- 1. © mimacom ag
A fixed-price project with
Scrum
Case Study
Jan Gregor
- 3. © mimacom ag
A fixed-price project with Scrum
• We will talk about...
└ The starting position
Extranet reporting application for a fixed price
└ The basics
Money for nothing - change for free (Sutherland)
└ The implementation
2 processes, 1 planning, 2 controls
5/15/13 3
- 4. © mimacom ag
Our Motto
5/15/13 4
Comment
• Systematical
Feedback
• Continous feedback
loops on every
level
└ in team
└ in project
└ to
managemenmt
└ to customer
Like
} Consequent
value driven
} Continous
evaluation of
every action
focused on the
desired value
Share
} One truth
} Shared toolchain
without barriers
- 5. © mimacom ag
A Fix-priced project with Scrum
5/15/13 5
• Online reports
• Web application
• Data warehouse
architecture
• 10‘000 users
• 2 TB data
• 2 years project
duration
• 10 PYs
• Individual development for fixed
price
Supplier
Classic
Project
Fixed price
Scrum
Customer
Features Changes
Bugs
Product Project
Middle
Business Value
- 6. © mimacom ag
Time & Material project
5/15/13 6
6
Euro
Effort (h)
Profit
Interest
Interest
Contractor
Customer
- 8. © mimacom ag
Money for nothing
5/15/13 8
8
Interest
Interest Interest
Effort (h)
Euro
Profit
Contractor
Customer
- 10. © mimacom ag
Freedom in Scope
Value
(per Feature)
Order
Jeff Sutherland, Money for Nothing
Degree of freedom
(Savings potential)
Feature
Good enough
Minimum
- 11. © mimacom ag
Change for free
Jeff Sutherland, Money for Nothing
Feature
New feature replaces the old
Value
(per Feature)
Order
û
- 13. © mimacom ag
Our cooperation
Basics
• The planning tool – rolling, visible for all
• Cost controll – daily status and forecast
• Value driven – expected succes navigates the project
Must
• Changes without change process – therefore cost-free (but not
free of charge)
• Value driven financing
• One planing for all - features, changes and bugs
Nice to have
• Freedom to invest either in bugs / new features
- 14. © mimacom ag
• Savings : 30% from all specified
features skipped
• 42% of total features changed
• Value driven approach
improved project steering in
management board
• Objective discussion by
separation of planning and
financing
• Cross-subsidization of
features may be dangerous
• Changes are not for free :
effort for specification,
clarification and planning
considered
Jan.Gregor@mimacom.com Joscha.Jenni@mimacom.com