Tanggal Volume (m3) Ket PIC
14/10/19 34+650 - 34+900 397.50 L2 P. Burhan
15/10/19 34+400 - 34+650 397.50 L2 P. Burhan
16/10/19 34+900 - 35+150 397.50 L2 P. Burhan
17/10/19 35+150 - 35+400 397.50 L2 P. Burhan
18/10/19 34+650 - 34+900 375.00 L3 P. Burhan
19/10/19 34+400 - 34+650 375.00 L3 P. Burhan
20/10/19 34+900 - 35+150 375.00 L3 P. Burhan
21/10/19 35+150 - 35+400 375.00 L3 P. Burhan
22/10/19 34+650 - 34+900 375.00 L1 P. Burhan
23/10/19 34+400 - 34+650 375.00 L1 P. Burhan
24/10/19 34+900 - 35+150 375.00 L1 P. Burhan
25/10/19 35+150 - 35+400 375.00 L1 P. Burhan
27/10/19 34+650 - 34+900 397.50 R2 P. Burhan
28/10/19 34+400 - 34+650 397.50 R2 P. Burhan
29/10/19 34+950 - 35+200 397.50 R2 P. Burhan
30/10/19 35+150 - 35+400 397.50 R2 P. Burhan
31/10/19 34+650 - 34+900 375.00 R3 P. Burhan
6,555.00
KEBUTUHAN BETON RIGID PROYEK CCTW SEKSI 2 ZONA 2
TOTAL
PEKERJAAN PERKERASAN LEAN CONCRETE
Lokasi (Mainroad)
Bulan Oktober
STRIPMAAP PEKERJAAN RIGID PROYEK CCTW SEKSI 2 STA 27+070 - 50+373
34+350
34+400
34+450
34+500
34+550
34+600
34+650
34+700
34+750
34+800
34+850
34+900
34+950
35+000
35+050
35+100
35+150
35+200
35+250
35+300
35+350
35+400
L3 = 5 m
L2= 5.3 m
L1= 5 m
Barier Drain
L3 = 5 m
L2 = 5.3 m
L1 = 5 m
28/10/19 27/10/19 29/10/19 30/10/19
07/11/19
17/10/19Kiri
Kiri
05/11/19 04/11/19 06/11/19
01/11/19 31/10/19 02/11/19
19/10/19 18/10/19 20/10/19
STA / ZONA
ZONA 2
21/10/19
23/10/19 25/10/1922/10/19
03/11/19
24/10/19
15/10/19 14/10/19 16/10/19
STA 34+400 - 35+400 ( 1km)
Alat : Wirtgen
Sisi L : 14.10.19 S/d 25.10.19
Sisi R : 27.10.19 S/d 7.11.19
Panjang Per hari 250 m'
Volume rata-rata per hari 385.59 m3
Tanggal Volume (m3) Ket PIC
10/10/19 45+070 - 45+165 142.50 L3 P. Purba
10/10/19 45+680 - 45+760 120.00 L1 P. Purba
12/10/19 45+560 - 45+760 318.00 R2 P. Purba
13/10/19 45+360 - 45+560 318.00 R2 P. Purba
14/10/19 45+160 - 45+360 318.00 R2 P. Purba
15/10/19 45+060 - 45+160 159.00 R2 P. Purba
16/10/19 45+060 - 45+260 318.00 L2 P. Purba
17/10/19 45+260 - 45+460 318.00 L2 P. Purba
18/10/19 45+460 - 45+660 318.00 L2 P. Purba
19/10/19 45+660 - 45+760 159.00 L2 P. Purba
20/10/19 44+750 - 44+850 159.00 R2 P. Purba
20/10/19 44+750 - 44+850 159.00 L2 P. Purba
22/10/19 44+350 - 44+600 397.50 R2 P. Purba
23/10/19 44+350 - 44+600 397.50 L2 P. Purba
27/10/19 40+680 - 40+880 300.00 R3 P. Purba
28/10/19 40+880 - 41+145 397.50 R3 P. Purba
29/10/19 41+000 - 41+145 217.50 R1 P. Purba
30/10/19 41+280 - 41+375 142.50 R1 P. Purba
30/10/19 41+280 - 41+375 142.50 R3 P. Purba
4,801.50
KEBUTUHAN BETON RIGID PROYEK CCTW SEKSI 2 ZONA 3
Bulan Oktober
PEKERJAAN PERKERASAN LEAN CONCRETE
Lokasi (Mainroad)
TOTAL
STRIPMAAP PEKERJAAN RIGID PROYEK CCTW SEKSI 2 STA 27+070 - 50+37340+518
40+600
40+650
40+700
40+750
40+800
40+850
40+900
40+950
41+000
41+050
41+100
41+150
41+200
41+250
41+300
41+350
41+400
41+750
44+300
44+350
44+400
44+450
44+500
44+550
44+600
44+650
44+700
44+750
44+800
44+850
44+900
44+950
45+000
45+050
45+100
45+150
45+200
45+250
45+300
45+350
45+400
45+450
45+500
45+550
45+600
45+650
45+700
45+750
L3 = 5 m
L2= 5.3 m
L1= 5 m
Barier Drain
L3 = 5 m
L2 = 5.3 m
L1 = 5 m
Kanan
29/10/19 30/10/19
22/10/19 20/10/19 16/10/19
27/10/19 28/10/19 30/10/19
23/10/19 20/10/19 15/10/19 14/10/19 13/10/19 12/10/19
JPO44+304
OPJl.Desa44+874
10/10/19
UPJl.Desa45+767
10/10/19
17/10/19 18/10/19 19/10/19
STA / ZONA
ZONA 3
Kiri
BOX40+549
STA 44+950 - 45+750 (1575 m')
(10/10/2019 - 19/10/2019)
Alat : Wirtgen
Sisi L : 875 m'
Sisi R : 700 m'
Panjang Per hari 200 m
Volume Rata-Rata Per Hari 248,85 m3
STA 40+680 - 41+375 (700 m')
(27/10/2019 - 30/10/2019)
Alat : Wirtgen
Sisi L : m'
Sisi R : 790 m'
Panjang Per hari 200 m'
STA 44+350 - 44+900 (700 m')
(20/10/2019 - 23/10/2019)
Alat : Wirtgen
Sisi L : 350 m'
Sisi R : 350 m'
Panjang Per hari 200 m'
Tanggal
Panjang
(m')
Volume (m3) Ket PIC
14/10/19 48+690 - 48+390 300 450.00 L1 P. Acong
48+385 48+330 55 L1
48+330 48+630 300 L3
48+635 48+690 55 L3
48+690 48+390 300 R1
48+385 48+330 55 R1
48+330 48+630 300 R3
48+635 48+690 55 R3
48+690 48+390 300 L2
48+385 48+330 55 L2
48+330 48+630 300 R2
20/10/19 48+635 48+690 55 87.45 R2 P. Acong
22/10/19 47+080 47+260 180 270.00 L1 P. Acong
23/10/19 47+080 47+260 180 270.00 L3 P. Acong
24/10/19 47+080 47+260 180 270.00 R1 P. Acong
25/10/19 47+080 47+260 180 270.00 R3 P. Acong
26/10/19 47+080 47+260 180 286.20 L2 P. Acong
27/10/19 47+080 47+260 180 286.20 R2 P. Acong
28/10/19 47+355 47+445 90 135.00 L1 P. Acong
29/10/19 47+355 47+445 90 135.00 L3 P. Acong
31/10/19 47+355 47+445 90 143.10 L2 P. Acong
3,480 5,324.40TOTAL
18/10/19 559.50 P. Acong
19/10/19 564.45 P. Acong
16/10/19 532.50 P. Acong
17/10/19 532.50 P. Acong
KEBUTUHAN BETON RIGID PROYEK CCTW SEKSI 2 ZONA 4
Bulan Oktober
Lokasi (Mainroad)
15/10/19 532.50 P. Acong
46+935
46+950
47+000
47+050
47+100
47+150
47+200
47+250
47+300
47+350
47+400
47+450
47+500
47+550
47+600
47+650
47+700
47+750
47+800
47+850
47+900
47+950
48+000
48+050
48+100
48+150
48+200
48+250
48+300
48+350
48+400
48+450
48+500
48+550
48+600
48+650
Barier Drain
STRIMAP RENCANA RIGID ZONA 4 CCTW 2
25/10/19 17/10/19
31/10/19 18/10/19
22/10/19 28/10/19 14/10/19
Kanan
24/10/19 16/10/19
27/10/19 19/10/19
STA / ZONA
MAIN ROAD ZONA 4
Kiri
23/10/19 29/10/19 15/10/19
26/10/19
Sta 47+080 s.d 47+260 Sisi L & R
Alat : G n Z
Start : 22/10/19
Finsh : 27/10/19
Panjang Per Hari 150 m'
Sta 48+330 s.d 48+690 Sisi L & R
Alat : G n Z
Start : 14/10/19
Finish : 20/10/19
Panjang Per Hari 150 m'
12
2 3
34
4 5
56
76
Sta 47+355 s.d 47+445 Sisi R
Alat : G n Z
Start : 28/10/19
Finish : 31/10/19
Panjang Per Hari 50 m'

More Related Content

Featured

Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 

Featured (20)

AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
 
Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
 
12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work
 
ChatGPT webinar slides
ChatGPT webinar slidesChatGPT webinar slides
ChatGPT webinar slides
 
More than Just Lines on a Map: Best Practices for U.S Bike Routes
More than Just Lines on a Map: Best Practices for U.S Bike RoutesMore than Just Lines on a Map: Best Practices for U.S Bike Routes
More than Just Lines on a Map: Best Practices for U.S Bike Routes
 

Stripmap rencana rigid cctw 2.xlsx

  • 1. Tanggal Volume (m3) Ket PIC 14/10/19 34+650 - 34+900 397.50 L2 P. Burhan 15/10/19 34+400 - 34+650 397.50 L2 P. Burhan 16/10/19 34+900 - 35+150 397.50 L2 P. Burhan 17/10/19 35+150 - 35+400 397.50 L2 P. Burhan 18/10/19 34+650 - 34+900 375.00 L3 P. Burhan 19/10/19 34+400 - 34+650 375.00 L3 P. Burhan 20/10/19 34+900 - 35+150 375.00 L3 P. Burhan 21/10/19 35+150 - 35+400 375.00 L3 P. Burhan 22/10/19 34+650 - 34+900 375.00 L1 P. Burhan 23/10/19 34+400 - 34+650 375.00 L1 P. Burhan 24/10/19 34+900 - 35+150 375.00 L1 P. Burhan 25/10/19 35+150 - 35+400 375.00 L1 P. Burhan 27/10/19 34+650 - 34+900 397.50 R2 P. Burhan 28/10/19 34+400 - 34+650 397.50 R2 P. Burhan 29/10/19 34+950 - 35+200 397.50 R2 P. Burhan 30/10/19 35+150 - 35+400 397.50 R2 P. Burhan 31/10/19 34+650 - 34+900 375.00 R3 P. Burhan 6,555.00 KEBUTUHAN BETON RIGID PROYEK CCTW SEKSI 2 ZONA 2 TOTAL PEKERJAAN PERKERASAN LEAN CONCRETE Lokasi (Mainroad) Bulan Oktober
  • 2. STRIPMAAP PEKERJAAN RIGID PROYEK CCTW SEKSI 2 STA 27+070 - 50+373 34+350 34+400 34+450 34+500 34+550 34+600 34+650 34+700 34+750 34+800 34+850 34+900 34+950 35+000 35+050 35+100 35+150 35+200 35+250 35+300 35+350 35+400 L3 = 5 m L2= 5.3 m L1= 5 m Barier Drain L3 = 5 m L2 = 5.3 m L1 = 5 m 28/10/19 27/10/19 29/10/19 30/10/19 07/11/19 17/10/19Kiri Kiri 05/11/19 04/11/19 06/11/19 01/11/19 31/10/19 02/11/19 19/10/19 18/10/19 20/10/19 STA / ZONA ZONA 2 21/10/19 23/10/19 25/10/1922/10/19 03/11/19 24/10/19 15/10/19 14/10/19 16/10/19 STA 34+400 - 35+400 ( 1km) Alat : Wirtgen Sisi L : 14.10.19 S/d 25.10.19 Sisi R : 27.10.19 S/d 7.11.19 Panjang Per hari 250 m' Volume rata-rata per hari 385.59 m3
  • 3. Tanggal Volume (m3) Ket PIC 10/10/19 45+070 - 45+165 142.50 L3 P. Purba 10/10/19 45+680 - 45+760 120.00 L1 P. Purba 12/10/19 45+560 - 45+760 318.00 R2 P. Purba 13/10/19 45+360 - 45+560 318.00 R2 P. Purba 14/10/19 45+160 - 45+360 318.00 R2 P. Purba 15/10/19 45+060 - 45+160 159.00 R2 P. Purba 16/10/19 45+060 - 45+260 318.00 L2 P. Purba 17/10/19 45+260 - 45+460 318.00 L2 P. Purba 18/10/19 45+460 - 45+660 318.00 L2 P. Purba 19/10/19 45+660 - 45+760 159.00 L2 P. Purba 20/10/19 44+750 - 44+850 159.00 R2 P. Purba 20/10/19 44+750 - 44+850 159.00 L2 P. Purba 22/10/19 44+350 - 44+600 397.50 R2 P. Purba 23/10/19 44+350 - 44+600 397.50 L2 P. Purba 27/10/19 40+680 - 40+880 300.00 R3 P. Purba 28/10/19 40+880 - 41+145 397.50 R3 P. Purba 29/10/19 41+000 - 41+145 217.50 R1 P. Purba 30/10/19 41+280 - 41+375 142.50 R1 P. Purba 30/10/19 41+280 - 41+375 142.50 R3 P. Purba 4,801.50 KEBUTUHAN BETON RIGID PROYEK CCTW SEKSI 2 ZONA 3 Bulan Oktober PEKERJAAN PERKERASAN LEAN CONCRETE Lokasi (Mainroad) TOTAL
  • 4. STRIPMAAP PEKERJAAN RIGID PROYEK CCTW SEKSI 2 STA 27+070 - 50+37340+518 40+600 40+650 40+700 40+750 40+800 40+850 40+900 40+950 41+000 41+050 41+100 41+150 41+200 41+250 41+300 41+350 41+400 41+750 44+300 44+350 44+400 44+450 44+500 44+550 44+600 44+650 44+700 44+750 44+800 44+850 44+900 44+950 45+000 45+050 45+100 45+150 45+200 45+250 45+300 45+350 45+400 45+450 45+500 45+550 45+600 45+650 45+700 45+750 L3 = 5 m L2= 5.3 m L1= 5 m Barier Drain L3 = 5 m L2 = 5.3 m L1 = 5 m Kanan 29/10/19 30/10/19 22/10/19 20/10/19 16/10/19 27/10/19 28/10/19 30/10/19 23/10/19 20/10/19 15/10/19 14/10/19 13/10/19 12/10/19 JPO44+304 OPJl.Desa44+874 10/10/19 UPJl.Desa45+767 10/10/19 17/10/19 18/10/19 19/10/19 STA / ZONA ZONA 3 Kiri BOX40+549 STA 44+950 - 45+750 (1575 m') (10/10/2019 - 19/10/2019) Alat : Wirtgen Sisi L : 875 m' Sisi R : 700 m' Panjang Per hari 200 m Volume Rata-Rata Per Hari 248,85 m3 STA 40+680 - 41+375 (700 m') (27/10/2019 - 30/10/2019) Alat : Wirtgen Sisi L : m' Sisi R : 790 m' Panjang Per hari 200 m' STA 44+350 - 44+900 (700 m') (20/10/2019 - 23/10/2019) Alat : Wirtgen Sisi L : 350 m' Sisi R : 350 m' Panjang Per hari 200 m'
  • 5. Tanggal Panjang (m') Volume (m3) Ket PIC 14/10/19 48+690 - 48+390 300 450.00 L1 P. Acong 48+385 48+330 55 L1 48+330 48+630 300 L3 48+635 48+690 55 L3 48+690 48+390 300 R1 48+385 48+330 55 R1 48+330 48+630 300 R3 48+635 48+690 55 R3 48+690 48+390 300 L2 48+385 48+330 55 L2 48+330 48+630 300 R2 20/10/19 48+635 48+690 55 87.45 R2 P. Acong 22/10/19 47+080 47+260 180 270.00 L1 P. Acong 23/10/19 47+080 47+260 180 270.00 L3 P. Acong 24/10/19 47+080 47+260 180 270.00 R1 P. Acong 25/10/19 47+080 47+260 180 270.00 R3 P. Acong 26/10/19 47+080 47+260 180 286.20 L2 P. Acong 27/10/19 47+080 47+260 180 286.20 R2 P. Acong 28/10/19 47+355 47+445 90 135.00 L1 P. Acong 29/10/19 47+355 47+445 90 135.00 L3 P. Acong 31/10/19 47+355 47+445 90 143.10 L2 P. Acong 3,480 5,324.40TOTAL 18/10/19 559.50 P. Acong 19/10/19 564.45 P. Acong 16/10/19 532.50 P. Acong 17/10/19 532.50 P. Acong KEBUTUHAN BETON RIGID PROYEK CCTW SEKSI 2 ZONA 4 Bulan Oktober Lokasi (Mainroad) 15/10/19 532.50 P. Acong
  • 6. 46+935 46+950 47+000 47+050 47+100 47+150 47+200 47+250 47+300 47+350 47+400 47+450 47+500 47+550 47+600 47+650 47+700 47+750 47+800 47+850 47+900 47+950 48+000 48+050 48+100 48+150 48+200 48+250 48+300 48+350 48+400 48+450 48+500 48+550 48+600 48+650 Barier Drain STRIMAP RENCANA RIGID ZONA 4 CCTW 2 25/10/19 17/10/19 31/10/19 18/10/19 22/10/19 28/10/19 14/10/19 Kanan 24/10/19 16/10/19 27/10/19 19/10/19 STA / ZONA MAIN ROAD ZONA 4 Kiri 23/10/19 29/10/19 15/10/19 26/10/19 Sta 47+080 s.d 47+260 Sisi L & R Alat : G n Z Start : 22/10/19 Finsh : 27/10/19 Panjang Per Hari 150 m' Sta 48+330 s.d 48+690 Sisi L & R Alat : G n Z Start : 14/10/19 Finish : 20/10/19 Panjang Per Hari 150 m' 12 2 3 34 4 5 56 76 Sta 47+355 s.d 47+445 Sisi R Alat : G n Z Start : 28/10/19 Finish : 31/10/19 Panjang Per Hari 50 m'