Diagrama de tiempos actividades v2
- 1. CONSTRUCCION MODULO POLICI… 20/08/13 21/02/14 185
MODULO 1 : OBRAS PRELIMINARES 20/08/13 24/08/13 4
1. INSTALACION DE FAENAS (MOV… 20/08/13 21/08/13 1
2. LETRERO DE OBRAS HAM (SEG… 21/08/13 22/08/13 1
3. REPLANTEO (ESTRUCTURAS Y … 22/08/13 24/08/13 2
MODULO 2 : OBRA GRUESA 24/08/13 11/10/13 48
4. EXCAVACION PARA ZAPATAS 0 … 24/08/13 27/08/13 3
5. EXCAVACION PARA CIMIENTOS… 27/08/13 30/08/13 3
6. HORMIGON ARMADO ZAPATAS 30/08/13 01/09/13 2
7. HORMIGON ARMADO DE COLU… 01/09/13 05/09/13 4
8. HORMIGON CICLOPEO CIMIENT… 05/09/13 09/09/13 4
9. HORMIGON POBRE DE NIVELA… 09/09/13 10/09/13 1
10. HORMIGON CICLOPEO SOBRE… 10/09/13 12/09/13 2
11. IMPERMEABILIZACION DE SOB… 12/09/13 14/09/13 2
12. MURO BLOQUE DE Ho 3H E=0.… 14/09/13 19/09/13 5
13. MURO LADRILLO 6 HUECOS (E… 19/09/13 23/09/13 4
14. HORMIGON ARMADO DE VIGA… 23/09/13 28/09/13 5
15. BOTAGUAS DE HºAº 01/10/13 02/10/13 1
16. CUBIERTA DE CALAMINA GAL… 28/09/13 29/09/13 1
17. CUMBRERA Y LIMAHOYA CALA… 29/09/13 30/09/13 1
18. CANALETA Y BAJANES DE CA… 30/09/13 01/10/13 1
19. CONTRAPISO DE CEMENTO + … 02/10/13 05/10/13 3
20. ACERAS DE PIEDRA Y CEMEN… 05/10/13 08/10/13 3
21. MESON DE H*A* C/REVESTIMI… 08/10/13 11/10/13 3
MODULO 3 : OBRA FINA 20/11/13 20/02/14 92
22. REV INTERIOR DE CAL S/MUR… 11/12/13 16/12/13 5
23. REVOQ. INT. DE YESO S/LADRI… 16/12/13 21/12/13 5
24. REVOQUE EXTERIOR DE CAL (… 21/12/13 27/12/13 6
25. CIELO FALSO DE YESO MAS M… 27/12/13 01/01/14 5
26. ALERO (BAJO CUBIERTA) 01/01/14 05/01/14 4
27. PINTURA INTERIOR LATEX 06/02/14 11/02/14 5
28. PINTURA EXTERIOR LATEX 11/02/14 16/02/14 5
29. PISO DE CERAMICA ESMALTA… 09/01/14 15/01/14 6
30. PISO DE CEMENTO ENLUCIDO… 15/01/14 19/01/14 4
31. REVESTIMIENTO AZULEJOS S/… 19/01/14 23/01/14 4
32. ZOCALO DE CERAMICA ESMA… 23/01/14 28/01/14 5
33. ZOCALO DE CEMENTO Y ARENA 05/01/14 09/01/14 4
34. PROV. Y COLOC. PUERTAS DE… 20/11/13 23/11/13 3
35. PUERTAS METALICAS CORRE… 23/11/13 27/11/13 4
36. REJAS METALICAS DE PROTE… 27/11/13 30/11/13 3
37. PROV. Y COLOC. VENTANAS D… 30/11/13 03/12/13 3
38. VENTANA METALICA 03/12/13 07/12/13 4
39. REJA METALICA PARA VENTANA 07/12/13 11/12/13 4
40. PINTURA AL ACEITE S/ CARP. … 16/02/14 20/02/14 4
41. QUINCALLERIA PUERTAS 28/01/14 30/01/14 2
42. QUINCALLERIA VENTANAS 30/01/14 03/02/14 4
43. PROV. Y COLOCADO DE VIDRI… 03/02/14 06/02/14 3
CRONOGRAMA DE EJECUCIÓN DE LA OBRA
CONSTRUCCION MODULO POLICIAL SAN CRISTOBAL
NOMBRE DE LA ACTIVIDAD Comienzo Terminación Días Ago '13 Sep '13 Oct '13 Nov '13 Dic '13 Ene '14 Feb '14
Página 1
- 2. MODULO 4 : INSTALACION SANIT… 11/10/13 24/11/13 44
44. EXCAVACION MANUAL CLASE … 11/10/13 12/10/13 1
45. PROV/TENDIDO TUBERIAS PV… 01/11/13 05/11/13 4
46. PROV/TENDIDO TUBERIAS PV… 08/11/13 11/11/13 3
47. PROV. TENDIDO TUBERIA DE … 05/11/13 08/11/13 3
48. CAMA DE ARENA 28/10/13 01/11/13 4
49. RELLENO DE ZANJA C/TIERRA… 11/11/13 15/11/13 4
50. REJILLA DE PISO 20 X 20 15/11/13 20/11/13 5
51. CAMARA DE INSPECCION (60X… 12/10/13 16/10/13 4
52. CAMARA DE REGISTRO (40X40… 16/10/13 20/10/13 4
53. CAMARA DE INSPECCION 20/10/13 24/10/13 4
54. CAMARA DESGRASADORA 24/10/13 28/10/13 4
55. PROV. Y COLOCADO YEE DE 6… 01/11/13 02/11/13 1
56. PROV. E INST. INODORO TAN… 20/11/13 21/11/13 1
57. LAVAMANOS BLANCO + PEDE… 20/11/13 21/11/13 1
58. DUCHA 21/11/13 22/11/13 1
59. URINARIO DE PARED 21/11/13 22/11/13 1
60. LAVAPLATOS 2 FOSAS- 2 ESC… 22/11/13 23/11/13 1
61. LAVARROPA DE HORMIGON H… 22/11/13 23/11/13 1
62. PROV. E INST. TOALLEROS DE… 23/11/13 24/11/13 1
63. JABONERAS 23/11/13 24/11/13 1
64. PROV. Y COLC. PAPELERO (C… 23/11/13 24/11/13 1
MODULO 5 : INSTALACION DE AG… 09/09/13 12/10/13 33
65. EXCAVACION MANUAL CLASE … 11/10/13 12/10/13 1
66. PROV.TENDI.TUBE.PVC 3/4"ES… 09/09/13 10/09/13 1
67. PROV.TENDI.TUBE.PVC 1/2"-E… 11/09/13 12/09/13 1
68. RELLENO DE ZANJA C/TIERRA… 11/09/13 12/09/13 1
69. CAMARA DE REGISTRO (40X40… 11/09/13 12/09/13 1
70. TANQUE ELEVADO DURALIT (5… 12/09/13 13/09/13 1
71. ESTRUCTURA PORTANTE TAN… 10/09/13 11/09/13 1
72. PROVC. Y COLOCADO LLAVE … 12/09/13 13/09/13 1
73. PROV. COLOC. TEE DE 1/2" 12/09/13 13/09/13 1
74. PROV. COLOC. CODO DE 90º 1… 12/09/13 13/09/13 1
MODULO 6 : INSTALACION ELECT… 10/09/13 12/10/13 32
75. INST. ELECT. - ILUMINACION I… 11/10/13 12/10/13 1
76. INST. ELECT. ILUMIN. FLUORE… 10/09/13 11/09/13 1
77. INST. ELECT. - TOMACORRIEN… 10/09/13 11/09/13 1
78. TOMACORRIENTE DOBLE 10/09/13 11/09/13 1
79. INTERRUPTORES ELECTRICO… 11/09/13 12/09/13 1
80. TABLERO DE TERMICO (3 LINE… 12/09/13 13/09/13 1
81. INST. ELECT. CONEXION A TI… 12/09/13 13/09/13 1
82. TOMA FUERZA (CAJA + TERMI… 12/09/13 13/09/13 1
83. MEDIDORES + ACCESORIOS 12/09/13 13/09/13 1
84. IE-78 POSTE DE TENDIDO ELE… 13/09/13 14/09/13 1
85. CABLEADO # 10 15/09/13 16/09/13 1
MODULO 7 : LIMPIEZA GENERAL … 20/02/14 21/02/14 1
86. LIMPIEZA GENERAL DE LA OB… 20/02/14 21/02/14 1
CRONOGRAMA DE EJECUCIÓN DE LA OBRA
CONSTRUCCION MODULO POLICIAL SAN CRISTOBAL
NOMBRE DE LA ACTIVIDAD Comienzo Terminación Días Ago '13 Sep '13 Oct '13 Nov '13 Dic '13 Ene '14 Feb '14
Página 2