2. Week 1
Construction Activity 1: SETTING OUT
DURATION: 8 Days
EQUIPMENTS:
1. Backhoe
2. Bulldozer
3. Excavator
SKILLED WORKERS:
1. 2 Construction Supervisors
2. 3 Equipment Operators
3. 1 Excavation Foreman
4. 1 Ground Leveling Staff
5. 3 Contractors
6. 1 Plumber
7. 1 Electrician
8. 1 Carpenter
TECHNICAL INFORMATION:
Before earthworks, the planned building is set out.
Building profiles and the use of string lines to mark the outside perimeters of the
construction and any other critical measurements. One of the most important things
in setting out is position and accuracy in which the hurdles are placed .
Excavations will proceed and plumbers will be able to install the underground
plumbing.
Electricians will be able to install the meter box and any pre-wires necessary.
Carpenters may also use these set out lines to begin framing on the construction.
Levels have to be set out based on benchmarks in the surroundings. Geometric
surveying measures the difference in height of a horizontally set up level from a
benchmark with levelling staff held vertically.
3. Week 2
Construction Activity 1: Earthwork
DURATION: 2 Days
EQUIPMENTS:
1. Backhoe
2. Bulldozer
3. Excavator
SKILLED WORKERS:
1. 3 Heavy Equipment Operator
2. 2 Construction Supervisor
3. 1 Excavation Foreman
4. 3 General Workers
TECHNICAL INFORMATION:
The earth may be moved to another location and formed into a desired shape for a
purpose.
Much of earthworks involves machine excavation and fill or backfill.
Preservation of topsoil, slope protection, soil formation, soil loosening and soil
improvement take part of the earthwork.
Preparing holes for the piles.
4. Week 3
Construction Activity 1: Piling
DURATION: 4 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
EQUIPMENTS:
1. 1 Hydraulic hammer
2. 1 Concrete vibrator
3. 1 Bar bending machine
SKILLED WORKERS:
1. 1 Pile Driver Operator
2. 2 Carpenters
3. 2 Bar Benders
4. 3 Construction Workers
TECHNICAL INFORMATION:
According to the location of the piles in the ground reinforced concrete piles are driven
to transfer the load-bearing from the building through the weak ground to the load
bearing ground below.
5. Week 3
Construction Activity 2: Pile Cap
DUARTION: 4 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber formwork
EQUIPMENT:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKER:
1. 2 Carpenters
2. 2 Bar Benders
3. 5 Construction workers
TECHNICAL INFORMATION:
After driving piles, reinforced concrete pile caps joins the head of the cluster of the
piles in order to distribute the load from a column among the piles.
The framework is installed and reinforced cage is also installed in the framework.
The mold is filled with the concrete.
The framework is removed after.
6. Week 7
Construction Activity 1: Stump
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcement
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 1 Bar Bender
3. 3 Construction Workers
TECHNICAL INFORMATION:
The stumps are installed between the pile cap and column.
The framework is installed and rebar is also installed in the framework.
The mold is filled with the concrete.
The framework is removed after.
7. Week 9
Construction Activity 1: Ground Beam
DURATION: 7 Days
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Bar Bending Machine
2. 1 Concrete Vibrator
SKILLED WORKERS:
1. 2 Bar Benders
2. 3 Carpenters
3. 4 Construction Workers
TECHNICAL INFORMATION:
Ground beams are mostly formed and placed along with the slab they support and to
distribute the tension forces.
8. Week 9
Construction Activity 2: Ground Floor Columns
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Bar Bending Machines
2. 1 Concrete Vibrator
3. Hammers
4. Nails
SKILLED WORKERS:
1. 2 Bar Benders
2. 3 Carpenters
3. 4 Construction Workers
TECHNICAL INFORMATION:
According to the location of the column plans, reinforced concrete fills the plywood
formwork placed.
9. Week 10
Construction Activity 1: Ground Floor Columns
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
3. Hammers
4. Nails
SKILLED WORKERS:
1. 2 Carpenters
2. 3 Construction Workers
3. 1 Bar Bender
TECHNICAL INFORMATION:
According to the location of the column plans, reinforced concrete fills the plywood
formwork placed.
10. Week 11
Construction Activity 1:First Floor Beam
DURATION: 7 Days
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 3 Construction Workers
TECHNICAL INFORMATION:
The beams are mostly formed and placed along with the slabs they support to
distribute the tension forces.
11. Week 11
Construction Activity 1:First Floor Slab
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 4 Construction Workers
TECHNICAL INFORMATION:
Concrete slab is a plate structure reinforced to span either a structural bay.
12. Week 13
Construction Activity 1: First Floor Columns
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 1 Bar Bender
3. 4 Construction Workers
TECHNICAL INFORMATION:
According to the location of the column plans, reinforced concrete fills the plywood
formwork placed.
13. Week 14
Construction Activity 1: First Floor Columns
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 1 Bar Bender
3. 3 Construction Workers
TECHNICAL INFORMATION:
According to the location of the column plans,
reinforced concrete fills the plywood formwork
placed.
14. Week 15
Construction Activity 1: Second Floor Beam
DURATION: 7 Days
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 4 Construction Workers
TECHNICAL INFORMATION:
The beams are mostly formed and placed along with the slab they support and to
distribute the tension forces throughout the building.
15. Week 15
Construction Activity 2: Second Floor Slab
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar benders
3. 4 Construction Workers
TECHNICAL INFORMATION:
Concrete slab is a plate structure
reinforced to span either a structural bay.
16. Week 17
Construction Activity 1: Ground Floor Slab
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 4 Construction Workers
TECHNICAL INFORMATION:
Concrete slab is a plate structure reinforced to span either a structural bay.
17. Week 19
Construction Activity 1: First Floor Columns
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenter
2. 1 Bar Bender
3. 3 Construction Workers
TECHNICAL INFORMATION:
According to the location of the column plans,
reinforced concrete fills the plywood formwork placed.
18. Week 21
Construction Activity 1: Ground Floor Staircase
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 1 Bar Bender
3. 3 Construction Workers
TECHNICAL INFORMATION:
After the formwork is installed, the reinforced bars
join the starter bars then the concrete is poured to fill
up the formwork which will be removed after the
concrete is cured.
19. Week 22
Construction Activity 1: First Floor Staircase
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 1 Bar Bender
3. 3 Construction Worker
TECHNICAL INFORMATION:
After the formwork is installed, the reinforced bars join
the starter bars then the concrete is poured to fill up
the formwork which will be removed after the
concrete is cured.
20. Week 23
Construction Activity 1: Roof Beam
DURATION: 7 Days
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending Machine
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 3 Construction Workers
TECHNICAL INFORMATION:
The beams are mostly formed and placed along with
the slab they support and to distribute the tension
forces.
21. Week 24
Construction Activity 1: Roof Slab
DURATION: 2 Weeks
MATERIALS:
1. Concrete Grade 30
2. Reinforcements
3. Timber Formwork
EQUIPMENTS:
1. 1 Concrete Vibrator
2. 1 Bar Bending
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 4 Construction Workers
TECHNICAL INFORMATION:
Concrete slab is a plate structure reinforced
to span either a structural bay.
The structure of a flat roof may consist of
reinforced concrete slabs, timber or steel
beams decking and wood or steel joints and
sheathing.
The roof slabs may be supported by reinforced concrete columns, reinforced concrete
frames or bearing walls of reinforced concrete.
22. Week 26
Construction Activity 1: Ground Floor Exterior Brickwork
DURATION: 3 Weeks
MATERIALS:
1. Common Clay Bricks
2. Mortar
3. Brickwork Reinforcement Mesh (Ex-Mesh)
EQUIPMENTS:
1. Brick Trowels
2. Leveling Instruments
3. Bucket
SKILLED WORKERS:
1. 1 Carpenter
2. 4 Construction Workers
TECHNICAL INFORMATION:
Except for the spaces for the curtain walls, windows and doors, exterior brick walls are
constructed. Ex-meshes are placed on every fifth brick joint to strengthen.
23. Week 27
Construction Activity 1: First Floor Exterior Brickwork
DURATION: 3 Weeks
MATERIALS:
1. Common Clay Brick
2. Mortar
3. Brickwork Reinforcement Mesh (Ex-Mesh)
EQUIPMENTS:
1. Brick Trowels
2. Leveling Instrument
3. Bucket
SKILLED WORKERS:
1. 1 Carpenter
2. 4 General Workers
TECHNICAL INFORMATION:
Except for the spaces for the curtain walls, windows and doors, exterior brick walls are
constructed. Ex-meshes are placed on every fifth brick joint to strengthen.
24. Week 28
Construction Activity 1: Second Floor Exterior Brickwork
DURATION: 3 Weeks
MATERIALS:
1. Common Clay Brick
2. Mortar
3. Brickwork Reinforcements Mesh (Ex-Mesh)
EQUIPMENTS:
1. Brick Trowels
2. Leveling Instruments
3. Bucket
SKILLED WORKERS:
1. 1 Carpenter
2. 4 Construction Workers
TECHNICAL INFORMATION:
Except for the spaces for the curtain walls, windows and doors, exterior brick walls are
constructed. Ex-meshes are placed on every fifth brick joint to strengthen.
25. Week 29
Construction Activity 1: Interior Brickwork
DURATION: 3 Weeks
MATERIALS:
1. Common Clay Brick
2. Mortar
3. Brickwork Reinforcement Mesh (Ex-
Mesh)
EQUIPMENTS:
1. Brick Trowels
2. Leveling Instruments
3. Bucket
SKILLED WORKERS:
1. 1 Carpenter
2. 4 General Workers
TECHNICAL INFORMATION:
Except for the spaces for the curtain walls, windows and doors, exterior brick walls are
constructed. Ex-meshes are placed on every fifth brick joint to strengthen.
GROUND FLOOR
27. Week 32
Construction Activity 1: Roof Tiling
DURATION: 3 Days
MATERIALS:
1. 1 Concrete Grade 30
2. Roof Tiles
EQUIPMENTS:
1. Mortar
2. Trowel
3. Mesh Tape
4. Sealer
SKILLED WORKERS:
1. 2 Carpenters
2. 2 Bar Benders
3. 4 Construction Workers
TECHNICAL INFORMATION:
Concrete slab is a plate structure reinforced to span either a structural bay.
The structure of a flat roof may consist of reinforced concrete slabs, timber or steel
beams decking and wood or steel joints and sheathing.
The roof slabs may be supported by reinforced concrete columns, reinforced concrete
frames or bearing walls of reinforced concrete.
28. Week 33
Construction Activity 1: Installation of the windows and doors frame
DURATION: 11 Days
MATERIALS:
1. Aluminum
2. Timber
EQUIPMENTS:
1. Hammers
2. Nails
3. Leveling Instruments
SKILLED WORKERS:
1. 3 Construction Workers
TECHNICAL INFORMATION:
The frames of windows and doors are installed o the space prepared after the
brickwork.
Week 35
Construction Activity 1: Plumbing and electrical
DURATION: 4 Weeks
MATERIALS:
1. Pipes
2. Wires
EQUIPMENTS:
1. Pliers
2. Cutters
3. Sealers
SKILLED WORKERS:
1. 1 Plumber
2. 1 Electrical Engineer
3. 2 Carpenters
4. 3 Construction Workers
TECHNICAL INFORMATION:
The pipes and wires are installed for the water and electricity supply system.
29. Week 49
Construction Activity 1: Exterior and Interior
walls finishing
DURATION: 6 Weeks
MATERIALS:
1. Primer
2. Paint
3. Wall Plaster
EQUIPMENTS:
1. Paint Brushes
2. Rollers
3. Ladders
4. Steel Wool
SKILLED WORKERS:
1. 2 Carpenters
2. 4 Construction Workers
TECHNICAL INFORMATION:
Painting on the exterior and interior for
both the protection and aesthetic purpose.
30. Week 45
Construction Activity 1: Installation of Door panels
DURATION: 7 Days
MATERIALS:
1. Wooden Door Panels
2. Hinge
EQUIPMENTS:
1. Screw Drivers
2. Sealers
SKILLED WORKERS:
1. 4 Construction Workers
TECHNICAL INFORMATION:
The wooden door panels are installed on the prepared
space with the frame.
Week 46
Construction Activity 1: Installation of Curtain walls and glass panel
DURATION: 2 Weeks
MATERIALS:
1. Steel Mullions
2. Sealant
3. Screws
EQUIPMENTS:
1. Screw Drivers
2. Sealers
SKILLED WORKERS:
1. 4 Construction Workers
TECHNICAL INFORMATION:
Curtain wall panel and glass panel are installed
on the prepared space with the frame. The
mullions are installed on the curtain walls after.
31. Week 47
Construction Activity 1: Installation of glass
sliding doors
DURATION: 2 Weeks
MATERIALS:
1. Glass panels
2. Sealant
EQUIPMENTS:
1. Sealer
SKILLED WORKERS:
1. 3 Construction Workers
TECHNICAL INFORMATION:
Glass panels are installed on the prepared
space with the frame.
Week 59
Construction Activity 1: Installation of
staircase railing
DURATION: 3 Days
MATERIALS:
1. Glass Panels
2. Sealant
3. Steel Rail
4. Screws
EQUIPMENTS:
1. Sealer
2. Screw Driver
SKILLED WORKERS:
1. 2 Construction Workers
TECHNICAL INFORMATION:
The steel railing and glass panels are
installed on the staircase.
32. Week 50
Construction Activity 1: Floor tile and wooden finishing
DURATION: 2 Weeks
MATERIALS:
1. Ceramic Tiles
2. Solid Timber Flooring
3. Porcelain Tiles
EQUIPMENTS:
5. Mortar
6. Trowel
7. Mesh Tape
8. Sealer
SKILLED WORKERS:
1. 2 Construction Workers
TECHNICAL INFORMATION:
The tile finishing for the living room, kitchen, balcony and bathroom and wooden
finishing for the rooms are installed.
33. Week 52
Construction Activity 1: Installation of Window Panels
DURATION: 7 Days
MATERIALS:
3. Wooden window
4. Hinge
EQUIPMENTS:
3. Screw Drivers
4. Sealers
SKILLED WORKERS:
2. 4 Construction Workers
TECHNICAL INFORMATION:
The wooden window panels are installed on the prepared space with the frame.
34. Week 53
Construction Activity 1: Installation of fixed furniture and utilities
DURATION: 2 Weeks
MATERIALS:
1. Medium and Soft Woods
2. Varnish
3. Glue
4. Water Heater
5. Paint
6. Light Bulbs
7. Fixed Electrical Appliances
EQUIPMENTS:
1. Hammers
2. Nails
3. Cutters
4. Table Saw
SKILLED WORKERS:
1. 2 Construction Workers
2. 1 Electrician
TECHNICAL INFORMATION:
The fixed furniture such as lighting , telephone, door bell, fan, bath tub, basin, toilet
bowl, cabinet and etc are installed at the end.