SlideShare a Scribd company logo
1 of 7
N o v e m b e r 2 1 , 2 0 1 4
Stephanie Bachmann
Performance
Improvement
Project at IU
Health Arnett
BackgroundInformation
Being efficient and always improving processes are goals at IU Health Arnett as there are
monthly meetings called Rapid Improvement Events (RIE). After observing the nutrition
services department for a few months, there were several areas in the department that could be
reevaluated and improved to make more efficient. One of these areas was the floor stock and
restocking of the provider’s lounge. The process for floor stock consisted of going to the
nutrition rooms and lobbies on each floor and restocking each up to par. Restocking the
provider’s lounge worked in a similar manner. The current process consisted of obtaining a
checklist with par levels and traveling to the provider’s lounge to take inventory. Once this was
completed, the foodservice employee would then travel back to the kitchen and gather needed
supplies and food items for the provider’s lounge on a cart. Once all needed supplies and food
items were collected, the foodservice employee would travel back to the provider’s lounge to
restock the supplies and food items. Both of these processes were preformed in a longer amount
of time than the managers, supervisors, and the primary preceptor thought was appropriate.
Observations of this process were made and it was determined that the process of restocking the
provider’s lounge could be performed in a more timely manner, with some modifications to the
current process.
Extensive research was conducted to decide which method would work best to decrease
the time spent by a foodservice employee restocking the provider’s lounge. St. Clair Hospital in
Pittsburg, Pennsylvania also used the par system in their nursing supply rooms. This system had
several flaws at St. Clair Hospital such as; nurses not being able to quickly locate supplies,
running out of supplies, nurse taking too many supplies, and over ordering of supplies. To limit
these flaws, St. Clair Hospital implemented a two bin system in their nursing supply room. A
two bin system requires two bins to be fully stocked on the shelf. The bins are placed on the
shelf with one in front of the other. The nurses take supplies from the front bin until it is empty.
Once the bin is empty, the bin is removed from the shelf and placed on the top shelf for the
materials handler to refill. The rear bin is then pulled forward on the shelf, and nurses take
supplies from this bin. After the materials handler refills the empty bin, it is placed behind the
bin that is currently being used. This process is then repeated when the bin in front becomes
empty.1 This process was also used at Seattle Children’s Hospital.2
Lean manufacturing was also researched as a possibility to decrease the time spent
restocking the provider’s lounge. The goal of lean manufacturing is to increase value to the
customer while in the meantime decreasing waste. This is accomplished through continual small
improvements.3 In this case the goal would be to more efficiently restock the provider’s lounge,
which provides value for the provider’s of the hospital while not wasting unnecessary time.
Lean manufacturing has many facets, two of which include having a location for everything and
labeling the location to make it easy to locate. Having everything in a logical place and labeling
the location reduces error and decreases time spent on the task at hand.4
Objective
The objective of this study was to observe the restocking process of the provider’s lounge
and decrease the amount of time spent restocking the provider’s lounge by five minutes by
implementing the changes of a modified checklist, a pre-stocked cart, and a labeled refrigerator.
Methods
Indicators Measured
For this study, two indicators were measured. These indicators included time spent
restocking the provider’s lounge and the number of steps taken by the foodservice employee
while restocking the provider’s lounge. The average of both time and the number of steps were
taken for this study. Time was measured using the clock on an iPhone 5c and was recorded.
Steps were measured using a Nike+ FuelBand SE and were also recorded.
Pilot Intervention for Improvement
On Wednesday November 12, 2014 and Thursday November 13, 2014 at 7AM, the
foodservice employee was observed restocking the provider’s lounge. On Friday November 21,
2014 at 7AM and 1PM, changes were implemented to the process of restocking the provider’s
lounge to make the process more efficient by reducing the time spent restocking. The
implemented changes included a modified two bin system and lean manufacturing. The
modified two bin system included a cart that was pre-stocked with food and supplies needed for
the provider’s lounge. The foodservice employee placed the new items that were on the
pre-stocked cart behind the older items already in the provider’s lounge. The purpose of the
pre-stocked cart was to eliminate the time spent initially traveling to the provider’s lounge to
take inventory of the provider’s lounge and then traveling back to the kitchen to obtain food and
supplies. Lean manufacturing was implemented by editing the checklist with par levels to be
more organized and easier to read. The checklist was split up into sections titled refrigerator,
table, coffee counter, condiment drawer, and flatware drawer. The sections were organized in
order of where food and supplies were placed in the provider’s lounge, requiring less time to
search for each item’s location. Additionally, the refrigerator was labeled to indicate where food
items were located which decreased the time the foodservice employee’s spent to find the food’s
location.
*See attached checklists
Pre-stocked cart
Labeled refrigerator
Labeled refrigerator
Data Collection
Average Time, Steps, and Step to Time Ratio Taken by Foodservice Employee Restocking the
Provider’s Lounge Before and After Changes to the Process were implemented
Time (Minutes) Steps Step:Time
(Steps/Minute)
Before Changes 51 542 10.6
After Changes 40.5 612.5 15.1
Results
Before the pilot intervention for improvement was implemented, the average time to
restock the provider’s lounge was 51 minutes. The average steps taken by the foodservice
employee before the pilot intervention for improvement was 542 steps. Prior to the pilot
intervention for improvement, the foodservice employee took 10.6 steps every minute. The
changes of using a pre-stocked cart, editing the checklist, and labeling where food was located in
the refrigerator was efficient in reducing the time spent restocking the provider’s lounge. The
pilot intervention for improvement decreased the time spent restocking the provider’s lounge by
10.5 minutes. The time spent restocking the provider’s lounge after the pilot intervention for
improvement was 40.5 minutes. After the pilot intervention for improvement the average steps
taken by the foodservice employee was 612.5 steps. This increase of 70.5 steps taken by the
foodservice employee led to 15.1 steps taken every minute after the changes were implemented.
The increase in steps per minute was not efficient. The increase in steps was most likely due to
the foodservice employee forgetting to pre-stock the cart with fruit creating an extra trip back to
the kitchen to obtain the fruit and then an additional trip to the provider’s lounge. The extra
steps can also be due to the foodservice employee inefficiently pre-stocking the cart. Since it
was the first time the foodservice employee pre-stocked a cart for the provider’s lounge extra
trips to and from the freezer, refrigerator, and dry storage were observed.
Discussionand Recommendations
Changes to the process of restocking the provider’s lounge were needed at IU Health
Arnett in Lafayette, Indiana due to the inefficiency of the process. The process of traveling from
the kitchen to the provider’s lounge then back to the kitchen to collect food and supplies and
again traveling back to the provider’s lounge to restock consumed more time than necessary.
The checklist with par levels also added additional time to this process. The foodservice
employee had to search for food and supplies since the food and supplies were not listed in order
on the checklist as they appeared in the provider’s lounge. Implementing a modified two bin
system and lean manufacturing greatly reduced the time spent restocking the provider’s lounge.
By having a pre-stocked cart fewer trips were made to and from the provider’s lounge.
Organizing the checklist by dividing the checklist into sections and putting the food and supplies
in order as the food and supplies appeared in the provider’s lounge reduced the time spent
searching for the location of the food and supplies. Additionally creating labels for the location
of food in the refrigerator also helped to reduce the time spent restocking the provider’s lounge.
Although additional steps were taken after implementing changes to the process, this can be
corrected with practice in pre-stocking the cart more efficiently. To continually improve this
process some recommendations can be made. When pre-stocking the cart, it needs to be done in
an organized manner and in the order as the food and supplies appear on the checklist. This will
allow for less confusion and less time finding the food and supplies on the cart when restocking
the provider’s lounge. The checklist and labels in the refrigeration should also be updated as
frequently as need as there are continual changes to the products purchased at IU Health Arnett.
One additional recommendation would be to restock the pre-stocked cart immediately after
restocking the provider’s lounge. By immediately restocking the pre-stocked cart, the
foodservice employee will be able to better remember what was just taken off the cart and put in
the provider’s lounge. This will allow for quicker thinking and less time spent restocking the
cart.
References
1.) Lyon T. Two Bin Supply System at St Clair Hospital [Video]. YouTube.
https://www.youtube.com/watch?v=yjSwwPF5BUU. Published July 12, 2012. Accessed
November 14, 2014.
2.) Weed J. Factory Efficiency Comes to the Hospital. New York Times. July 10, 2010.
http://www.nytimes.com/2010/07/11/business/11seattle.html?pagewanted=all&_r=1&.
Accessed November 16, 2014.
3.) What is Lean?. Lean Enterprise Institute Web site. http://www.lean.org/whatslean/
Published 2009. Updated 2014. Accessed November 16. 2014.
4.) Beyer P. Lean Manufacturing Tour [Video]. YouTube.
https://www.youtube.com/watch?v=mqgHUwSaKj8. Published February 18, 2010.
Accessed November 16, 2014.

More Related Content

Viewers also liked

Времена года
Времена годаВремена года
Времена годаInnesa09
 
Pipeline & Gas Journal_ Dec11_p40
Pipeline & Gas Journal_ Dec11_p40Pipeline & Gas Journal_ Dec11_p40
Pipeline & Gas Journal_ Dec11_p40D.K. Das
 
Top 12 bank resume tips
Top 12 bank resume tipsTop 12 bank resume tips
Top 12 bank resume tipsbankcareer
 
Hyper text transfer protocol
Hyper text transfer protocolHyper text transfer protocol
Hyper text transfer protocolShowmmo
 
Kitchen Cleaning Service Dubai
Kitchen Cleaning Service DubaiKitchen Cleaning Service Dubai
Kitchen Cleaning Service Dubaihomemaids
 
Jornada nacional de vacunacion
Jornada nacional de vacunacionJornada nacional de vacunacion
Jornada nacional de vacunacionzeusg
 
Satisfação dos profissionais brasileiros com a qualidade de vida no trabalho
Satisfação dos profissionais brasileiros com a qualidade de vida no trabalhoSatisfação dos profissionais brasileiros com a qualidade de vida no trabalho
Satisfação dos profissionais brasileiros com a qualidade de vida no trabalhoSolides Tecnologia
 

Viewers also liked (12)

Secret to Service Success
Secret to Service SuccessSecret to Service Success
Secret to Service Success
 
Времена года
Времена годаВремена года
Времена года
 
Pipeline & Gas Journal_ Dec11_p40
Pipeline & Gas Journal_ Dec11_p40Pipeline & Gas Journal_ Dec11_p40
Pipeline & Gas Journal_ Dec11_p40
 
Top 12 bank resume tips
Top 12 bank resume tipsTop 12 bank resume tips
Top 12 bank resume tips
 
Hyper text transfer protocol
Hyper text transfer protocolHyper text transfer protocol
Hyper text transfer protocol
 
Athens branding
Athens brandingAthens branding
Athens branding
 
Kitchen Cleaning Service Dubai
Kitchen Cleaning Service DubaiKitchen Cleaning Service Dubai
Kitchen Cleaning Service Dubai
 
Jornada nacional de vacunacion
Jornada nacional de vacunacionJornada nacional de vacunacion
Jornada nacional de vacunacion
 
Belajar Expressions for apologizing
Belajar Expressions for apologizingBelajar Expressions for apologizing
Belajar Expressions for apologizing
 
Satisfação dos profissionais brasileiros com a qualidade de vida no trabalho
Satisfação dos profissionais brasileiros com a qualidade de vida no trabalhoSatisfação dos profissionais brasileiros com a qualidade de vida no trabalho
Satisfação dos profissionais brasileiros com a qualidade de vida no trabalho
 
GABUNGAN BLACK BOX DAN GLASS BOX
GABUNGAN BLACK BOX DAN GLASS BOXGABUNGAN BLACK BOX DAN GLASS BOX
GABUNGAN BLACK BOX DAN GLASS BOX
 
Часы
ЧасыЧасы
Часы
 

Similar to Performance Improvement Project

Evaluation of food quality
Evaluation of food quality Evaluation of food quality
Evaluation of food quality foodresearch
 
AIFST Presentation
AIFST PresentationAIFST Presentation
AIFST PresentationGreg Evans
 
Management and Inventory control.pptx
Management and Inventory control.pptxManagement and Inventory control.pptx
Management and Inventory control.pptxDanchadi
 
3-4CBLM FOR COMMERCIAL COOKING NC III.docx
3-4CBLM FOR COMMERCIAL COOKING NC III.docx3-4CBLM FOR COMMERCIAL COOKING NC III.docx
3-4CBLM FOR COMMERCIAL COOKING NC III.docxBobieTinaya2
 
Week 10 Food And Beverage Production Methods 2 2552
Week 10  Food And Beverage Production Methods 2 2552Week 10  Food And Beverage Production Methods 2 2552
Week 10 Food And Beverage Production Methods 2 2552Pavit Tansakul
 
Team L - Six Sigma Project (The Sloopy's) - Revised.2
Team L - Six Sigma Project (The Sloopy's) - Revised.2Team L - Six Sigma Project (The Sloopy's) - Revised.2
Team L - Six Sigma Project (The Sloopy's) - Revised.2Baozheng (Michael) Ge
 
Week 10 Food And Beverage Production Methods 3 2552
Week 10  Food And Beverage Production Methods 3 2552Week 10  Food And Beverage Production Methods 3 2552
Week 10 Food And Beverage Production Methods 3 2552Pavit Tansakul
 
CAMC Internship Report
CAMC Internship ReportCAMC Internship Report
CAMC Internship ReportCorey Messer
 
Dressing Supplies at Discharge: A LEAN Cost Reduction Process
Dressing Supplies at Discharge: A LEAN Cost Reduction ProcessDressing Supplies at Discharge: A LEAN Cost Reduction Process
Dressing Supplies at Discharge: A LEAN Cost Reduction ProcessMegan Dobbs, BSN RN, CMSRN
 
PROJECT STORYBOARD: Lean Six Sigma Helps Feed People In Need 45% Faster
PROJECT STORYBOARD: Lean Six Sigma Helps Feed People In Need 45% FasterPROJECT STORYBOARD: Lean Six Sigma Helps Feed People In Need 45% Faster
PROJECT STORYBOARD: Lean Six Sigma Helps Feed People In Need 45% FasterGoLeanSixSigma.com
 
JUSTIFICATION REPORTJustification ReportComment by David Al.docx
JUSTIFICATION REPORTJustification ReportComment by David Al.docxJUSTIFICATION REPORTJustification ReportComment by David Al.docx
JUSTIFICATION REPORTJustification ReportComment by David Al.docxDIPESH30
 
Lean and Flexible Manufacturing System
Lean and Flexible Manufacturing SystemLean and Flexible Manufacturing System
Lean and Flexible Manufacturing SystemTaruchit Goyal
 
new food product development
new food product developmentnew food product development
new food product developmentfoodresearch
 
The Key Principles of Commercial Kitchen Design.pptx
The Key Principles of Commercial Kitchen Design.pptxThe Key Principles of Commercial Kitchen Design.pptx
The Key Principles of Commercial Kitchen Design.pptximpruve llc
 

Similar to Performance Improvement Project (20)

Evaluation of food quality
Evaluation of food quality Evaluation of food quality
Evaluation of food quality
 
Lean in Hospitals
Lean in HospitalsLean in Hospitals
Lean in Hospitals
 
AIFST Presentation
AIFST PresentationAIFST Presentation
AIFST Presentation
 
Management and Inventory control.pptx
Management and Inventory control.pptxManagement and Inventory control.pptx
Management and Inventory control.pptx
 
3-4CBLM FOR COMMERCIAL COOKING NC III.docx
3-4CBLM FOR COMMERCIAL COOKING NC III.docx3-4CBLM FOR COMMERCIAL COOKING NC III.docx
3-4CBLM FOR COMMERCIAL COOKING NC III.docx
 
Operation management
Operation managementOperation management
Operation management
 
Week 10 Food And Beverage Production Methods 2 2552
Week 10  Food And Beverage Production Methods 2 2552Week 10  Food And Beverage Production Methods 2 2552
Week 10 Food And Beverage Production Methods 2 2552
 
Menu labeling risk mitigation
Menu labeling  risk mitigationMenu labeling  risk mitigation
Menu labeling risk mitigation
 
Team L - Six Sigma Project (The Sloopy's) - Revised.2
Team L - Six Sigma Project (The Sloopy's) - Revised.2Team L - Six Sigma Project (The Sloopy's) - Revised.2
Team L - Six Sigma Project (The Sloopy's) - Revised.2
 
Week 10 Food And Beverage Production Methods 3 2552
Week 10  Food And Beverage Production Methods 3 2552Week 10  Food And Beverage Production Methods 3 2552
Week 10 Food And Beverage Production Methods 3 2552
 
ABRAR GURMANI
ABRAR GURMANIABRAR GURMANI
ABRAR GURMANI
 
CAMC Internship Report
CAMC Internship ReportCAMC Internship Report
CAMC Internship Report
 
Dressing Supplies at Discharge: A LEAN Cost Reduction Process
Dressing Supplies at Discharge: A LEAN Cost Reduction ProcessDressing Supplies at Discharge: A LEAN Cost Reduction Process
Dressing Supplies at Discharge: A LEAN Cost Reduction Process
 
PROJECT STORYBOARD: Lean Six Sigma Helps Feed People In Need 45% Faster
PROJECT STORYBOARD: Lean Six Sigma Helps Feed People In Need 45% FasterPROJECT STORYBOARD: Lean Six Sigma Helps Feed People In Need 45% Faster
PROJECT STORYBOARD: Lean Six Sigma Helps Feed People In Need 45% Faster
 
inventory control of foods
inventory control of foodsinventory control of foods
inventory control of foods
 
JUSTIFICATION REPORTJustification ReportComment by David Al.docx
JUSTIFICATION REPORTJustification ReportComment by David Al.docxJUSTIFICATION REPORTJustification ReportComment by David Al.docx
JUSTIFICATION REPORTJustification ReportComment by David Al.docx
 
Lean and Flexible Manufacturing System
Lean and Flexible Manufacturing SystemLean and Flexible Manufacturing System
Lean and Flexible Manufacturing System
 
new food product development
new food product developmentnew food product development
new food product development
 
Ambo Plant Protection Research Laboratory Under Progress
Ambo Plant Protection Research Laboratory Under ProgressAmbo Plant Protection Research Laboratory Under Progress
Ambo Plant Protection Research Laboratory Under Progress
 
The Key Principles of Commercial Kitchen Design.pptx
The Key Principles of Commercial Kitchen Design.pptxThe Key Principles of Commercial Kitchen Design.pptx
The Key Principles of Commercial Kitchen Design.pptx
 

More from Stephanie Bachmann (16)

Project Report
Project ReportProject Report
Project Report
 
Picnic Ideas
Picnic IdeasPicnic Ideas
Picnic Ideas
 
Physical Activity
Physical ActivityPhysical Activity
Physical Activity
 
MyPlate
MyPlateMyPlate
MyPlate
 
10 Tips for Picky Eaters
10 Tips for Picky Eaters10 Tips for Picky Eaters
10 Tips for Picky Eaters
 
Food Demo for Bariatric Patients
Food Demo for Bariatric PatientsFood Demo for Bariatric Patients
Food Demo for Bariatric Patients
 
Feasibility Study
Feasibility StudyFeasibility Study
Feasibility Study
 
bariatric demo recipe cards
bariatric demo recipe cardsbariatric demo recipe cards
bariatric demo recipe cards
 
Purchasing and storing Whole ILA
Purchasing and storing Whole ILAPurchasing and storing Whole ILA
Purchasing and storing Whole ILA
 
Make Better Beverage Choices ILA
Make Better Beverage Choices ILAMake Better Beverage Choices ILA
Make Better Beverage Choices ILA
 
Healthy Snacking ILA
Healthy Snacking ILAHealthy Snacking ILA
Healthy Snacking ILA
 
Got Your Dairy Today ILA
Got Your Dairy Today ILAGot Your Dairy Today ILA
Got Your Dairy Today ILA
 
Choose MyPlate ILA
Choose MyPlate ILAChoose MyPlate ILA
Choose MyPlate ILA
 
Build a Healthy Meal ILA
Build a Healthy Meal ILABuild a Healthy Meal ILA
Build a Healthy Meal ILA
 
Become an Active Family ILA
Become an Active Family ILABecome an Active Family ILA
Become an Active Family ILA
 
Case Study Presentation
Case Study PresentationCase Study Presentation
Case Study Presentation
 

Performance Improvement Project

  • 1. N o v e m b e r 2 1 , 2 0 1 4 Stephanie Bachmann Performance Improvement Project at IU Health Arnett
  • 2. BackgroundInformation Being efficient and always improving processes are goals at IU Health Arnett as there are monthly meetings called Rapid Improvement Events (RIE). After observing the nutrition services department for a few months, there were several areas in the department that could be reevaluated and improved to make more efficient. One of these areas was the floor stock and restocking of the provider’s lounge. The process for floor stock consisted of going to the nutrition rooms and lobbies on each floor and restocking each up to par. Restocking the provider’s lounge worked in a similar manner. The current process consisted of obtaining a checklist with par levels and traveling to the provider’s lounge to take inventory. Once this was completed, the foodservice employee would then travel back to the kitchen and gather needed supplies and food items for the provider’s lounge on a cart. Once all needed supplies and food items were collected, the foodservice employee would travel back to the provider’s lounge to restock the supplies and food items. Both of these processes were preformed in a longer amount of time than the managers, supervisors, and the primary preceptor thought was appropriate. Observations of this process were made and it was determined that the process of restocking the provider’s lounge could be performed in a more timely manner, with some modifications to the current process. Extensive research was conducted to decide which method would work best to decrease the time spent by a foodservice employee restocking the provider’s lounge. St. Clair Hospital in Pittsburg, Pennsylvania also used the par system in their nursing supply rooms. This system had several flaws at St. Clair Hospital such as; nurses not being able to quickly locate supplies, running out of supplies, nurse taking too many supplies, and over ordering of supplies. To limit these flaws, St. Clair Hospital implemented a two bin system in their nursing supply room. A two bin system requires two bins to be fully stocked on the shelf. The bins are placed on the shelf with one in front of the other. The nurses take supplies from the front bin until it is empty. Once the bin is empty, the bin is removed from the shelf and placed on the top shelf for the materials handler to refill. The rear bin is then pulled forward on the shelf, and nurses take supplies from this bin. After the materials handler refills the empty bin, it is placed behind the bin that is currently being used. This process is then repeated when the bin in front becomes empty.1 This process was also used at Seattle Children’s Hospital.2 Lean manufacturing was also researched as a possibility to decrease the time spent restocking the provider’s lounge. The goal of lean manufacturing is to increase value to the customer while in the meantime decreasing waste. This is accomplished through continual small improvements.3 In this case the goal would be to more efficiently restock the provider’s lounge, which provides value for the provider’s of the hospital while not wasting unnecessary time. Lean manufacturing has many facets, two of which include having a location for everything and labeling the location to make it easy to locate. Having everything in a logical place and labeling the location reduces error and decreases time spent on the task at hand.4
  • 3. Objective The objective of this study was to observe the restocking process of the provider’s lounge and decrease the amount of time spent restocking the provider’s lounge by five minutes by implementing the changes of a modified checklist, a pre-stocked cart, and a labeled refrigerator. Methods Indicators Measured For this study, two indicators were measured. These indicators included time spent restocking the provider’s lounge and the number of steps taken by the foodservice employee while restocking the provider’s lounge. The average of both time and the number of steps were taken for this study. Time was measured using the clock on an iPhone 5c and was recorded. Steps were measured using a Nike+ FuelBand SE and were also recorded. Pilot Intervention for Improvement On Wednesday November 12, 2014 and Thursday November 13, 2014 at 7AM, the foodservice employee was observed restocking the provider’s lounge. On Friday November 21, 2014 at 7AM and 1PM, changes were implemented to the process of restocking the provider’s lounge to make the process more efficient by reducing the time spent restocking. The implemented changes included a modified two bin system and lean manufacturing. The modified two bin system included a cart that was pre-stocked with food and supplies needed for the provider’s lounge. The foodservice employee placed the new items that were on the pre-stocked cart behind the older items already in the provider’s lounge. The purpose of the pre-stocked cart was to eliminate the time spent initially traveling to the provider’s lounge to take inventory of the provider’s lounge and then traveling back to the kitchen to obtain food and supplies. Lean manufacturing was implemented by editing the checklist with par levels to be more organized and easier to read. The checklist was split up into sections titled refrigerator, table, coffee counter, condiment drawer, and flatware drawer. The sections were organized in order of where food and supplies were placed in the provider’s lounge, requiring less time to search for each item’s location. Additionally, the refrigerator was labeled to indicate where food items were located which decreased the time the foodservice employee’s spent to find the food’s location. *See attached checklists
  • 6. Data Collection Average Time, Steps, and Step to Time Ratio Taken by Foodservice Employee Restocking the Provider’s Lounge Before and After Changes to the Process were implemented Time (Minutes) Steps Step:Time (Steps/Minute) Before Changes 51 542 10.6 After Changes 40.5 612.5 15.1 Results Before the pilot intervention for improvement was implemented, the average time to restock the provider’s lounge was 51 minutes. The average steps taken by the foodservice employee before the pilot intervention for improvement was 542 steps. Prior to the pilot intervention for improvement, the foodservice employee took 10.6 steps every minute. The changes of using a pre-stocked cart, editing the checklist, and labeling where food was located in the refrigerator was efficient in reducing the time spent restocking the provider’s lounge. The pilot intervention for improvement decreased the time spent restocking the provider’s lounge by 10.5 minutes. The time spent restocking the provider’s lounge after the pilot intervention for improvement was 40.5 minutes. After the pilot intervention for improvement the average steps taken by the foodservice employee was 612.5 steps. This increase of 70.5 steps taken by the foodservice employee led to 15.1 steps taken every minute after the changes were implemented. The increase in steps per minute was not efficient. The increase in steps was most likely due to the foodservice employee forgetting to pre-stock the cart with fruit creating an extra trip back to the kitchen to obtain the fruit and then an additional trip to the provider’s lounge. The extra steps can also be due to the foodservice employee inefficiently pre-stocking the cart. Since it was the first time the foodservice employee pre-stocked a cart for the provider’s lounge extra trips to and from the freezer, refrigerator, and dry storage were observed. Discussionand Recommendations Changes to the process of restocking the provider’s lounge were needed at IU Health Arnett in Lafayette, Indiana due to the inefficiency of the process. The process of traveling from the kitchen to the provider’s lounge then back to the kitchen to collect food and supplies and again traveling back to the provider’s lounge to restock consumed more time than necessary. The checklist with par levels also added additional time to this process. The foodservice employee had to search for food and supplies since the food and supplies were not listed in order on the checklist as they appeared in the provider’s lounge. Implementing a modified two bin system and lean manufacturing greatly reduced the time spent restocking the provider’s lounge. By having a pre-stocked cart fewer trips were made to and from the provider’s lounge. Organizing the checklist by dividing the checklist into sections and putting the food and supplies
  • 7. in order as the food and supplies appeared in the provider’s lounge reduced the time spent searching for the location of the food and supplies. Additionally creating labels for the location of food in the refrigerator also helped to reduce the time spent restocking the provider’s lounge. Although additional steps were taken after implementing changes to the process, this can be corrected with practice in pre-stocking the cart more efficiently. To continually improve this process some recommendations can be made. When pre-stocking the cart, it needs to be done in an organized manner and in the order as the food and supplies appear on the checklist. This will allow for less confusion and less time finding the food and supplies on the cart when restocking the provider’s lounge. The checklist and labels in the refrigeration should also be updated as frequently as need as there are continual changes to the products purchased at IU Health Arnett. One additional recommendation would be to restock the pre-stocked cart immediately after restocking the provider’s lounge. By immediately restocking the pre-stocked cart, the foodservice employee will be able to better remember what was just taken off the cart and put in the provider’s lounge. This will allow for quicker thinking and less time spent restocking the cart. References 1.) Lyon T. Two Bin Supply System at St Clair Hospital [Video]. YouTube. https://www.youtube.com/watch?v=yjSwwPF5BUU. Published July 12, 2012. Accessed November 14, 2014. 2.) Weed J. Factory Efficiency Comes to the Hospital. New York Times. July 10, 2010. http://www.nytimes.com/2010/07/11/business/11seattle.html?pagewanted=all&_r=1&. Accessed November 16, 2014. 3.) What is Lean?. Lean Enterprise Institute Web site. http://www.lean.org/whatslean/ Published 2009. Updated 2014. Accessed November 16. 2014. 4.) Beyer P. Lean Manufacturing Tour [Video]. YouTube. https://www.youtube.com/watch?v=mqgHUwSaKj8. Published February 18, 2010. Accessed November 16, 2014.