx
 
Lec 08 project scope_management
Lec 08 project scope_managementLec 08 project scope_management
Lec 08 project scope_management
 
integration management
 integration management integration management
integration management
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project Management
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
Pmp4
Pmp4Pmp4
Pmp4
 
Sas Presentation
Sas PresentationSas Presentation
Sas Presentation
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planning
 

More from healdkathaleen

Mill proposes his Art of Life, but he also insists that it is not ve.docx
Mill proposes his Art of Life, but he also insists that it is not ve.docxMill proposes his Art of Life, but he also insists that it is not ve.docx
Mill proposes his Art of Life, but he also insists that it is not ve.docx
healdkathaleen
 
Milford Bank and Trust Company is revamping its credit management de.docx
Milford Bank and Trust Company is revamping its credit management de.docxMilford Bank and Trust Company is revamping its credit management de.docx
Milford Bank and Trust Company is revamping its credit management de.docx
healdkathaleen
 
milies (most with teenage children) and the Baby Boomers (teens and .docx
milies (most with teenage children) and the Baby Boomers (teens and .docxmilies (most with teenage children) and the Baby Boomers (teens and .docx
milies (most with teenage children) and the Baby Boomers (teens and .docx
healdkathaleen
 
Midterm Paper - Recombinant DNA TechnologySome scientists are conc.docx
Midterm Paper - Recombinant DNA TechnologySome scientists are conc.docxMidterm Paper - Recombinant DNA TechnologySome scientists are conc.docx
Midterm Paper - Recombinant DNA TechnologySome scientists are conc.docx
healdkathaleen
 
Midterm Study GuideAnswers need to be based on the files i will em.docx
Midterm Study GuideAnswers need to be based on the files i will em.docxMidterm Study GuideAnswers need to be based on the files i will em.docx
Midterm Study GuideAnswers need to be based on the files i will em.docx
healdkathaleen
 
Michelle Carroll is a coworker of yours and she overheard a conversa.docx
Michelle Carroll is a coworker of yours and she overheard a conversa.docxMichelle Carroll is a coworker of yours and she overheard a conversa.docx
Michelle Carroll is a coworker of yours and she overheard a conversa.docx
healdkathaleen
 
Michelle is attending college and has a part-time job. Once she fini.docx
Michelle is attending college and has a part-time job. Once she fini.docxMichelle is attending college and has a part-time job. Once she fini.docx
Michelle is attending college and has a part-time job. Once she fini.docx
healdkathaleen
 
Midterm Assignment Instructions (due 31 August)The mid-term essay .docx
Midterm Assignment Instructions (due 31 August)The mid-term essay .docxMidterm Assignment Instructions (due 31 August)The mid-term essay .docx
Midterm Assignment Instructions (due 31 August)The mid-term essay .docx
healdkathaleen
 
Milestone 2Outline of Final PaperYou will create a robust.docx
Milestone 2Outline of Final PaperYou will create a robust.docxMilestone 2Outline of Final PaperYou will create a robust.docx
Milestone 2Outline of Final PaperYou will create a robust.docx
healdkathaleen
 
MigrationThe human population has lived a rural lifestyle thro.docx
MigrationThe human population has lived a rural lifestyle thro.docxMigrationThe human population has lived a rural lifestyle thro.docx
MigrationThe human population has lived a rural lifestyle thro.docx
healdkathaleen
 
Mid-TermDismiss Mid-Term1) As you consider the challenges fa.docx
Mid-TermDismiss Mid-Term1) As you consider the challenges fa.docxMid-TermDismiss Mid-Term1) As you consider the challenges fa.docx
Mid-TermDismiss Mid-Term1) As you consider the challenges fa.docx
healdkathaleen
 
MicroeconomicsUse what you have learned about economic indicators .docx
MicroeconomicsUse what you have learned about economic indicators .docxMicroeconomicsUse what you have learned about economic indicators .docx
MicroeconomicsUse what you have learned about economic indicators .docx
healdkathaleen
 
Michael Dell began building and selling computers from his dorm room.docx
Michael Dell began building and selling computers from his dorm room.docxMichael Dell began building and selling computers from his dorm room.docx
Michael Dell began building and selling computers from his dorm room.docx
healdkathaleen
 
Michael is a three-year-old boy with severe seizure activity. He h.docx
Michael is a three-year-old boy with severe seizure activity. He h.docxMichael is a three-year-old boy with severe seizure activity. He h.docx
Michael is a three-year-old boy with severe seizure activity. He h.docx
healdkathaleen
 
Michael graduates from New York University and on February 1st of th.docx
Michael graduates from New York University and on February 1st of th.docxMichael graduates from New York University and on February 1st of th.docx
Michael graduates from New York University and on February 1st of th.docx
healdkathaleen
 
Message Using Multisim 11, please help me build a home security sys.docx
Message Using Multisim 11, please help me build a home security sys.docxMessage Using Multisim 11, please help me build a home security sys.docx
Message Using Multisim 11, please help me build a home security sys.docx
healdkathaleen
 
Methodology of H&M internationalization Research purposeRe.docx
Methodology of H&M internationalization Research purposeRe.docxMethodology of H&M internationalization Research purposeRe.docx
Methodology of H&M internationalization Research purposeRe.docx
healdkathaleen
 
Mental Disability DiscussionConsider the typification of these c.docx
Mental Disability DiscussionConsider the typification of these c.docxMental Disability DiscussionConsider the typification of these c.docx
Mental Disability DiscussionConsider the typification of these c.docx
healdkathaleen
 
Meningitis Analyze the assigned neurological disorder and prepar.docx
Meningitis Analyze the assigned neurological disorder and prepar.docxMeningitis Analyze the assigned neurological disorder and prepar.docx
Meningitis Analyze the assigned neurological disorder and prepar.docx
healdkathaleen
 
Memoir Format(chart this)Introduction (that captures the r.docx
Memoir Format(chart this)Introduction (that captures the r.docxMemoir Format(chart this)Introduction (that captures the r.docx
Memoir Format(chart this)Introduction (that captures the r.docx
healdkathaleen
 

More from healdkathaleen (20)

Mill proposes his Art of Life, but he also insists that it is not ve.docx
Mill proposes his Art of Life, but he also insists that it is not ve.docxMill proposes his Art of Life, but he also insists that it is not ve.docx
Mill proposes his Art of Life, but he also insists that it is not ve.docx
 
Milford Bank and Trust Company is revamping its credit management de.docx
Milford Bank and Trust Company is revamping its credit management de.docxMilford Bank and Trust Company is revamping its credit management de.docx
Milford Bank and Trust Company is revamping its credit management de.docx
 
milies (most with teenage children) and the Baby Boomers (teens and .docx
milies (most with teenage children) and the Baby Boomers (teens and .docxmilies (most with teenage children) and the Baby Boomers (teens and .docx
milies (most with teenage children) and the Baby Boomers (teens and .docx
 
Midterm Paper - Recombinant DNA TechnologySome scientists are conc.docx
Midterm Paper - Recombinant DNA TechnologySome scientists are conc.docxMidterm Paper - Recombinant DNA TechnologySome scientists are conc.docx
Midterm Paper - Recombinant DNA TechnologySome scientists are conc.docx
 
Midterm Study GuideAnswers need to be based on the files i will em.docx
Midterm Study GuideAnswers need to be based on the files i will em.docxMidterm Study GuideAnswers need to be based on the files i will em.docx
Midterm Study GuideAnswers need to be based on the files i will em.docx
 
Michelle Carroll is a coworker of yours and she overheard a conversa.docx
Michelle Carroll is a coworker of yours and she overheard a conversa.docxMichelle Carroll is a coworker of yours and she overheard a conversa.docx
Michelle Carroll is a coworker of yours and she overheard a conversa.docx
 
Michelle is attending college and has a part-time job. Once she fini.docx
Michelle is attending college and has a part-time job. Once she fini.docxMichelle is attending college and has a part-time job. Once she fini.docx
Michelle is attending college and has a part-time job. Once she fini.docx
 
Midterm Assignment Instructions (due 31 August)The mid-term essay .docx
Midterm Assignment Instructions (due 31 August)The mid-term essay .docxMidterm Assignment Instructions (due 31 August)The mid-term essay .docx
Midterm Assignment Instructions (due 31 August)The mid-term essay .docx
 
Milestone 2Outline of Final PaperYou will create a robust.docx
Milestone 2Outline of Final PaperYou will create a robust.docxMilestone 2Outline of Final PaperYou will create a robust.docx
Milestone 2Outline of Final PaperYou will create a robust.docx
 
MigrationThe human population has lived a rural lifestyle thro.docx
MigrationThe human population has lived a rural lifestyle thro.docxMigrationThe human population has lived a rural lifestyle thro.docx
MigrationThe human population has lived a rural lifestyle thro.docx
 
Mid-TermDismiss Mid-Term1) As you consider the challenges fa.docx
Mid-TermDismiss Mid-Term1) As you consider the challenges fa.docxMid-TermDismiss Mid-Term1) As you consider the challenges fa.docx
Mid-TermDismiss Mid-Term1) As you consider the challenges fa.docx
 
MicroeconomicsUse what you have learned about economic indicators .docx
MicroeconomicsUse what you have learned about economic indicators .docxMicroeconomicsUse what you have learned about economic indicators .docx
MicroeconomicsUse what you have learned about economic indicators .docx
 
Michael Dell began building and selling computers from his dorm room.docx
Michael Dell began building and selling computers from his dorm room.docxMichael Dell began building and selling computers from his dorm room.docx
Michael Dell began building and selling computers from his dorm room.docx
 
Michael is a three-year-old boy with severe seizure activity. He h.docx
Michael is a three-year-old boy with severe seizure activity. He h.docxMichael is a three-year-old boy with severe seizure activity. He h.docx
Michael is a three-year-old boy with severe seizure activity. He h.docx
 
Michael graduates from New York University and on February 1st of th.docx
Michael graduates from New York University and on February 1st of th.docxMichael graduates from New York University and on February 1st of th.docx
Michael graduates from New York University and on February 1st of th.docx
 
Message Using Multisim 11, please help me build a home security sys.docx
Message Using Multisim 11, please help me build a home security sys.docxMessage Using Multisim 11, please help me build a home security sys.docx
Message Using Multisim 11, please help me build a home security sys.docx
 
Methodology of H&M internationalization Research purposeRe.docx
Methodology of H&M internationalization Research purposeRe.docxMethodology of H&M internationalization Research purposeRe.docx
Methodology of H&M internationalization Research purposeRe.docx
 
Mental Disability DiscussionConsider the typification of these c.docx
Mental Disability DiscussionConsider the typification of these c.docxMental Disability DiscussionConsider the typification of these c.docx
Mental Disability DiscussionConsider the typification of these c.docx
 
Meningitis Analyze the assigned neurological disorder and prepar.docx
Meningitis Analyze the assigned neurological disorder and prepar.docxMeningitis Analyze the assigned neurological disorder and prepar.docx
Meningitis Analyze the assigned neurological disorder and prepar.docx
 
Memoir Format(chart this)Introduction (that captures the r.docx
Memoir Format(chart this)Introduction (that captures the r.docxMemoir Format(chart this)Introduction (that captures the r.docx
Memoir Format(chart this)Introduction (that captures the r.docx
 

Recently uploaded

Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
Celine George
 
B.ed spl. HI pdusu exam paper-2023-24.pdf
B.ed spl. HI pdusu exam paper-2023-24.pdfB.ed spl. HI pdusu exam paper-2023-24.pdf
B.ed spl. HI pdusu exam paper-2023-24.pdf
Special education needs
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
Celine George
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptxSolid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
Denish Jangid
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
timhan337
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
Steve Thomason
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
Excellence Foundation for South Sudan
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
Fundacja Rozwoju Społeczeństwa Przedsiębiorczego
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
bennyroshan06
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 

Recently uploaded (20)

Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
 
B.ed spl. HI pdusu exam paper-2023-24.pdf
B.ed spl. HI pdusu exam paper-2023-24.pdfB.ed spl. HI pdusu exam paper-2023-24.pdf
B.ed spl. HI pdusu exam paper-2023-24.pdf
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptxSolid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 

Running head CHANGE CONTROL1Executive SummaryThe Lewis .docx

  • 1. Running head: CHANGE CONTROL 1Executive Summary The Lewis project has exceeded its projected cost and the project team is running behind on the project’s time. Frank’s team has been overwhelmed with reporting requests coming in from Lewis’ representatives and the company’s suppliers have affected the project’s time by delivering some of the project parts late. At the moment, the project cost is 30% more than the project team expected and the project team seeks some solutions to bring it back on track. The project team suggests the implementation of change controls that would ensure that the project’s scope is controlled and the costs minimized and ensure that the project is completed on time with all the deliverables achieved. The project team suggests the implementation of some changes in the project team’s communication processes and how procurements are made in order to bring the project back on track. Keywords: scope, deliverables, project team. Table of Contents 2Executive Summary 4Introduction Processes Involved in Change Request……………………………………………………………… ……….............4
  • 2. 4Identified Project Issues Control Change Requests………....................................................................... .............................6 8Conclusion 10References Introduction The Lewis project is lagging behind the project sponsor’s expectations, as the project’s cost, time and deliverable goals seem to be unattainable with the amount of time remaining. One of the problems that can be noticed from the project is the fact that the project was running way over the projected budget with the project team estimating that the project would cost 30% above the projected budget. Besides that, the project had experienced some serious material delays, as the procurement processes were quite inefficient and expensive. The core purpose of this proposal document is to come up with an in-depth analysis of the problems that are affecting Frank’s effectiveness in handling the project and come up with proposed changes that could be implemented to make the project get back on track within the remaining project time. Processes Involved in Change Request Due to a failure of coming up with a concrete plan, the project team has come up with the idea of submitting a request to deal with the changes necessary to alter the project. There are certain processes they will have to go through in order to help the company to get back on track. The company needs to rework on the purpose and objectives that were initially carried out by Frank’s before the start of the project. As the cost and time of the project was going way up beyond the expectations, Franks’
  • 3. would need to look over the scope of the project. The change request team then fills out the change request form in which they would identify a proposed change and then justifies the identified change. They would continue on to identify the impacts of change on time, cost, schedule and on stakeholders as well. After a complete working on this change, the management would continue on to change the management roles for example they would set the employees according to their positions unlike before. The management would then submit the change request, review the proposed changes and after that, if approved, the request will be approved. Identified Project Issues Communication Breakdown The project team experienced some serious communication issues in the course of the project, which made the Lewis project, go out of scope. To start with, Frank’s project team required its suppliers to have a meeting with them for every part the company acquired from them. Initially, Frank normally held meetings with suppliers for parts that were deemed complex and had specific design requirements. However, for this project, the team scheduled meetings with all the suppliers for all the parts, even for small off-the-shelf parts that didn’t need to be modified. The meetings were not productive, as the project team and the suppliers discussed the same things that were discussed in their project proposals. This communication flaw led to time-wastage, as the team was involved in time-wasting meetings instead of actually focusing on the project. Besides that, the Lewis representatives needed to hold update meetings with Frank’s project team every week on Wednesday. Although the motive was pure from Lewis, they didn’t need to involve the whole project team. The project team felt overwhelmed by these weekly meetings and even had to hold internal meetings every Tuesday in order for them to be on the same page on the Wednesday meetings. Therefore, the project team focused more on the meetings than the actual project work,
  • 4. leading to time wastage. Apart from that, the Lewis team always wanted constant updates from the Frank team, which made it difficult for the Frank team to work effectively. For example, the Lewis team wanted special reports from the procurement team every week, a move that made it difficult for the project team to work effectively when it comes to the issue of identifying and preventing problems that were related to procurement of parts. The communication updates needed by the Lewis team went further until they had direct access to the project team members, a scenario that was not supposed to occur at all, as both clients had agreed before the commencement of the project. The communication breakdown led to communication lapses, as Frank’s upper project management team wasn’t looped in in some of the direct communications that took place between the project team and Lewis’ representatives. Procurement Flaws As mentioned in the previous section, the project team needed to schedule meetings with potential vendors for all parts, instead of doing so for complex parts only. Those unnecessary meetings caused a lot of time wastages from both teams, as nothing concrete was achieved from such meetings. Therefore, if Frank’s project management team had just used their normal procurement process, the project team would have had better project progress than it is currently. Besides that, Frank’s project management team did not manage the process of acquiring project spare parts effectively. The company usually required the vendors to have lists of spare parts ready in the last three weeks of the scheduled delivery (assuming the order was made fifteen weeks prior to the delivery). The vendors would use that time to come up with accurate lists of the supply parts and their proposed shelf life. However, since the project didn’t have a lot of float time, the acceleration of the spare part lists acquisition processes resulted
  • 5. into the project becoming more expensive whenever the engineers needed to make changes to the plant. These changes were accompanied with different spare part lists, a process that became too complex to manage forcing Frank’s project team to bring a full-time spare parts coordinator into the project. Lack of a Risk Management Plan Frank’s project team didn’t come up with a proper risk management plan to address the issues that would affect the project. Frank’s project management team was used to conducting projects that dealt with iron and steel or petroleum products. However, for this project, the company had to work with both teams in order to accomplish the project. The project team did not foresee issues where the vendors would face some bankruptcy issues, leading to late deliveries and affecting the Lewis project deliverables. As a mitigation plan, the procurement team could have come up with a list of backup providers for parts in case the primary ones were unable to deliver on time. Operational Inefficiencies The project team was involved in tasks that were affecting the effectiveness of the whole project. For example, the use of overqualified individuals for small project tasks in order to impress Lewis’ representatives affected the overall project costs and man-hours used in the project. Apart from that, the request for frequent reports and meetings between the project stakeholders affected the project team’s effectiveness in general, which resulted in time wastage. Besides that, the constant reshuffle of project team representatives and constant addition of project team members to the project, was a clear sign that the project team had some serious operational flows. For example, the addition of a team member to manage the spare parts acquisition process was a clear indication of how the process was flawed. Control Change
  • 6. Request Basically, when there are some changes occurs in project then project manager has to deal with it and its very hard to keep the project on track therefore it is very important to follow good clear processes to control the change as project can easily go out of control like frank’s project. There are always three components on baseline project plan which are scope(deliverables), cost or budget, time (schedule) and quality which is beginning of project. then company have to face with many issues, risk which have direct impact on these three components and change is required where all representative made change request to control it and its impact on other components. Then recommendation and suggestions or solution are discovered for that change which is documented on change request log including all changes occurs during the project with description, date, impact on other component. Then change management control board have to attend meeting periodically to control, analyse, evaluate and manage those changes and once they approved the change then only those changes are used into the project plan which also include rebase line the project plan. Therefore, this is basic things to do while controlling change request in project (Project Management Videos 2013). Proposed Scope Changes To start with, the company has to ensure that it changes its communication strategy with Lewis’ representatives. Frank could ensure that the project managers are the only people who would be in contact with Lewis’ representatives. Although the client will not like the move, it would be necessary in order to ensure that the assigned project team members focus on the project tasks at hand, a move that would ensure that the project costs and deliverables are met for the remaining part of the project. Therefore, communications should be done on a high- level basis and proper channels followed when the project team is reporting to the project sponsor (Meredith, Mantel Jr & Shafer, 2017). Apart from that, the project team would need to streamline its
  • 7. operations across all organizational levels. For example, the number of trips taken by the project team to meet the project sponsors should be minimized and replaced with other forms of communication. Technology has provided us with an opportunity to communicate more efficiently and channels such as Skype, Slack or email could be used instead of having the team make visits, a move that saves the project’s time and leads to efficient allocation of resources, which ensures that the project is completed on time (Meredith, Mantel Jr & Shafer, 2017). Finally, the problem of having late delivery of project materials could be resolved by having the suppliers make components available within shorter turnaround times. For this change to be accomplished, the procurement team would have to find other suppliers to make the components available for the cases where some of the suppliers have filed for bankruptcy. Besides that, Frank’s team should ensure that Service Level Agreements are signed with suppliers before they are awarded tenders for such projects (Snyder, 2013). This change would require the project team to change how it manages its spare part lists, with the project team having to revert to its initial plan of having suppliers making them available when the components are delivered to the company’s production plants. Besides that, the project team could also ensure that suppliers work together in order to have the parts meet their specific needs. Successful companies such as Boeing are able to assemble parts from different suppliers such as Rolls Royce who supply the company with jet engines and have them designed according to the company’s specifications. Frank could use this move would save the company a lot of money, especially when making changes to the plant’s design and SLAs would save the project’s time. Conclusion Different issues that have been caused by Lewis and Frank’s representatives have affected the project scope. Some of the
  • 8. issues have something to do with communication flaws, operational issues and other issues that have been discussed in the change control proposal. The issues discussed have made the project lag behind and more expensive to implement and the project team may not complete the project on time if the same trend continues. Therefore, the purpose of the proposed changes is to bring the project back on track, greatly minimize on the project’s cost and time. Therefore, there’s a possibility that the project may not be completed on time but the work rate would greatly be improved. References Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge. Heagney, J. (2016). Fundamentals of project management. Amacom. kerzner, H. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Meredith, J. R., Mantel Jr, S. J., & Shafer, S. M. (2017). Project management: a managerial approach. John Wiley & Sons. Project Management Videos. (2013). How to Control Change Requests on a Project (Streaming video). Retrieved from https://www.youtube.com/watch?v=WWdgFFVkPgA Snyder, C. S. (2013). A project manager’s book of forms: A companion to the PMBOK guide (2nd ed.). Indianapolis, IN: Wiley Publishing. RISK REGISTER (Snyder, 2013, P111). Project Title: Date Risk ID Risk Statement Probability
  • 10. Revised Probability Revised Impact Revised Score Responsible Party Actions Status Comments Scope/ Quality Schedule/ Cost
  • 11.
  • 12. PROBABILITY AND IMPACT MATRIX (Snyder, 2013, P118). Project Title: Date Prepared: Very High High Medium Low Very Low
  • 13. Very Low Low Medium High Very High It was Friday afternoon, a late November day in 2003, and Ron Katz, a purchas- ing agent for Robert L. Frank Construction, poured over the latest earned value measurement reports. The results kept pointing out the same fact; the Lewis project was seriously over budget. Man-hours expended to date were running 30 percent over the projection and, despite this fact, the project was not progressing sufficiently to satisfy the customer. Material deliveries had experienced several slippages, and the unofficial indication from the project scheduler was that, due to delivery delays on several of the project’s key items, the completion date of the coal liquefaction pilot plant was no longer possible. Katz was completely baffled. Each day for the past few months as he reviewed the daily printout of project time charges, he would note that the pur- chasing and expediting departments were working on the Lewis project, even
  • 14. though it was not an unusually large project, dollarwise, for Frank. Two years ear- lier, Frank was working on a $300 million contract, a $100 million contract and a $50 million contract concurrently with the Frank Chicago purchasing depart- ment responsible for all the purchasing, inspection, and expediting on all three contracts. The Lewis project was the largest project in house and was valued at only $90 million. What made this project so different from previous contracts and caused such problems? There was little Katz felt that he could do to correct the situation. All that could be done was to understand what had occurred in an effort Robert L. Frank Construction Company 665 c17.qxd 12/21/12 7:00 PM Page 665 to prevent a recurrence. He began to write his man-hour report for requested by the project manager the next day. COMPANY BACKGROUND Robert L. Frank Construction Company was an engineering and construction firm serving the petroleum, petrochemical, chemical, iron and steel,
  • 15. mining, pharma- ceutical, and food-processing industries from its corporate headquarters in Chicago, Illinois, and its worldwide offices. Its services include engineering, pur- chasing, inspection, expediting, construction, and consultation. Frank’s history began in 1947 when Robert L. Frank opened his office. In 1955, a corporation was formed, and by 1960 the company had completed con- tracts for the majority of the American producers of iron and steel. In 1962, an event occurred that was to have a large impact on Frank’s future. This was the merger of Wilson Engineering Company, a successful refinery concern, with Robert L. Frank, now a highly successful iron and steel concern. This merger greatly expanded Frank’s scope of operations and brought with it a strong period of growth. Several offices were opened in the United States in an effort to better handle the increase in business. Future expansions and mergers enlarged the Frank organization to the point where it had fifteen offices or subsidiaries located throughout the United States and twenty offices worldwide. Through its first twenty years of operations, Frank had more than 2,500 contracts for projects hav- ing an erected value of over $1 billion. Frank’s organizational structure has been well suited to the type of work undertaken. The projects Frank contracted for typically had a
  • 16. time constraint, a budget constraint, and a performance constraint. They all involved an outside cus- tomer such as a major petroleum company or a steel manufacturer. Upon accep- tance of a project, a project manager was chosen (and usually identified in the proposal). The project manager would head up the project office, typically con- sisting of the project manager, one to three project engineers, a project control manager, and the project secretaries. The project team also included the necessary functional personnel from the engineering, purchasing, estimating, cost control, and scheduling areas. Exhibit I is a simplified depiction. Of the functional areas, the purchasing department is somewhat unique in its organizational structure. The purchasing department is organized on a project management basis much as the project as a whole would be organized. Within the purchasing department, each project had a project office that included a project purchasing agent, one or more project expeditors and a project purchasing secretary. Within the purchasing department the project purchasing agent had line authority over only the project expeditor(s) and project secretary. However, for the project pur- chasing agent to accomplish his goals, the various functions within the purchasing 666 ROBERT L. FRANK CONSTRUCTION COMPANY c17.qxd 12/21/12 7:00 PM Page 666
  • 17. Exhibit I. Frank organization VP Eng. VP Control VP Procurement Purchasing Project A Project B Project C Mechanical Piping Electrical Civil Estimate Schedule 667 c17.qxd 12/21/12 7:00 PM Page 667 department had to commit sufficient resources. Exhibit II illustrates the organi- zation within the purchasing department. HISTORY OF THE LEWIS PROJECT Since 1998, the work backlog at Frank has been steadily declining. The Rovery Project, valued at $600 million, had increased company employment sharply since its inception in 1997. In fact, the engineering on the Rovery project was such a large undertaking that in addition to the Chicago office’s
  • 18. participation, two other U.S. offices, the Canadian office, and the Italian subsidiary were heavily involved. However, since the Rovery project completion in 2001, not enough new 668 ROBERT L. FRANK CONSTRUCTION COMPANY Exhibit II. Frank purchasing organization Mgr. Procurement Mgr. Buying, Esp., Insp. Project A Project B Project C Admin. Assistant Chief Inspector InspectionMgr. Buying Mgr. Traffic Chief Expediter Buying Traffic Expediting Project D Project E c17.qxd 12/21/12 7:00 PM Page 668
  • 19. work was received to support the work force thus necessitating recent lay-offs of engineers, including a few project engineers. Company officials were very disturbed with the situation. Frank’s company policy was to “maintain an efficient organization of sufficient size and resources, and staffed by people with the necessary qualifications, to execute projects in any location for the industries served by Frank.” However, the recent down- turn in business meant that there was not enough work even with the reduction in employees. Further cutbacks would jeopardize Frank’s prospects of obtaining future large projects as prospective clients look to contractors with a sufficient staff of qualified people to accomplish their work. By contrast, supporting employees out of overhead was not the way to do business, either. It became increasingly important to “cut the fat out” of the proposals being submitted for possible projects. Despite this, new projects were few and far between, and the projects that were received were small in scope and dollar value and therefore did not provide work for very many employees. When rumors of a possible construction project for a new coal liquefaction pilot plant started circulating, Frank officials were extremely interested in bidding for the work. It was an excellent prospect for two reasons. Besides Frank’s des-
  • 20. perate need for work, the Lewis chemical process used in the pilot plant would benefit Frank in the long run by the development of state-of- the-art technology. If the pilot plant project could be successfully executed, when it came time to construct the full-scale facility, Frank would have the inside track as they had already worked with the technology. The full-scale facility offered prospects exceeding the Rovery project, Frank’s largest project to date. Top priority was therefore put on obtaining the Lewis project. It was felt that Frank had a slight edge due to successful completion of a Lewis project six years ago. The proposal submitted to Lewis contained estimates for material costs, man- hours, and the fee. Any changes in scope after contract award would be handled by change order to the contract. Both Lewis and Frank had excellent scope change control processes as part of their configuration management plans. The functional department affected would submit an estimate of extra man-hours involved to the project man- ager, who would review the request and submit it to the client for approval. Frank’s preference was for cost-plus-fixed-fee contracts. One of the unique aspects stated in the Lewis proposal was the requirement for participation by both of Frank Chicago’s operating divisions. Previous Frank contracts were well suited to either Frank’s Petroleum and Chemical Division
  • 21. (P & C) or the Iron and Steel Division (I & S). However, due to the unusual chem- ical process, one that starts with coal and ends up with a liquid energy form, one of the plant’s three units was well suited to the P & C Division and one was well suited to the I & S Division. The third unit was an off-site unit and was not of par- ticular engineering significance. History of the Lewis Project 669 c17.qxd 12/21/12 7:00 PM Page 669 The award of the contract six weeks later led to expectations by most Frank personnel that the company’s future was back on track again. The project began inauspiciously. The project manager was a well-liked, easy- going sort who had been manager of several Frank projects. The project office included three of Frank’s most qualified project engineers. In the purchasing department, the project purchasing agent (PPA) assigned to the project was Frank’s most experienced PPA. Bill Hall had just completed his assignment on the Rovery Project and had done well, considering the magnitude of the job. The project had its problems, but they were small in comparison to the achievements. He had alienated some of the departments slightly but that was to
  • 22. be expected. Purchasing upper management was somewhat dissatisfied with him in that, due to the size of the project, he didn’t always use the normal Frank pur- chasing methods; rather, he used whatever method he felt was in the best interest of the project. Also, after the Rovery project, a purchasing upper management reshuffling left him in the same position but with less power and authority rather than receiving a promotion he had felt he had earned. As a result, he began to sub- tly criticize the purchasing management. This action caused upper management to hold him in less than high regard but, at the time of the Lewis Project, Hall was the best person available. Due to the lack of float in the schedule and the early field start date, it was necessary to fast start the Lewis Project. All major equipment was to be pur- chased within the first three months. This, with few exceptions, was accom- plished. The usual problems occurred such as late receipt of requisition from engineering and late receipt of bids from suppliers. One of the unique aspects of the Lewis project was the requirement for pur- chase order award meetings with vendors. Typically, Frank would hold award meetings with vendors of major equipment such as reactors, compressors, large process towers, or large pumps. However, almost each time Lewis approved pur-
  • 23. chase of a mechanical item or vessel, it requested that the vendor come in for a meeting. Even if the order was for an on-the-shelf stock pump or small drum or tank, a meeting was held. Initially, the purchasing department meeting attendees included the project purchasing agent, the buyer, the manager of the traffic depart- ment, the chief expeditor, and the chief Inspector. Engineering representatives included the responsible engineer and one or two of the project engineers. Other Frank attendees were the project control manager and the scheduler. Quite often, these meetings would accomplish nothing except the reiteration of what had been included in the proposal or what could have been resolved with a phone call or even e-mail. The project purchasing agent was responsible for issuing meeting notes after each meeting. One day at the end of the first three-month period, the top- ranking Lewis rep- resentative met with Larry Broyles, the Frank project manager. 670 ROBERT L. FRANK CONSTRUCTION COMPANY c17.qxd 12/21/12 7:00 PM Page 670 Lewis rep: Larry, the project is progressing but I’m a little concerned. We don’t feel like we have our finger on the pulse of the project. The information
  • 24. we are getting is sketchy and untimely. What we would like to do is meet with Frank every Wednesday to review progress and resolve problems. Larry: I’d be more than happy to meet with any of the Lewis people because I think your request has a lot of merit. Lewis rep: Well, Larry, what I had in mind was a meeting between all the Lewis people, yourself, your project office, the project purchasing agent, his assistant, and your scheduling and cost control people. Larry: This sounds like a pretty involved meeting. We’re going to tie up a lot of our people for one full day a week. I’d like to scale this thing down. Our pro- posal took into consideration meetings, but not to the magnitude we’re talking about. Lewis rep: Larry, I’m sorry but we’re footing the bill on this project and we’ve got to know what’s going on. Larry: I’ll set it up for this coming Wednesday. Lewis rep: Good. The required personnel were informed by the project manager that effective immediately, meetings with the client would be held weekly. However, Lewis was dissatisfied with the results of the meetings, so the Frank project manager
  • 25. informed his people that a premeeting would be held each Tuesday to prepare the Frank portion of the Wednesday meeting. All of the Wednesday participants attended the Tuesday premeetings. Lewis requests for additional special reports from the purchasing department were given into without comment. The project purchasing agent and his assistants (project started with one and expanded to four) were devoting a great majority of their time to special reports and putting out fires instead of being able to track progress and prevent problems. For example, recommended spare parts lists were normally required from vendors on all Frank projects. Lewis was no exception. However, after the project began, Lewis decided it wanted the spare parts recom- mendations early into the job. Usually, spare parts lists are left for the end of an order. For example, on a pump with fifteen-week delivery, normally Frank would pursue the recommended spare parts list three to four weeks prior to shipment, as it would tend to be more accurate. This improved accuracy was due to the fact that at this point in the order, all changes probably had been made. In the case of the Lewis project, spare parts recommendations had to be expedited from the day the material was released for fabrication. Changes could still be made that could dramatically affect the design of the pump. Thus, a change in the pump after
  • 26. receipt of the spare parts list would necessitate a new spare parts list. The time involved in this method of expediting the spare parts list was much greater than the History of the Lewis Project 671 c17.qxd 12/21/12 7:00 PM Page 671 time involved in the normal Frank method. Added to this situation was Lewis’s request for a fairly involved biweekly report on the status of spare parts lists on all the orders. In addition, a full time spare parts coordinator was assigned to the project. The initial lines of communication between Frank and Lewis were initially well defined. The seven in-house Lewis representatives occupied the area adja- cent to the Frank project office (see Exhibit III). Initially, all communications from Lewis were channeled through the Frank project office to the applicable functional employee. In the case of the purchasing department, the Frank project office would channel Lewis requests through the purchasing project office. Responses or return communications followed the reverse route. Soon the volume of communications increased to the point where response time was becoming unacceptable. In several special cases, an effort was made to cut
  • 27. this response time. Larry Broyles told the Lewis team members to call or go see the functional per- son (i.e., buyer or engineer) for the answer. However, this practice soon became the rule rather than the exception. Initially, the project office was kept informed 672 ROBERT L. FRANK CONSTRUCTION COMPANY Exhibit III. Floor plan—Lewis project teams Project Manager Assistant to Project Manager Procurement Advisor Inspection Coordinator Vacant Project Control Manager Chief Project Engineer Project
  • 28. Manager Project Engineer Project Engineer Project Engineer Assistant Project Engineer Engineer Engineer Cost Control Grey boxed text Indicates Lewis Personnel Normal text Indicates Frank Personnel c17.qxd 12/21/12 7:00 PM Page 672 of these conversations, but this soon stopped. The Lewis personnel had integrated themselves into the Frank organization to the point where they became part of the organization.
  • 29. The project continued on, and numerous problems cropped up. Vendors’ material delays occurred, companies with Frank purchase orders went bankrupt, and progress was not to Lewis’s satisfaction. Upper management soon became aware the problems on this project due to its sensitive nature, and the Lewis project was now receiving much more intense involvement by senior management than it had previously. Upper management sat in on the weekly meetings in an attempt to pacify Lewis. Further problems plagued the project. Purchasing management, in an attempt to placate Lewis, replaced the project purchasing agent. Ron Katz, a promising young MBA graduate, had five years of experience as an assistant to several of the project purchasing agents. He was most recently a project purchas- ing agent on a fairly small project that had been very successful. It was thought by purchasing upper management that this move was a good one, for two reasons. First, it would remove Bill Hall from the project as PPA. Second, by appointing Ron Katz, Lewis would be pacified, as Katz was a promising talent with a suc- cessful project under his belt. However, the project under direction of Katz still experienced problems in the purchasing area. Revisions by engineering to material already on order caused serious delivery delays. Recently requisitioned material could not be located with
  • 30. an acceptable delivery promise. Katz and purchasing upper management, in an attempt to improve the situation, assigned more personnel to the project, personnel that were more qualified than the positions dictated. Buyers and upper-level pur- chasing officials were sent on trips to vendors’ facilities that were normally han- dled by traveling expediters. In the last week the Lewis representative met with the project manager, Broyles: Lewis rep: Larry, I’ve been reviewing these man-hour expenditures, and I’m disturbed by them. Larry: Why’s that? Lewis rep: The man-hour expenditures are far outrunning project progress. Three months ago, you reported that the project completion percentage was 30 percent, but according to my calculations, we’ve used 47 percent of the man hours. Last month you reported 40 percent project completion and I show a 60 percent expenditure of man-hours. Larry: Well, as you know, due to problems with vendors’ deliveries, we’ve really had to expedite intensively to try to bring them back in line. Lewis rep: Larry, I’m being closely watched by my people on this project, and a cost or schedule overrun not only makes Frank look bad,
  • 31. it makes me look bad. Larry: Where do we go from here? History of the Lewis Project 673 c17.qxd 12/21/12 7:00 PM Page 673 Lewis rep: What I want is an estimate from your people on what is left, man- hour wise. Then I can sit down with my people and see where we are. Larry: I’ll have something for you the day after tomorrow. Lewis rep: Good. The functional areas were requested to provide this information, which was reviewed and combined by the project manager and submitted to Lewis for approval. Lewis’s reaction was unpleasant, to say the least. The estimated man- hours in the proposal were now insufficient. The revised estimate was for almost 40 percent over the proposal. The Lewis representative immediately demanded an extensive report on the requested increase. In response to this, the project man- ager requested man-hour breakdowns from the functional areas. Purchasing was told to do a purchase order by purchase order breakdown of expediting and inspection man-hours. The buying section had to break down the
  • 32. estimate of the man-hours needed to purchase each requisition, many of which were not even issued. Things appeared to have gone from bad to worse. 674 ROBERT L. FRANK CONSTRUCTION COMPANY c17.qxd 12/21/12 7:00 PM Page 674