المعايير الزمنية لعقود الفيديك
1. Date of
Submission
of Tender
Decision by DAB
after Receiving
Reference
(84 Days)
(20.4)
Arbitration
Initiation
(56 Days)
(20.5)
Submission of
Statement at
Completion
(84 Days)
(11.3)
Notice by the
Contractor
(14 Days)
(10.1)
Issuance of T.O or
Rejection
(28 Days)
(10.1)
Payment of First
Half of Retention
Money
(14 Days)
(14.9)
Defect Remedial
(Further Tests)
(28 Days)
(11.6)
Suspension of
Work
(84 Days)
(8.11)
Contractor
request to
Proceed….
Engineer’s
Reply
(28 Days)
(8.11)
Termination by
Contractor
(8.11)
Release of
Performance
Certificate
(10.1)
Payment of
Remaining Half of
Retention Money
(14 Days)
(14.9)
Final Statement
(56 Days)
(14.11)
Issuance of Final
Payment Certificate
(28 Days)
(14.13)
Maximum Defect
Liability Period
(02 Years)
(11.3)PRE-CONSTRUCTION
PHASE
OPERATION &
MAINTENANCE PHASEEXECUTION PHASE
FIDIC General Conditions
Timeline
(28 Days)
(1.1.3.1)
Submission of Full
Detail Claim by
Contractor
(42 Days)
(20.1)Notice of
Commencement
(7 Days)
(8.1)
Contractor
Termination of
Contract
(21 Days)
(16.1)
No Receiving of IPC
Reply
(42 Days)
(16.1)
Delay in IPC by
Employer
(21 Days)
(16.1)
Suspension of
Work
(21 Days)
(16.1)
Request to show
Employer Financials
(28 Days)
(2.4)
Decided Deliverables
Notification to
Employer for Claim
(28 Days)
(20.1)
IPC Request
(14.6)
Taking Over
Certificate
(10.1)
Base
Date
Submission of
Performance
Security (28 Days)
(8.1)
Commencement of
Works (28 Days)
(8.1)
Sign of Contract
Agreement (28 Days)
(8.1)
Submission of Proposed
Breakdown of Lump sum
Amount (28 Days)
(14.1)
First Estimate of Payment
Submission (42 Days)
(14.4)
Receiving of
Letter of
Acceptance
(LOA) by
Contractor
(4.2)
Programme
Submission
(28 Days)
(8.3)
Engineer’s Reply
(21 Days)
(4.2)
Agreement on
Insurances
(8.1) Issuance of IPC by
Engineer
(28 Days)
(14.6)
Floating Deliverables
Termination by the
Employer
(28 Days)
(15.5)
After Late Dates:
Contractor
Receives Notice
Employer Return
Performance
Security
Notice to other
Party if Dis-
satisfied
(28 Days)
(20.4)
Claim after
notification
(28 Days)
(17.5)
Testing
(24 hrs to engr.)
(7.4)
Engineer
Replacement
(42 Days)
(3.4)
Force Majeure
Awareness
Notification
(14 Days)
(19.2)
Termination
Notice (Force
Majeure)
(84/140 Days)
(19.6)