3. 2018#apricot2018 45
Upstream Providers
• Subisu Cablenet Pvt. Ltd (AS4007)
– 2 X 10 Gbps Link from two different pops for IP Transit
– 1 X 1Gbps Link for npIX
• Worldlink Communication Pvt. Ltd (AS 17501)
– 2 X 10 Gbps Link from two different pops for IP Transit
• Full BGP feed IPv4 and IPv6 from both providers
6. 2018#apricot2018 45
Timeline
• Before 15 Feb: equipment collection, planning, route
announcements, fiber drop to Hotel
• 15 Feb : Move-in, rack/gateway setups
• 16-18 Feb : Ethernet cabling to all areas, AP / Switch installation,
network optimization
• 19 – 24 Feb : Workshop Week support and prep for conference
week
• 25-28 Feb : Conference setup
• 28 Feb – 2 March : Turn down.
6