Compulsory Purchase and Utilities
Survey
Initial Results
CHARLES COWAP
RICS NATIONAL RURAL
CONFERENCE
CIRENCESTER
20 June ...
Background
• Much dissatisfaction with
compulsory purchase and utility
claims
• Evidence? Largely anecdotal
• Upper Tribun...
Upper Tribunal: what do we know?
• 1 January 2016 – 1 May 2018: 16 awards on compulsory purchase
• Of these
Topic Number
P...
A survey!
INITIAL FINDINGS FROM FIRST 40 RESPONSES
Please do your bit!
Who do respondents act for?
What promoters are we dealing with?
Statutory authority
Where?
Which stages?
Which elements of claim
Value:
• Total value where value given:
c. £56 million
• Average per value given
c. £1.6 million
• Range minimum
£5,000
• ...
Code of Practice issued?
Timescale
for payment
from
agreement
How did we rate each other?
Claimant satisfaction with process and payment
Comparison
with other
claims?
The good the bad
and the ugly
We can do better!
Please please keep them
coming …..
Contact Details
In-house CPD programmes, professional-technical updates, organisational
consultancy, and more:
 cdcowap@g...
Upcoming SlideShare
Loading in …5
×

of

Compulsory Purchase and Utilities Initial Survey Results Slide 1 Compulsory Purchase and Utilities Initial Survey Results Slide 2 Compulsory Purchase and Utilities Initial Survey Results Slide 3 Compulsory Purchase and Utilities Initial Survey Results Slide 4 Compulsory Purchase and Utilities Initial Survey Results Slide 5 Compulsory Purchase and Utilities Initial Survey Results Slide 6 Compulsory Purchase and Utilities Initial Survey Results Slide 7 Compulsory Purchase and Utilities Initial Survey Results Slide 8 Compulsory Purchase and Utilities Initial Survey Results Slide 9 Compulsory Purchase and Utilities Initial Survey Results Slide 10 Compulsory Purchase and Utilities Initial Survey Results Slide 11 Compulsory Purchase and Utilities Initial Survey Results Slide 12 Compulsory Purchase and Utilities Initial Survey Results Slide 13 Compulsory Purchase and Utilities Initial Survey Results Slide 14 Compulsory Purchase and Utilities Initial Survey Results Slide 15 Compulsory Purchase and Utilities Initial Survey Results Slide 16 Compulsory Purchase and Utilities Initial Survey Results Slide 17 Compulsory Purchase and Utilities Initial Survey Results Slide 18 Compulsory Purchase and Utilities Initial Survey Results Slide 19 Compulsory Purchase and Utilities Initial Survey Results Slide 20
Upcoming SlideShare
What to Upload to SlideShare
Next
Download to read offline and view in fullscreen.

2 Likes

Share

Download to read offline

Compulsory Purchase and Utilities Initial Survey Results

Download to read offline

Slides presented at the RICS National Rural Conference, Royal Agricultural University Cirencester on 20 June 2018

The survey remains open for further responses at https://www.surveymonkey.co.uk/r/7KDRHRJ

Related Books

Free with a 30 day trial from Scribd

See all

Compulsory Purchase and Utilities Initial Survey Results

  1. 1. Compulsory Purchase and Utilities Survey Initial Results CHARLES COWAP RICS NATIONAL RURAL CONFERENCE CIRENCESTER 20 June 2018
  2. 2. Background • Much dissatisfaction with compulsory purchase and utility claims • Evidence? Largely anecdotal • Upper Tribunal Lands Chamber • Not seen by UT as a problem • Few references • Simplified and written procedures available
  3. 3. Upper Tribunal: what do we know? • 1 January 2016 – 1 May 2018: 16 awards on compulsory purchase • Of these Topic Number Places of worship enfranchisement 2 Director remuneration 1 Application to strike out claim 1 Dispute over planning permission 1 Financial Awards included Number/Value Financial awards 12 Minimum award £2,500 Highest award £1.5 million Average award £275,175
  4. 4. A survey! INITIAL FINDINGS FROM FIRST 40 RESPONSES Please do your bit!
  5. 5. Who do respondents act for?
  6. 6. What promoters are we dealing with?
  7. 7. Statutory authority
  8. 8. Where?
  9. 9. Which stages?
  10. 10. Which elements of claim
  11. 11. Value: • Total value where value given: c. £56 million • Average per value given c. £1.6 million • Range minimum £5,000 • Range maximum £20 million +
  12. 12. Code of Practice issued?
  13. 13. Timescale for payment from agreement
  14. 14. How did we rate each other?
  15. 15. Claimant satisfaction with process and payment
  16. 16. Comparison with other claims?
  17. 17. The good the bad and the ugly
  18. 18. We can do better!
  19. 19. Please please keep them coming …..
  20. 20. Contact Details In-house CPD programmes, professional-technical updates, organisational consultancy, and more:  cdcowap@gmail.com  07947 706505 Twitter: @charlescowap Blog: http://charlescowap.wordpress.com/ Slideshare: http://www.slideshare.net/cdcowap Translating new knowledge for rural professional practice
  • AshleyDumont1

    Nov. 26, 2021
  • JessicaWard72

    Nov. 23, 2021

Slides presented at the RICS National Rural Conference, Royal Agricultural University Cirencester on 20 June 2018 The survey remains open for further responses at https://www.surveymonkey.co.uk/r/7KDRHRJ

Views

Total views

741

On Slideshare

0

From embeds

0

Number of embeds

490

Actions

Downloads

0

Shares

0

Comments

0

Likes

2

×