TECHNICAL DEPARTMENT
Maximo Project Implementation Update
(Mini LMM)
November 2005
B. El Medkour & M. Al-Muhaisen
2
Maximo Project/ Mini LMM November 2005
Contents
 Why Maximo Project?
 What is Maximo templates?
 Project preparations in Year 2004
 JCF Vision for the Maximo Project
 Maximo Project Implementation
 Rashadiya Plant Projects ( 2005/2006)
 Equipment data file project
 Fuhais Plant Projects (2005/2006)
 Equipment data file project
 Executable job plan project & inspection/planning Action Plans
3
Maximo Project/ Mini LMM November 2005
Why Maximo Project?
4
Maximo Project/ Mini LMM November 2005
Maximo Project Objectives
• Maximo will be a tool for improving P.M. practices
• Tool to help maintenance organization to control their activities
( inspection, executions, scheduling, planning,
costing,management, improvement, etc.)
• Improve maintenance efficiency through easy analysis of
historical data, retrieval & traceability of all information
• To unifying both plant best practices & behaviors such as same
reports, procedures, etc.
• Tool for controlling & analyzing the performance of
maintenance organization in both plants
Retune
5
Maximo Project/ Mini LMM November 2005
What is Maximo Template?
6
Maximo Project/ Mini LMM November 2005
Maximo Template Definition
What is a Template :
The Template is only a tool which formalizes & helps maintenance practices evaluation and
service Lafarge Maintenance policy, it contains
 Validated and documented Best practices
 Key performance indicators
 Pre customized modules
 Interfaces with other Templates or standard tool
 e.g. Interface Maximo and JDE for purchasing
 e.g. Interface Maximo and ADAP
Best Practices
Pre customized Tool
7
Maximo Project/ Mini LMM November 2005
 Methodology for roll out
 Training kit (users, tool,etc.)
 Central support for roll out
 Template maintenance and evolution
Material for training & roll out
Support
Why the Maximo Template Project ?
 End 2000, the Division decided to develop a template for Maximo :
 to design and build a pre-configured tool to support Maintenance Best Practices
and to be used as a catalyst for their implementation
 to reduce cost and time of implementation
Associated
service
Retune
8
Maximo Project/ Mini LMM November 2005
Project Preparation in Year 2004
9
Maximo Project/ Mini LMM November 2005
Project Preparation in Year 2004
 Audit & Review all the maintenance activities & best practices
in both plants and the following was noticed & observed:-
1. 1st level inspection is well practiced
2. Some of the Job Plans requires enhancement & improvement in content
3. Specific Job Plans are not fully implemented and not managed through
PMS
4. Inspectors needs a support from execution team in order to perform
specific Job Plans without difficulties as per schedules :
 To provide qualified skills to help inspectors during dismantling & assembling
 To arrange a weekly coordination meeting between Method & Execution Departments
5. There is no inspection job plan for execution team. Most of the executable
prepared Job Plans are having the concept of Replaceable Job Plans
(condition based job plans).
6. All the specific Job Plans that are related to Packing Plant are not
implemented Yet
7. New Job Plans During stoppage need to be created for certain equipment
10
Maximo Project/ Mini LMM November 2005
• Based on the Audit results an Emergency Action Plan were put
and covered the following actions :-
• Job Plans enhancement & improvement as listed in TD Report
• Implementing of new executable Job Plans for level 5 & some of level
6 equipments
• Packing plant Specific Job Plans implementation & coaching
• Implementing new Job Plans during stoppage for 1st level
• New form creation as listed in TD report
• Selecting Job Plans from 1st & specific Job Plans for routine periodic
inspection for Raw Mills, Kilns & Cement Mills
• Weekly generation of Job Plans in Summary Sheet
• Weekly maintenance coordination meeting for Job Plans
• Work order cycle review & enhancement
• Manage the New created executable Job Plans through PMS
Project Preparation in Year 2004
11
Maximo Project/ Mini LMM November 2005
• Preparation & Activities carried out on the Maximo Project
Level :-
1. Nomination of Both Plant coachers & Rashadiya Plant Project Core team
2. Training both Plant coacher on Maximo 4i Screens & Menus (July 2004)
2. Preparation of JCF main vision for the whole project
3. 1st Draft for Project charter, Budget and schedule was discussed & reviewed with
CTI & BS End of June 2004 at Amman with attendance from both TD & IT
Departments
4. JCF vision for the project was presented and all Maximo project documentations
were distributed in October 2004
5. Investment credit for the whole project was opened on October 2004
6. All the project Hardware was ordered on October 2004 ( all the Servers)
9. Present JCF vision for the project in the Rashadiya Plant( November 2004)
10. A Weekly coordination meeting between TD & IT Dept. Started since November
2004 to review the progress in the project prerequisites & to prepare detailed
schedule for:-
 Hardware installation ( servers)
 Software installation. ( Oracle 9i & standard Maximo)
Project Preparation in Year 2004
Retune
12
Maximo Project/ Mini LMM November 2005
JCF Vision for Maximo Project
13
Maximo Project/ Mini LMM November 2005
• We started the implementation with what run P.M.’s
• The implementation will is split into Two Stages and each stage consists of
multi-Phases as follow:
1. Stage one in year 2005 concentrated on ( Rashadiya plant):-
• Equipment codification
• 1st & specific inspection job plans
• Execution Job plans
• Lubrication Job plan
• Safety aspects written in the Job plans
• Equipment Data file (only equipment specifications)
• Work order cycle with workflow
• Basic Planning & scheduling
• Basic reports
Note: Same Stage activities will be repeated in 2006 for Fuhais Plant
2. Live Run implementation was performed in 3 Phases
JCF Maximo Project Methodology & Approach
14
Maximo Project/ Mini LMM November 2005
3. Stage Two in year 2006 (Rashadiya Plant) and this will cover remaining
activities :-
• All the interfaces (Maximo-JDE, Maximo-MS-project, etc)
• Equipment Data file ( Spare parts)
• Advance Planning & scheduling
• Budget management
• Safety management as per BU-BP-0064
• History files ( if required to customize special screen)
• Other Reports
• On 2nd half of 2006, we will start preparation for all production data (
inspections, house keeping, No load-Start up tests) and these will be test
before End of project
Note: Same stage Two activities will be repeated in 1st Quarter of 2007 for
Fuhais Plant
JCF Maximo Project Methodology & Approach
15
Maximo Project/ Mini LMM November 2005
Methodology & Approach
• Start implementation on January 2005 with Rashadiya Plant Followed
after by Fuhais Plant, due to following:
• High number of End users
• Rashadiya plant is more prepared than Fuhais
• It was agreed that 2 coachers at Plant level will be fully dedicated to the
project & working with TD and those will :-
• Learn MAXIMO Template and maintenance BPs
• Participate in analysis and Process Improvement Workshops
• Support the end-users to perform their tasks after the training session
• Train with other trainers the end-users
• Future MAXIMO administrator at plant level
• As agreed with Fuhais Plant Management, implementation will be started
in the plant on beginning of June 2006 & Fuhais plant Coacher will
Participate in Rashadiya Implementation
16
Maximo Project/ Mini LMM November 2005
Maximo Roll-out Organisation
Regional
Level
Division
Level
BU
Level
Plant
Level
Business Side « IT » Side
IT Competency Centre
Montreal
Business Competency Centre
Lyon (DPC)
Technical Direction
IT Correspondant
Maintenance
Champion
Maintenance Template Coordination
(DPC + Business Systems)
Technical Centre
IT Department
IT Regional
Maintenance
Project
17
Maximo Project/ Mini LMM November 2005
Project Organization
• Two level of organization is going to be during the project implementation
and mainly that covers the need for Year 2005. In Year 2006 the
organization will be adjusted as per requirements. The levels are as
follow:-
A- Technical Department ( TD) & IT Dept. Level
B- Plant Level
• TD is leading all the project organization at TD & Plant level
• The project progressed in collaboration with Technical Centre (CTI),
Lafarge IT, Maximo competency Centre, Plant personnel and the local
supplier if required
18
Maximo Project/ Mini LMM November 2005
Project Organization chart
Project Manager
Project Champion
(Start to End)
Rashadiya Plant Maximo Champion
(25% of the Time)
Mech. Inspectors ( 1 Year)
Elect/Inst Inspector(6 Months)
Planners/ Lubrication( 1 Year )
Draft man( As needed)
Data entry ( Start to End)
Maximo Coach/Rashadiya
(100% of the Time)
Maximo Coach/Fuhais
(100% of the Time
Fuhais Plant Maximo Champion
(25% of the Time)
Mech. Inspectors ( 1 Year)
Elect/Inst Inspector(6 Months)
Planners/ Lubrication( 1 Year )
Draft man( As needed)
Data entry ( Start to End)
IT Specialist
(100% of the Time)
IT Coordinator
(30% of the Time)
At BU level during
JED/Maximo interface
stage, Finance &
Purchasing Departments
will be involved in the
project
Note:
Plant Core team members at
Plant level will be adjusted as per
project requirements during Year
2006 ( i.e. Production checklist,
JED interface, Safety, etc.)
19
Maximo Project/ Mini LMM November 2005
Project Organization
• Two committees on the Top Management Level is formed in order to Control,
Assist & Evaluate the project progress as follow :-
A- Executive Committee ( Monthly)
To coordinate the day to day activities of the project and derive and manage
project plan . Also to monitor progress against the plan & budget, also identifying
logistics and resources
B- Steering / EXCOM Committee ( Every 4 month)
To provide overall guidance to the project and monitoring the progress, also to
address local requirement issues, project planning and tracking and other site-
specific issues such as logistics and resources
20
Maximo Project/ Mini LMM November 2005
Jordan Cement Company Maximo Project Executive committee
Maximo
Project
Manager
IT Manager Fuhais
Maintenance
Manager
Fuhias
Method
Manager
( Plant
Maximo
Champion)
Rashadiya
Plant Deputy
Manager
Rashadiya
Maintenance
Manager
Rashadiya
Method
Manager
( Plant
Maximo
Champion)
Maximo
Project
Champion
Jordan Cement Company Maximo Project Steering committee
Manufacturing
V.P.
Technical V.P. Fuhais Plant
Manager
Rashadiya Plant
Manager
CTI
Relation Director
Financial V.P.
21
Maximo Project/ Mini LMM November 2005
Roll-Out Organization/Roles & Responsibilities
CTI :
1. Assistance to Project Charter
2. Organization of training sessions specific to Maximo Template
with cement Division resources
3. Assistance for consistency of Maximo Template implementation
according to Cement Division rules and objectives
MCC/ BS (Maximo Competency Center / Business System) :
1. Assistance to Project Charter
2. Recommend/validate hardware, software and network Architecture
3. Provide Maximo Template material and Template for interface to JDE
(including MEA part)
4. Systems expertise and support for IT Template related issues
5. Ensure knowledge transfer for the IT part
22
Maximo Project/ Mini LMM November 2005
Roll-Out Organization/Roles & Responsibilities
BU Team ( TD) :
1. Develop and update implementation schedules and plan& monitor and
track budget to actual
2. Communicate high level status of the project
3. Facilitate execution of the project plan & provide 1st level support
4. Learn MAXIMO Template and maintenance BPs
5. Conduct analysis and Process Improvement Workshops
6. Ensure MAXIMO Coach prepare end user training materials
7. Coordinate with Lafarge to train MAXIMO Coach and other relevant
participants
8. Manage implementation team members’ involvement
23
Maximo Project/ Mini LMM November 2005
Roll-Out Organization/Roles & Responsibilities
BU (IT) :
1. Facilitate MAXIMO implementation for IT
2. Coordinate with competency center and MRO
3. Prepare IT environment (PC installation, Network adjustment, software
installation and etc …)
4. Provide first IT level support for both hardware and software
5. Assist Project Champion when require
6. Participate in MAXIMO/JDE & Maximo/MS Project Interface
preparation, implementation,testing and lunching
7. Manage the MAXIMO & JDE installation
Local Supplier :
1. Hardware supply, configuration and maintenance
2. Oracle database installation & Basic Maximo installation (if required)
3. Possible developments for localization (data conversion, additional
reports, additional interface with automation systems…)
24
Maximo Project/ Mini LMM November 2005
Plant Core Team :-
1. Up-date all the Job plans ( Mech.& Elect. ) 1st, specific, executions, lubrication etc.
2. Build P.M templates as Per Lafarge requirements
3. Implement equipment data files
4. Lead, implement and monitor MAXIMO Best Practices and Maintenance organization
best practices
5. Ensure that all pre-requisites of Maintenance organization & best practices are in
practice for smooth implementation of this project.
6. Ensure all documents (Job Plan, Inspection plan, Preventive Maintenance and etc …)
will be ready at the right time
7. Adopt and practice all pre-requisites of Maintenance organization & best practices
8. Ensure all documents (Job Plan, Inspection plan, Preventive Maintenance and etc …)
captured in MAXIMO contain detail & meaningful information
9. Data Conversion verification for MAXIMO data
10. Prepare all the open date balance for meter base PM’s ( Lubrication Mainly)
Roll-Out Organization/Roles & Responsibilities
25
Maximo Project/ Mini LMM November 2005
Rashadiya Plant Roll out Project Activities schedule
26
Maximo Project/ Mini LMM November 2005
Training
A) Technical Department (TD) & Coacher level (During Year 2004) :-
• Visit to a plant that has a successful implementation of Maximo.
• Detailed training on Maximo 5.2 Template & Business processes
• Discuss with CTI/BS the latest Lafarge Maximo 5-2 template & Business processes
B) Plant Core Team level :-
• Awareness program for Maximo screens (one day during 2004).
• MRO basic training course on Managing Work with Maximo 5.2
• Training on Maximo 5.2 Template( Data Base Creation ,Jan. 2005)
C) Plant End User level :-
• Awareness program for Maximo screens (one day during April 2005).
• Training on Maximo 5.2 By Profile and as per project stages (2nd half of Year 2005)
Note: Item B & C will be repeated in year of 2006 for Fuhais Plant
Retune
27
Maximo Project/ Mini LMM November 2005
Maximo Project implementation
28
Maximo Project/ Mini LMM November 2005
Project Progress
• MAXIMO Implementation Project Progress
• Project Preparation: March 2004
• Project start : 1st January 2005
• Project Expected completion date : 31st December 2006
• Project Overall Progress : 46 % up to 17th October 2005
29
Maximo Project/ Mini LMM November 2005
BU
Plant
Fuhais
Budget
Return
WBS Start Finsh Progress %
1 17-May-04 31-Dec-06 46%
1-1 17-May-04 31-Dec-06 68%
1-2 24-Nov-04 31-Dec-06 40%
1-2-1 24-Nov-04 28-Dec-05 93%
1-2-1-1 24-Nov-04 28-Dec-05 93%
1-2-1-1.5
Maximo Pilot Shop Rashadiya Plant -
Phase I (Raw Mix)
2-Jan-05 30-Jun-05 100%
1-2-1-1.6
Maximo Roll Out in Rashadiya Plant -
Phase II (Burning, Crushing & Utilities)
22-May-05 13-Oct-05 95%
1-2-1-1.7
Maximo Roll Out in Rashadiya Plant -
Phase III ( CM's, Packing & all remaining
Plant Stages)
26-Sep-05 28-Dec-05 35%
1-2-2 24-Nov-05 31-Dec-06 0%
1-2-2-1 A- Fuhais Plant 2-Jan-06 27-Dec-06 0%
1-2-2-2 B- Interfaces 2-Jan-06 28-Dec-06 0%
1-2-2-3 C- Budget Management 2-Jan-06 31-Dec-06 0%
1-2-2-4 D- Safety Management 24-Nov-05 30-Dec-06 0%
1-2-2-5 E- Production Data 2-Jan-06 31-Dec-06 0%
1-3 Meetings 17-Jan-05 28-Dec-06 30%
Task Name
Stage One - Year 2005
Rashadiya Plant
Stage Two - Year 2006
Maximo at BU level
Maximo at Plant Level
MAXIMO Implementation
Project for Jordan Cement
Company
Project Progress up to October 2005
30
Maximo Project/ Mini LMM November 2005
• BU Level (TD & IT)
1. Preparation of Project charter, Budget & detail project schedule
2. Ordering & installation of all Software & hardware
3. Installation of Maximo Template with support from MCC
4. Train all the End users(Around 55 person) on How to utilize Lafarge best
practices through Maximo Software. All training was conduct by Maximo BU
Team for almost 3 weeks (NO Outside consultant)
5. Coach all the End users for around 7 weeks before, during Go live period and
2 days weekly after implementation
6. Preparation of all Maximo database Environments (Test, Train, & Production)
7. Freeze & stop using the existing Work Order System for All Plant Stages ( all
corrective WO’s Running through Maximo since 22nd September 2005) .
8. Discussing with MCC & CTI about all the required enhancements &
modification needed on the Maximo Template
9. Prepare locally all the tables & data for Light interface which launched in
October 2005.
10. BU (TD & IT) overall project progress is 68 %
Maximo Project Progress/ Rashadiya Plant
Return
31
Maximo Project/ Mini LMM November 2005
• Plant Level
1. Maximo Minimum coding & location creation
2. Creation of Mechanical Execution Job Plan (119 Job Plan)
3. Creation for Lubrication 1st level inspection for whole plant.
4. Identify the specific Job Plan Measuring points
5. Review the Job plans content & make the required enhancements .
6. Creation of PM routes
7. Prepare the User & Workflow Privileges
8. Prepare linked documents
9. Review & refine all the users privilege on the Maximo Production
Environment database.
10. Review all Maximo Production Environment Mechanical, Electrical &
instrumentation PM’s and fixing the start date for all PM’s .
Maximo Project Progress/ Rashadiya Plant
32
Maximo Project/ Mini LMM November 2005
• Plant Level
11. Reviewing & checking all created Routes ( 1st level inspection) on Maximo
Production Environment .
12. Work order generation for all the PM’s on the Maximo Production
Environment
13. Go live for step Phase I &II was launched on July & September 2005
14. Run all corrective WO’s through Maximo
15. Arabic instructions document was prepared by Maximo coacher for End
users to facilitate their navigation
16. Rashadiya Plant overall project progress is around 72%
Maximo Project Progress/ Rashadiya Plant
33
Maximo Project/ Mini LMM November 2005
Next Activities
Maximo Project Progress
 Create All asset catalogue templates on Maximo & fill the data on Maximo equipment
module screens
 Link Each Equipment with it’s spare parts through the Spare parts Tab in the
Equipment Module
 Run interface between Maximo-MS-Project in order to be ready before Major
shutdown (waiting to Purchase MS Project version 2003)
 Prepare the schedule for advance training courses:-
 Mainly Planners & inspectors
 IT & Maintenance staff for Actuate Report writer
 Adjust the IT & plant core team Organization based on Year 2006 requirements
 Start Preparing all the Repairable/Replaceable Job Plan
 Start Preparing to create Production Job plans (Shift Production checks, shutdown &
cleaning activities)
The go live for Phase III is Expected to be Mid of November 2005
(one & half Month before Schedule)
(this will complete the stage I of Maximo project Implementation)
 Implement all activities for project Stage II during Year 2006 Return
34
Maximo Project/ Mini LMM November 2005
Maximo project at Fuhais plant
 TD and plant are working on the required organization of this project
next, the objective is to nominate Maximo team on December
 The plant team will be built according to the progress of all maintenance
actions followed by TD at Fuhais plant
 Implementation will start beginning of January 2006
Return
35
Maximo Project/ Mini LMM November 2005
Maximo Project/ Mechanical Execution Job Plans
Why Mechanical Execution Job Plans??
These are a 1st level Inspection Job plans with a minor repair performed
during equipment stoppage by execution team, and they have a big impact
to improve RF for equipments.
• Creation of (119) New Mechanical Executable Job Plan By Maximo team
• TD team with Maximo Plant coacher,coached the implementation of these
new type of job plans & explained to Execution team How to perform them
& almost around.
• Project progress is around (119/119)= 100%
Return
36
Maximo Project/ Mini LMM November 2005
 All the Plant lubrication system was schedule to be Launched with
Maximo 1st phase Implementation for the whole plant and it was
launched completely starting from September 2005
 Work order generation for all Lubrication PM’s on the Maximo
Production Environment:-
 1st Level inspection (make up Lubrication)
 Specific inspection ( Shutdown, Drain )
 The feedback got from Lubrication team is promising & they are happy
with the system ( 1st in Lafarge Group using Maximo 5.2 in managing
Lubrication Activities)
Maximo Project/ Lubrication System
Return
37
Maximo Project/ Mini LMM November 2005
Maximo Project Progress/ Hardware Configuration
Return
38
Maximo Project/ Mini LMM November 2005
• Total Appropriation Value : 426 KJD
• Total Forecasting Value : 1.5 KJD
• Total Actual Booking Value (Paid) : 179.073 KJD
• Total Appropriation Balance Value : 245.427KJD
Investment Project Cost Control
39
Maximo Project/ Mini LMM November 2005
Summary of the Estimated Project Budget/ Based on
Centralized Scenario
Budget Item Cost (KUSD)
Consulting 276
Hardware 100
Software 122
Training 41
Grand Total 544
Grand Total with 10%
Contingency
599
Retune
40
Maximo Project/ Mini LMM November 2005
Data File Project Progress/Rashadiya
 The team accomplished a very good progress in Data sheet preparation
compared with last two month progress & they achieved :-
 68 % progress up to 15th September 2005
 In parallel, progress in Spare Part Defining is :
 46 % progress up to 15th September 2005
 Team started up loading all the prepared Data in to Maximo manually &
linking all JDE spare with equipments starting from End of September
2005.
 Target competition date for the project is End of Year 2006.
Retune
41
Maximo Project/ Mini LMM November 2005
B- Fuhais Plant Projects
42
Maximo Project/ Mini LMM November 2005
1. A presentation that included an examples & explanation on the concept
of these Job Plans was conducted by TD to all Plant Mechanical
Engineers. (January & February 2005)
2. A round 100 Mechanical Execution Job plans examples from Rashadiya
Plant were Provided to Fuhais Maintenance Manager
3. Cement mills already completed and validated by TD, it will be launched
end of October
4. Crusher area completed and validated by TD, it will be launched after
kiln shutdown beginning of November
5. Ram mill area under progress
6. Commitment by team that all executable job plan will be completed
before major shutdown
Mechanical Execution Job Plans
43
Maximo Project/ Mini LMM November 2005
Data File Project Progress/Fuhais
 Pilot shop (shop 226) was completed on 20th March 2005 :
 100% in Electrical equipment data sheet specifications ( 38 equipment)
 100% in Mechanical equipment data sheet specifications ( 43 equipment)
 100% Progress in Spare parts
 The new team accomplished a very good progress in Data sheet preparation
(CM 2 shop) compared with last period & they achieved :-
 41 % progress up to 13th October 2005
 A detailed draft schedule for the whole plant will was prepared end of
October 2005
 All the prepared spare part will be sent to Planning Section Head for
validation.
Retune
44
Maximo Project/ Mini LMM November 2005
The End

More Related Content

Similar to Maximo_Mini LMM November 2005.ppt

Spm ksp
Spm kspSpm ksp
Spm kspktosri
 
Presentation how a traditional project manager transforms to scrum - final
Presentation   how a traditional project manager transforms to scrum - finalPresentation   how a traditional project manager transforms to scrum - final
Presentation how a traditional project manager transforms to scrum - finalSadaf Saad
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011tigcap
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011tigcap
 
GIS_Office_Project_Management_Framework_Presentation
GIS_Office_Project_Management_Framework_PresentationGIS_Office_Project_Management_Framework_Presentation
GIS_Office_Project_Management_Framework_PresentationBert Bruijn
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sampleNada Sallam
 
Operation Management
Operation ManagementOperation Management
Operation ManagementPrabu U
 
PMO standardisation - simple tracking process
PMO standardisation - simple tracking processPMO standardisation - simple tracking process
PMO standardisation - simple tracking processPM Majik
 
eCIO PPT Roles for a SAP and Systems Integration Project
eCIO PPT Roles for a SAP and Systems Integration ProjecteCIO PPT Roles for a SAP and Systems Integration Project
eCIO PPT Roles for a SAP and Systems Integration ProjectDavid Niles
 
CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)Pamela Garrett
 
Arokia Raj RM Resume
Arokia Raj RM  ResumeArokia Raj RM  Resume
Arokia Raj RM Resumearokiagetz
 
PM B Presentation
PM B PresentationPM B Presentation
PM B PresentationMariam Ali
 
Having a PMO with agile flavor
Having a PMO with agile flavorHaving a PMO with agile flavor
Having a PMO with agile flavorImad Alsadeq
 
Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...IRJET Journal
 

Similar to Maximo_Mini LMM November 2005.ppt (20)

Spm ksp
Spm kspSpm ksp
Spm ksp
 
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
 
Practical experiences of portfolio management
Practical experiences of portfolio managementPractical experiences of portfolio management
Practical experiences of portfolio management
 
Blackbaud project kick off summary
Blackbaud project kick off summaryBlackbaud project kick off summary
Blackbaud project kick off summary
 
Presentation how a traditional project manager transforms to scrum - final
Presentation   how a traditional project manager transforms to scrum - finalPresentation   how a traditional project manager transforms to scrum - final
Presentation how a traditional project manager transforms to scrum - final
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011
 
module%202.pptx
module%202.pptxmodule%202.pptx
module%202.pptx
 
GIS_Office_Project_Management_Framework_Presentation
GIS_Office_Project_Management_Framework_PresentationGIS_Office_Project_Management_Framework_Presentation
GIS_Office_Project_Management_Framework_Presentation
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 
Operation Management
Operation ManagementOperation Management
Operation Management
 
Erp.ppt
Erp.pptErp.ppt
Erp.ppt
 
PMO standardisation - simple tracking process
PMO standardisation - simple tracking processPMO standardisation - simple tracking process
PMO standardisation - simple tracking process
 
eCIO PPT Roles for a SAP and Systems Integration Project
eCIO PPT Roles for a SAP and Systems Integration ProjecteCIO PPT Roles for a SAP and Systems Integration Project
eCIO PPT Roles for a SAP and Systems Integration Project
 
CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)
 
SAP sample
SAP sampleSAP sample
SAP sample
 
Arokia Raj RM Resume
Arokia Raj RM  ResumeArokia Raj RM  Resume
Arokia Raj RM Resume
 
PM B Presentation
PM B PresentationPM B Presentation
PM B Presentation
 
Having a PMO with agile flavor
Having a PMO with agile flavorHaving a PMO with agile flavor
Having a PMO with agile flavor
 
Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...
 

Recently uploaded

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 

Recently uploaded (20)

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 

Maximo_Mini LMM November 2005.ppt

  • 1. TECHNICAL DEPARTMENT Maximo Project Implementation Update (Mini LMM) November 2005 B. El Medkour & M. Al-Muhaisen
  • 2. 2 Maximo Project/ Mini LMM November 2005 Contents  Why Maximo Project?  What is Maximo templates?  Project preparations in Year 2004  JCF Vision for the Maximo Project  Maximo Project Implementation  Rashadiya Plant Projects ( 2005/2006)  Equipment data file project  Fuhais Plant Projects (2005/2006)  Equipment data file project  Executable job plan project & inspection/planning Action Plans
  • 3. 3 Maximo Project/ Mini LMM November 2005 Why Maximo Project?
  • 4. 4 Maximo Project/ Mini LMM November 2005 Maximo Project Objectives • Maximo will be a tool for improving P.M. practices • Tool to help maintenance organization to control their activities ( inspection, executions, scheduling, planning, costing,management, improvement, etc.) • Improve maintenance efficiency through easy analysis of historical data, retrieval & traceability of all information • To unifying both plant best practices & behaviors such as same reports, procedures, etc. • Tool for controlling & analyzing the performance of maintenance organization in both plants Retune
  • 5. 5 Maximo Project/ Mini LMM November 2005 What is Maximo Template?
  • 6. 6 Maximo Project/ Mini LMM November 2005 Maximo Template Definition What is a Template : The Template is only a tool which formalizes & helps maintenance practices evaluation and service Lafarge Maintenance policy, it contains  Validated and documented Best practices  Key performance indicators  Pre customized modules  Interfaces with other Templates or standard tool  e.g. Interface Maximo and JDE for purchasing  e.g. Interface Maximo and ADAP Best Practices Pre customized Tool
  • 7. 7 Maximo Project/ Mini LMM November 2005  Methodology for roll out  Training kit (users, tool,etc.)  Central support for roll out  Template maintenance and evolution Material for training & roll out Support Why the Maximo Template Project ?  End 2000, the Division decided to develop a template for Maximo :  to design and build a pre-configured tool to support Maintenance Best Practices and to be used as a catalyst for their implementation  to reduce cost and time of implementation Associated service Retune
  • 8. 8 Maximo Project/ Mini LMM November 2005 Project Preparation in Year 2004
  • 9. 9 Maximo Project/ Mini LMM November 2005 Project Preparation in Year 2004  Audit & Review all the maintenance activities & best practices in both plants and the following was noticed & observed:- 1. 1st level inspection is well practiced 2. Some of the Job Plans requires enhancement & improvement in content 3. Specific Job Plans are not fully implemented and not managed through PMS 4. Inspectors needs a support from execution team in order to perform specific Job Plans without difficulties as per schedules :  To provide qualified skills to help inspectors during dismantling & assembling  To arrange a weekly coordination meeting between Method & Execution Departments 5. There is no inspection job plan for execution team. Most of the executable prepared Job Plans are having the concept of Replaceable Job Plans (condition based job plans). 6. All the specific Job Plans that are related to Packing Plant are not implemented Yet 7. New Job Plans During stoppage need to be created for certain equipment
  • 10. 10 Maximo Project/ Mini LMM November 2005 • Based on the Audit results an Emergency Action Plan were put and covered the following actions :- • Job Plans enhancement & improvement as listed in TD Report • Implementing of new executable Job Plans for level 5 & some of level 6 equipments • Packing plant Specific Job Plans implementation & coaching • Implementing new Job Plans during stoppage for 1st level • New form creation as listed in TD report • Selecting Job Plans from 1st & specific Job Plans for routine periodic inspection for Raw Mills, Kilns & Cement Mills • Weekly generation of Job Plans in Summary Sheet • Weekly maintenance coordination meeting for Job Plans • Work order cycle review & enhancement • Manage the New created executable Job Plans through PMS Project Preparation in Year 2004
  • 11. 11 Maximo Project/ Mini LMM November 2005 • Preparation & Activities carried out on the Maximo Project Level :- 1. Nomination of Both Plant coachers & Rashadiya Plant Project Core team 2. Training both Plant coacher on Maximo 4i Screens & Menus (July 2004) 2. Preparation of JCF main vision for the whole project 3. 1st Draft for Project charter, Budget and schedule was discussed & reviewed with CTI & BS End of June 2004 at Amman with attendance from both TD & IT Departments 4. JCF vision for the project was presented and all Maximo project documentations were distributed in October 2004 5. Investment credit for the whole project was opened on October 2004 6. All the project Hardware was ordered on October 2004 ( all the Servers) 9. Present JCF vision for the project in the Rashadiya Plant( November 2004) 10. A Weekly coordination meeting between TD & IT Dept. Started since November 2004 to review the progress in the project prerequisites & to prepare detailed schedule for:-  Hardware installation ( servers)  Software installation. ( Oracle 9i & standard Maximo) Project Preparation in Year 2004 Retune
  • 12. 12 Maximo Project/ Mini LMM November 2005 JCF Vision for Maximo Project
  • 13. 13 Maximo Project/ Mini LMM November 2005 • We started the implementation with what run P.M.’s • The implementation will is split into Two Stages and each stage consists of multi-Phases as follow: 1. Stage one in year 2005 concentrated on ( Rashadiya plant):- • Equipment codification • 1st & specific inspection job plans • Execution Job plans • Lubrication Job plan • Safety aspects written in the Job plans • Equipment Data file (only equipment specifications) • Work order cycle with workflow • Basic Planning & scheduling • Basic reports Note: Same Stage activities will be repeated in 2006 for Fuhais Plant 2. Live Run implementation was performed in 3 Phases JCF Maximo Project Methodology & Approach
  • 14. 14 Maximo Project/ Mini LMM November 2005 3. Stage Two in year 2006 (Rashadiya Plant) and this will cover remaining activities :- • All the interfaces (Maximo-JDE, Maximo-MS-project, etc) • Equipment Data file ( Spare parts) • Advance Planning & scheduling • Budget management • Safety management as per BU-BP-0064 • History files ( if required to customize special screen) • Other Reports • On 2nd half of 2006, we will start preparation for all production data ( inspections, house keeping, No load-Start up tests) and these will be test before End of project Note: Same stage Two activities will be repeated in 1st Quarter of 2007 for Fuhais Plant JCF Maximo Project Methodology & Approach
  • 15. 15 Maximo Project/ Mini LMM November 2005 Methodology & Approach • Start implementation on January 2005 with Rashadiya Plant Followed after by Fuhais Plant, due to following: • High number of End users • Rashadiya plant is more prepared than Fuhais • It was agreed that 2 coachers at Plant level will be fully dedicated to the project & working with TD and those will :- • Learn MAXIMO Template and maintenance BPs • Participate in analysis and Process Improvement Workshops • Support the end-users to perform their tasks after the training session • Train with other trainers the end-users • Future MAXIMO administrator at plant level • As agreed with Fuhais Plant Management, implementation will be started in the plant on beginning of June 2006 & Fuhais plant Coacher will Participate in Rashadiya Implementation
  • 16. 16 Maximo Project/ Mini LMM November 2005 Maximo Roll-out Organisation Regional Level Division Level BU Level Plant Level Business Side « IT » Side IT Competency Centre Montreal Business Competency Centre Lyon (DPC) Technical Direction IT Correspondant Maintenance Champion Maintenance Template Coordination (DPC + Business Systems) Technical Centre IT Department IT Regional Maintenance Project
  • 17. 17 Maximo Project/ Mini LMM November 2005 Project Organization • Two level of organization is going to be during the project implementation and mainly that covers the need for Year 2005. In Year 2006 the organization will be adjusted as per requirements. The levels are as follow:- A- Technical Department ( TD) & IT Dept. Level B- Plant Level • TD is leading all the project organization at TD & Plant level • The project progressed in collaboration with Technical Centre (CTI), Lafarge IT, Maximo competency Centre, Plant personnel and the local supplier if required
  • 18. 18 Maximo Project/ Mini LMM November 2005 Project Organization chart Project Manager Project Champion (Start to End) Rashadiya Plant Maximo Champion (25% of the Time) Mech. Inspectors ( 1 Year) Elect/Inst Inspector(6 Months) Planners/ Lubrication( 1 Year ) Draft man( As needed) Data entry ( Start to End) Maximo Coach/Rashadiya (100% of the Time) Maximo Coach/Fuhais (100% of the Time Fuhais Plant Maximo Champion (25% of the Time) Mech. Inspectors ( 1 Year) Elect/Inst Inspector(6 Months) Planners/ Lubrication( 1 Year ) Draft man( As needed) Data entry ( Start to End) IT Specialist (100% of the Time) IT Coordinator (30% of the Time) At BU level during JED/Maximo interface stage, Finance & Purchasing Departments will be involved in the project Note: Plant Core team members at Plant level will be adjusted as per project requirements during Year 2006 ( i.e. Production checklist, JED interface, Safety, etc.)
  • 19. 19 Maximo Project/ Mini LMM November 2005 Project Organization • Two committees on the Top Management Level is formed in order to Control, Assist & Evaluate the project progress as follow :- A- Executive Committee ( Monthly) To coordinate the day to day activities of the project and derive and manage project plan . Also to monitor progress against the plan & budget, also identifying logistics and resources B- Steering / EXCOM Committee ( Every 4 month) To provide overall guidance to the project and monitoring the progress, also to address local requirement issues, project planning and tracking and other site- specific issues such as logistics and resources
  • 20. 20 Maximo Project/ Mini LMM November 2005 Jordan Cement Company Maximo Project Executive committee Maximo Project Manager IT Manager Fuhais Maintenance Manager Fuhias Method Manager ( Plant Maximo Champion) Rashadiya Plant Deputy Manager Rashadiya Maintenance Manager Rashadiya Method Manager ( Plant Maximo Champion) Maximo Project Champion Jordan Cement Company Maximo Project Steering committee Manufacturing V.P. Technical V.P. Fuhais Plant Manager Rashadiya Plant Manager CTI Relation Director Financial V.P.
  • 21. 21 Maximo Project/ Mini LMM November 2005 Roll-Out Organization/Roles & Responsibilities CTI : 1. Assistance to Project Charter 2. Organization of training sessions specific to Maximo Template with cement Division resources 3. Assistance for consistency of Maximo Template implementation according to Cement Division rules and objectives MCC/ BS (Maximo Competency Center / Business System) : 1. Assistance to Project Charter 2. Recommend/validate hardware, software and network Architecture 3. Provide Maximo Template material and Template for interface to JDE (including MEA part) 4. Systems expertise and support for IT Template related issues 5. Ensure knowledge transfer for the IT part
  • 22. 22 Maximo Project/ Mini LMM November 2005 Roll-Out Organization/Roles & Responsibilities BU Team ( TD) : 1. Develop and update implementation schedules and plan& monitor and track budget to actual 2. Communicate high level status of the project 3. Facilitate execution of the project plan & provide 1st level support 4. Learn MAXIMO Template and maintenance BPs 5. Conduct analysis and Process Improvement Workshops 6. Ensure MAXIMO Coach prepare end user training materials 7. Coordinate with Lafarge to train MAXIMO Coach and other relevant participants 8. Manage implementation team members’ involvement
  • 23. 23 Maximo Project/ Mini LMM November 2005 Roll-Out Organization/Roles & Responsibilities BU (IT) : 1. Facilitate MAXIMO implementation for IT 2. Coordinate with competency center and MRO 3. Prepare IT environment (PC installation, Network adjustment, software installation and etc …) 4. Provide first IT level support for both hardware and software 5. Assist Project Champion when require 6. Participate in MAXIMO/JDE & Maximo/MS Project Interface preparation, implementation,testing and lunching 7. Manage the MAXIMO & JDE installation Local Supplier : 1. Hardware supply, configuration and maintenance 2. Oracle database installation & Basic Maximo installation (if required) 3. Possible developments for localization (data conversion, additional reports, additional interface with automation systems…)
  • 24. 24 Maximo Project/ Mini LMM November 2005 Plant Core Team :- 1. Up-date all the Job plans ( Mech.& Elect. ) 1st, specific, executions, lubrication etc. 2. Build P.M templates as Per Lafarge requirements 3. Implement equipment data files 4. Lead, implement and monitor MAXIMO Best Practices and Maintenance organization best practices 5. Ensure that all pre-requisites of Maintenance organization & best practices are in practice for smooth implementation of this project. 6. Ensure all documents (Job Plan, Inspection plan, Preventive Maintenance and etc …) will be ready at the right time 7. Adopt and practice all pre-requisites of Maintenance organization & best practices 8. Ensure all documents (Job Plan, Inspection plan, Preventive Maintenance and etc …) captured in MAXIMO contain detail & meaningful information 9. Data Conversion verification for MAXIMO data 10. Prepare all the open date balance for meter base PM’s ( Lubrication Mainly) Roll-Out Organization/Roles & Responsibilities
  • 25. 25 Maximo Project/ Mini LMM November 2005 Rashadiya Plant Roll out Project Activities schedule
  • 26. 26 Maximo Project/ Mini LMM November 2005 Training A) Technical Department (TD) & Coacher level (During Year 2004) :- • Visit to a plant that has a successful implementation of Maximo. • Detailed training on Maximo 5.2 Template & Business processes • Discuss with CTI/BS the latest Lafarge Maximo 5-2 template & Business processes B) Plant Core Team level :- • Awareness program for Maximo screens (one day during 2004). • MRO basic training course on Managing Work with Maximo 5.2 • Training on Maximo 5.2 Template( Data Base Creation ,Jan. 2005) C) Plant End User level :- • Awareness program for Maximo screens (one day during April 2005). • Training on Maximo 5.2 By Profile and as per project stages (2nd half of Year 2005) Note: Item B & C will be repeated in year of 2006 for Fuhais Plant Retune
  • 27. 27 Maximo Project/ Mini LMM November 2005 Maximo Project implementation
  • 28. 28 Maximo Project/ Mini LMM November 2005 Project Progress • MAXIMO Implementation Project Progress • Project Preparation: March 2004 • Project start : 1st January 2005 • Project Expected completion date : 31st December 2006 • Project Overall Progress : 46 % up to 17th October 2005
  • 29. 29 Maximo Project/ Mini LMM November 2005 BU Plant Fuhais Budget Return WBS Start Finsh Progress % 1 17-May-04 31-Dec-06 46% 1-1 17-May-04 31-Dec-06 68% 1-2 24-Nov-04 31-Dec-06 40% 1-2-1 24-Nov-04 28-Dec-05 93% 1-2-1-1 24-Nov-04 28-Dec-05 93% 1-2-1-1.5 Maximo Pilot Shop Rashadiya Plant - Phase I (Raw Mix) 2-Jan-05 30-Jun-05 100% 1-2-1-1.6 Maximo Roll Out in Rashadiya Plant - Phase II (Burning, Crushing & Utilities) 22-May-05 13-Oct-05 95% 1-2-1-1.7 Maximo Roll Out in Rashadiya Plant - Phase III ( CM's, Packing & all remaining Plant Stages) 26-Sep-05 28-Dec-05 35% 1-2-2 24-Nov-05 31-Dec-06 0% 1-2-2-1 A- Fuhais Plant 2-Jan-06 27-Dec-06 0% 1-2-2-2 B- Interfaces 2-Jan-06 28-Dec-06 0% 1-2-2-3 C- Budget Management 2-Jan-06 31-Dec-06 0% 1-2-2-4 D- Safety Management 24-Nov-05 30-Dec-06 0% 1-2-2-5 E- Production Data 2-Jan-06 31-Dec-06 0% 1-3 Meetings 17-Jan-05 28-Dec-06 30% Task Name Stage One - Year 2005 Rashadiya Plant Stage Two - Year 2006 Maximo at BU level Maximo at Plant Level MAXIMO Implementation Project for Jordan Cement Company Project Progress up to October 2005
  • 30. 30 Maximo Project/ Mini LMM November 2005 • BU Level (TD & IT) 1. Preparation of Project charter, Budget & detail project schedule 2. Ordering & installation of all Software & hardware 3. Installation of Maximo Template with support from MCC 4. Train all the End users(Around 55 person) on How to utilize Lafarge best practices through Maximo Software. All training was conduct by Maximo BU Team for almost 3 weeks (NO Outside consultant) 5. Coach all the End users for around 7 weeks before, during Go live period and 2 days weekly after implementation 6. Preparation of all Maximo database Environments (Test, Train, & Production) 7. Freeze & stop using the existing Work Order System for All Plant Stages ( all corrective WO’s Running through Maximo since 22nd September 2005) . 8. Discussing with MCC & CTI about all the required enhancements & modification needed on the Maximo Template 9. Prepare locally all the tables & data for Light interface which launched in October 2005. 10. BU (TD & IT) overall project progress is 68 % Maximo Project Progress/ Rashadiya Plant Return
  • 31. 31 Maximo Project/ Mini LMM November 2005 • Plant Level 1. Maximo Minimum coding & location creation 2. Creation of Mechanical Execution Job Plan (119 Job Plan) 3. Creation for Lubrication 1st level inspection for whole plant. 4. Identify the specific Job Plan Measuring points 5. Review the Job plans content & make the required enhancements . 6. Creation of PM routes 7. Prepare the User & Workflow Privileges 8. Prepare linked documents 9. Review & refine all the users privilege on the Maximo Production Environment database. 10. Review all Maximo Production Environment Mechanical, Electrical & instrumentation PM’s and fixing the start date for all PM’s . Maximo Project Progress/ Rashadiya Plant
  • 32. 32 Maximo Project/ Mini LMM November 2005 • Plant Level 11. Reviewing & checking all created Routes ( 1st level inspection) on Maximo Production Environment . 12. Work order generation for all the PM’s on the Maximo Production Environment 13. Go live for step Phase I &II was launched on July & September 2005 14. Run all corrective WO’s through Maximo 15. Arabic instructions document was prepared by Maximo coacher for End users to facilitate their navigation 16. Rashadiya Plant overall project progress is around 72% Maximo Project Progress/ Rashadiya Plant
  • 33. 33 Maximo Project/ Mini LMM November 2005 Next Activities Maximo Project Progress  Create All asset catalogue templates on Maximo & fill the data on Maximo equipment module screens  Link Each Equipment with it’s spare parts through the Spare parts Tab in the Equipment Module  Run interface between Maximo-MS-Project in order to be ready before Major shutdown (waiting to Purchase MS Project version 2003)  Prepare the schedule for advance training courses:-  Mainly Planners & inspectors  IT & Maintenance staff for Actuate Report writer  Adjust the IT & plant core team Organization based on Year 2006 requirements  Start Preparing all the Repairable/Replaceable Job Plan  Start Preparing to create Production Job plans (Shift Production checks, shutdown & cleaning activities) The go live for Phase III is Expected to be Mid of November 2005 (one & half Month before Schedule) (this will complete the stage I of Maximo project Implementation)  Implement all activities for project Stage II during Year 2006 Return
  • 34. 34 Maximo Project/ Mini LMM November 2005 Maximo project at Fuhais plant  TD and plant are working on the required organization of this project next, the objective is to nominate Maximo team on December  The plant team will be built according to the progress of all maintenance actions followed by TD at Fuhais plant  Implementation will start beginning of January 2006 Return
  • 35. 35 Maximo Project/ Mini LMM November 2005 Maximo Project/ Mechanical Execution Job Plans Why Mechanical Execution Job Plans?? These are a 1st level Inspection Job plans with a minor repair performed during equipment stoppage by execution team, and they have a big impact to improve RF for equipments. • Creation of (119) New Mechanical Executable Job Plan By Maximo team • TD team with Maximo Plant coacher,coached the implementation of these new type of job plans & explained to Execution team How to perform them & almost around. • Project progress is around (119/119)= 100% Return
  • 36. 36 Maximo Project/ Mini LMM November 2005  All the Plant lubrication system was schedule to be Launched with Maximo 1st phase Implementation for the whole plant and it was launched completely starting from September 2005  Work order generation for all Lubrication PM’s on the Maximo Production Environment:-  1st Level inspection (make up Lubrication)  Specific inspection ( Shutdown, Drain )  The feedback got from Lubrication team is promising & they are happy with the system ( 1st in Lafarge Group using Maximo 5.2 in managing Lubrication Activities) Maximo Project/ Lubrication System Return
  • 37. 37 Maximo Project/ Mini LMM November 2005 Maximo Project Progress/ Hardware Configuration Return
  • 38. 38 Maximo Project/ Mini LMM November 2005 • Total Appropriation Value : 426 KJD • Total Forecasting Value : 1.5 KJD • Total Actual Booking Value (Paid) : 179.073 KJD • Total Appropriation Balance Value : 245.427KJD Investment Project Cost Control
  • 39. 39 Maximo Project/ Mini LMM November 2005 Summary of the Estimated Project Budget/ Based on Centralized Scenario Budget Item Cost (KUSD) Consulting 276 Hardware 100 Software 122 Training 41 Grand Total 544 Grand Total with 10% Contingency 599 Retune
  • 40. 40 Maximo Project/ Mini LMM November 2005 Data File Project Progress/Rashadiya  The team accomplished a very good progress in Data sheet preparation compared with last two month progress & they achieved :-  68 % progress up to 15th September 2005  In parallel, progress in Spare Part Defining is :  46 % progress up to 15th September 2005  Team started up loading all the prepared Data in to Maximo manually & linking all JDE spare with equipments starting from End of September 2005.  Target competition date for the project is End of Year 2006. Retune
  • 41. 41 Maximo Project/ Mini LMM November 2005 B- Fuhais Plant Projects
  • 42. 42 Maximo Project/ Mini LMM November 2005 1. A presentation that included an examples & explanation on the concept of these Job Plans was conducted by TD to all Plant Mechanical Engineers. (January & February 2005) 2. A round 100 Mechanical Execution Job plans examples from Rashadiya Plant were Provided to Fuhais Maintenance Manager 3. Cement mills already completed and validated by TD, it will be launched end of October 4. Crusher area completed and validated by TD, it will be launched after kiln shutdown beginning of November 5. Ram mill area under progress 6. Commitment by team that all executable job plan will be completed before major shutdown Mechanical Execution Job Plans
  • 43. 43 Maximo Project/ Mini LMM November 2005 Data File Project Progress/Fuhais  Pilot shop (shop 226) was completed on 20th March 2005 :  100% in Electrical equipment data sheet specifications ( 38 equipment)  100% in Mechanical equipment data sheet specifications ( 43 equipment)  100% Progress in Spare parts  The new team accomplished a very good progress in Data sheet preparation (CM 2 shop) compared with last period & they achieved :-  41 % progress up to 13th October 2005  A detailed draft schedule for the whole plant will was prepared end of October 2005  All the prepared spare part will be sent to Planning Section Head for validation. Retune
  • 44. 44 Maximo Project/ Mini LMM November 2005 The End