Your agile team has been asked by senior management to produce and distribute a weekly performance report on the status of the overall project. Which of the following is not typically included on this report? a) Actual task start and finish dates b) Completed and accepted user stories c) Product Backlog progress d) Comparison of user stories delivered and sprint/iteration plans.