ECOtality ccse 10.04.10

  1. 1. • $230 million • 6 States & DC • Nissan Leaf / Chevy Volt • Approx. 8000 EVs • Over 15,000 EVSE
  2. 2. •EV Project in San Diego •EV Chargers •1000+ residential Level 2 EV chargers free for EV Project Participants •1,450 Publicly Available Level 2 EV chargers •60 Commercial DC Fast Chargers •Infrastructure Planning – 2010 Jan through Sept •Installations – November 2010 through June 2011 •Data collection – July 2011 through December 2012
  3. 3. •EV Project in San Diego (continued) •City permitting coordination •Permit processes •Requirements •Installations by professional contractor network managed by ECOtality
  4. 4. Charging Network

×