1. Minutes of the Meeting held on 20th
October 2014 under the
Chairmanship of ACS (P&D)
Subject: Evaluation of EOIs/Pre-Qualification of Investors for Five Star
Resort / Hotel Project at Changla Gali and Tourist Recreation
/ Sports Facilities / Theme Parks at Hund
Meeting of the committee constituted vide Notification NO:
SO(Tourism) 5 - 75/2010/2538-40 Dated 9th April 2014 for tourism related
projects was held on Monday, 20th October 2014 at 2:00 PM in the Committee
Room of P & D Department under the Chairmanship of Additional Chief
Secretary, P & D.
The following attended;
1. Mir Javed Hasmat,
CEO/Secretary, Khyber Pakhtunkhwa Board of Investment & Trade
2. Mr. Hamayun,
Additional Secretary Tourism Department
3. Mr. Khanzeb Khan
Additional Secretary Finance Department
3. Mr. Nazar Hussain Shah,
Director General Galliat Development Authority
4. Mr. Mushtaq Ahmad,
Managing Director Tourism Corporation Khyber Pakhtunkhwa
5. Mr. Sajjad Hameed,
General Manager, Tourism Corporation Khyber Pakhtunkhwa
6. Mr. Muhammad Iqbal,
General Manager Projects, Sarhad Development Authority
The chairman in his opening remarks suggested that as per
previous practice adopted in case of Malam Jabba Ski / Chairlift and Hotel
Project a sub-committee may be constituted on similar lines to prepare a
criteria for the pre-qualification of interested parties/firms as well as the
criteria for scrutiny of technical proposals to be received from the pre-qualified
2. bidders. The sub-committee will present the proposed criteria for approval of
the main committee.
The Sub-committee for the Changla Gali project will comprise of the
followings:
1. Managing Director, Tourism Corporation Khyber Pakhtunkhwa
Chairman of the sub-committee
2. Member of Finance Department
3. Member of Khyber Pakhtunkhwa Board of Investment and Trade
4. Member of Galliat Development Authority
5. One or two co-opted members who will be the subject specialists of
Hotel projects
The main committee has allowed the sub-committee to select
the independent subject specialists of Hotel projects from the open market for
support in the scrutiny process.
In case of the Recreation/Sports Facilities/Theme Parks Project
at Hund, District Swabi, It was suggested by the Chairman that
representatives of Irrigation Department and Fisheries Department may be
included in the above sub-committee for Changla Gali project.
The chairman while fixing the timeline suggested that the sub-
committee will submit its recommendations to the main committee by 6th
November 2014. It was decided that that a meeting of the sub-committee may
be held on Monday, 27th October 2014 at 11:00 AM in the office of Managing
Director, Tourism Corporation Khyber Pakhtunkhwa to expedite the matter.
Meeting ended with a vote of thanks.