SlideShare a Scribd company logo
1 of 29
Red Zuma Project
RED ZUMA PROJECT- Bucher
RED ZUMA PROJECT
(PARTS 1 and 2)
Brian J. Bucher
Liberty University
BUSI-313-B02
June 5, 2017
Bachelors of Science in Business Administration: Leadership
APA Style
RED ZUMA PROJECT MEMO
1. When is the project estimated to be completed? How long
will the project take?
The project is estimated to be completed on 1/11/16. The
project will take 260 working days.
2. What is the critical path for the project?
The critical path is shown in red on the Gantt chart below. The
tasks in the critical path are 1.1, 1.2, 1.4, 1.7, 1.8, 1.10, 1.11,
1.12, 1.14, 1.15, & 1.16.
3. Which activity has the greatest amount of slack?
The activity has the greatest amount of slack is task 1.5
Detailed Marketing Plan with a total of 179 days of slack.
4. How sensitive is this network?
The project is not sensitive because the activities that are not on
the critical paths have a lot of slack and there is only one
critical path.
5. Identify two sensible milestones and explain your choices.
Build Prototypes is most important milestones because
based on that then worker know what to build.
Install Production Equipment is also important milestones
because if they install something that is not supposed to be
installed then project gets delay and it will be over budget.
GANTT CHART
NETWORK DIAGRAM (With Critical Path)
SCHEDULE TABLE WITH SLACK
PART 2A MEMO
1. Which if any of the resources are over allocated?
Marketing Specialist, Design Engineer and Industrial Engineer.
2. Assume that the project is time constrained and try to resolve
any over allocation problems by leveling within slack. What
happens?
When I leveled the slack it removed the over allocation off of
the Detailed Marking Plan, but it did not resolve all over
allocations. It also reduced the number of slack days on the
Manufacturing study by 10 days to 0 days. It also reduced the
179 days of slack on the Details Marketing Plan to 134 days.
The Manufacturing Process went from 55 days to 10 days and
the Lab Test Prototypes went from 5 to 0 days. The Order
Components task did not change and stayed at 27 days of slack.
3. What is the impact of leveling within slack on the sensitivity
of the network?
(Include a Gantt chart with the schedule table after leveling
within slack).
The Red Zuma project schedule changed with the leveling
because it added in multiple paths as well as reducing the
overall slack days.
GANTT CHART Leveling within Slack
GANTT CHART Free and Total Slack
4. Assume that the project is resource constrained and no
additional personnel are available. How long will the project
take given the resources assigned? (Hint: Undo leveling
performed in Part A before answering this question.)
With no additional personnel added, the project timeline will
need to increase to 310 days with a new finish date of
03/21/2016.
5. How does the new duration compare with the estimated
completion date generated from Part 1? What does this tell you
about the impact resources can have on a schedule?
The new date is 2 months past the original completion date and
added 50 work days to the schedule. Having the required
resources is critical to completing each step of a project on
schedule. Major delays will happen if they are not allocated
properly at the start of the project.
GANTT CHART with ACTUAL TIMELINE
PART 2B MEMO
1. What was the impact of introducing Start-to-Start lags to the
schedule and budget?
By introducing start-to-start lag into the schedule and budget, it
would shorten the overall duration of the project but it
increased the budget to support the additional requirements.
2. Which, if any additional personnel assignments, would you
choose to complete the project before the January 17th
deadline? Explain your choices as well as the reasons for not
choosing other options.
The need for additional Industrial Engineers is necessary to
complete multiple project steps on time. All other resources
have additional capacity to complete their workload within the
established timeline.
3. How have these changes affected the sensitivity of the
network and the critical path?
With the additional resources the critical path will be able to
flow without delays and will be very insensitive overall.
GANTT CHART WITH FREE AND TOTAL SLACK
Include a Gantt chart with a schedule table displaying free and
total slack for the new schedule.
Note: Do not assign new personnel to specific tasks, simply add
them to the Resource Sheet. All new personnel are available full
time (100%).
The non-adoption of best/accepted/promising practices in
projects
towards a theory of complicity
Share
CONFERENCE PAPER16 July 2008
Maylor, Harvey | Brady, Tim | Thomas, Janice
How to cite this article:
Maylor, H., Brady, T., & Thomas, J. (2008). The non-adoption
of best/accepted/promising practices in projects: towards a
theory of complicity. Paper presented at PMI® Research
Conference: Defining the Future of Project Management,
Warsaw, Poland. Newtown Square, PA: Project Management
Institute.
TIM BRADY, PHD
CENTRIM, University of Brighton, United Kingdom
JANICE THOMAS
Athabasca University, Calgary, Canada
Introduction
This paper describes an observed phenomenon: the non-
adoption of best / accepted / promising practices in a particular
project setting.
During data gathering for a project to determine the value of
project management1 we visited organizations and conducted
in-depth interviews. We observed the phenomenon of non-
adoption of best practice, even good practice, and collected data
that would help us understand why this was so. It was observed
in a case that a prime customer (major government department)
was accepting poor levels of performance from a major supplier.
After many years of accepting this poor performance, a crisis
point was reached when pressure from outside forced both
parties to recognize the situation. This threatened the very
existence of the program. So, a series of actions was undertaken
to address the situation. Analysis of the case made little sense;
following the reforms, the supplier was being highly complacent
about their performance, and the customer was simply
concerned with keeping the project out of the press and ‘below-
the-radar'. The costs to both the supplier and the customer were
considerable, yet they were both talking about the project as a
good news story. For this to happen, the firm would have had to
adopt a much greater range of accepted practices. Similarly,
there was no sense of following fashion here: Indeed, there was
considerable knowledge of such practices elsewhere in the
organization, and these were conspicuous by their absence.
However, they continued with a very low level of development
of their project management processes. Our case findings show
that rather than making positive choices to implement or test
process innovations, individuals were able to decide not to
pursue particular approaches, regardless of the potential
(economic) benefits to the organization.
The phenomenon is certainly not unique but there are particular
circumstances with the case being investigated that highlighted
its occurrence. Further, it is not restricted to project
environments; though it is worth investigating whether there is
something particular about project environments that allow such
behavior to flourish.
A challenge for management academics and practitioners is the
non-adoption of what organizations and individuals term
as best, accepted, or even promising practices (Leseure, Bauer,
Birdi, Neely, & Denyer, 2004). Often encouraged by
governments in search of better economic performance (e.g.,
AIM initiative in the United Kingdom [UK]) or customers
(usually large organizations as part of their supplier
development activities), organizations will assimilate processes
or approaches that are new to them. Past examples of processes
that organizations have adopted include Total Quality
Management, Business Process Reengineering, Lean, and Agile.
These represent a normalization of practices; one persistent
criticism of the project management literature is that it
encourages such normalization. In actuality, it is clear that there
are many project management practices (now classified
as accepted practices) that could be used beneficially. This
includes those practices that are not being used by individuals
or organizations. Such a lack of adoption and application of
existing project management knowledge remains a challenge for
such theories of normalization and, in many cases, represents a
missed opportunity for organizations attempting to continually
improve their performance.
There are two significant views about the adoption of particular
practices (Robertson, Swan, & Newell, 1996). The first comes
from rational choice theory, which proposes that managers are
predominantly rational adopters who make technically efficient
choices, and hence, are driven by economic rationality and
institutional theory, which proposes that managers
predominantly respond to institutional mechanisms that may
lead them to choose practices that are technically inefficient and
driven by normative rationality. Such a normative rationality
may include conformance to fads and fashions (Abrahamson,
1996).
This paper considers this issue in the context of organizations
and projects where there is a low rate of adopting existing tools
and techniques, and which, because of this, leads to observably
poor project performance. This issue is not easily explained by
the existing theory. So, this paper begins with a practical
question:
If a practice appears to yield benefits for an organization, why
is it not adopted?
By taking a critical perspective and exploring the power
dynamics at work in organizations, we lay the groundwork for
an explanation of complicity theory, a view which sees
organizational members as actively and passively serving as
accomplices in acts of questionable value to the organization.
Methodology
Drawing from a recent study and data collection activity, we
attempt to explain common behavior on the part of otherwise
seemingly reasonable individuals who either fail to support or
actively suppress the adoption of practices that are commonly
recognized as important to the success of projects. We start by
describing the study we draw from; then we explore other meta
theoretical lenses that serve to clarify the motivation for this
behavior.
A grounded case study research (Eisenhardt, 1989, 1991) was
appropriate for advancing theory about social processes (Hallier
& Forbes, 2004; Strauss & Corbin, 2002). A case-based
methodology was used for in-depth interviews with 12
management and project-related staff, for further interviews
with the client organization, and for a survey of 21 managers
connected to the project. However, the methodology differs
from mainstream research: The researchers did not start with a
particularly theoretical lens. The phenomenon observed was not
expected and therefore presents the opportunity for multi-
paradigmatic analysis to be undertaken (Schultz & Hatch,
1996).
The Observed Phenomenon
The project studied was to design, develop, and eventually,
manufacture a new piece of military hardware. From its outset
in 1996, it was the subject to continual slippage and cost
escalation. Just two years into the project, the contractor
informed the client that it was unlikely to meet timescales; a
revised in-service date was agreed for March 2005. There
followed a series of renegotiations of the contract terms as both
sides revised their expectations for the project and introduced
new approaches. By May 2002, for example, a new incremental
approach to product delivery was adopted which reflected a
revised assessment of operations requirements. By the end of
the year, the contractor disclosed further slippage in both the
budget and the schedule. These slippages were related to the
contractor's underestimation of the project's technology risks,
an underestimation which placed the project team under severe
cost-related pressures which required further contract
negotiations. The first full product test date was moved back
from mid-2002 to late-2002, then to the second half of 2003.
The situation failed to improve, despite a plethora of advice
resulting from 11 separate reviews, which presented 255 issues
to the management team.
According to the project's independent auditors:
Difficulties on (XXX) stem from ‘the design challenge being
hugely underestimated by industry, perhaps as a result of
continuing to see the project as if it were the adaptation of an
existing [product], as it was originally intended to be, when in
fact 95% of the [product] is new.
Against the background of the fixed price contract, the
consequent cost pressure and financial losses provided little
incentive on (the contractor) to deliver. These difficulties were
compounded by a weak programme management culture which
lacked transparency, neglected or overrode project control
systems and disciplines, and produced forecasts that lacked
depth and reality. The [client's] oversight and influence was
also restricted by the limited access and insight provided by the
fixed price contract
This threw the project into complete crisis, and in 2003, the two
parties agreed, in effect, to create a new agreement which
accepted the slippage, which by then, totaled 71 months. They
agreed to share the costs between the two parties. Then new,
revised milestones were introduced: First complete test, June
2004; award of manufacturing contract, late-2005; in-service
date, 2009.
Evidence of practices within the organization prior to 2003
included the following comment from one of the interviewees
that:
The client was worried about performance. The company was
worried about cost. No-one worried about schedule.
Given the continuing delays, this was to key to the idea that
there was a kind of collusion here, that each party trying to
protect their own interests, while missing one of the major
issues that was central to the overall success of the project.
Similarly, much mention was made of the prevailing technical
culture, where the focus was on achieving technical excellence
rather than meeting the needs of a business case. For instance,
another interviewee commented:
We had basic [project management] mechanisms but the
‘culture’ was not there. I was fairly typical of managers who
were not concerned with business case – just did numbers to
save getting [email protected]:?>< by the boss... We used to aim
to surpass customers’ expectations – regardless of whether he
wanted the features and the gold-plating.
This culminated in the organization being described as:
It was a terrible place to work – there was fear, the project was
a dead-duck and morale was very low.
And another:
The programme was out of control—people weren't being true
to each other about what could be achieved—either in our own
organisation or the customer's organisation. We both wanted to
understand that—that was as much of a driver as the
performance itself.
The organization responded by slowing progress further by
initiating no fewer than 11 separate audits and reviews of the
project which required over 170 high-level actions for
management.
As a result of the restructuring of the contract, the development,
manufacture, and service contracts were separated out and
project reforms were introduced. These project reforms
included:
· Allowing the client organization fuller access to industry
schedule, cost, and programmed data; allowing the co-location
of staff at both the manufacturing and operational bases.
· The introduction of anchor milestones—targets that when
achieved provide assurance that the in-service date or other
contractual obligation will be met—to incentivize reform of
project control systems.
· A joint risk register was introduced.
· Three-point estimates would be jointly calculated to measure
confidence levels in the time and cost estimates for various
elements of the program.
· Financial data on the development and production activities
would be reviewed on a monthly basis, at a joint meeting
between the contractor and the client.
· Earned value management (EVM) would be used to measure
and communicate progress and achievement against costs and
provide confidence in the quality of anchor milestone elements.
The focus would be on measuring outcomes achieved rather than
effort expended.
These reforms were, according to company documentation,
‘embedded in a robust and open partnering approach that raises
access, information, communication and behaviors with a
greater emphasis on delivery, cost minimization and schedule
adherence.’ One manager stated the benefits of this as:
We now have control and predictability and can understand
cause and effect in the schedule. The customer particularly likes
that. We used to be cheesed off about his requirements
constantly changing. It [the new approach] reduces flexibility
but now easier as you can show the effects of particular
changes. Plan becomes a heuristic tool as there are knock-on
effects.
In addition, the organization put in place a behavioral
program—one aiming to legitimize and professionalize project
management—as well as a leadership development program and
partnering development program.
However, the changes were relatively straightforward. One
manager commented:
Our objective was very simple—we needed conformance to a
fairly basic level of proceduralisation.
Within the contractor company, the reform program is held up
as a great success. The project is now seen as
exemplifying good or best practice throughout the parent
organization. A prime outcome of the reforms is that the
program is no longer under threat of closure. The company
retained the business and the project now has fallen below the
client's radar. The relationship with the customer is much
better. Planning disciplines have been implemented. People
working on the project appear motivated and confident in both
the product and the new processes.
However, below the surface, there is very little critique of what
has been achieved in comparison to external benchmarks.
During our research, we found very low levels of knowledge
and certification in the firm. Management qualifications were
not recognized: There was only one MBA, although the
contractor intended to change this. The customer was similarly
unknowledgeable. In terms of project management maturity,
they have moved from chaotic to the use of some basic
processes. More surprising, there is no desire or requirement for
ongoing improvement:
I don't believe we'll move the bar much beyond where it has
gone already.
We won't spend any more money on comparing a good
programme with a bad programme – we'll send them out into the
hinterland as disciples and bring in more junior people to train
up. (Project Director).
Despite the reforms, the project showed continued slippage in
schedule and cost performance, albeit at a slower rate than
before.
The complicity that was stagnating performance was well
established in the organization again. Data from the 21 project
managers surveyed showed that:
· Fifteen of the 21 agreed, and 1 strongly agreed, with the
statement that they were well trained (5 neutral).
· Fourteen of the 21 agreed, and 2 strongly agreed, with the
statement that they had suitable education to fulfill their jobs (5
neutral).
· Three strongly agreed, and 12 agreed, that management
provides advanced development and training programs for
organizational members.
This is despite the fact that there was not a single recognized
qualification among the 180 project office staff. We interpret
this difference as a form of collusion. Further, this was
reflected in the views of the organizational project management
capability:
· Fourteen of the 21 agreed, and 2 strongly agreed, with the
statement that the organization is viewed as having a very
strong management capability (3 neutral and 2 disagreed).
· Eleven agreed, and 7 strongly agreed, that the organization
had very high project management standards.
· Fifteen agreed, and 2 strongly agreed, that this organization
has superior project management practices.
The benchmark here was taken as knowledge of the bodies of
knowledge (APM/PMI). Not one of the interviewees
demonstrated such knowledge. The last statement provides
another interesting contrast with the performance that the
project was again demonstrating. On the subject of
performance:
· Only 5 agreed that the project management practices of the
organization consistently exceed expectations (15 neutral and 2
disagreed).
The self delusion is evidenced by:
· Eight agreed, and 2 strongly agreed, with the statement that
‘Projects in this organization are more successful than in other
organizations I know’ (9 neutral and 2 disagree).
· Twelve agreed, and 5 strongly agreed, that the organization
delivered high quality products and services.
· Twelve agreed, and 2 strongly agreed, that projects were
successfully delivered.
· Twelve agreed (5 neutral, 4 disagreed) that projects managed
by the organization consistently deliver on their objectives.
However, when broken down, we see that this was mostly in
terms of technical specifications:
· Two strongly agreed and 11 agreed that projects achieved
their technical objectives.
Whereas:
· Only 5 agreed that they met their schedule objectives (10
disagreed and 1 strongly disagreed).
· Nine disagreed, and 1 strongly disagreed, that they met
budget objectives.
In relation to their opinion of the clients’ view of projects:
· Eleven agreed, and 10 were neutral, in relation to the
statement: Clients are consistently satisfied by the process by
which projects are managed.
While the question of who is the client can here be argued, the
client themselves had no reason to be satisfied with a
renegotiated and very late project that was continuing to slip,
albeit at a slower rate than before.
Overall, what we witnessed was a complicity between the client
and the contractor (just stay out of the press), propped up by
complicity within the contracting organization (it is a good
news story), and complicity in the project team (we are well
qualified, knowledgeable, and doing well). The result is that
poor processes and poor performance were allowed to continue
with no obvious vector for improvement.
Can the Theory Help Explain This?
There are several theoretical approaches which might explain
this observed phenomenon, including innovation diffusion
theory, institutional theory, the fads and fashions literature,
rational choice theory, and organizational learning.
Innovation Diffusion Theory
Diffusion theory concerns the role adopted by different actors:
early adopters or laggards (Rogers, 1983). The first phase of the
diffusion of innovative practice sees it adopted by a relatively
few innovators, the early adopters. Once the efficacy of the
practice is demonstrated by these early adopters, it is taken up
by other organizations, and so it diffuses more generally over
time, until it becomes standard practice. What we have observed
above does not seem to fit easily with this, in that it is more
about many years in avoiding the use of good practices that had
already diffused widely into other project settings. In order for
new practices to be adopted, these must first be found in some
kind of search activity. It appears that there was little attempt to
find a better practice until the major crisis in 2003, where the
threat of program closure forced the contractor to seek
alternatives. Once these were implemented, however, there was
no further change. Perhaps the case organization could simply
be viewed as laggards, but this is not necessarily helpful in
explaining the full range of behaviors.
Institutional theory would suggest that organizations in the
same industry exhibit isomorphism: They will adopt similar
working practices (DiMaggio & Powell, 1983). On the one
hand, diffusing practices seen as best practice takes place
encouraged by the legitimacy argument. The introduction of
earned value (EV) by the project organization was legitimized
by the widespread and successful use of the technique in the
company's United States (US) business. Furthermore, a new
manager was appointed to oversee the changes. This individual
had previously worked in the US business. On the other hand,
the benefits achieved by the adoption of successful practice may
inhibit the adoption of superior practices in the future (Arthur,
1989). In this case, the non-adoption of superior practice in the
future is not so much a result of the successful adoption of the
EV technique but more a deliberate strategy not to go beyond
what has already been achieved.
At the level of the organization, some practices become
institutionalized as rules (i.e., the way we do things around
here). Such practices become embedded and are very resistant to
change (Oliver, 1992). It appears that the new good practice has
become institutionalized as a rule in the organization, and
hence, it will be hard to change it in the future.
Rational Choice
Rational choice approaches to the adoption of new practices and
their impact on performance include the behavioral theory of
the firm (Cyert & March, 1963; March & Simon, 1967) and
evolutionary economics (Nelson & Winter, 1982). These
suggest that the primary driver for organizational innovations is
the identification of performance gaps. When a firm's actual
performance drops below its desired performance level, its
performance is determined either by past performance and
internal targets (Lant & Mezias, 1992) or by comparison to an
external reference group (Massini, Lewin, & Greve, 2005). This
performance gap will lead managers to search for new practices
to improve performance. Once the new practice has been
adopted and put into use, managers will compare before-and-
after performance to determine whether it should be retained or
discarded. Thus, rational choice presents the identification,
selection, evaluation, and retention or discarding of
management practices as relatively straightforward for
managers, who should thus be viewed as rational actors
searching for new practices to maintain or improve
organizational performance.
This clearly has not happened, except when forced in a one-step
change. The project was performing poorly for many years
before any change was implemented. (Problems were identified
beginning in 1998 through to the final melt-down in 2003.)
Furthermore, despite the opportunity for further improvement,
no improvements were realized.
The Institutional Approach
An alternate perspective to rational choice is the institutional
approach, which derives from sociology, and shifts the main
focus of attention from rational choice and technical efficiency
to pressures from the organization's external environment
(DiMaggio & Powell, 1983). The institutional approach views
all economic activity as embedded in social contexts. While
firms may aspire to rational solutions to performance gaps,
because of the uncertainty involved in competing practices and
performance outcomes, or the alternative practices that might
plausibly achieve the same outcomes, firms may be uncertain
about how to achieve rational solutions. Managers instead
appear as rational and progressive, according to norms of
rationality (March & Olsen, 1976), they will tend to adopt
institutionalized organizational practices, such as those taken-
for-granted as the most appropriate means of improving
performance, and hence perceive these as legitimate by key
institutional actors (Abrahamson, 1996).
From an institutional perspective, the explanations
accompanying the adoption of a new practice become important
because explaining how the practice helps managers achieve the
desired performance outcomes legitimizes the practice (Green,
2004). It is also essential to constructing certain practices as
taken-for-granted (Green, 2004; Suddaby & Greenwood, 2005).
Hence, a focus on managerial discourse often accompanies an
institutional analysis of diffusion and adoption of management
innovations. The management fashion perspective (Abrahamson,
1991; Abrahamson, 1996; Abrahamson & Fairchild, 1999;
Strang & Macy, 2001; Strang & Still, 2004) focuses particularly
on the role of rhetoric and social networks in the diffusion of
new practices, and the presence of bandwagons, or the number
of adopters (Abrahamson & Rosenkopf, 1997). Managers must,
therefore, heed key institutional actors, including consulting
firms, management gurus, business mass-media publications,
and business schools, each who provide important sources of
information for managers about what other firms are doing.
Institutional theory further specifies that the diffusion and
adoption of management practices will be influenced by
mimetic, coercive, and normative pressures from the external
environment (Scott, 2001) to adopt certain practices. Mimetic
pressures are pressures for firms to imitate the practices of
other, usually successful, firms; coercive pressures are
pressures to avoid sanctions from regulatory agencies and other
institutional actors; normative pressures are pressures to
conform to perceived professional norms. Institutional actors
are thus important in driving the diffusion and adoption of
management practices (Paauwe & Boselie, 2005) and there are
strong sanctions associated with failing to adopt certain
practices (Nelson, Peterhansl, & Sampat, 2004). However,
diffusion and adoption is not only a social process, since
technical, economic, and socio-psychological forces jointly
shape the demand for new practices, and diffusion and adoption
of practice is ultimately driven by the need to respond to
organizational performance gaps.
In this case, the focus of the theory is on adoption of practices,
rather than explaining non-adoption as we have seen here. For
instance, while there has clearly been a project management
bandwagon, the case organization have taken conscious
decisions to ignore it.
The Organizational Learning Approach
Another perspective is provided by the organizational learning
literature which accepts that organizational issues create
barriers to learning and improvement. We would suggest that
this perspective is the most useful to help us understand the
case presented above. In particular we draw on the concept of
defensive routines (Argyris, 1993) to explain the non-adoption
of promising practices from elsewhere. Organizational
defensive routines exist in both private and governmental
organizations, but few studies have been undertaken about how
to overcome these (Argyris, 1993, p.242). Those few that do
offer advice seem to suggest either bypassing the defensive
routines and covering up the bypass or else acting in ways that
actually strengthen the routines rather than get rid of them.
An organizational defensive routine is any policy or action that
inhibits individuals, groups, inter-groups or organisations from
experiencing embarrassment or threat and at the same time
prevents the actors from identifying the causes of
embarrassment or threat. Organizational defensive routines are
antilearning and over-protective. (Argyris, 1993, p. 15)
The immediate effect of such policies, practices, and behaviors
is to inhibit the detection and correction of error. A second-
order effect is to inhibit problem solving and decision making.
The third order effect is less effective organizational
performance.
The case above can be seen as a clear example of this. Despite
the embarrassment of continually being over budget and late on
schedule, the situation was allowed to continue for many years
because the organization refused to experience the
embarrassment. The refusal to become embarrassed by the poor
performance led both sides to ignore the signals. There was
complicity in this. This refusal to accept the obvious inhibited
problem solving and decision making. Better to turn a blind eye
than to see the problem because then something would have to
be done about it. Better not to hear the news that things were
going badly. Managers commented:
The Company didn't ask questions because it didn't want the
answers.
In a programme that on day 1 was going to fail, the culture was
‘don't want to hear bad news.’
In a study of defensive routines in government, Argyris (1993)
observed that “neither the official policies nor the
administrator's espoused values was there encouragement to
deceive, to manipulate, or to distort information. Nevertheless,
the actions were robust; they appeared in spite of (and even
because of) their deviancy from ideas in good currency on how
to administer governmental agencies” (p. 19).
In a similar way, neither the policies nor the espoused values of
the employees and managers in the company we studied
encouraged them to actively deceive, manipulate, or distort
information. They simply ignored the information coming from
external assessment (e.g., the auditor's reports). Their denial
was robust.
According to Argyris (1993), organizational defensive routines
are caused by a circular, self-reinforcing process in which
individuals’ theories in use produce individual strategies of
bypass and cover-up, which reinforce the individuals’ theories
in use. Thus the explanation for organizational defensive
routines is both individual and organizational. This means that
it is necessary to change both organizational and individual
routines to achieve sustained change of behavior. The reform
programs that the company undertook addressed this by creating
a standardized approach to project management in the program
so that all individuals operated in the same way and to the same
norms. Our interviews confirmed this; individuals were pleased
to adopt the new practices, as they could see benefit from these
and their theories in use became closer to the espoused theories
in the new situation.
Towards a Theory of Complicity
We found that when the behavior exhibited was not explained
by innovation diffusion theory, the outcome was counter-
rational; and it was not following the path that a fad and fashion
would lead us to expect. We obtained a partial explanation for
this by examining the construction and usage of defensive
routines as barriers to organizational learning. This partial
explanation is not satisfactory because it does not address their
causes. Therefore, for both theoretical and practical purposes,
some further explanation is required.
The data provides evidence of complicity in the performance
and rate of change at multiple levels: Between the client and the
contracting organization, between the organization and the
project, and within the project hierarchy. This complicity is
causal to the failure to remove defensive routines. During the
transition phase in 2003, complicity was removed at all levels,
and process improvement took place. Complicity was then re-
established and no further changes were made. The proposition
we derive is this:
Processes and practices will remain within the defensive
routines of the organisation where there is complicity for them
to do so.
Further, we posit that:
Complicity is an active state achieved where the parties to the
complicity collude to allow it to be so.
This is evidenced by the positive statements supporting no
change that were made during each of the complicity states
(pre- and post-2003).
With these propositions in mind, it is appropriate to see if they
may have a wider currency. For instance, there is concern about
the level of improvements that are being achieved in project
performance. The Standish Group's Chaos reports chronicle the
outcome of IT projects (PMI, 2003; Standish Group
International Inc., 2004). The project outcomes are also
measured by their completion on time, budget, and quality. The
TechRepublic Study by the Gartner Group paints a similar
picture. In 2000, 1275 North American IT specialists were
asked about the outcome of internal IT projects in terms of
achieving time, cost, and quality objectives. The picture is
consistently inconsistent: There are some organizations making
great progress with improving process and performance, but the
data from these studies does suggest that there are a
considerable number who are making little progress. We
speculate that complicity provides a possible root cause for such
a situation, and that further research would demonstrate if this
was in fact the case.
Is There Something Particular about Project Settings that
Encourages this Behavior?
As suggested above, the complicity demonstrated in this case
may not be an isolated occurrence. Similar to Flyvbjerg,
Bruzelius, and Rothengatters (2003) studies of mega projects in
transportation, key stakeholders ranging from owner
organizations, government officials, and key contractors
cooperated to use less than best practice project procedures.
So is there something about project settings that encourages this
kind of behavior? Again, the literature is not terribly helpful on
this. The level of uncertainty faced by the organization is
recognized as playing an important influence in best practice
diffusion. O'Neill, Pouder, and Buchholtz (1998) suggest that
organizations that operate in highly uncertain environments
have to be very flexible and able to adapt and change their
practices rapidly to meet the demands of the environmental
changes. This would tend to favor rapid adoption of best
practice, especially if firm survival depends on being at the
forefront. In times of severe crisis, however, even these firms
tend to backtrack and rely on tried-and-tested methods, thus
reducing flexibility and centralizing authority (Staw,
Sandelands, & Dutton, 1981). On the other hand organizations
operating in highly stable environments may not see the need to
change at all.
According to this view then project-based organizations, which
typically work in an unstable environment, would tend to be
flexible and open to rapid adoption of new practices. Our case
shows the opposite. Here is a project-based organization (PBO)
with high levels of uncertainty in the product it is producing
and which is inherently conservative in its adoption of new
practices. Furthermore, it is only when it goes into a deep crisis
that it responds by introducing a change of approach and the
introduction of a limited range of new tools and methods.
According to Levy (2007), stability is all-important, even at the
expense of innovation and change. Perhaps, in the project
environment, people seek stability, not from the organization
(inherently unstable, temporary, and shifting as project
progresses), the product (outcome being uncertain), but in the
process, in the way they work. Tolerance of uncertainty thus
limits behavior. This behavior is exhibited in defensive
routines. Collusion is not a random occurrence, it is led.
The collusion often wears the mask of its opposite. The
collusion seeks calm waters and seeks, either consciously or
unconsciously, to create safety and security through non-
challenge and superficial tolerance. The result: mediocrity
(Levy, 2007).
This mask promotes excellence: The limited changes are held up
as an amazing transformation in the corporation. It is espoused
by all but the most senior people, and in the case above,
including them. It is the organization's culture that presents the
biggest barrier to learning. The default position is of non-
change in these organizations. Even when they are forced to
change by some crisis, they quickly shift back to type and rather
than becoming a changed organization that is open to learning
(double-loop learning), they quickly adopt a new defensive
routine.
Project-based organizations may therefore be more susceptible
to complicity.
However, it is clear that projects are not doomed to live in this
world of non-adoption, as the following case will illustrate.
Contrast Case: T5
The new Terminal 5 building (T5) at London's Heathrow
Airport stands out as an example of rapid application of
innovative approaches and processes. BAA, the client and
owner of Heathrow Airport, implemented a strategic program of
capability building to improve the management of its projects,
and in particular, the management of T5, its biggest project
ever. They learned from previous projects, individuals, and
organizations that contributed to the innovative approach used
to manage the T5 project. Between 2000 and 2002, BAA
conducted in-depth analysis of every major UK construction
project (over £1billion) in the previous ten years and on every
international airport that had been opened in the previous ten
years. This research showed that none of them had been
delivered on-time and within-budget, or to the quality standards
expected. They realized the only way to deliver T5 was to
change the rules of the game by creating a set of behaviors that
allowed people to come up with innovative solutions to
problems. Not only did BAA learn internally from its past
projects, it also learned externally from other airport projects,
from other sectors, and from leading practice in supply chain
management (SCM) and project management (Brady, Davies,
Gann, & Rush, 2006).
Further investigation of the approach demonstrates that there
were a number of key elements present here that prevented the
negative behavior of complicity that was evident in the main
case. These were elements include the following:
1. Clear Policy Deployment: The objective at the outset of the
project included ‘setting a new standard for project delivery’
and ‘no surprises for BAA shareholders.’ (www.baa.com ) This
provided a clear statement for how resources would be allocated
in support of the new standard. The behavioral contract that was
put in place with contractors required this to be operationalized.
2. Knowledge Management: Learning internally from previous
projects, as well as carefully selecting appropriate practices
from other industries, was evident. Ongoing learning within the
project was evident too, with practices such as Last Planner
being used.
3. Performance Management: As stated by rational choice
theory, the application of new approaches requires that there is
some means to identify whether the performance is improved by
any new approach. This was evident in the T5 case.
The three conditions to remove the complicity also apply in the
transition phase of the main case: There was a clear policy for
the change, deployed throughout the project organization. There
was appropriate knowledge brought in and process measures of
performance installed. However, when these were removed, the
complicity was reestablished.
Conclusion
This paper has demonstrated that the non-adoption of promising
or good practice is supported by the existence of defensive
routines. The attempts using institutional and rational choice
theories to explain the phenomenon were only limited in their
success. As a result, we have proposed a theory of complicity,
summarized in the proposition that practices and processes will
remain within the defensive routines of the organization where
such complicity exists. The complicity we describe is a multi-
level collusion that accepts the status quo.
Project environments may be particularly susceptible to such
collusion, and this may contribute to understanding why the
performance of organizations in project terms is so variable,
and headline rates of performance demonstrate only limited
improvements. Contrary to the literature, project environments
which are full of uncertainty do not appear to be the locus of
rapid adoption of new practice. We further suggest that this is
due in part to the desire for stability in an uncertain
environment. Where the technology is uncertain, where the
relationships with stakeholders are uncertain, then project
members seek stability in the processes they use. There is a
built-in desire not to rock the boat. Even when crises arise
which force a change, the change in underlying behavior is only
temporary and they snap back into their old ways of working.
New defensive routines emerge to replace the old ones. It takes
an enormous effort to make sustainable changes in this
environment. Much further research is required before we can
try to generalize these findings. However, the T5 project
appears to offer hope that such sustainable change in behavior
may be possible, given the right environment.
While there is a general acceptance that increasing an
organization's project management maturity is desirable, there
are clearly some conditions that lead to this. First, there is the
recognition of better and improved ways and the benefits that
they would bring to the project organization. With the low level
of knowledge that was demonstrated in the case organization,
there is limited identification of areas for improvement. Second,
even if these had been identified, there was no policy to drive
the improvement through; in fact, the opposite was
demonstrated. Last, it is clear that there was no performance
management system in place that would detect if the changes
had indeed been successful. The result was that there was
nothing to oppose the root cause of the defensive routines that
had built up in the organization, and nothing to prevent
complicity from being re-established.
We started from a case-based method which yielded a particular
phenomenon which was unexpected. The application of various
theoretical lenses provided only limited explanation of the
phenomenon. Starting the research without a pre-determined
theoretical stance allowed the exploration of the phenomenon in
ways that would not have otherwise been possible. This appears
to be useful in contributing to the methodological development
of the project management discipline.
References
Abrahamson, E. (1991). Managerial fads and fashions: The
diffusion and refection of innovations. Academy of Management
Review, 16(3), 586 - 612.
Abrahamson, E. (1996). Management fashion. Academy of
Management Review, 21(1), 254 - 285.
Abrahamson, E., & Fairchild, G. (1999). Management fashion:
Lifecycles, triggers, and collective learning
processes. Administrative Science Quarterly, 44(4), 708 - 740.
Abrahamson, E., & Rosenkopf, L. (1997). Social network
effects on the extent of innovation diffusion: A computer
simulation. Organization Science, 8(3), 289 - 309.
Argyris, C. (1993). Knowledge for action: A guide to
overcoming barriers to organizational change. Thousand Oaks,
CA: Sage Publications.
Arthur, W. B. (1989). Competing technologies, increasing
returns, and lock-in by historical events. The Economic Journal,
99(394), 116 - 131.
Brady, T., Davies, A., Gann, D., & Rush, A. (2006,
October). Learning to manage mega projects: The case of BAA
and Heathrow Terminal 5. Paper presented at IRNOP VII
Project Research Conference, Xi'an China.
Cyert, R. M., & March, J. G. (1963). A behavioural theory of
the firm. Englewood Cliffs, NJ: Blackwell Publishers.
DiMaggio, P. J., & Powell, W. W. (1983). The iron cage
revisited: Institutional isomorphism and collective rationality in
organizational fields. American Sociological Review, 48(2), 147
- 160.
Eisenhardt, K. M. (1989). Building theories from case study
research. Academy of Management Review, 14(4), 532 - 550.
Eisenhardt, K. M. (1991). Better stories and better constructs:
The case for rigor and comparative logic. Academy of
Management Review, 16(3), 620 - 627.
Flyvbjerg, B., Bruzelius, N., & Rothengatter, W.
(2003). Megaprojects and risk: An anatomy of
ambition. Cambridge, UK: Cambridge University Press.
Green, S. E., Jr. (2004). A rhetorical theory of
diffusion. Academy of Management Review, 29(4), 653 - 669.
Hallier, J., & Forbes, T. (2004). In search of theory
development in grounded investigations: Doctors’ experiences
of managing as an example of fitted and prospective
theorizing. Journal of Management Studies, 41(8), 1379 -1410.
Lant, T. K., & Mezias, S. J. (1992). An organizational learning
model of convergence and reorientation. Organization Science,
3(1), 47 - 71.
Leseure, M. J., Bauer, J., Birdi, K., Neely, A., & Denyer, D.
(2004). Adoption of promising practices: A systematic review
of the evidence. International Journal of Management Reviews,
5-6(3-4), 169 - 190.
Levy, P. (2007). The dynamics of change. In L. Darso, S.
Mesiek, & E. Boje (Eds.), The thin book of organisational
theatre, ch. 4,_-_). _Aalborg, Denmark: Learning Lab.
March, J. G., & Olsen, J. P., (1976). Ambiguity and choice in
organizations. Bergen, Norway: Universitetsforlaget. March, J.
G., & Simon, H. A. (1967). Organizations. New York: John
Wiley.
Massini, S., Lewin, A. Y., & Greve, H. R. (2005). Innovators
and imitators: Organisational reference groups and adoption of
organizational routines. Research Policy, 34(12), 1550 - 1569.
Nelson, R., & Winter, S. (1982). An evolutionary theory of
economic change. Cambridge, MA: Belknap Press.
Nelson, R. R., Peterhansl, A., & Sampat, B. (2004). Why and
how innovations get adopted: A tale of four models.
Industrial & Corporate Change, 13(5), 679 - 699.
Oliver, C. (1992). The antecedents of
deinstitutionalization. Organization Studies, 13(7), 563 - 588.
O'Neill, H. M., Pouder, R. W., & Buchholtz, A. K. (1998).
Patterns in the diffusion of strategies across organizations:
Insights from the innovation diffusion literature. The Academy
of Management Review, 23(1), 98 -114.
Paauwe, J., & Boselie, P. (2005). ‘Best practices…in spite of
performance’: Just a matter of imitation? International Journal
of Human Resource Management, 16(6), 987 - 1003.
Robertson, M., Swan, J., & Newell, S. (1996). The role of
networks in the diffusion of technological innovation. Journal
of Management Studies, 33(3), 333 - 360.
Rogers, E. (1983). The diffusion of innovation. New York: Free
Press.
Schultz, M., & Hatch, M. J. (1996). Living with multiple
paradigms: The case of paradigm interplay in organizational
culture studies. The Academy of Management Review, 21(2),
529 - 557.
Scott, W. R. (2001). Institutions and organisations. Thousand
Oaks, CA:Sage Publications.
Standish Group International Inc. (2004). The Chaos Report.
West Yarmouth, MA:The Standish Group International Inc.
Staw, B. M.. Sandelands, L. E., & Dutton, J. E, (1981). Threat
rigidity effects in organizational behavior: A multilevel
analysis. Administrative Science Quarterly, 26(4), 501 - 524.
Strang, D., & Macy, M. W. (2001). In search of excellence:
Fads, success stories, and adaptive emulation. American Journal
of Sociology, 107(1), 147 - 182.
Strang, D., & Still, M. C. (2004). In search of the élite:
Revising a model of adaptive emulation with evidence from
benchmarking teams. Industrial & Corporate Change, 13(2), 309
- 333.
Strauss, A. L., & Corbin, J. (2002). Basics of qualitative
research: Grounded theory procedures and techniques. Thousand
Oaks, CA: Sage Publications.
Suddaby, R., & Greenwood, R. (2005). Rhetorical strategies of
legitimacy. Administrative Science Quarterly, 50(1), 35 - 67.
1 Project funded by PMI
This material has been reproduced with the permission of the
copyright owner. Unauthorized reproduction of this material is
strictly prohibited. For permission to reproduce this material,
please contact PMI or any listed author.
© 2008 Project Management Institute

More Related Content

What's hot

Introduction to Facebook
Introduction to FacebookIntroduction to Facebook
Introduction to FacebookSophia Guevara
 
Social media content planning like a boss
Social media content planning like a bossSocial media content planning like a boss
Social media content planning like a bossKirstie Smith
 
The Business of Business Development
The Business of Business Development The Business of Business Development
The Business of Business Development Intelligent_ly
 
Ideapoke digital marketing interview assignment
Ideapoke digital marketing interview assignmentIdeapoke digital marketing interview assignment
Ideapoke digital marketing interview assignmentMuthali Ganesh
 
Facebook Powerpoint
Facebook PowerpointFacebook Powerpoint
Facebook Powerpointmyra14
 
New Product Overview PowerPoint Presentation Slides
New Product Overview PowerPoint Presentation SlidesNew Product Overview PowerPoint Presentation Slides
New Product Overview PowerPoint Presentation SlidesSlideTeam
 
Big kola company team alpha presentation wk 4
Big kola company team alpha presentation wk 4Big kola company team alpha presentation wk 4
Big kola company team alpha presentation wk 4Peggy Sue Carpenter
 
Sales Reports PowerPoint Presentation Slides
Sales Reports PowerPoint Presentation Slides Sales Reports PowerPoint Presentation Slides
Sales Reports PowerPoint Presentation Slides SlideTeam
 
Twitter for Business Presentation
Twitter for Business PresentationTwitter for Business Presentation
Twitter for Business Presentation6S Marketing
 
Lrm boeien en binden in de zorg 19-08-13
Lrm   boeien en binden in de zorg 19-08-13Lrm   boeien en binden in de zorg 19-08-13
Lrm boeien en binden in de zorg 19-08-13LRM Group
 
Personal Branding: The Power of You - Creating an Influential & Credible Per...
Personal Branding: The Power of You - Creating an Influential & Credible Per...Personal Branding: The Power of You - Creating an Influential & Credible Per...
Personal Branding: The Power of You - Creating an Influential & Credible Per...Elizabeth Lupfer
 
Different Types of Social Media Channels - Sysomos
Different Types of Social Media Channels - SysomosDifferent Types of Social Media Channels - Sysomos
Different Types of Social Media Channels - SysomosSysomos
 
Gail perry Presentation
Gail perry PresentationGail perry Presentation
Gail perry PresentationChris Baylis
 
Starbucks Social Media Strategy
Starbucks Social Media StrategyStarbucks Social Media Strategy
Starbucks Social Media StrategyAshlee Benson
 
Professional Networking Power Point
Professional Networking Power PointProfessional Networking Power Point
Professional Networking Power PointPhillip0582
 
"Driving SaaS Success Using Key Metrics" at SaaStr Annual 2016
"Driving SaaS Success Using Key Metrics" at SaaStr Annual 2016"Driving SaaS Success Using Key Metrics" at SaaStr Annual 2016
"Driving SaaS Success Using Key Metrics" at SaaStr Annual 2016saastr
 
Budowanie Personal Brandingu na LinkedIn || Autokreacja || Anna Ledwoń 2019
Budowanie Personal Brandingu na LinkedIn || Autokreacja || Anna Ledwoń 2019Budowanie Personal Brandingu na LinkedIn || Autokreacja || Anna Ledwoń 2019
Budowanie Personal Brandingu na LinkedIn || Autokreacja || Anna Ledwoń 2019Anna Ledwoń-Blacha
 

What's hot (20)

Business Model for Startups
Business Model for StartupsBusiness Model for Startups
Business Model for Startups
 
Introduction to Facebook
Introduction to FacebookIntroduction to Facebook
Introduction to Facebook
 
Social media content planning like a boss
Social media content planning like a bossSocial media content planning like a boss
Social media content planning like a boss
 
The Business of Business Development
The Business of Business Development The Business of Business Development
The Business of Business Development
 
Ideapoke digital marketing interview assignment
Ideapoke digital marketing interview assignmentIdeapoke digital marketing interview assignment
Ideapoke digital marketing interview assignment
 
Facebook Powerpoint
Facebook PowerpointFacebook Powerpoint
Facebook Powerpoint
 
New Product Overview PowerPoint Presentation Slides
New Product Overview PowerPoint Presentation SlidesNew Product Overview PowerPoint Presentation Slides
New Product Overview PowerPoint Presentation Slides
 
Big kola company team alpha presentation wk 4
Big kola company team alpha presentation wk 4Big kola company team alpha presentation wk 4
Big kola company team alpha presentation wk 4
 
Sales Reports PowerPoint Presentation Slides
Sales Reports PowerPoint Presentation Slides Sales Reports PowerPoint Presentation Slides
Sales Reports PowerPoint Presentation Slides
 
Twitter for Business Presentation
Twitter for Business PresentationTwitter for Business Presentation
Twitter for Business Presentation
 
Lrm boeien en binden in de zorg 19-08-13
Lrm   boeien en binden in de zorg 19-08-13Lrm   boeien en binden in de zorg 19-08-13
Lrm boeien en binden in de zorg 19-08-13
 
Personal Branding: The Power of You - Creating an Influential & Credible Per...
Personal Branding: The Power of You - Creating an Influential & Credible Per...Personal Branding: The Power of You - Creating an Influential & Credible Per...
Personal Branding: The Power of You - Creating an Influential & Credible Per...
 
Different Types of Social Media Channels - Sysomos
Different Types of Social Media Channels - SysomosDifferent Types of Social Media Channels - Sysomos
Different Types of Social Media Channels - Sysomos
 
Gail perry Presentation
Gail perry PresentationGail perry Presentation
Gail perry Presentation
 
Facebook ppt
Facebook pptFacebook ppt
Facebook ppt
 
Starbucks Social Media Strategy
Starbucks Social Media StrategyStarbucks Social Media Strategy
Starbucks Social Media Strategy
 
Professional Networking Power Point
Professional Networking Power PointProfessional Networking Power Point
Professional Networking Power Point
 
"Driving SaaS Success Using Key Metrics" at SaaStr Annual 2016
"Driving SaaS Success Using Key Metrics" at SaaStr Annual 2016"Driving SaaS Success Using Key Metrics" at SaaStr Annual 2016
"Driving SaaS Success Using Key Metrics" at SaaStr Annual 2016
 
Budowanie Personal Brandingu na LinkedIn || Autokreacja || Anna Ledwoń 2019
Budowanie Personal Brandingu na LinkedIn || Autokreacja || Anna Ledwoń 2019Budowanie Personal Brandingu na LinkedIn || Autokreacja || Anna Ledwoń 2019
Budowanie Personal Brandingu na LinkedIn || Autokreacja || Anna Ledwoń 2019
 
Work from home job a rising trend
Work from home job   a rising trendWork from home job   a rising trend
Work from home job a rising trend
 

Similar to Theories of non-adoption and complicity in project management

Project Management: A Critical Examination of the PPARS Project
Project Management: A Critical Examination of the PPARS ProjectProject Management: A Critical Examination of the PPARS Project
Project Management: A Critical Examination of the PPARS ProjectOlivia Moran
 
BBA 3626, Project Management Overview 1 Course Learni
 BBA 3626, Project Management Overview 1 Course Learni BBA 3626, Project Management Overview 1 Course Learni
BBA 3626, Project Management Overview 1 Course LearniMargaritoWhitt221
 
Case study 1 (zaileha,suryani,anis,ilyana) version 2
Case study 1 (zaileha,suryani,anis,ilyana) version 2Case study 1 (zaileha,suryani,anis,ilyana) version 2
Case study 1 (zaileha,suryani,anis,ilyana) version 2ilyanaismarau90
 
Case study 1 (zaileha,suryani,anis,ilyana)
Case study 1 (zaileha,suryani,anis,ilyana)Case study 1 (zaileha,suryani,anis,ilyana)
Case study 1 (zaileha,suryani,anis,ilyana)ilyanaismarau90
 
A practical guide to service improvement in healthcare.
A practical guide to service improvement in healthcare.A practical guide to service improvement in healthcare.
A practical guide to service improvement in healthcare.Jonathan Popoola
 
A presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project ManagersA presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project ManagersAdeolu Adeleye
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train WrecksPete Luan
 
Jayantobose prashantshrivastava-131008015757-phpapp01
Jayantobose prashantshrivastava-131008015757-phpapp01Jayantobose prashantshrivastava-131008015757-phpapp01
Jayantobose prashantshrivastava-131008015757-phpapp01PMI_IREP_TP
 
Jayanto bose prashantshrivastava
Jayanto bose prashantshrivastavaJayanto bose prashantshrivastava
Jayanto bose prashantshrivastavaPMI2011
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slidesdotesch
 
Applied Research________________________________________________.docx
Applied Research________________________________________________.docxApplied Research________________________________________________.docx
Applied Research________________________________________________.docxjustine1simpson78276
 
Case Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdf
Case Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdfCase Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdf
Case Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdfsales88
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Renee Jones
 
Agile software development
Agile software developmentAgile software development
Agile software developmentVarun Mahajan
 
Assignment 1 Team Project Part 1 Project Charter and Team Plan f.docx
Assignment 1 Team Project Part 1 Project Charter and Team Plan f.docxAssignment 1 Team Project Part 1 Project Charter and Team Plan f.docx
Assignment 1 Team Project Part 1 Project Charter and Team Plan f.docxmaribethy2y
 
Project management synopsis [www.writekraft.com]
Project management synopsis  [www.writekraft.com]Project management synopsis  [www.writekraft.com]
Project management synopsis [www.writekraft.com]WriteKraft Dissertations
 
The Rules of Lean Project Management
The Rules of Lean Project ManagementThe Rules of Lean Project Management
The Rules of Lean Project ManagementClaude Emond
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project ManagementMostafa Ewees
 
Writing evaluation report of a project
Writing evaluation report of a projectWriting evaluation report of a project
Writing evaluation report of a project03363635718
 

Similar to Theories of non-adoption and complicity in project management (20)

Project Management: A Critical Examination of the PPARS Project
Project Management: A Critical Examination of the PPARS ProjectProject Management: A Critical Examination of the PPARS Project
Project Management: A Critical Examination of the PPARS Project
 
BBA 3626, Project Management Overview 1 Course Learni
 BBA 3626, Project Management Overview 1 Course Learni BBA 3626, Project Management Overview 1 Course Learni
BBA 3626, Project Management Overview 1 Course Learni
 
Case study 1 (zaileha,suryani,anis,ilyana) version 2
Case study 1 (zaileha,suryani,anis,ilyana) version 2Case study 1 (zaileha,suryani,anis,ilyana) version 2
Case study 1 (zaileha,suryani,anis,ilyana) version 2
 
Case study 1 (zaileha,suryani,anis,ilyana)
Case study 1 (zaileha,suryani,anis,ilyana)Case study 1 (zaileha,suryani,anis,ilyana)
Case study 1 (zaileha,suryani,anis,ilyana)
 
PERT
PERTPERT
PERT
 
A practical guide to service improvement in healthcare.
A practical guide to service improvement in healthcare.A practical guide to service improvement in healthcare.
A practical guide to service improvement in healthcare.
 
A presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project ManagersA presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project Managers
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train Wrecks
 
Jayantobose prashantshrivastava-131008015757-phpapp01
Jayantobose prashantshrivastava-131008015757-phpapp01Jayantobose prashantshrivastava-131008015757-phpapp01
Jayantobose prashantshrivastava-131008015757-phpapp01
 
Jayanto bose prashantshrivastava
Jayanto bose prashantshrivastavaJayanto bose prashantshrivastava
Jayanto bose prashantshrivastava
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slides
 
Applied Research________________________________________________.docx
Applied Research________________________________________________.docxApplied Research________________________________________________.docx
Applied Research________________________________________________.docx
 
Case Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdf
Case Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdfCase Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdf
Case Study - Rescuing a Troubled Project C.A. McCall-Peat Liberty Li.pdf
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
 
Agile software development
Agile software developmentAgile software development
Agile software development
 
Assignment 1 Team Project Part 1 Project Charter and Team Plan f.docx
Assignment 1 Team Project Part 1 Project Charter and Team Plan f.docxAssignment 1 Team Project Part 1 Project Charter and Team Plan f.docx
Assignment 1 Team Project Part 1 Project Charter and Team Plan f.docx
 
Project management synopsis [www.writekraft.com]
Project management synopsis  [www.writekraft.com]Project management synopsis  [www.writekraft.com]
Project management synopsis [www.writekraft.com]
 
The Rules of Lean Project Management
The Rules of Lean Project ManagementThe Rules of Lean Project Management
The Rules of Lean Project Management
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project Management
 
Writing evaluation report of a project
Writing evaluation report of a projectWriting evaluation report of a project
Writing evaluation report of a project
 

More from audeleypearl

Mr. Bush, a 45-year-old middle school teacher arrives at the emergen.docx
Mr. Bush, a 45-year-old middle school teacher arrives at the emergen.docxMr. Bush, a 45-year-old middle school teacher arrives at the emergen.docx
Mr. Bush, a 45-year-old middle school teacher arrives at the emergen.docxaudeleypearl
 
Movie Project Presentation Movie TroyInclude Architecture i.docx
Movie Project Presentation Movie TroyInclude Architecture i.docxMovie Project Presentation Movie TroyInclude Architecture i.docx
Movie Project Presentation Movie TroyInclude Architecture i.docxaudeleypearl
 
Motivation and Retention Discuss the specific strategies you pl.docx
Motivation and Retention Discuss the specific strategies you pl.docxMotivation and Retention Discuss the specific strategies you pl.docx
Motivation and Retention Discuss the specific strategies you pl.docxaudeleypearl
 
Mother of the Year In recognition of superlative paren.docx
Mother of the Year         In recognition of superlative paren.docxMother of the Year         In recognition of superlative paren.docx
Mother of the Year In recognition of superlative paren.docxaudeleypearl
 
Mrs. G, a 55 year old Hispanic female, presents to the office for he.docx
Mrs. G, a 55 year old Hispanic female, presents to the office for he.docxMrs. G, a 55 year old Hispanic female, presents to the office for he.docx
Mrs. G, a 55 year old Hispanic female, presents to the office for he.docxaudeleypearl
 
Mr. Rivera is a 72-year-old patient with end stage COPD who is in th.docx
Mr. Rivera is a 72-year-old patient with end stage COPD who is in th.docxMr. Rivera is a 72-year-old patient with end stage COPD who is in th.docx
Mr. Rivera is a 72-year-old patient with end stage COPD who is in th.docxaudeleypearl
 
Mr. B, a 40-year-old avid long-distance runner previously in goo.docx
Mr. B, a 40-year-old avid long-distance runner previously in goo.docxMr. B, a 40-year-old avid long-distance runner previously in goo.docx
Mr. B, a 40-year-old avid long-distance runner previously in goo.docxaudeleypearl
 
Moving members of the organization through the change process ca.docx
Moving members of the organization through the change process ca.docxMoving members of the organization through the change process ca.docx
Moving members of the organization through the change process ca.docxaudeleypearl
 
Mr. Friend is acrime analystwith the SantaCruz, Califo.docx
Mr. Friend is acrime analystwith the SantaCruz, Califo.docxMr. Friend is acrime analystwith the SantaCruz, Califo.docx
Mr. Friend is acrime analystwith the SantaCruz, Califo.docxaudeleypearl
 
Mr. E is a pleasant, 70-year-old, black, maleSource Self, rel.docx
Mr. E is a pleasant, 70-year-old, black, maleSource Self, rel.docxMr. E is a pleasant, 70-year-old, black, maleSource Self, rel.docx
Mr. E is a pleasant, 70-year-old, black, maleSource Self, rel.docxaudeleypearl
 
Motor Milestones occur in a predictable developmental progression in.docx
Motor Milestones occur in a predictable developmental progression in.docxMotor Milestones occur in a predictable developmental progression in.docx
Motor Milestones occur in a predictable developmental progression in.docxaudeleypearl
 
Most women experience their closest friendships with those of th.docx
Most women experience their closest friendships with those of th.docxMost women experience their closest friendships with those of th.docx
Most women experience their closest friendships with those of th.docxaudeleypearl
 
Most patients with mental health disorders are not aggressive. Howev.docx
Most patients with mental health disorders are not aggressive. Howev.docxMost patients with mental health disorders are not aggressive. Howev.docx
Most patients with mental health disorders are not aggressive. Howev.docxaudeleypearl
 
Most of our class readings and discussions to date have dealt wi.docx
Most of our class readings and discussions to date have dealt wi.docxMost of our class readings and discussions to date have dealt wi.docx
Most of our class readings and discussions to date have dealt wi.docxaudeleypearl
 
Most people agree we live in stressful times. Does stress and re.docx
Most people agree we live in stressful times. Does stress and re.docxMost people agree we live in stressful times. Does stress and re.docx
Most people agree we live in stressful times. Does stress and re.docxaudeleypearl
 
Most of the ethical prescriptions of normative moral philosophy .docx
Most of the ethical prescriptions of normative moral philosophy .docxMost of the ethical prescriptions of normative moral philosophy .docx
Most of the ethical prescriptions of normative moral philosophy .docxaudeleypearl
 
Most healthcare organizations in the country are implementing qualit.docx
Most healthcare organizations in the country are implementing qualit.docxMost healthcare organizations in the country are implementing qualit.docx
Most healthcare organizations in the country are implementing qualit.docxaudeleypearl
 
More work is necessary on how to efficiently model uncertainty in ML.docx
More work is necessary on how to efficiently model uncertainty in ML.docxMore work is necessary on how to efficiently model uncertainty in ML.docx
More work is necessary on how to efficiently model uncertainty in ML.docxaudeleypearl
 
Mortgage-Backed Securities and the Financial CrisisKelly Finn.docx
Mortgage-Backed Securities and the Financial CrisisKelly Finn.docxMortgage-Backed Securities and the Financial CrisisKelly Finn.docx
Mortgage-Backed Securities and the Financial CrisisKelly Finn.docxaudeleypearl
 
Moral Development  Lawrence Kohlberg developed six stages to mora.docx
Moral Development  Lawrence Kohlberg developed six stages to mora.docxMoral Development  Lawrence Kohlberg developed six stages to mora.docx
Moral Development  Lawrence Kohlberg developed six stages to mora.docxaudeleypearl
 

More from audeleypearl (20)

Mr. Bush, a 45-year-old middle school teacher arrives at the emergen.docx
Mr. Bush, a 45-year-old middle school teacher arrives at the emergen.docxMr. Bush, a 45-year-old middle school teacher arrives at the emergen.docx
Mr. Bush, a 45-year-old middle school teacher arrives at the emergen.docx
 
Movie Project Presentation Movie TroyInclude Architecture i.docx
Movie Project Presentation Movie TroyInclude Architecture i.docxMovie Project Presentation Movie TroyInclude Architecture i.docx
Movie Project Presentation Movie TroyInclude Architecture i.docx
 
Motivation and Retention Discuss the specific strategies you pl.docx
Motivation and Retention Discuss the specific strategies you pl.docxMotivation and Retention Discuss the specific strategies you pl.docx
Motivation and Retention Discuss the specific strategies you pl.docx
 
Mother of the Year In recognition of superlative paren.docx
Mother of the Year         In recognition of superlative paren.docxMother of the Year         In recognition of superlative paren.docx
Mother of the Year In recognition of superlative paren.docx
 
Mrs. G, a 55 year old Hispanic female, presents to the office for he.docx
Mrs. G, a 55 year old Hispanic female, presents to the office for he.docxMrs. G, a 55 year old Hispanic female, presents to the office for he.docx
Mrs. G, a 55 year old Hispanic female, presents to the office for he.docx
 
Mr. Rivera is a 72-year-old patient with end stage COPD who is in th.docx
Mr. Rivera is a 72-year-old patient with end stage COPD who is in th.docxMr. Rivera is a 72-year-old patient with end stage COPD who is in th.docx
Mr. Rivera is a 72-year-old patient with end stage COPD who is in th.docx
 
Mr. B, a 40-year-old avid long-distance runner previously in goo.docx
Mr. B, a 40-year-old avid long-distance runner previously in goo.docxMr. B, a 40-year-old avid long-distance runner previously in goo.docx
Mr. B, a 40-year-old avid long-distance runner previously in goo.docx
 
Moving members of the organization through the change process ca.docx
Moving members of the organization through the change process ca.docxMoving members of the organization through the change process ca.docx
Moving members of the organization through the change process ca.docx
 
Mr. Friend is acrime analystwith the SantaCruz, Califo.docx
Mr. Friend is acrime analystwith the SantaCruz, Califo.docxMr. Friend is acrime analystwith the SantaCruz, Califo.docx
Mr. Friend is acrime analystwith the SantaCruz, Califo.docx
 
Mr. E is a pleasant, 70-year-old, black, maleSource Self, rel.docx
Mr. E is a pleasant, 70-year-old, black, maleSource Self, rel.docxMr. E is a pleasant, 70-year-old, black, maleSource Self, rel.docx
Mr. E is a pleasant, 70-year-old, black, maleSource Self, rel.docx
 
Motor Milestones occur in a predictable developmental progression in.docx
Motor Milestones occur in a predictable developmental progression in.docxMotor Milestones occur in a predictable developmental progression in.docx
Motor Milestones occur in a predictable developmental progression in.docx
 
Most women experience their closest friendships with those of th.docx
Most women experience their closest friendships with those of th.docxMost women experience their closest friendships with those of th.docx
Most women experience their closest friendships with those of th.docx
 
Most patients with mental health disorders are not aggressive. Howev.docx
Most patients with mental health disorders are not aggressive. Howev.docxMost patients with mental health disorders are not aggressive. Howev.docx
Most patients with mental health disorders are not aggressive. Howev.docx
 
Most of our class readings and discussions to date have dealt wi.docx
Most of our class readings and discussions to date have dealt wi.docxMost of our class readings and discussions to date have dealt wi.docx
Most of our class readings and discussions to date have dealt wi.docx
 
Most people agree we live in stressful times. Does stress and re.docx
Most people agree we live in stressful times. Does stress and re.docxMost people agree we live in stressful times. Does stress and re.docx
Most people agree we live in stressful times. Does stress and re.docx
 
Most of the ethical prescriptions of normative moral philosophy .docx
Most of the ethical prescriptions of normative moral philosophy .docxMost of the ethical prescriptions of normative moral philosophy .docx
Most of the ethical prescriptions of normative moral philosophy .docx
 
Most healthcare organizations in the country are implementing qualit.docx
Most healthcare organizations in the country are implementing qualit.docxMost healthcare organizations in the country are implementing qualit.docx
Most healthcare organizations in the country are implementing qualit.docx
 
More work is necessary on how to efficiently model uncertainty in ML.docx
More work is necessary on how to efficiently model uncertainty in ML.docxMore work is necessary on how to efficiently model uncertainty in ML.docx
More work is necessary on how to efficiently model uncertainty in ML.docx
 
Mortgage-Backed Securities and the Financial CrisisKelly Finn.docx
Mortgage-Backed Securities and the Financial CrisisKelly Finn.docxMortgage-Backed Securities and the Financial CrisisKelly Finn.docx
Mortgage-Backed Securities and the Financial CrisisKelly Finn.docx
 
Moral Development  Lawrence Kohlberg developed six stages to mora.docx
Moral Development  Lawrence Kohlberg developed six stages to mora.docxMoral Development  Lawrence Kohlberg developed six stages to mora.docx
Moral Development  Lawrence Kohlberg developed six stages to mora.docx
 

Recently uploaded

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 

Recently uploaded (20)

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 

Theories of non-adoption and complicity in project management

  • 1. Red Zuma Project RED ZUMA PROJECT- Bucher RED ZUMA PROJECT (PARTS 1 and 2) Brian J. Bucher Liberty University BUSI-313-B02 June 5, 2017 Bachelors of Science in Business Administration: Leadership APA Style RED ZUMA PROJECT MEMO 1. When is the project estimated to be completed? How long will the project take? The project is estimated to be completed on 1/11/16. The project will take 260 working days.
  • 2. 2. What is the critical path for the project? The critical path is shown in red on the Gantt chart below. The tasks in the critical path are 1.1, 1.2, 1.4, 1.7, 1.8, 1.10, 1.11, 1.12, 1.14, 1.15, & 1.16. 3. Which activity has the greatest amount of slack? The activity has the greatest amount of slack is task 1.5 Detailed Marketing Plan with a total of 179 days of slack. 4. How sensitive is this network? The project is not sensitive because the activities that are not on the critical paths have a lot of slack and there is only one critical path. 5. Identify two sensible milestones and explain your choices. Build Prototypes is most important milestones because based on that then worker know what to build. Install Production Equipment is also important milestones because if they install something that is not supposed to be installed then project gets delay and it will be over budget. GANTT CHART
  • 3. NETWORK DIAGRAM (With Critical Path) SCHEDULE TABLE WITH SLACK PART 2A MEMO 1. Which if any of the resources are over allocated? Marketing Specialist, Design Engineer and Industrial Engineer. 2. Assume that the project is time constrained and try to resolve any over allocation problems by leveling within slack. What happens? When I leveled the slack it removed the over allocation off of the Detailed Marking Plan, but it did not resolve all over allocations. It also reduced the number of slack days on the Manufacturing study by 10 days to 0 days. It also reduced the 179 days of slack on the Details Marketing Plan to 134 days. The Manufacturing Process went from 55 days to 10 days and the Lab Test Prototypes went from 5 to 0 days. The Order Components task did not change and stayed at 27 days of slack. 3. What is the impact of leveling within slack on the sensitivity of the network? (Include a Gantt chart with the schedule table after leveling within slack). The Red Zuma project schedule changed with the leveling because it added in multiple paths as well as reducing the
  • 4. overall slack days. GANTT CHART Leveling within Slack GANTT CHART Free and Total Slack 4. Assume that the project is resource constrained and no additional personnel are available. How long will the project take given the resources assigned? (Hint: Undo leveling performed in Part A before answering this question.) With no additional personnel added, the project timeline will need to increase to 310 days with a new finish date of 03/21/2016. 5. How does the new duration compare with the estimated completion date generated from Part 1? What does this tell you about the impact resources can have on a schedule? The new date is 2 months past the original completion date and added 50 work days to the schedule. Having the required resources is critical to completing each step of a project on schedule. Major delays will happen if they are not allocated properly at the start of the project. GANTT CHART with ACTUAL TIMELINE
  • 5. PART 2B MEMO 1. What was the impact of introducing Start-to-Start lags to the schedule and budget? By introducing start-to-start lag into the schedule and budget, it would shorten the overall duration of the project but it increased the budget to support the additional requirements. 2. Which, if any additional personnel assignments, would you choose to complete the project before the January 17th deadline? Explain your choices as well as the reasons for not choosing other options. The need for additional Industrial Engineers is necessary to complete multiple project steps on time. All other resources have additional capacity to complete their workload within the established timeline. 3. How have these changes affected the sensitivity of the network and the critical path? With the additional resources the critical path will be able to flow without delays and will be very insensitive overall. GANTT CHART WITH FREE AND TOTAL SLACK Include a Gantt chart with a schedule table displaying free and total slack for the new schedule. Note: Do not assign new personnel to specific tasks, simply add them to the Resource Sheet. All new personnel are available full time (100%). The non-adoption of best/accepted/promising practices in projects towards a theory of complicity
  • 6. Share CONFERENCE PAPER16 July 2008 Maylor, Harvey | Brady, Tim | Thomas, Janice How to cite this article: Maylor, H., Brady, T., & Thomas, J. (2008). The non-adoption of best/accepted/promising practices in projects: towards a theory of complicity. Paper presented at PMI® Research Conference: Defining the Future of Project Management, Warsaw, Poland. Newtown Square, PA: Project Management Institute. TIM BRADY, PHD CENTRIM, University of Brighton, United Kingdom JANICE THOMAS Athabasca University, Calgary, Canada Introduction This paper describes an observed phenomenon: the non- adoption of best / accepted / promising practices in a particular project setting. During data gathering for a project to determine the value of project management1 we visited organizations and conducted in-depth interviews. We observed the phenomenon of non- adoption of best practice, even good practice, and collected data that would help us understand why this was so. It was observed in a case that a prime customer (major government department) was accepting poor levels of performance from a major supplier. After many years of accepting this poor performance, a crisis point was reached when pressure from outside forced both parties to recognize the situation. This threatened the very existence of the program. So, a series of actions was undertaken to address the situation. Analysis of the case made little sense; following the reforms, the supplier was being highly complacent about their performance, and the customer was simply concerned with keeping the project out of the press and ‘below- the-radar'. The costs to both the supplier and the customer were considerable, yet they were both talking about the project as a good news story. For this to happen, the firm would have had to
  • 7. adopt a much greater range of accepted practices. Similarly, there was no sense of following fashion here: Indeed, there was considerable knowledge of such practices elsewhere in the organization, and these were conspicuous by their absence. However, they continued with a very low level of development of their project management processes. Our case findings show that rather than making positive choices to implement or test process innovations, individuals were able to decide not to pursue particular approaches, regardless of the potential (economic) benefits to the organization. The phenomenon is certainly not unique but there are particular circumstances with the case being investigated that highlighted its occurrence. Further, it is not restricted to project environments; though it is worth investigating whether there is something particular about project environments that allow such behavior to flourish. A challenge for management academics and practitioners is the non-adoption of what organizations and individuals term as best, accepted, or even promising practices (Leseure, Bauer, Birdi, Neely, & Denyer, 2004). Often encouraged by governments in search of better economic performance (e.g., AIM initiative in the United Kingdom [UK]) or customers (usually large organizations as part of their supplier development activities), organizations will assimilate processes or approaches that are new to them. Past examples of processes that organizations have adopted include Total Quality Management, Business Process Reengineering, Lean, and Agile. These represent a normalization of practices; one persistent criticism of the project management literature is that it encourages such normalization. In actuality, it is clear that there are many project management practices (now classified as accepted practices) that could be used beneficially. This includes those practices that are not being used by individuals or organizations. Such a lack of adoption and application of existing project management knowledge remains a challenge for such theories of normalization and, in many cases, represents a
  • 8. missed opportunity for organizations attempting to continually improve their performance. There are two significant views about the adoption of particular practices (Robertson, Swan, & Newell, 1996). The first comes from rational choice theory, which proposes that managers are predominantly rational adopters who make technically efficient choices, and hence, are driven by economic rationality and institutional theory, which proposes that managers predominantly respond to institutional mechanisms that may lead them to choose practices that are technically inefficient and driven by normative rationality. Such a normative rationality may include conformance to fads and fashions (Abrahamson, 1996). This paper considers this issue in the context of organizations and projects where there is a low rate of adopting existing tools and techniques, and which, because of this, leads to observably poor project performance. This issue is not easily explained by the existing theory. So, this paper begins with a practical question: If a practice appears to yield benefits for an organization, why is it not adopted? By taking a critical perspective and exploring the power dynamics at work in organizations, we lay the groundwork for an explanation of complicity theory, a view which sees organizational members as actively and passively serving as accomplices in acts of questionable value to the organization. Methodology Drawing from a recent study and data collection activity, we attempt to explain common behavior on the part of otherwise seemingly reasonable individuals who either fail to support or actively suppress the adoption of practices that are commonly recognized as important to the success of projects. We start by describing the study we draw from; then we explore other meta theoretical lenses that serve to clarify the motivation for this behavior. A grounded case study research (Eisenhardt, 1989, 1991) was
  • 9. appropriate for advancing theory about social processes (Hallier & Forbes, 2004; Strauss & Corbin, 2002). A case-based methodology was used for in-depth interviews with 12 management and project-related staff, for further interviews with the client organization, and for a survey of 21 managers connected to the project. However, the methodology differs from mainstream research: The researchers did not start with a particularly theoretical lens. The phenomenon observed was not expected and therefore presents the opportunity for multi- paradigmatic analysis to be undertaken (Schultz & Hatch, 1996). The Observed Phenomenon The project studied was to design, develop, and eventually, manufacture a new piece of military hardware. From its outset in 1996, it was the subject to continual slippage and cost escalation. Just two years into the project, the contractor informed the client that it was unlikely to meet timescales; a revised in-service date was agreed for March 2005. There followed a series of renegotiations of the contract terms as both sides revised their expectations for the project and introduced new approaches. By May 2002, for example, a new incremental approach to product delivery was adopted which reflected a revised assessment of operations requirements. By the end of the year, the contractor disclosed further slippage in both the budget and the schedule. These slippages were related to the contractor's underestimation of the project's technology risks, an underestimation which placed the project team under severe cost-related pressures which required further contract negotiations. The first full product test date was moved back from mid-2002 to late-2002, then to the second half of 2003. The situation failed to improve, despite a plethora of advice resulting from 11 separate reviews, which presented 255 issues to the management team. According to the project's independent auditors: Difficulties on (XXX) stem from ‘the design challenge being hugely underestimated by industry, perhaps as a result of
  • 10. continuing to see the project as if it were the adaptation of an existing [product], as it was originally intended to be, when in fact 95% of the [product] is new. Against the background of the fixed price contract, the consequent cost pressure and financial losses provided little incentive on (the contractor) to deliver. These difficulties were compounded by a weak programme management culture which lacked transparency, neglected or overrode project control systems and disciplines, and produced forecasts that lacked depth and reality. The [client's] oversight and influence was also restricted by the limited access and insight provided by the fixed price contract This threw the project into complete crisis, and in 2003, the two parties agreed, in effect, to create a new agreement which accepted the slippage, which by then, totaled 71 months. They agreed to share the costs between the two parties. Then new, revised milestones were introduced: First complete test, June 2004; award of manufacturing contract, late-2005; in-service date, 2009. Evidence of practices within the organization prior to 2003 included the following comment from one of the interviewees that: The client was worried about performance. The company was worried about cost. No-one worried about schedule. Given the continuing delays, this was to key to the idea that there was a kind of collusion here, that each party trying to protect their own interests, while missing one of the major issues that was central to the overall success of the project. Similarly, much mention was made of the prevailing technical culture, where the focus was on achieving technical excellence rather than meeting the needs of a business case. For instance, another interviewee commented: We had basic [project management] mechanisms but the ‘culture’ was not there. I was fairly typical of managers who were not concerned with business case – just did numbers to save getting [email protected]:?>< by the boss... We used to aim
  • 11. to surpass customers’ expectations – regardless of whether he wanted the features and the gold-plating. This culminated in the organization being described as: It was a terrible place to work – there was fear, the project was a dead-duck and morale was very low. And another: The programme was out of control—people weren't being true to each other about what could be achieved—either in our own organisation or the customer's organisation. We both wanted to understand that—that was as much of a driver as the performance itself. The organization responded by slowing progress further by initiating no fewer than 11 separate audits and reviews of the project which required over 170 high-level actions for management. As a result of the restructuring of the contract, the development, manufacture, and service contracts were separated out and project reforms were introduced. These project reforms included: · Allowing the client organization fuller access to industry schedule, cost, and programmed data; allowing the co-location of staff at both the manufacturing and operational bases. · The introduction of anchor milestones—targets that when achieved provide assurance that the in-service date or other contractual obligation will be met—to incentivize reform of project control systems. · A joint risk register was introduced. · Three-point estimates would be jointly calculated to measure confidence levels in the time and cost estimates for various elements of the program. · Financial data on the development and production activities would be reviewed on a monthly basis, at a joint meeting between the contractor and the client. · Earned value management (EVM) would be used to measure and communicate progress and achievement against costs and provide confidence in the quality of anchor milestone elements.
  • 12. The focus would be on measuring outcomes achieved rather than effort expended. These reforms were, according to company documentation, ‘embedded in a robust and open partnering approach that raises access, information, communication and behaviors with a greater emphasis on delivery, cost minimization and schedule adherence.’ One manager stated the benefits of this as: We now have control and predictability and can understand cause and effect in the schedule. The customer particularly likes that. We used to be cheesed off about his requirements constantly changing. It [the new approach] reduces flexibility but now easier as you can show the effects of particular changes. Plan becomes a heuristic tool as there are knock-on effects. In addition, the organization put in place a behavioral program—one aiming to legitimize and professionalize project management—as well as a leadership development program and partnering development program. However, the changes were relatively straightforward. One manager commented: Our objective was very simple—we needed conformance to a fairly basic level of proceduralisation. Within the contractor company, the reform program is held up as a great success. The project is now seen as exemplifying good or best practice throughout the parent organization. A prime outcome of the reforms is that the program is no longer under threat of closure. The company retained the business and the project now has fallen below the client's radar. The relationship with the customer is much better. Planning disciplines have been implemented. People working on the project appear motivated and confident in both the product and the new processes. However, below the surface, there is very little critique of what has been achieved in comparison to external benchmarks. During our research, we found very low levels of knowledge and certification in the firm. Management qualifications were
  • 13. not recognized: There was only one MBA, although the contractor intended to change this. The customer was similarly unknowledgeable. In terms of project management maturity, they have moved from chaotic to the use of some basic processes. More surprising, there is no desire or requirement for ongoing improvement: I don't believe we'll move the bar much beyond where it has gone already. We won't spend any more money on comparing a good programme with a bad programme – we'll send them out into the hinterland as disciples and bring in more junior people to train up. (Project Director). Despite the reforms, the project showed continued slippage in schedule and cost performance, albeit at a slower rate than before. The complicity that was stagnating performance was well established in the organization again. Data from the 21 project managers surveyed showed that: · Fifteen of the 21 agreed, and 1 strongly agreed, with the statement that they were well trained (5 neutral). · Fourteen of the 21 agreed, and 2 strongly agreed, with the statement that they had suitable education to fulfill their jobs (5 neutral). · Three strongly agreed, and 12 agreed, that management provides advanced development and training programs for organizational members. This is despite the fact that there was not a single recognized qualification among the 180 project office staff. We interpret this difference as a form of collusion. Further, this was reflected in the views of the organizational project management capability: · Fourteen of the 21 agreed, and 2 strongly agreed, with the statement that the organization is viewed as having a very strong management capability (3 neutral and 2 disagreed). · Eleven agreed, and 7 strongly agreed, that the organization had very high project management standards.
  • 14. · Fifteen agreed, and 2 strongly agreed, that this organization has superior project management practices. The benchmark here was taken as knowledge of the bodies of knowledge (APM/PMI). Not one of the interviewees demonstrated such knowledge. The last statement provides another interesting contrast with the performance that the project was again demonstrating. On the subject of performance: · Only 5 agreed that the project management practices of the organization consistently exceed expectations (15 neutral and 2 disagreed). The self delusion is evidenced by: · Eight agreed, and 2 strongly agreed, with the statement that ‘Projects in this organization are more successful than in other organizations I know’ (9 neutral and 2 disagree). · Twelve agreed, and 5 strongly agreed, that the organization delivered high quality products and services. · Twelve agreed, and 2 strongly agreed, that projects were successfully delivered. · Twelve agreed (5 neutral, 4 disagreed) that projects managed by the organization consistently deliver on their objectives. However, when broken down, we see that this was mostly in terms of technical specifications: · Two strongly agreed and 11 agreed that projects achieved their technical objectives. Whereas: · Only 5 agreed that they met their schedule objectives (10 disagreed and 1 strongly disagreed). · Nine disagreed, and 1 strongly disagreed, that they met budget objectives. In relation to their opinion of the clients’ view of projects: · Eleven agreed, and 10 were neutral, in relation to the statement: Clients are consistently satisfied by the process by which projects are managed. While the question of who is the client can here be argued, the client themselves had no reason to be satisfied with a
  • 15. renegotiated and very late project that was continuing to slip, albeit at a slower rate than before. Overall, what we witnessed was a complicity between the client and the contractor (just stay out of the press), propped up by complicity within the contracting organization (it is a good news story), and complicity in the project team (we are well qualified, knowledgeable, and doing well). The result is that poor processes and poor performance were allowed to continue with no obvious vector for improvement. Can the Theory Help Explain This? There are several theoretical approaches which might explain this observed phenomenon, including innovation diffusion theory, institutional theory, the fads and fashions literature, rational choice theory, and organizational learning. Innovation Diffusion Theory Diffusion theory concerns the role adopted by different actors: early adopters or laggards (Rogers, 1983). The first phase of the diffusion of innovative practice sees it adopted by a relatively few innovators, the early adopters. Once the efficacy of the practice is demonstrated by these early adopters, it is taken up by other organizations, and so it diffuses more generally over time, until it becomes standard practice. What we have observed above does not seem to fit easily with this, in that it is more about many years in avoiding the use of good practices that had already diffused widely into other project settings. In order for new practices to be adopted, these must first be found in some kind of search activity. It appears that there was little attempt to find a better practice until the major crisis in 2003, where the threat of program closure forced the contractor to seek alternatives. Once these were implemented, however, there was no further change. Perhaps the case organization could simply be viewed as laggards, but this is not necessarily helpful in explaining the full range of behaviors. Institutional theory would suggest that organizations in the same industry exhibit isomorphism: They will adopt similar working practices (DiMaggio & Powell, 1983). On the one
  • 16. hand, diffusing practices seen as best practice takes place encouraged by the legitimacy argument. The introduction of earned value (EV) by the project organization was legitimized by the widespread and successful use of the technique in the company's United States (US) business. Furthermore, a new manager was appointed to oversee the changes. This individual had previously worked in the US business. On the other hand, the benefits achieved by the adoption of successful practice may inhibit the adoption of superior practices in the future (Arthur, 1989). In this case, the non-adoption of superior practice in the future is not so much a result of the successful adoption of the EV technique but more a deliberate strategy not to go beyond what has already been achieved. At the level of the organization, some practices become institutionalized as rules (i.e., the way we do things around here). Such practices become embedded and are very resistant to change (Oliver, 1992). It appears that the new good practice has become institutionalized as a rule in the organization, and hence, it will be hard to change it in the future. Rational Choice Rational choice approaches to the adoption of new practices and their impact on performance include the behavioral theory of the firm (Cyert & March, 1963; March & Simon, 1967) and evolutionary economics (Nelson & Winter, 1982). These suggest that the primary driver for organizational innovations is the identification of performance gaps. When a firm's actual performance drops below its desired performance level, its performance is determined either by past performance and internal targets (Lant & Mezias, 1992) or by comparison to an external reference group (Massini, Lewin, & Greve, 2005). This performance gap will lead managers to search for new practices to improve performance. Once the new practice has been adopted and put into use, managers will compare before-and- after performance to determine whether it should be retained or discarded. Thus, rational choice presents the identification, selection, evaluation, and retention or discarding of
  • 17. management practices as relatively straightforward for managers, who should thus be viewed as rational actors searching for new practices to maintain or improve organizational performance. This clearly has not happened, except when forced in a one-step change. The project was performing poorly for many years before any change was implemented. (Problems were identified beginning in 1998 through to the final melt-down in 2003.) Furthermore, despite the opportunity for further improvement, no improvements were realized. The Institutional Approach An alternate perspective to rational choice is the institutional approach, which derives from sociology, and shifts the main focus of attention from rational choice and technical efficiency to pressures from the organization's external environment (DiMaggio & Powell, 1983). The institutional approach views all economic activity as embedded in social contexts. While firms may aspire to rational solutions to performance gaps, because of the uncertainty involved in competing practices and performance outcomes, or the alternative practices that might plausibly achieve the same outcomes, firms may be uncertain about how to achieve rational solutions. Managers instead appear as rational and progressive, according to norms of rationality (March & Olsen, 1976), they will tend to adopt institutionalized organizational practices, such as those taken- for-granted as the most appropriate means of improving performance, and hence perceive these as legitimate by key institutional actors (Abrahamson, 1996). From an institutional perspective, the explanations accompanying the adoption of a new practice become important because explaining how the practice helps managers achieve the desired performance outcomes legitimizes the practice (Green, 2004). It is also essential to constructing certain practices as taken-for-granted (Green, 2004; Suddaby & Greenwood, 2005). Hence, a focus on managerial discourse often accompanies an institutional analysis of diffusion and adoption of management
  • 18. innovations. The management fashion perspective (Abrahamson, 1991; Abrahamson, 1996; Abrahamson & Fairchild, 1999; Strang & Macy, 2001; Strang & Still, 2004) focuses particularly on the role of rhetoric and social networks in the diffusion of new practices, and the presence of bandwagons, or the number of adopters (Abrahamson & Rosenkopf, 1997). Managers must, therefore, heed key institutional actors, including consulting firms, management gurus, business mass-media publications, and business schools, each who provide important sources of information for managers about what other firms are doing. Institutional theory further specifies that the diffusion and adoption of management practices will be influenced by mimetic, coercive, and normative pressures from the external environment (Scott, 2001) to adopt certain practices. Mimetic pressures are pressures for firms to imitate the practices of other, usually successful, firms; coercive pressures are pressures to avoid sanctions from regulatory agencies and other institutional actors; normative pressures are pressures to conform to perceived professional norms. Institutional actors are thus important in driving the diffusion and adoption of management practices (Paauwe & Boselie, 2005) and there are strong sanctions associated with failing to adopt certain practices (Nelson, Peterhansl, & Sampat, 2004). However, diffusion and adoption is not only a social process, since technical, economic, and socio-psychological forces jointly shape the demand for new practices, and diffusion and adoption of practice is ultimately driven by the need to respond to organizational performance gaps. In this case, the focus of the theory is on adoption of practices, rather than explaining non-adoption as we have seen here. For instance, while there has clearly been a project management bandwagon, the case organization have taken conscious decisions to ignore it. The Organizational Learning Approach Another perspective is provided by the organizational learning literature which accepts that organizational issues create
  • 19. barriers to learning and improvement. We would suggest that this perspective is the most useful to help us understand the case presented above. In particular we draw on the concept of defensive routines (Argyris, 1993) to explain the non-adoption of promising practices from elsewhere. Organizational defensive routines exist in both private and governmental organizations, but few studies have been undertaken about how to overcome these (Argyris, 1993, p.242). Those few that do offer advice seem to suggest either bypassing the defensive routines and covering up the bypass or else acting in ways that actually strengthen the routines rather than get rid of them. An organizational defensive routine is any policy or action that inhibits individuals, groups, inter-groups or organisations from experiencing embarrassment or threat and at the same time prevents the actors from identifying the causes of embarrassment or threat. Organizational defensive routines are antilearning and over-protective. (Argyris, 1993, p. 15) The immediate effect of such policies, practices, and behaviors is to inhibit the detection and correction of error. A second- order effect is to inhibit problem solving and decision making. The third order effect is less effective organizational performance. The case above can be seen as a clear example of this. Despite the embarrassment of continually being over budget and late on schedule, the situation was allowed to continue for many years because the organization refused to experience the embarrassment. The refusal to become embarrassed by the poor performance led both sides to ignore the signals. There was complicity in this. This refusal to accept the obvious inhibited problem solving and decision making. Better to turn a blind eye than to see the problem because then something would have to be done about it. Better not to hear the news that things were going badly. Managers commented: The Company didn't ask questions because it didn't want the answers. In a programme that on day 1 was going to fail, the culture was
  • 20. ‘don't want to hear bad news.’ In a study of defensive routines in government, Argyris (1993) observed that “neither the official policies nor the administrator's espoused values was there encouragement to deceive, to manipulate, or to distort information. Nevertheless, the actions were robust; they appeared in spite of (and even because of) their deviancy from ideas in good currency on how to administer governmental agencies” (p. 19). In a similar way, neither the policies nor the espoused values of the employees and managers in the company we studied encouraged them to actively deceive, manipulate, or distort information. They simply ignored the information coming from external assessment (e.g., the auditor's reports). Their denial was robust. According to Argyris (1993), organizational defensive routines are caused by a circular, self-reinforcing process in which individuals’ theories in use produce individual strategies of bypass and cover-up, which reinforce the individuals’ theories in use. Thus the explanation for organizational defensive routines is both individual and organizational. This means that it is necessary to change both organizational and individual routines to achieve sustained change of behavior. The reform programs that the company undertook addressed this by creating a standardized approach to project management in the program so that all individuals operated in the same way and to the same norms. Our interviews confirmed this; individuals were pleased to adopt the new practices, as they could see benefit from these and their theories in use became closer to the espoused theories in the new situation. Towards a Theory of Complicity We found that when the behavior exhibited was not explained by innovation diffusion theory, the outcome was counter- rational; and it was not following the path that a fad and fashion would lead us to expect. We obtained a partial explanation for this by examining the construction and usage of defensive routines as barriers to organizational learning. This partial
  • 21. explanation is not satisfactory because it does not address their causes. Therefore, for both theoretical and practical purposes, some further explanation is required. The data provides evidence of complicity in the performance and rate of change at multiple levels: Between the client and the contracting organization, between the organization and the project, and within the project hierarchy. This complicity is causal to the failure to remove defensive routines. During the transition phase in 2003, complicity was removed at all levels, and process improvement took place. Complicity was then re- established and no further changes were made. The proposition we derive is this: Processes and practices will remain within the defensive routines of the organisation where there is complicity for them to do so. Further, we posit that: Complicity is an active state achieved where the parties to the complicity collude to allow it to be so. This is evidenced by the positive statements supporting no change that were made during each of the complicity states (pre- and post-2003). With these propositions in mind, it is appropriate to see if they may have a wider currency. For instance, there is concern about the level of improvements that are being achieved in project performance. The Standish Group's Chaos reports chronicle the outcome of IT projects (PMI, 2003; Standish Group International Inc., 2004). The project outcomes are also measured by their completion on time, budget, and quality. The TechRepublic Study by the Gartner Group paints a similar picture. In 2000, 1275 North American IT specialists were asked about the outcome of internal IT projects in terms of achieving time, cost, and quality objectives. The picture is consistently inconsistent: There are some organizations making great progress with improving process and performance, but the data from these studies does suggest that there are a considerable number who are making little progress. We
  • 22. speculate that complicity provides a possible root cause for such a situation, and that further research would demonstrate if this was in fact the case. Is There Something Particular about Project Settings that Encourages this Behavior? As suggested above, the complicity demonstrated in this case may not be an isolated occurrence. Similar to Flyvbjerg, Bruzelius, and Rothengatters (2003) studies of mega projects in transportation, key stakeholders ranging from owner organizations, government officials, and key contractors cooperated to use less than best practice project procedures. So is there something about project settings that encourages this kind of behavior? Again, the literature is not terribly helpful on this. The level of uncertainty faced by the organization is recognized as playing an important influence in best practice diffusion. O'Neill, Pouder, and Buchholtz (1998) suggest that organizations that operate in highly uncertain environments have to be very flexible and able to adapt and change their practices rapidly to meet the demands of the environmental changes. This would tend to favor rapid adoption of best practice, especially if firm survival depends on being at the forefront. In times of severe crisis, however, even these firms tend to backtrack and rely on tried-and-tested methods, thus reducing flexibility and centralizing authority (Staw, Sandelands, & Dutton, 1981). On the other hand organizations operating in highly stable environments may not see the need to change at all. According to this view then project-based organizations, which typically work in an unstable environment, would tend to be flexible and open to rapid adoption of new practices. Our case shows the opposite. Here is a project-based organization (PBO) with high levels of uncertainty in the product it is producing and which is inherently conservative in its adoption of new practices. Furthermore, it is only when it goes into a deep crisis that it responds by introducing a change of approach and the introduction of a limited range of new tools and methods.
  • 23. According to Levy (2007), stability is all-important, even at the expense of innovation and change. Perhaps, in the project environment, people seek stability, not from the organization (inherently unstable, temporary, and shifting as project progresses), the product (outcome being uncertain), but in the process, in the way they work. Tolerance of uncertainty thus limits behavior. This behavior is exhibited in defensive routines. Collusion is not a random occurrence, it is led. The collusion often wears the mask of its opposite. The collusion seeks calm waters and seeks, either consciously or unconsciously, to create safety and security through non- challenge and superficial tolerance. The result: mediocrity (Levy, 2007). This mask promotes excellence: The limited changes are held up as an amazing transformation in the corporation. It is espoused by all but the most senior people, and in the case above, including them. It is the organization's culture that presents the biggest barrier to learning. The default position is of non- change in these organizations. Even when they are forced to change by some crisis, they quickly shift back to type and rather than becoming a changed organization that is open to learning (double-loop learning), they quickly adopt a new defensive routine. Project-based organizations may therefore be more susceptible to complicity. However, it is clear that projects are not doomed to live in this world of non-adoption, as the following case will illustrate. Contrast Case: T5 The new Terminal 5 building (T5) at London's Heathrow Airport stands out as an example of rapid application of innovative approaches and processes. BAA, the client and owner of Heathrow Airport, implemented a strategic program of capability building to improve the management of its projects, and in particular, the management of T5, its biggest project ever. They learned from previous projects, individuals, and organizations that contributed to the innovative approach used
  • 24. to manage the T5 project. Between 2000 and 2002, BAA conducted in-depth analysis of every major UK construction project (over £1billion) in the previous ten years and on every international airport that had been opened in the previous ten years. This research showed that none of them had been delivered on-time and within-budget, or to the quality standards expected. They realized the only way to deliver T5 was to change the rules of the game by creating a set of behaviors that allowed people to come up with innovative solutions to problems. Not only did BAA learn internally from its past projects, it also learned externally from other airport projects, from other sectors, and from leading practice in supply chain management (SCM) and project management (Brady, Davies, Gann, & Rush, 2006). Further investigation of the approach demonstrates that there were a number of key elements present here that prevented the negative behavior of complicity that was evident in the main case. These were elements include the following: 1. Clear Policy Deployment: The objective at the outset of the project included ‘setting a new standard for project delivery’ and ‘no surprises for BAA shareholders.’ (www.baa.com ) This provided a clear statement for how resources would be allocated in support of the new standard. The behavioral contract that was put in place with contractors required this to be operationalized. 2. Knowledge Management: Learning internally from previous projects, as well as carefully selecting appropriate practices from other industries, was evident. Ongoing learning within the project was evident too, with practices such as Last Planner being used. 3. Performance Management: As stated by rational choice theory, the application of new approaches requires that there is some means to identify whether the performance is improved by any new approach. This was evident in the T5 case. The three conditions to remove the complicity also apply in the transition phase of the main case: There was a clear policy for the change, deployed throughout the project organization. There
  • 25. was appropriate knowledge brought in and process measures of performance installed. However, when these were removed, the complicity was reestablished. Conclusion This paper has demonstrated that the non-adoption of promising or good practice is supported by the existence of defensive routines. The attempts using institutional and rational choice theories to explain the phenomenon were only limited in their success. As a result, we have proposed a theory of complicity, summarized in the proposition that practices and processes will remain within the defensive routines of the organization where such complicity exists. The complicity we describe is a multi- level collusion that accepts the status quo. Project environments may be particularly susceptible to such collusion, and this may contribute to understanding why the performance of organizations in project terms is so variable, and headline rates of performance demonstrate only limited improvements. Contrary to the literature, project environments which are full of uncertainty do not appear to be the locus of rapid adoption of new practice. We further suggest that this is due in part to the desire for stability in an uncertain environment. Where the technology is uncertain, where the relationships with stakeholders are uncertain, then project members seek stability in the processes they use. There is a built-in desire not to rock the boat. Even when crises arise which force a change, the change in underlying behavior is only temporary and they snap back into their old ways of working. New defensive routines emerge to replace the old ones. It takes an enormous effort to make sustainable changes in this environment. Much further research is required before we can try to generalize these findings. However, the T5 project appears to offer hope that such sustainable change in behavior may be possible, given the right environment. While there is a general acceptance that increasing an organization's project management maturity is desirable, there are clearly some conditions that lead to this. First, there is the
  • 26. recognition of better and improved ways and the benefits that they would bring to the project organization. With the low level of knowledge that was demonstrated in the case organization, there is limited identification of areas for improvement. Second, even if these had been identified, there was no policy to drive the improvement through; in fact, the opposite was demonstrated. Last, it is clear that there was no performance management system in place that would detect if the changes had indeed been successful. The result was that there was nothing to oppose the root cause of the defensive routines that had built up in the organization, and nothing to prevent complicity from being re-established. We started from a case-based method which yielded a particular phenomenon which was unexpected. The application of various theoretical lenses provided only limited explanation of the phenomenon. Starting the research without a pre-determined theoretical stance allowed the exploration of the phenomenon in ways that would not have otherwise been possible. This appears to be useful in contributing to the methodological development of the project management discipline. References Abrahamson, E. (1991). Managerial fads and fashions: The diffusion and refection of innovations. Academy of Management Review, 16(3), 586 - 612. Abrahamson, E. (1996). Management fashion. Academy of Management Review, 21(1), 254 - 285. Abrahamson, E., & Fairchild, G. (1999). Management fashion: Lifecycles, triggers, and collective learning processes. Administrative Science Quarterly, 44(4), 708 - 740. Abrahamson, E., & Rosenkopf, L. (1997). Social network effects on the extent of innovation diffusion: A computer simulation. Organization Science, 8(3), 289 - 309. Argyris, C. (1993). Knowledge for action: A guide to overcoming barriers to organizational change. Thousand Oaks, CA: Sage Publications. Arthur, W. B. (1989). Competing technologies, increasing
  • 27. returns, and lock-in by historical events. The Economic Journal, 99(394), 116 - 131. Brady, T., Davies, A., Gann, D., & Rush, A. (2006, October). Learning to manage mega projects: The case of BAA and Heathrow Terminal 5. Paper presented at IRNOP VII Project Research Conference, Xi'an China. Cyert, R. M., & March, J. G. (1963). A behavioural theory of the firm. Englewood Cliffs, NJ: Blackwell Publishers. DiMaggio, P. J., & Powell, W. W. (1983). The iron cage revisited: Institutional isomorphism and collective rationality in organizational fields. American Sociological Review, 48(2), 147 - 160. Eisenhardt, K. M. (1989). Building theories from case study research. Academy of Management Review, 14(4), 532 - 550. Eisenhardt, K. M. (1991). Better stories and better constructs: The case for rigor and comparative logic. Academy of Management Review, 16(3), 620 - 627. Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003). Megaprojects and risk: An anatomy of ambition. Cambridge, UK: Cambridge University Press. Green, S. E., Jr. (2004). A rhetorical theory of diffusion. Academy of Management Review, 29(4), 653 - 669. Hallier, J., & Forbes, T. (2004). In search of theory development in grounded investigations: Doctors’ experiences of managing as an example of fitted and prospective theorizing. Journal of Management Studies, 41(8), 1379 -1410. Lant, T. K., & Mezias, S. J. (1992). An organizational learning model of convergence and reorientation. Organization Science, 3(1), 47 - 71. Leseure, M. J., Bauer, J., Birdi, K., Neely, A., & Denyer, D. (2004). Adoption of promising practices: A systematic review of the evidence. International Journal of Management Reviews, 5-6(3-4), 169 - 190. Levy, P. (2007). The dynamics of change. In L. Darso, S. Mesiek, & E. Boje (Eds.), The thin book of organisational theatre, ch. 4,_-_). _Aalborg, Denmark: Learning Lab.
  • 28. March, J. G., & Olsen, J. P., (1976). Ambiguity and choice in organizations. Bergen, Norway: Universitetsforlaget. March, J. G., & Simon, H. A. (1967). Organizations. New York: John Wiley. Massini, S., Lewin, A. Y., & Greve, H. R. (2005). Innovators and imitators: Organisational reference groups and adoption of organizational routines. Research Policy, 34(12), 1550 - 1569. Nelson, R., & Winter, S. (1982). An evolutionary theory of economic change. Cambridge, MA: Belknap Press. Nelson, R. R., Peterhansl, A., & Sampat, B. (2004). Why and how innovations get adopted: A tale of four models. Industrial & Corporate Change, 13(5), 679 - 699. Oliver, C. (1992). The antecedents of deinstitutionalization. Organization Studies, 13(7), 563 - 588. O'Neill, H. M., Pouder, R. W., & Buchholtz, A. K. (1998). Patterns in the diffusion of strategies across organizations: Insights from the innovation diffusion literature. The Academy of Management Review, 23(1), 98 -114. Paauwe, J., & Boselie, P. (2005). ‘Best practices…in spite of performance’: Just a matter of imitation? International Journal of Human Resource Management, 16(6), 987 - 1003. Robertson, M., Swan, J., & Newell, S. (1996). The role of networks in the diffusion of technological innovation. Journal of Management Studies, 33(3), 333 - 360. Rogers, E. (1983). The diffusion of innovation. New York: Free Press. Schultz, M., & Hatch, M. J. (1996). Living with multiple paradigms: The case of paradigm interplay in organizational culture studies. The Academy of Management Review, 21(2), 529 - 557. Scott, W. R. (2001). Institutions and organisations. Thousand Oaks, CA:Sage Publications. Standish Group International Inc. (2004). The Chaos Report. West Yarmouth, MA:The Standish Group International Inc. Staw, B. M.. Sandelands, L. E., & Dutton, J. E, (1981). Threat rigidity effects in organizational behavior: A multilevel
  • 29. analysis. Administrative Science Quarterly, 26(4), 501 - 524. Strang, D., & Macy, M. W. (2001). In search of excellence: Fads, success stories, and adaptive emulation. American Journal of Sociology, 107(1), 147 - 182. Strang, D., & Still, M. C. (2004). In search of the élite: Revising a model of adaptive emulation with evidence from benchmarking teams. Industrial & Corporate Change, 13(2), 309 - 333. Strauss, A. L., & Corbin, J. (2002). Basics of qualitative research: Grounded theory procedures and techniques. Thousand Oaks, CA: Sage Publications. Suddaby, R., & Greenwood, R. (2005). Rhetorical strategies of legitimacy. Administrative Science Quarterly, 50(1), 35 - 67. 1 Project funded by PMI This material has been reproduced with the permission of the copyright owner. Unauthorized reproduction of this material is strictly prohibited. For permission to reproduce this material, please contact PMI or any listed author. © 2008 Project Management Institute