Public Service Enterprise Group

  PSEG Earnings Conference Call
  4th Quarter and Year-End 2008

         February 3, 2009
Forward-Looking Statement

    Readers are cautioned that statements contained in this presentation about our and our subsidiaries' future performance, including future
    revenues, earnings, strategies, prospects and all other statements that are not purely historical, are forward-looking statements for purposes of
    the safe harbor provisions under The Private Securities Litigation Reform Act of 1995. Although we believe that our expectations are based on
    reasonable assumptions, we can give no assurance they will be achieved. The results or events predicted in these statements may differ
    materially from actual results or events. Factors which could cause results or events to differ from current expectations include, but are not
    limited to:

•   Adverse changes in energy industry, policies and regulation, including market structures and rules.
•   Any inability of our energy transmission and distribution businesses to obtain adequate and timely rate relief and regulatory approvals from
    federal and state regulators.
•   Changes in federal and state environmental regulations that could increase our costs or limit operations of our generating units.
•   Changes in nuclear regulation and/or developments in the nuclear power industry generally, that could limit operations of our nuclear generating
    units.
•   Actions or activities at one of our nuclear units that might adversely affect our ability to continue to operate that unit or other units at the same
    site.
•   Any inability to balance our energy obligations, available supply and trading risks.
•   Any deterioration in our credit quality.
•   Availability of capital and credit at reasonable pricing terms and our ability to meet cash needs.
•   Any inability to realize anticipated tax benefits or retain tax credits.
•   Increases in the cost of or interruption in the supply of fuel and other commodities necessary to the operation of our generating units.
•   Delays or cost escalations in our construction and development activities.
•   Adverse investment performance of our decommissioning and defined benefit plan trust funds, and changes in discount rates and funding
    requirements.
•   Changes in technology and increased customer conservation.

    For further information, please refer to our Annual Report on Form 10-K, including Item 1A. Risk Factors, and subsequent reports on Form 10-Q
    and Form 8-K filed with the Securities and Exchange Commission. These documents address in further detail our business, industry issues and
    other factors that could cause actual results to differ materially from those indicated in this presentation. In addition, any forward-looking
    statements included herein represent our estimates only as of today and should not be relied upon as representing our estimates as of any
    subsequent date. While we may elect to update forward-looking statements from time to time, we specifically disclaim any obligation to do so,
    even if our estimates change, unless otherwise required by applicable securities laws.

                                                                                                                                                            1
GAAP Disclaimer


   PSEG presents Operating Earnings in addition to its Net Income reported
   in accordance with accounting principles generally accepted in the United
   States (GAAP). Operating Earnings is a non-GAAP financial measure that
   differs from Net Income because it excludes the impact of the sale of
   certain non-core domestic and international assets and material
   impairments and lease-transaction-related charges. PSEG presents
   Operating Earnings because management believes that it is appropriate
   for investors to consider results excluding these items in addition to the
   results reported in accordance with GAAP. PSEG believes that the non-
   GAAP financial measure of Operating Earnings provides a consistent and
   comparable measure of performance of its businesses to help
   shareholders understand performance trends. This information is
   not intended to be viewed as an alternative to GAAP information. The last
   slide in this presentation includes a list of items excluded from Income
   from Continuing Operations to reconcile to Operating Earnings, with a
   reference to that slide included on each of the slides where the non-GAAP
   information appears.

                                                                                2
PSEG
2008 Q4 Review

Ralph Izzo
Chairman, President and Chief Executive Officer
Q4 2008 Earnings Summary



                                                                                                              Quarter ended December 31,

                                                                                                                  2008          2007
                            $ millions (except EPS)
        Operating Earnings                                                                                       $ 250         $ 272

        Asset Sales and Impairments                                                                                (13)          (53)

        Income from Continuing Operations                                                                          237           219

        Discontinued Operations                                                                                     (3)            6

        Net Income                                                                                                 234           225

                                         EPS from Operating Earnings*                                            $ 0.49        $ 0.53




                                                                                                                                           4

* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
Full-year 2008 Earnings Summary

                                                                                                              For the year ended December 31,

                                                                                                                   2008            2007
                                $ millions (except EPS)
           Operating Earnings                                                                                     $ 1,487         $ 1,385

           Lease Reserves                                                                                           (490)              ---

           Asset Sales and Impairments                                                                               (14)            (60)

           Income from Continuing Operations                                                                         983            1,325

           Discontinued Operations, net of tax                                                                       205               10

           Net Income                                                                                               1,188           1,335

                                       EPS from Operating Earnings*                                                $ 2.92          $ 2.72




                                                                                                                                                5

* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
PSEG – 2008: Answering Challenges – Meeting Objectives

  2008 earnings within guidance

  Focused on operational excellence
     Record generation production
     Top decile reliability standards maintained at PSE&G
     Controlling operating and maintenance expenses to meet challenging economic
     environment

  Foundation laid for future
     Carbon abatement
     Capital infrastructure and energy efficiency capital programs
     Generation environmental upgrades on target; within budget

  Financial position strengthened; risk reduced
     Major international assets sold
         Debt reduced
         Credit targets achieved
     Additional reserve for LILO/SILO tax risk recognized


                                                                              6
PSEG – 2009: Meeting the Challenge




                                                                                                              $3.00 - $3.25
                                                                                          $2.92
                                $2.72




                     2007 Operating Earnings*                                 2008 Operating Earnings*          2009 Guidance
                                                                                                                                7
* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
PSEG
2008 Q4 Operating Company Review

Tom O’Flynn
Executive Vice President and Chief Financial Officer
Q4 Operating Earnings by Subsidiary


                                                                                                        Quarter ended December 31,

                                                                                  Operating Earnings                     Earnings per Share
                                                                                       2008                   2007        2008       2007
                      $ millions (except EPS)
                             PSEG Power                                                 $ 207                 $ 205       $ 0.40     $ 0.40

                                   PSE&G                                                         76                77        0.15      0.15

                 PSEG Energy Holdings                                                         (23)                 10       (0.04)     0.02

                                Enterprise                                                    (10)                (20)      (0.02)    (0.04)

                    Operating Earnings*                                                 $ 250                 $   272     $ 0.49     $ 0.53




                                                                                                                                               9

* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
Full-year 2008 Operating Earnings by Subsidiary



                                                                                                 For the year ended December 31,
                                                                                  Operating Earnings                    Earnings per Share
                                                                                       2008                   2007       2008       2007
                       $ millions (except EPS)
                             PSEG Power                                             $ 1,050                   $ 949      $ 2.06     $ 1.86

                                   PSE&G                                                       360               376        0.71      0.74

                 PSEG Energy Holdings                                                          101               123        0.20      0.24

                                Enterprise                                                    (24)               (63)      (0.05)    (0.12)

                    Operating Earnings*                                             $ 1,487                   $ 1,385    $ 2.92     $ 2.72




                                                                                                                                              10

* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
PSEG EPS Reconciliation – Q4 2008 versus Q4 2007

               0.60
                                                                                    .00
                                                         .00
                             $.53                                                                             (.06)
                                                                                                                                           $.49
                                                                                                                              .02
                                                  Recontracting                Weather .01
                                                   and Strong
                                                                               Gas Margin
                                                   Markets .07
                                                                                  (.01)               Texas – MTM (.05);    Interest
                                                     O&M .03                                           Operations (.02)
                                                                                 O&M .04
               0.40                                  NDT (.10)                                          2007 Asset Sales
                                                                              Depreciation
                                                                                                        and Settlements
                                                                             and Taxes (.04)
                                                                                                              (.03)
   $ / share




                                                                                                      Lease Income (.02)
                                                                                                       Effective Tax Rate
                                                                                                         and Other .05
                                                                                                     Interest Expense .01
               0.20




               0.00
                          Q4 2007                                                                                                         Q4 2008
                                                                                                          PSEG Energy       Enterprise
                                                 PSEG Power                      PSE&G
                         operating                                                                                                       operating
                                                                                                            Holdings
                         earnings*                                                                                                       earnings*


                                                                                                                                                     11

* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
PSEG EPS Reconciliation – Full-year 2008 versus Full-
        year 2007

                                                                                                                                        $2.92
                                                                                   (.03)
               3.00                                      .20                                                                 .07
                                                                                                              (.04)
                             $2.72
                                                                                                                           Interest
                                                                               Margin – Gas,           2007 Asset Sales
                                                                                Electric and           and Settlements
                                                   Recontracting
                                                                               Transmission                  (.13)
                                                    and Strong
                                                                                    (.04)
                                                    Markets .43                                      Lease Income (.04)
                                                                               Weather (.01)
                                                  MTM and BGSS                                        Texas – MTM (.03)
                                                       .03                        O&M .02              Operations .05
                                                       NDT (.16)               Depreciation,           Interest Expense
   $ / share




                                                                               Interest and                   .07
                                                      O&M (.07)
                                                                                Other (.02)
               2.00                                                                                   Effective Tax Rate
                                                    Depreciation,
                                                                               Effective Tax            and Other .04
                                                 Interest and Taxes
                                                                                 Rate .02
                                                        (.03)




               1.00
                           2007                                                                                                           2008
                                                                                                        PSEG Energy        Enterprise
                                                   PSEG Power                      PSE&G
                         operating                                                                                                      operating
                                                                                                          Holdings
                         earnings*                                                                                                      earnings*


                                                                                                                                                    12

* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
PSEG Power
2008 Q4 Review
PSEG Power – Q4 2008 EPS Summary



                                                                                                    Q4 2008          Q4 2007    Variance
                              $ millions (except EPS)
          Operating Revenues                                                                            $ 1,939       $ 1,762      $ 177

          Operating Earnings                                                                                  207        205           2

          Income from Continuing Operations/                                                                  207        205           2
          Net Income
                         EPS from Operating Earnings*                                                 $       0.40    $ 0.40          ---




                                                                                                                                            14

* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
PSEG Power EPS Reconciliation – Q4 2008 versus Q4 2007


                   0.50                                                                         (.10)
                                                                 .07


                                                                                                                     $.40
                                                                                                              .03
                                 $.40

                                                            Recontracting
                                                             and Strong
                                                                                                  NDT         O&M
                                                              Markets
       $ / share




                   0.00
                              Q4 2007                                                                                Q4 2008
                             operating                                                                              operating
                             earnings*                                                                              earnings*
                                                                                                                                15

* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
PSEG Power – Generation Measures
                                                 PSEG Power – Generation (GWh)
                       Quarter ended December 31,                         Twelve months ended December 31,
   15,000                                                        60,000
                                                                                                55,292
                                                                               53,197
                           12,391                 12,518
                                                                                                 13,090
                                                                               11,820
                                                   2,516
                            2,761

   10,000                                                        40,000

                                                                                                 12,918
                                                   2,642                       13,014
                            3,089




    5,000                                                        20,000

                                                   7,360                                         29,284
                                                                               28,363
                            6,541




          0                                                          0
                            2007                   2008                         2007              2008
                                                                                           Total Oil &       16
                                        Total Nuclear           Total Coal*
                                                                                           Natural Gas
* Includes figures for Pumped Storage
PSEG Power – Fuel Costs


                                     PSEG Power – Fuel Costs


                         Quarter ended December 31,                         Year ended December 31,
     ($ millions)          2007           2008           ($ millions)        2007          2008
   Coal                      84            92         Coal                    336          423
   Oil & Gas                200            192        Oil & Gas               847          1141
          Total Fossil     $284           $284               Total Fossil   $1,183        $1,564
   Nuclear                   28            33         Nuclear                 122          129
    Total Fuel Cost        $312           $317          Total Fuel Cost     $1,305        $1,693

                                                      Total Generation
   Total Generation                                                         53,197        55,292
                          12,391         12,518            (GWhr)
        (GWhr)

                                                                  $ / MWh   $24.50        $30.60
             $ / MWh      $25.20         $25.30




                                                                                                      17
Strong Pricing Supports Margin Improvement
                                  PSEG Power Gross Margin* ($/MWh)

                 Quarter ended December 31,             Twelve months ended December 31,

                                                  $60
           $60                                                                        $57 - $58
                                                                                  -5%
                                                                                3
                                                                            +
                                    $56
                             0%                                          $55
                           +1                                        %
                                                                 0
                                                              +1
                    $51
                                                           $50




                                                  $40
           $40
                                                          2007           2008        2009E
                    2007            2008                                                          18
* Includes MTM
PSEG Power – Q4 Operating Highlights

      Operations
  4Q output +1%; full-year increase of 3.9% leading to record production.
      4Q nuclear capacity factor at 91.3%; full-year at 92.6%.
      Coal plant availability affected by BET related work.
  Environmental work at Hudson and Mercer proceeding on schedule; on budget.



 Regulatory and Market Environment

  Renegotiated contract with Indonesian coal supplier.
  Seeing impact on pricing from declining economic growth.
  CAIR reinstated; too early to predict impact of change in administration on energy and
  environmental policy.


       Financial
  $25 million dividend paid to Enterprise in 4Q; $500 million for full-year.
  Successful launch of $500 million retail MTN program.

                                                                                           19
PSE&G
2008 Q4 Review
PSE&G – Q4 2008 Earnings Summary


                                 $ millions (except EPS)                                                Q4 2008         Q4 2007    Variance
             Operating Revenues                                                                               $ 2,288    $ 2,153      $ 135
             Operating Expenses
                                                                          Energy Costs                         1,545      1,415         130
                                                     Operation & Maintenance                                     345        361        (16)
                                                Depreciation & Amortization                                      140        142         (2)
                                          Taxes Other than Income Taxes                                           35         35          ---
             Total Operating Expenses                                                                          2,065      1,953         112
             Operating Earnings                                                                                   76         77         (1)
             Income from Continuing Operations/                                                                   76         77         (1)
             Net Income
                            EPS from Operating Earnings*                                                       $ 0.15     $ 0.15         ---



                                                                                                                                               21

* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
PSE&G EPS Reconciliation – Q4 2008 versus Q4 2007

                0.20                                                                                          .04      (.04)


                                                                                     (.01)
                                                           .01
                               $.15                                                                                                  $.15

                                                         Weather                 Gas Margin                   O&M   Depreciation
                                                                                                                     and Taxes
    $ / share




                0.10




                0.00
                              Q4 2007                                                                                               Q4 2008
                             operating                                                                                             operating
                             earnings*                                                                                             earnings*



                                                                                                                                               22

* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
PSE&G – Q4 Operating Highlights
      Operations
  Declining economic growth having impact on sales growth.
  O&M costs remain under control.
  Focused on containing impact of economic fallout on customers and accounts
  through support of outreach programs.


 Regulatory and Market Environment
  PSE&G filed for NJ BPU approval to construct the Susquehanna – Roseland
  transmission line. The $750 million project is scheduled to be in-service by year-
  end 2012.
  NJ BPU approved a four-year $46 million program to curb energy consumption
  and reduce CO2 emissions.
  PSE&G proposed a two-year $888 million capital program supporting energy
  infrastructure ($698 million) and energy efficiency ($190 million).

       Financial
  Outlook for electric sales growth hurt by weak economy.
  Capital to be invested in areas with regulatory support.                             23
PSEG Energy Holdings
2008 Q4 Review
PSEG Energy Holdings – Q4 2008 Earnings Summary



                                                                                                              Q4 2008 Q4 2007 Variance
                                 $ millions (except EPS)
             Operating (Loss) / Earnings                                                                        ($ 23)   $ 10      ($ 33)

             Asset Sales and Impairments                                                                           13       53       (40)

             Loss from Continuing Operations                                                                     (36)      (43)        7

             Discontinued Operations                                                                               (3)       6        (9)

             Net Loss                                                                                            (39)      (37)       (2)

                EPS from Operating (Loss) / Earnings*                                                         ($ 0.04)   $ 0.02   ($0.06)




                                                                                                                                            25

* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
PSEG Energy Holdings EPS Reconciliation – Q4 2008 versus
  Q4 2007
               0.05

                            $.02                     (.07)


               0.00



                                                                                                                            .01
   $ / share




                                                                            (.03)                              .05
                                                                                                                                     (.04)
               -0.05
                                                                                                                          Interest
                                                 Texas -
                                                                                                                          Expense
                                             Operations (.02)
                                                                                                   (.02)
                                               MTM (.05)

                                                                         2007 Asset
                                                                          Sales and
                                                                         Settlements
               -0.10
                                                                                                              Effective
                                                                                                   Lease
                                                                                                              Tax Rate
                                                                                                  Income
                                                                                                              and Other




               -0.15
                            Q4 2007                                                                                                   Q4 2008
                           operating                                                                                                 operating
                           earnings*                                                                                                 earnings*

                                                                                                                                             26

* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
PSEG Energy Holdings – Q4 Operating Highlights
      Operations
  Texas – 2,000 MW gas-fired combined cycle capacity
      1,000 MW Guadalupe facility experienced improved capacity factor and spark spreads.
      1,000 MW Odessa facility experienced a reduction in capacity and availability.
                               Spark Spread                         Production (GWh)
                    4Q 2007   4Q 2008   2007     2008     4Q 2007   4Q 2008   2007     2008
        Guadalupe   $10.30    $14.83    $14.77   $24.56     .85       1.15    4.20     4.98
         Odessa     $26.88    $26.37    $23.16   $32.72     .82       .45     4.30     2.85


 Regulatory and Market Environment
  Submitted RFP on 500 MW of 1,000 MW Odessa plant for a 10-15 year agreement
  to provide energy and capacity.
  Change in administration and energy policy could favor development of
  renewables.

      Financial
    Recognized impairment of investments in PPN and Turboven.
       Remaining international investments total $24 million.
    Received approximately $700 million from Q3 and Q4 international asset sales.
                                                                                              27
PSEG
Outlook for Pension Expense




                                                                                                                January 2009
                                                                              2008 Actual
                                                                                                                 Estimate**
                                           PSE&G                                   $15.0*                            $80.0*
                                      PSEG Power                                     14.0                            76.0
                                             Other                                    2.0                             4.0
                                            TOTAL                                    31.0                            160.0*
                                     Discount Rate                                 6.50%                             6.80%




                                                                                                                               29
* After capitalized amount; pre-tax figure.
** The January 2009 estimate represents an increase from our October 2008 forecast of $110 - $120 million pre-tax.
2009 Operating Earnings Guidance



                                                                                                              2008A*         2009E
                               $ millions (except EPS)

                                      PSEG Power                                                              $ 1,050   $ 1,210 – $ 1,285

                                             PSE&G                                                            $ 360      $ 320 – $ 345

                          PSEG Energy Holdings                                                                $ 101        $ 0 – $ 20

                                         Enterprise                                                           ($ 24)      ($ 10) – $ 0

                               Operating Earnings                                                             $ 1,487   $ 1,520 – $ 1,650

                               Earnings per Share                                                             $ 2.92     $ 3.00 – $ 3.25




                                                                                                                                            30

* See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
PSEG Liquidity as of December 31, 2008

                                                               Expiration    Total                Primary            Usage at Available Liquidity
Company                         Facility                         Date       Facility              Purpose           12/31/2008     12/31/2008

                                                                                       1
                     5-year Credit Facility                     12-Dec      $1,000         CP Support/Funding/LCs     $13            $987
 PSEG
                    Bilateral Credit Facility                    9-Jun       $100           CP Support/Funding        $0             $100
                Uncommitted Bilateral Agreement                   N/A         N/A                 Funding              0              N/A

                                                                                       3
                       5-Year Credit Facility                   12-Dec       1,600              Funding/LCs            222           1,378
 Power
                      Bilateral Credit Facility                  9-Jun        100               Funding/LCs             0             100
                      Bilateral Credit Facility                  9-Mar        150               Funding/LCs            52              98
                      Bilateral Credit Facility                  9-Sep         50                 Funding               0              50
                      Bilateral Credit Facility                 10-Mar        100               Funding/LCs            14              86

                                                                                       2
                     5-year Credit Facility                      12-Jun       600          CP Support/Funding/LCs      20             580
 PSE&G
                Uncommitted Bilateral Agreement                   N/A         N/A                 Funding               0             N/A

                        5-year Credit Facility                   10-Jun       136               Funding/LCs            21             115
 Energy
Holdings


                                                                 Total      $3,836                                                  $3,494

          1
              PSEG Facility reduces by $47 million in 2012
          2
              PSE&G Facility reduces by $28 million in 2012
          3
              Pow er Facility reduces by $75 million in 2012



                                                                                                                                                31
Items Excluded from Income from Continuing Operations to
Reconcile to Operating Earnings
                                                                 For the Quarters Ended     For the Twelve Months Ended
                                                                      December 31,                    December 31,
                      Pro-forma Adjustments, net of tax           2008            2007           2008         2007

                         Earnings Impact (in Millions)

        Asset Sales and Impairments:
              Impairment of PPN                                  $     (9)     $     (2)       $     (9)    $     (2)
              Impairment of Turboven                                   (4)            -              (4)          (7)
              Loss on Sale of Chilquinta and Luz del Sur                -           (23)              -          (23)
              Premium on Bond Redemption                                -           (28)             (1)         (28)
        Total Asset Sales and Impairments                             (13)          (53)            (14)         (60)

        Lease Reserves                                                    -             -          (490)             -

                                                                 $    (13)     $    (53)       $   (504)    $    (60)
        Total Pro-forma to Operating Earnings

        Fully Diluted Average Shares Outstanding (in Millions)        507           510             508          509

                          Per Share Impact (Diluted)

        Asset Sales and Impairments:
              Impairment of PPN                                  $   (0.02)    $     -         $   (0.02)   $     -
              Impairment of Turboven                                 (0.01)          -             (0.01)       (0.01)
              Loss on Sale of Chilquinta and Luz del Sur               -           (0.05)            -          (0.05)
              Premium on Bond Redemption                               -           (0.06)            -          (0.06)
        Total Asset Sales and Impairments                            (0.03)        (0.11)          (0.03)       (0.12)

        Lease Reserves                                                -             -              (0.96)        -

                                                                 $   (0.03)    $   (0.11)      $   (0.99)   $   (0.12)
        Total Pro-forma to Operating Earnings




Please see Slide 2 for an explanation of PSEG’s use of Operating Earnings as a non-GAAP financial measure and how
                                                                                                                32
it differs from Net Income.

More Related Content

Viewers also liked

6 effective indoor activities for employee engagement - fast collab _ blog
6 effective indoor activities for employee engagement  - fast collab _ blog6 effective indoor activities for employee engagement  - fast collab _ blog
6 effective indoor activities for employee engagement - fast collab _ blogYabibo
 
ALABI AYODEJI SAMUEL
ALABI AYODEJI SAMUEL ALABI AYODEJI SAMUEL
ALABI AYODEJI SAMUEL Ayodeji Alabi
 
PeopleMovers Recommendation Letter
PeopleMovers Recommendation LetterPeopleMovers Recommendation Letter
PeopleMovers Recommendation LetterTara Simpson-Russell
 
시알리스 구입방법 카톡:DDF11 & DDF11.KR 시알리스 50mg정품구입,시알리스 100mg정품판매,시알리스 100mg정품구입,시알리...
시알리스 구입방법 카톡:DDF11 & DDF11.KR 시알리스 50mg정품구입,시알리스 100mg정품판매,시알리스 100mg정품구입,시알리...시알리스 구입방법 카톡:DDF11 & DDF11.KR 시알리스 50mg정품구입,시알리스 100mg정품판매,시알리스 100mg정품구입,시알리...
시알리스 구입방법 카톡:DDF11 & DDF11.KR 시알리스 50mg정품구입,시알리스 100mg정품판매,시알리스 100mg정품구입,시알리...bark man
 
US Postal Service_MTSC_Letter of Recommendation
US Postal Service_MTSC_Letter of RecommendationUS Postal Service_MTSC_Letter of Recommendation
US Postal Service_MTSC_Letter of RecommendationHasib Rahman, MBA
 
Economic development update 10_2016
Economic development update 10_2016Economic development update 10_2016
Economic development update 10_2016Frank Miles, M.P.A.
 
БИТ:Управление транспортной логистикой 8
БИТ:Управление транспортной логистикой 8БИТ:Управление транспортной логистикой 8
БИТ:Управление транспортной логистикой 8bitkiev
 
Electronic Health Records ISSUES AND CHALLENGES
Electronic Health Records ISSUES AND CHALLENGESElectronic Health Records ISSUES AND CHALLENGES
Electronic Health Records ISSUES AND CHALLENGESelryuzakisora
 
IF YOU BUILD IT SCAN
IF YOU BUILD IT SCANIF YOU BUILD IT SCAN
IF YOU BUILD IT SCANRob Bick
 

Viewers also liked (11)

6 effective indoor activities for employee engagement - fast collab _ blog
6 effective indoor activities for employee engagement  - fast collab _ blog6 effective indoor activities for employee engagement  - fast collab _ blog
6 effective indoor activities for employee engagement - fast collab _ blog
 
ALABI AYODEJI SAMUEL
ALABI AYODEJI SAMUEL ALABI AYODEJI SAMUEL
ALABI AYODEJI SAMUEL
 
PeopleMovers Recommendation Letter
PeopleMovers Recommendation LetterPeopleMovers Recommendation Letter
PeopleMovers Recommendation Letter
 
시알리스 구입방법 카톡:DDF11 & DDF11.KR 시알리스 50mg정품구입,시알리스 100mg정품판매,시알리스 100mg정품구입,시알리...
시알리스 구입방법 카톡:DDF11 & DDF11.KR 시알리스 50mg정품구입,시알리스 100mg정품판매,시알리스 100mg정품구입,시알리...시알리스 구입방법 카톡:DDF11 & DDF11.KR 시알리스 50mg정품구입,시알리스 100mg정품판매,시알리스 100mg정품구입,시알리...
시알리스 구입방법 카톡:DDF11 & DDF11.KR 시알리스 50mg정품구입,시알리스 100mg정품판매,시알리스 100mg정품구입,시알리...
 
SHINY MAGAZINE 0 ITA
SHINY MAGAZINE 0 ITASHINY MAGAZINE 0 ITA
SHINY MAGAZINE 0 ITA
 
US Postal Service_MTSC_Letter of Recommendation
US Postal Service_MTSC_Letter of RecommendationUS Postal Service_MTSC_Letter of Recommendation
US Postal Service_MTSC_Letter of Recommendation
 
Economic development update 10_2016
Economic development update 10_2016Economic development update 10_2016
Economic development update 10_2016
 
БИТ:Управление транспортной логистикой 8
БИТ:Управление транспортной логистикой 8БИТ:Управление транспортной логистикой 8
БИТ:Управление транспортной логистикой 8
 
Ianko - PRINCE2
Ianko - PRINCE2Ianko - PRINCE2
Ianko - PRINCE2
 
Electronic Health Records ISSUES AND CHALLENGES
Electronic Health Records ISSUES AND CHALLENGESElectronic Health Records ISSUES AND CHALLENGES
Electronic Health Records ISSUES AND CHALLENGES
 
IF YOU BUILD IT SCAN
IF YOU BUILD IT SCANIF YOU BUILD IT SCAN
IF YOU BUILD IT SCAN
 

Similar to public serviceenterprise group Investor library.corporate

public serviceenterprise group 3Q 2008 slides
public serviceenterprise group 3Q 2008 slidespublic serviceenterprise group 3Q 2008 slides
public serviceenterprise group 3Q 2008 slidesfinance20
 
el paso 02_274Q2006Earnings_FINAL_FINAL_bb
el paso  02_274Q2006Earnings_FINAL_FINAL_bbel paso  02_274Q2006Earnings_FINAL_FINAL_bb
el paso 02_274Q2006Earnings_FINAL_FINAL_bbfinance49
 
EP1Q2007Earnings_FINAL(Web)
EP1Q2007Earnings_FINAL(Web)EP1Q2007Earnings_FINAL(Web)
EP1Q2007Earnings_FINAL(Web)finance49
 
el paso 1Q2008EarningsFINALFINAL(Web)
el paso  1Q2008EarningsFINALFINAL(Web)el paso  1Q2008EarningsFINALFINAL(Web)
el paso 1Q2008EarningsFINALFINAL(Web)finance49
 
el paso 1Q2008EarningsFINALFINAL(Web)
el paso  1Q2008EarningsFINALFINAL(Web)el paso  1Q2008EarningsFINALFINAL(Web)
el paso 1Q2008EarningsFINALFINAL(Web)finance49
 
celanese 1q06_earnings_slides_-_final
celanese 1q06_earnings_slides_-_finalcelanese 1q06_earnings_slides_-_final
celanese 1q06_earnings_slides_-_finalfinance44
 
public serviceenterprise group 2Q_2008_Webcast_Slides_FINAL
public serviceenterprise group 2Q_2008_Webcast_Slides_FINALpublic serviceenterprise group 2Q_2008_Webcast_Slides_FINAL
public serviceenterprise group 2Q_2008_Webcast_Slides_FINALfinance20
 
public serviceenterprise group 2Q_2008_Webcast_Slides_FINAL
public serviceenterprise group 2Q_2008_Webcast_Slides_FINALpublic serviceenterprise group 2Q_2008_Webcast_Slides_FINAL
public serviceenterprise group 2Q_2008_Webcast_Slides_FINALfinance20
 
EP4Q2007Earnings_FINALv2(Web)
EP4Q2007Earnings_FINALv2(Web)EP4Q2007Earnings_FINALv2(Web)
EP4Q2007Earnings_FINALv2(Web)finance49
 
EP4Q2007Earnings_FINALv2(Web)
EP4Q2007Earnings_FINALv2(Web)EP4Q2007Earnings_FINALv2(Web)
EP4Q2007Earnings_FINALv2(Web)finance49
 
public serviceenterprise group 2Q2007Slides
public serviceenterprise group 2Q2007Slidespublic serviceenterprise group 2Q2007Slides
public serviceenterprise group 2Q2007Slidesfinance20
 
public serviceenterprise group 2Q2007Slides
public serviceenterprise group 2Q2007Slidespublic serviceenterprise group 2Q2007Slides
public serviceenterprise group 2Q2007Slidesfinance20
 
EPElPasoCorporation1Q06WebcastFinal
EPElPasoCorporation1Q06WebcastFinalEPElPasoCorporation1Q06WebcastFinal
EPElPasoCorporation1Q06WebcastFinalfinance49
 
celanese 3q_2006_earnings_slides
celanese 3q_2006_earnings_slidescelanese 3q_2006_earnings_slides
celanese 3q_2006_earnings_slidesfinance44
 
Hexion FinalQ407
Hexion FinalQ407Hexion FinalQ407
Hexion FinalQ407finance36
 
celanese q4_2005_ir_slides
celanese q4_2005_ir_slidescelanese q4_2005_ir_slides
celanese q4_2005_ir_slidesfinance44
 
el paso 2Q2007EarningsFINAL(B&WPrint)
el paso  2Q2007EarningsFINAL(B&WPrint)el paso  2Q2007EarningsFINAL(B&WPrint)
el paso 2Q2007EarningsFINAL(B&WPrint)finance49
 
el paso 2Q2007EarningsFINAL(B&WPrint)
el paso  2Q2007EarningsFINAL(B&WPrint)el paso  2Q2007EarningsFINAL(B&WPrint)
el paso 2Q2007EarningsFINAL(B&WPrint)finance49
 
celanese q2_2006_presentation
celanese q2_2006_presentationcelanese q2_2006_presentation
celanese q2_2006_presentationfinance44
 

Similar to public serviceenterprise group Investor library.corporate (20)

public serviceenterprise group 3Q 2008 slides
public serviceenterprise group 3Q 2008 slidespublic serviceenterprise group 3Q 2008 slides
public serviceenterprise group 3Q 2008 slides
 
el paso 02_274Q2006Earnings_FINAL_FINAL_bb
el paso  02_274Q2006Earnings_FINAL_FINAL_bbel paso  02_274Q2006Earnings_FINAL_FINAL_bb
el paso 02_274Q2006Earnings_FINAL_FINAL_bb
 
EP1Q2007Earnings_FINAL(Web)
EP1Q2007Earnings_FINAL(Web)EP1Q2007Earnings_FINAL(Web)
EP1Q2007Earnings_FINAL(Web)
 
el paso 1Q2008EarningsFINALFINAL(Web)
el paso  1Q2008EarningsFINALFINAL(Web)el paso  1Q2008EarningsFINALFINAL(Web)
el paso 1Q2008EarningsFINALFINAL(Web)
 
el paso 1Q2008EarningsFINALFINAL(Web)
el paso  1Q2008EarningsFINALFINAL(Web)el paso  1Q2008EarningsFINALFINAL(Web)
el paso 1Q2008EarningsFINALFINAL(Web)
 
celanese 1q06_earnings_slides_-_final
celanese 1q06_earnings_slides_-_finalcelanese 1q06_earnings_slides_-_final
celanese 1q06_earnings_slides_-_final
 
public serviceenterprise group 2Q_2008_Webcast_Slides_FINAL
public serviceenterprise group 2Q_2008_Webcast_Slides_FINALpublic serviceenterprise group 2Q_2008_Webcast_Slides_FINAL
public serviceenterprise group 2Q_2008_Webcast_Slides_FINAL
 
public serviceenterprise group 2Q_2008_Webcast_Slides_FINAL
public serviceenterprise group 2Q_2008_Webcast_Slides_FINALpublic serviceenterprise group 2Q_2008_Webcast_Slides_FINAL
public serviceenterprise group 2Q_2008_Webcast_Slides_FINAL
 
EP4Q2007Earnings_FINALv2(Web)
EP4Q2007Earnings_FINALv2(Web)EP4Q2007Earnings_FINALv2(Web)
EP4Q2007Earnings_FINALv2(Web)
 
EP4Q2007Earnings_FINALv2(Web)
EP4Q2007Earnings_FINALv2(Web)EP4Q2007Earnings_FINALv2(Web)
EP4Q2007Earnings_FINALv2(Web)
 
public serviceenterprise group 2Q2007Slides
public serviceenterprise group 2Q2007Slidespublic serviceenterprise group 2Q2007Slides
public serviceenterprise group 2Q2007Slides
 
public serviceenterprise group 2Q2007Slides
public serviceenterprise group 2Q2007Slidespublic serviceenterprise group 2Q2007Slides
public serviceenterprise group 2Q2007Slides
 
EPElPasoCorporation1Q06WebcastFinal
EPElPasoCorporation1Q06WebcastFinalEPElPasoCorporation1Q06WebcastFinal
EPElPasoCorporation1Q06WebcastFinal
 
celanese 3q_2006_earnings_slides
celanese 3q_2006_earnings_slidescelanese 3q_2006_earnings_slides
celanese 3q_2006_earnings_slides
 
Hexion FinalQ407
Hexion FinalQ407Hexion FinalQ407
Hexion FinalQ407
 
celanese q4_2005_ir_slides
celanese q4_2005_ir_slidescelanese q4_2005_ir_slides
celanese q4_2005_ir_slides
 
.credit-suisse - Presentation
 .credit-suisse - Presentation .credit-suisse - Presentation
.credit-suisse - Presentation
 
el paso 2Q2007EarningsFINAL(B&WPrint)
el paso  2Q2007EarningsFINAL(B&WPrint)el paso  2Q2007EarningsFINAL(B&WPrint)
el paso 2Q2007EarningsFINAL(B&WPrint)
 
el paso 2Q2007EarningsFINAL(B&WPrint)
el paso  2Q2007EarningsFINAL(B&WPrint)el paso  2Q2007EarningsFINAL(B&WPrint)
el paso 2Q2007EarningsFINAL(B&WPrint)
 
celanese q2_2006_presentation
celanese q2_2006_presentationcelanese q2_2006_presentation
celanese q2_2006_presentation
 

More from finance20

pg& e crop 2008 VotingResults
pg& e crop 2008 VotingResultspg& e crop 2008 VotingResults
pg& e crop 2008 VotingResultsfinance20
 
pg& e crop 2008 ProxyStatement
pg& e crop 2008 ProxyStatementpg& e crop 2008 ProxyStatement
pg& e crop 2008 ProxyStatementfinance20
 
pg & e crop 2004 Proxy Statement
pg & e crop 2004 Proxy Statementpg & e crop 2004 Proxy Statement
pg & e crop 2004 Proxy Statementfinance20
 
pg & e crop 2005 Proxy Statement
pg & e crop 2005 Proxy Statementpg & e crop 2005 Proxy Statement
pg & e crop 2005 Proxy Statementfinance20
 
pg & e crop 2006 Proxy Statement
pg & e crop 2006 Proxy Statementpg & e crop 2006 Proxy Statement
pg & e crop 2006 Proxy Statementfinance20
 
pg & e crop 2007 Proxy Statement
pg & e crop 2007 Proxy Statementpg & e crop 2007 Proxy Statement
pg & e crop 2007 Proxy Statementfinance20
 
pg & e crop 2008 Proxy Statement
pg & e crop 2008 Proxy Statementpg & e crop 2008 Proxy Statement
pg & e crop 2008 Proxy Statementfinance20
 
pg & e crop 2003 Annual Report
pg & e crop 2003 Annual Reportpg & e crop 2003 Annual Report
pg & e crop 2003 Annual Reportfinance20
 
pg & e crop 2004 Annual Report
pg & e crop 2004 Annual Reportpg & e crop 2004 Annual Report
pg & e crop 2004 Annual Reportfinance20
 
pg & e crop 2005 Annual Report
pg & e crop 2005 Annual Reportpg & e crop 2005 Annual Report
pg & e crop 2005 Annual Reportfinance20
 
pg & e crop 2006 Annual Report
pg & e crop 2006 Annual Reportpg & e crop 2006 Annual Report
pg & e crop 2006 Annual Reportfinance20
 
pg & e crop 2007 Annual Report
pg & e crop 2007 Annual Reportpg & e crop 2007 Annual Report
pg & e crop 2007 Annual Reportfinance20
 
waste management Groundwater_Well
waste management Groundwater_Wellwaste management Groundwater_Well
waste management Groundwater_Wellfinance20
 
waste management Gas_Probe
waste management Gas_Probewaste management Gas_Probe
waste management Gas_Probefinance20
 
waste management Anatomy of a Landfill
waste management Anatomy of a Landfillwaste management Anatomy of a Landfill
waste management Anatomy of a Landfillfinance20
 
waste management Waste By Rail
waste management Waste By Railwaste management Waste By Rail
waste management Waste By Railfinance20
 
waste management Flyer
waste management Flyerwaste management Flyer
waste management Flyerfinance20
 
waste management Renewable_Energy_Brochure
waste management Renewable_Energy_Brochurewaste management Renewable_Energy_Brochure
waste management Renewable_Energy_Brochurefinance20
 
waste management WM RA FactSheet
waste management WM RA FactSheetwaste management WM RA FactSheet
waste management WM RA FactSheetfinance20
 
waste management 2003 annual
waste management 2003 annualwaste management 2003 annual
waste management 2003 annualfinance20
 

More from finance20 (20)

pg& e crop 2008 VotingResults
pg& e crop 2008 VotingResultspg& e crop 2008 VotingResults
pg& e crop 2008 VotingResults
 
pg& e crop 2008 ProxyStatement
pg& e crop 2008 ProxyStatementpg& e crop 2008 ProxyStatement
pg& e crop 2008 ProxyStatement
 
pg & e crop 2004 Proxy Statement
pg & e crop 2004 Proxy Statementpg & e crop 2004 Proxy Statement
pg & e crop 2004 Proxy Statement
 
pg & e crop 2005 Proxy Statement
pg & e crop 2005 Proxy Statementpg & e crop 2005 Proxy Statement
pg & e crop 2005 Proxy Statement
 
pg & e crop 2006 Proxy Statement
pg & e crop 2006 Proxy Statementpg & e crop 2006 Proxy Statement
pg & e crop 2006 Proxy Statement
 
pg & e crop 2007 Proxy Statement
pg & e crop 2007 Proxy Statementpg & e crop 2007 Proxy Statement
pg & e crop 2007 Proxy Statement
 
pg & e crop 2008 Proxy Statement
pg & e crop 2008 Proxy Statementpg & e crop 2008 Proxy Statement
pg & e crop 2008 Proxy Statement
 
pg & e crop 2003 Annual Report
pg & e crop 2003 Annual Reportpg & e crop 2003 Annual Report
pg & e crop 2003 Annual Report
 
pg & e crop 2004 Annual Report
pg & e crop 2004 Annual Reportpg & e crop 2004 Annual Report
pg & e crop 2004 Annual Report
 
pg & e crop 2005 Annual Report
pg & e crop 2005 Annual Reportpg & e crop 2005 Annual Report
pg & e crop 2005 Annual Report
 
pg & e crop 2006 Annual Report
pg & e crop 2006 Annual Reportpg & e crop 2006 Annual Report
pg & e crop 2006 Annual Report
 
pg & e crop 2007 Annual Report
pg & e crop 2007 Annual Reportpg & e crop 2007 Annual Report
pg & e crop 2007 Annual Report
 
waste management Groundwater_Well
waste management Groundwater_Wellwaste management Groundwater_Well
waste management Groundwater_Well
 
waste management Gas_Probe
waste management Gas_Probewaste management Gas_Probe
waste management Gas_Probe
 
waste management Anatomy of a Landfill
waste management Anatomy of a Landfillwaste management Anatomy of a Landfill
waste management Anatomy of a Landfill
 
waste management Waste By Rail
waste management Waste By Railwaste management Waste By Rail
waste management Waste By Rail
 
waste management Flyer
waste management Flyerwaste management Flyer
waste management Flyer
 
waste management Renewable_Energy_Brochure
waste management Renewable_Energy_Brochurewaste management Renewable_Energy_Brochure
waste management Renewable_Energy_Brochure
 
waste management WM RA FactSheet
waste management WM RA FactSheetwaste management WM RA FactSheet
waste management WM RA FactSheet
 
waste management 2003 annual
waste management 2003 annualwaste management 2003 annual
waste management 2003 annual
 

Recently uploaded

Unveiling the Top Chartered Accountants in India and Their Staggering Net Worth
Unveiling the Top Chartered Accountants in India and Their Staggering Net WorthUnveiling the Top Chartered Accountants in India and Their Staggering Net Worth
Unveiling the Top Chartered Accountants in India and Their Staggering Net WorthShaheen Kumar
 
The Triple Threat | Article on Global Resession | Harsh Kumar
The Triple Threat | Article on Global Resession | Harsh KumarThe Triple Threat | Article on Global Resession | Harsh Kumar
The Triple Threat | Article on Global Resession | Harsh KumarHarsh Kumar
 
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxOAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxhiddenlevers
 
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办fqiuho152
 
Vp Girls near me Delhi Call Now or WhatsApp
Vp Girls near me Delhi Call Now or WhatsAppVp Girls near me Delhi Call Now or WhatsApp
Vp Girls near me Delhi Call Now or WhatsAppmiss dipika
 
Call Girls Near Golden Tulip Essential Hotel, New Delhi 9873777170
Call Girls Near Golden Tulip Essential Hotel, New Delhi 9873777170Call Girls Near Golden Tulip Essential Hotel, New Delhi 9873777170
Call Girls Near Golden Tulip Essential Hotel, New Delhi 9873777170Sonam Pathan
 
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...shivangimorya083
 
Financial Leverage Definition, Advantages, and Disadvantages
Financial Leverage Definition, Advantages, and DisadvantagesFinancial Leverage Definition, Advantages, and Disadvantages
Financial Leverage Definition, Advantages, and Disadvantagesjayjaymabutot13
 
Stock Market Brief Deck for "this does not happen often".pdf
Stock Market Brief Deck for "this does not happen often".pdfStock Market Brief Deck for "this does not happen often".pdf
Stock Market Brief Deck for "this does not happen often".pdfMichael Silva
 
SBP-Market-Operations and market managment
SBP-Market-Operations and market managmentSBP-Market-Operations and market managment
SBP-Market-Operations and market managmentfactical
 
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...Amil baba
 
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...yordanosyohannes2
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...makika9823
 
Lundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdfLundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdfAdnet Communications
 
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service AizawlVip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawlmakika9823
 
Governor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraintGovernor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraintSuomen Pankki
 
fca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdffca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdfHenry Tapper
 
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130  Available With RoomVIP Kolkata Call Girl Serampore 👉 8250192130  Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Roomdivyansh0kumar0
 
Classical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithClassical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithAdamYassin2
 
Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex
 

Recently uploaded (20)

Unveiling the Top Chartered Accountants in India and Their Staggering Net Worth
Unveiling the Top Chartered Accountants in India and Their Staggering Net WorthUnveiling the Top Chartered Accountants in India and Their Staggering Net Worth
Unveiling the Top Chartered Accountants in India and Their Staggering Net Worth
 
The Triple Threat | Article on Global Resession | Harsh Kumar
The Triple Threat | Article on Global Resession | Harsh KumarThe Triple Threat | Article on Global Resession | Harsh Kumar
The Triple Threat | Article on Global Resession | Harsh Kumar
 
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxOAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
 
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
 
Vp Girls near me Delhi Call Now or WhatsApp
Vp Girls near me Delhi Call Now or WhatsAppVp Girls near me Delhi Call Now or WhatsApp
Vp Girls near me Delhi Call Now or WhatsApp
 
Call Girls Near Golden Tulip Essential Hotel, New Delhi 9873777170
Call Girls Near Golden Tulip Essential Hotel, New Delhi 9873777170Call Girls Near Golden Tulip Essential Hotel, New Delhi 9873777170
Call Girls Near Golden Tulip Essential Hotel, New Delhi 9873777170
 
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
 
Financial Leverage Definition, Advantages, and Disadvantages
Financial Leverage Definition, Advantages, and DisadvantagesFinancial Leverage Definition, Advantages, and Disadvantages
Financial Leverage Definition, Advantages, and Disadvantages
 
Stock Market Brief Deck for "this does not happen often".pdf
Stock Market Brief Deck for "this does not happen often".pdfStock Market Brief Deck for "this does not happen often".pdf
Stock Market Brief Deck for "this does not happen often".pdf
 
SBP-Market-Operations and market managment
SBP-Market-Operations and market managmentSBP-Market-Operations and market managment
SBP-Market-Operations and market managment
 
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
 
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
 
Lundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdfLundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdf
 
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service AizawlVip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
 
Governor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraintGovernor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraint
 
fca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdffca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdf
 
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130  Available With RoomVIP Kolkata Call Girl Serampore 👉 8250192130  Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
 
Classical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithClassical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam Smith
 
Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024
 

public serviceenterprise group Investor library.corporate

  • 1. Public Service Enterprise Group PSEG Earnings Conference Call 4th Quarter and Year-End 2008 February 3, 2009
  • 2. Forward-Looking Statement Readers are cautioned that statements contained in this presentation about our and our subsidiaries' future performance, including future revenues, earnings, strategies, prospects and all other statements that are not purely historical, are forward-looking statements for purposes of the safe harbor provisions under The Private Securities Litigation Reform Act of 1995. Although we believe that our expectations are based on reasonable assumptions, we can give no assurance they will be achieved. The results or events predicted in these statements may differ materially from actual results or events. Factors which could cause results or events to differ from current expectations include, but are not limited to: • Adverse changes in energy industry, policies and regulation, including market structures and rules. • Any inability of our energy transmission and distribution businesses to obtain adequate and timely rate relief and regulatory approvals from federal and state regulators. • Changes in federal and state environmental regulations that could increase our costs or limit operations of our generating units. • Changes in nuclear regulation and/or developments in the nuclear power industry generally, that could limit operations of our nuclear generating units. • Actions or activities at one of our nuclear units that might adversely affect our ability to continue to operate that unit or other units at the same site. • Any inability to balance our energy obligations, available supply and trading risks. • Any deterioration in our credit quality. • Availability of capital and credit at reasonable pricing terms and our ability to meet cash needs. • Any inability to realize anticipated tax benefits or retain tax credits. • Increases in the cost of or interruption in the supply of fuel and other commodities necessary to the operation of our generating units. • Delays or cost escalations in our construction and development activities. • Adverse investment performance of our decommissioning and defined benefit plan trust funds, and changes in discount rates and funding requirements. • Changes in technology and increased customer conservation. For further information, please refer to our Annual Report on Form 10-K, including Item 1A. Risk Factors, and subsequent reports on Form 10-Q and Form 8-K filed with the Securities and Exchange Commission. These documents address in further detail our business, industry issues and other factors that could cause actual results to differ materially from those indicated in this presentation. In addition, any forward-looking statements included herein represent our estimates only as of today and should not be relied upon as representing our estimates as of any subsequent date. While we may elect to update forward-looking statements from time to time, we specifically disclaim any obligation to do so, even if our estimates change, unless otherwise required by applicable securities laws. 1
  • 3. GAAP Disclaimer PSEG presents Operating Earnings in addition to its Net Income reported in accordance with accounting principles generally accepted in the United States (GAAP). Operating Earnings is a non-GAAP financial measure that differs from Net Income because it excludes the impact of the sale of certain non-core domestic and international assets and material impairments and lease-transaction-related charges. PSEG presents Operating Earnings because management believes that it is appropriate for investors to consider results excluding these items in addition to the results reported in accordance with GAAP. PSEG believes that the non- GAAP financial measure of Operating Earnings provides a consistent and comparable measure of performance of its businesses to help shareholders understand performance trends. This information is not intended to be viewed as an alternative to GAAP information. The last slide in this presentation includes a list of items excluded from Income from Continuing Operations to reconcile to Operating Earnings, with a reference to that slide included on each of the slides where the non-GAAP information appears. 2
  • 4. PSEG 2008 Q4 Review Ralph Izzo Chairman, President and Chief Executive Officer
  • 5. Q4 2008 Earnings Summary Quarter ended December 31, 2008 2007 $ millions (except EPS) Operating Earnings $ 250 $ 272 Asset Sales and Impairments (13) (53) Income from Continuing Operations 237 219 Discontinued Operations (3) 6 Net Income 234 225 EPS from Operating Earnings* $ 0.49 $ 0.53 4 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 6. Full-year 2008 Earnings Summary For the year ended December 31, 2008 2007 $ millions (except EPS) Operating Earnings $ 1,487 $ 1,385 Lease Reserves (490) --- Asset Sales and Impairments (14) (60) Income from Continuing Operations 983 1,325 Discontinued Operations, net of tax 205 10 Net Income 1,188 1,335 EPS from Operating Earnings* $ 2.92 $ 2.72 5 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 7. PSEG – 2008: Answering Challenges – Meeting Objectives 2008 earnings within guidance Focused on operational excellence Record generation production Top decile reliability standards maintained at PSE&G Controlling operating and maintenance expenses to meet challenging economic environment Foundation laid for future Carbon abatement Capital infrastructure and energy efficiency capital programs Generation environmental upgrades on target; within budget Financial position strengthened; risk reduced Major international assets sold Debt reduced Credit targets achieved Additional reserve for LILO/SILO tax risk recognized 6
  • 8. PSEG – 2009: Meeting the Challenge $3.00 - $3.25 $2.92 $2.72 2007 Operating Earnings* 2008 Operating Earnings* 2009 Guidance 7 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 9. PSEG 2008 Q4 Operating Company Review Tom O’Flynn Executive Vice President and Chief Financial Officer
  • 10. Q4 Operating Earnings by Subsidiary Quarter ended December 31, Operating Earnings Earnings per Share 2008 2007 2008 2007 $ millions (except EPS) PSEG Power $ 207 $ 205 $ 0.40 $ 0.40 PSE&G 76 77 0.15 0.15 PSEG Energy Holdings (23) 10 (0.04) 0.02 Enterprise (10) (20) (0.02) (0.04) Operating Earnings* $ 250 $ 272 $ 0.49 $ 0.53 9 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 11. Full-year 2008 Operating Earnings by Subsidiary For the year ended December 31, Operating Earnings Earnings per Share 2008 2007 2008 2007 $ millions (except EPS) PSEG Power $ 1,050 $ 949 $ 2.06 $ 1.86 PSE&G 360 376 0.71 0.74 PSEG Energy Holdings 101 123 0.20 0.24 Enterprise (24) (63) (0.05) (0.12) Operating Earnings* $ 1,487 $ 1,385 $ 2.92 $ 2.72 10 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 12. PSEG EPS Reconciliation – Q4 2008 versus Q4 2007 0.60 .00 .00 $.53 (.06) $.49 .02 Recontracting Weather .01 and Strong Gas Margin Markets .07 (.01) Texas – MTM (.05); Interest O&M .03 Operations (.02) O&M .04 0.40 NDT (.10) 2007 Asset Sales Depreciation and Settlements and Taxes (.04) (.03) $ / share Lease Income (.02) Effective Tax Rate and Other .05 Interest Expense .01 0.20 0.00 Q4 2007 Q4 2008 PSEG Energy Enterprise PSEG Power PSE&G operating operating Holdings earnings* earnings* 11 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 13. PSEG EPS Reconciliation – Full-year 2008 versus Full- year 2007 $2.92 (.03) 3.00 .20 .07 (.04) $2.72 Interest Margin – Gas, 2007 Asset Sales Electric and and Settlements Recontracting Transmission (.13) and Strong (.04) Markets .43 Lease Income (.04) Weather (.01) MTM and BGSS Texas – MTM (.03) .03 O&M .02 Operations .05 NDT (.16) Depreciation, Interest Expense $ / share Interest and .07 O&M (.07) Other (.02) 2.00 Effective Tax Rate Depreciation, Effective Tax and Other .04 Interest and Taxes Rate .02 (.03) 1.00 2007 2008 PSEG Energy Enterprise PSEG Power PSE&G operating operating Holdings earnings* earnings* 12 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 15. PSEG Power – Q4 2008 EPS Summary Q4 2008 Q4 2007 Variance $ millions (except EPS) Operating Revenues $ 1,939 $ 1,762 $ 177 Operating Earnings 207 205 2 Income from Continuing Operations/ 207 205 2 Net Income EPS from Operating Earnings* $ 0.40 $ 0.40 --- 14 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 16. PSEG Power EPS Reconciliation – Q4 2008 versus Q4 2007 0.50 (.10) .07 $.40 .03 $.40 Recontracting and Strong NDT O&M Markets $ / share 0.00 Q4 2007 Q4 2008 operating operating earnings* earnings* 15 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 17. PSEG Power – Generation Measures PSEG Power – Generation (GWh) Quarter ended December 31, Twelve months ended December 31, 15,000 60,000 55,292 53,197 12,391 12,518 13,090 11,820 2,516 2,761 10,000 40,000 12,918 2,642 13,014 3,089 5,000 20,000 7,360 29,284 28,363 6,541 0 0 2007 2008 2007 2008 Total Oil & 16 Total Nuclear Total Coal* Natural Gas * Includes figures for Pumped Storage
  • 18. PSEG Power – Fuel Costs PSEG Power – Fuel Costs Quarter ended December 31, Year ended December 31, ($ millions) 2007 2008 ($ millions) 2007 2008 Coal 84 92 Coal 336 423 Oil & Gas 200 192 Oil & Gas 847 1141 Total Fossil $284 $284 Total Fossil $1,183 $1,564 Nuclear 28 33 Nuclear 122 129 Total Fuel Cost $312 $317 Total Fuel Cost $1,305 $1,693 Total Generation Total Generation 53,197 55,292 12,391 12,518 (GWhr) (GWhr) $ / MWh $24.50 $30.60 $ / MWh $25.20 $25.30 17
  • 19. Strong Pricing Supports Margin Improvement PSEG Power Gross Margin* ($/MWh) Quarter ended December 31, Twelve months ended December 31, $60 $60 $57 - $58 -5% 3 + $56 0% $55 +1 % 0 +1 $51 $50 $40 $40 2007 2008 2009E 2007 2008 18 * Includes MTM
  • 20. PSEG Power – Q4 Operating Highlights Operations 4Q output +1%; full-year increase of 3.9% leading to record production. 4Q nuclear capacity factor at 91.3%; full-year at 92.6%. Coal plant availability affected by BET related work. Environmental work at Hudson and Mercer proceeding on schedule; on budget. Regulatory and Market Environment Renegotiated contract with Indonesian coal supplier. Seeing impact on pricing from declining economic growth. CAIR reinstated; too early to predict impact of change in administration on energy and environmental policy. Financial $25 million dividend paid to Enterprise in 4Q; $500 million for full-year. Successful launch of $500 million retail MTN program. 19
  • 22. PSE&G – Q4 2008 Earnings Summary $ millions (except EPS) Q4 2008 Q4 2007 Variance Operating Revenues $ 2,288 $ 2,153 $ 135 Operating Expenses Energy Costs 1,545 1,415 130 Operation & Maintenance 345 361 (16) Depreciation & Amortization 140 142 (2) Taxes Other than Income Taxes 35 35 --- Total Operating Expenses 2,065 1,953 112 Operating Earnings 76 77 (1) Income from Continuing Operations/ 76 77 (1) Net Income EPS from Operating Earnings* $ 0.15 $ 0.15 --- 21 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 23. PSE&G EPS Reconciliation – Q4 2008 versus Q4 2007 0.20 .04 (.04) (.01) .01 $.15 $.15 Weather Gas Margin O&M Depreciation and Taxes $ / share 0.10 0.00 Q4 2007 Q4 2008 operating operating earnings* earnings* 22 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 24. PSE&G – Q4 Operating Highlights Operations Declining economic growth having impact on sales growth. O&M costs remain under control. Focused on containing impact of economic fallout on customers and accounts through support of outreach programs. Regulatory and Market Environment PSE&G filed for NJ BPU approval to construct the Susquehanna – Roseland transmission line. The $750 million project is scheduled to be in-service by year- end 2012. NJ BPU approved a four-year $46 million program to curb energy consumption and reduce CO2 emissions. PSE&G proposed a two-year $888 million capital program supporting energy infrastructure ($698 million) and energy efficiency ($190 million). Financial Outlook for electric sales growth hurt by weak economy. Capital to be invested in areas with regulatory support. 23
  • 26. PSEG Energy Holdings – Q4 2008 Earnings Summary Q4 2008 Q4 2007 Variance $ millions (except EPS) Operating (Loss) / Earnings ($ 23) $ 10 ($ 33) Asset Sales and Impairments 13 53 (40) Loss from Continuing Operations (36) (43) 7 Discontinued Operations (3) 6 (9) Net Loss (39) (37) (2) EPS from Operating (Loss) / Earnings* ($ 0.04) $ 0.02 ($0.06) 25 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 27. PSEG Energy Holdings EPS Reconciliation – Q4 2008 versus Q4 2007 0.05 $.02 (.07) 0.00 .01 $ / share (.03) .05 (.04) -0.05 Interest Texas - Expense Operations (.02) (.02) MTM (.05) 2007 Asset Sales and Settlements -0.10 Effective Lease Tax Rate Income and Other -0.15 Q4 2007 Q4 2008 operating operating earnings* earnings* 26 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 28. PSEG Energy Holdings – Q4 Operating Highlights Operations Texas – 2,000 MW gas-fired combined cycle capacity 1,000 MW Guadalupe facility experienced improved capacity factor and spark spreads. 1,000 MW Odessa facility experienced a reduction in capacity and availability. Spark Spread Production (GWh) 4Q 2007 4Q 2008 2007 2008 4Q 2007 4Q 2008 2007 2008 Guadalupe $10.30 $14.83 $14.77 $24.56 .85 1.15 4.20 4.98 Odessa $26.88 $26.37 $23.16 $32.72 .82 .45 4.30 2.85 Regulatory and Market Environment Submitted RFP on 500 MW of 1,000 MW Odessa plant for a 10-15 year agreement to provide energy and capacity. Change in administration and energy policy could favor development of renewables. Financial Recognized impairment of investments in PPN and Turboven. Remaining international investments total $24 million. Received approximately $700 million from Q3 and Q4 international asset sales. 27
  • 29. PSEG
  • 30. Outlook for Pension Expense January 2009 2008 Actual Estimate** PSE&G $15.0* $80.0* PSEG Power 14.0 76.0 Other 2.0 4.0 TOTAL 31.0 160.0* Discount Rate 6.50% 6.80% 29 * After capitalized amount; pre-tax figure. ** The January 2009 estimate represents an increase from our October 2008 forecast of $110 - $120 million pre-tax.
  • 31. 2009 Operating Earnings Guidance 2008A* 2009E $ millions (except EPS) PSEG Power $ 1,050 $ 1,210 – $ 1,285 PSE&G $ 360 $ 320 – $ 345 PSEG Energy Holdings $ 101 $ 0 – $ 20 Enterprise ($ 24) ($ 10) – $ 0 Operating Earnings $ 1,487 $ 1,520 – $ 1,650 Earnings per Share $ 2.92 $ 3.00 – $ 3.25 30 * See page 32 for Items excluded from Income from Continuing Operations to reconcile to Operating Earnings.
  • 32. PSEG Liquidity as of December 31, 2008 Expiration Total Primary Usage at Available Liquidity Company Facility Date Facility Purpose 12/31/2008 12/31/2008 1 5-year Credit Facility 12-Dec $1,000 CP Support/Funding/LCs $13 $987 PSEG Bilateral Credit Facility 9-Jun $100 CP Support/Funding $0 $100 Uncommitted Bilateral Agreement N/A N/A Funding 0 N/A 3 5-Year Credit Facility 12-Dec 1,600 Funding/LCs 222 1,378 Power Bilateral Credit Facility 9-Jun 100 Funding/LCs 0 100 Bilateral Credit Facility 9-Mar 150 Funding/LCs 52 98 Bilateral Credit Facility 9-Sep 50 Funding 0 50 Bilateral Credit Facility 10-Mar 100 Funding/LCs 14 86 2 5-year Credit Facility 12-Jun 600 CP Support/Funding/LCs 20 580 PSE&G Uncommitted Bilateral Agreement N/A N/A Funding 0 N/A 5-year Credit Facility 10-Jun 136 Funding/LCs 21 115 Energy Holdings Total $3,836 $3,494 1 PSEG Facility reduces by $47 million in 2012 2 PSE&G Facility reduces by $28 million in 2012 3 Pow er Facility reduces by $75 million in 2012 31
  • 33. Items Excluded from Income from Continuing Operations to Reconcile to Operating Earnings For the Quarters Ended For the Twelve Months Ended December 31, December 31, Pro-forma Adjustments, net of tax 2008 2007 2008 2007 Earnings Impact (in Millions) Asset Sales and Impairments: Impairment of PPN $ (9) $ (2) $ (9) $ (2) Impairment of Turboven (4) - (4) (7) Loss on Sale of Chilquinta and Luz del Sur - (23) - (23) Premium on Bond Redemption - (28) (1) (28) Total Asset Sales and Impairments (13) (53) (14) (60) Lease Reserves - - (490) - $ (13) $ (53) $ (504) $ (60) Total Pro-forma to Operating Earnings Fully Diluted Average Shares Outstanding (in Millions) 507 510 508 509 Per Share Impact (Diluted) Asset Sales and Impairments: Impairment of PPN $ (0.02) $ - $ (0.02) $ - Impairment of Turboven (0.01) - (0.01) (0.01) Loss on Sale of Chilquinta and Luz del Sur - (0.05) - (0.05) Premium on Bond Redemption - (0.06) - (0.06) Total Asset Sales and Impairments (0.03) (0.11) (0.03) (0.12) Lease Reserves - - (0.96) - $ (0.03) $ (0.11) $ (0.99) $ (0.12) Total Pro-forma to Operating Earnings Please see Slide 2 for an explanation of PSEG’s use of Operating Earnings as a non-GAAP financial measure and how 32 it differs from Net Income.