A brief presentation about insights, strategies, and next steps from the FERC 201 workshop series sponsored by the INGAA Foundation and facilitated by POWER Engineers. These ongoing workshops have promoted meaningful, productive, and interactive dialogue among owners/operators, agencies, and service providers in the interstate natural gas transmission industry.
3. • Need for more in-depth discussion
and dialogue between
– Industry and Federal Agencies
– FERC and Federal Agencies
– Construction Contractors and Industry
• Sponsored by INGAA Foundation
and the EHS Committee Construction
Task Force
History
4. • Objectives
– Establish a neutral forum
• Examine emerging or reoccurring challenges
• Exchange information and ideas
• Promote shared learning in an open and collaborative
environment
– Promote meaningful, productive, and interactive dialogue
– Focus on solutions
• Desired outcomes
– Increase understanding
– Identify next steps, action items, and follow-up discussions
Workshop Series Overview
5. FERC Pre-Filing and Environmental Reporting November 2014
2014–2016 Workshop Series
Working with Other Federal Agencies March 2015
Construction Challenges July 2015
Post-Construction and Minor Projects May 2016
Permit Synchronization and Process Improvements August 2016
1
2
3
4
5
13. Want to know
the message
being
communicated
to the public
ahead of time
Don’t have
time or
resources to
respond to no
permit/no
effect requests
Need
verification that
applicant is
authorized to
consult
General Agency Insights
14. Only provide
information
relevant to the
authorization
A single NEPA
document
must meet
other agencies’
NEPA
requirements
Conduct
engineering
design earlier
in the planning
process
General Agency Insights
16. Early agency
outreach
supported
Notify FERC to
avoid surprises
Burden of
proof for route
selection falls
on Company
not commenter
Outreach
must be
Consistent
Documented
Throughout the
life of the project
FERC Insights
17. Want to be
engaged
early
USACE Insights
100%
survey
coverage
not needed
for complete
application
May request
additional
items
beyond what
FERC
requests
Cannot
issue a
conditional
approval
19. Avoid routing a
project where
an RMP
amendment is
needed
Needed before
project review
can begin
ROW application
POD
Cost recovery
Consult prior to
conducting
field surveys
BLM Insights
21. MBTA philosophies
differ by region
Eastern U.S. focuses on
mitigation
Western U.S. focuses on
protection of birds
Engage the correct
technical resource leads
Field office for ESA
consultations
Regional office for MBTA
coordination
USFWS Insights
22. NRCS Insights
Nationwide shapefiles
for NRCS easements
available
Different levels of
mitigation for WRP land
impacts
Penalty for landowner
breaking WRP agreement
Wetland impacts
25. Create agency
“cheat sheets”
identifying major
concerns,
requirements,
and timeframes
Ensure the right
people are
receiving
submittals
Provide clear
differentiation
when multiple
projects occur
simultaneously or
in same
geography
Improvement Strategies
Provide training
opportunities
Consider
augmenting
agency staff
26. Improvement Strategies
Include a
signature line
on consultation
letters
• No effect
• No historic
properties affected
Ensure permits
and MOUs cover
all phases and
aspects of project
• Easements
• Maintenance
• Access roads
Use USFWS
IPaC Tool for
“no effect”
determinations
Maintain good
records and
documentation
• Surveyed areas
• Previously disturbed/
construction
work areas
27. In Summary
Federal agencies are
open to…
Learning more
Maintaining an open
dialogue
Discussing options for
permit synchronization
Participants
acknowledge…
There is much work to do
Knowledge needs to be
transferred to the
state/field office level
29. Results of Workshops 1–4
27 Specific action items
Narrowed down to 8
Aka, the
“TOP 5”
30. Top 5 Action Items
Pre-application information sheet and checklist
identifying pre-application meeting
requirements, major resource concerns,
submittal requirements, and timeframes for
each of the major federal permits/authorizations
1
Lead:
Federal
agencies
31. Top 5 Action Items
Guidance document
on using and
submitting remote
sensing wetland data
to the USACE
Pipeline Construction
Training course for
federal/state
agencies
2
Lead:
INGAA
Foundation
Lead:
USACE
2
32. Top 5 Action Items
FERC Environmental
Review Process
training courses for
federal/state
agencies
Programmatic
agreement for
Section 7 ESA
consultations
3
Lead:
FERC and
USFWS
(+ industry)
Lead:
INGAA
Foundation
3
33. Top 5 Action Items
Agency training toolbox materials
(e.g., pipeline construction 101 video, resource-
specific construction topics)
4
Lead:
INGAA
Foundation
34. Top 5 Action Items
Guidance document
on FERC regulations
pertaining to “Ex
Parte Rules and
Expectations for
Federal Agencies”
Federal Agency
Environmental
Review Process 101
trainings/WebEx for
industry
5
Lead:
INGAA
Foundation
Lead:
FERC
5
35. Next Steps
Build on established relationships and
understanding achieved so far1
Workshop 5—Permit Synchronization
Process Improvements, Part II2
Annual workshops thereafter3
37. Opportunity to
discuss
permitting
issues
In greater detail
Multi-agency
audience
Process
improvement
tools
Guidance
documents
Authorization-
Specific
Information
Sheets
Ongoing
dialogue with
federal
agencies
Challenges
Regulatory
drivers
Trends
Lessons learned
Benefits