SlideShare a Scribd company logo
1 of 38
Download to read offline
What We
from the FERC 201 Workshops
Insights, Strategies, & Next Steps
by Stacey Atella
Learned
WHAT ARE THE
FERC 201
WORKSHOPS?
• Need for more in-depth discussion
and dialogue between
– Industry and Federal Agencies
– FERC and Federal Agencies
– Construction Contractors and Industry
• Sponsored by INGAA Foundation
and the EHS Committee Construction
Task Force
History
• Objectives
– Establish a neutral forum
• Examine emerging or reoccurring challenges
• Exchange information and ideas
• Promote shared learning in an open and collaborative
environment
– Promote meaningful, productive, and interactive dialogue
– Focus on solutions
• Desired outcomes
– Increase understanding
– Identify next steps, action items, and follow-up discussions
Workshop Series Overview
FERC Pre-Filing and Environmental Reporting November 2014
2014–2016 Workshop Series
Working with Other Federal Agencies March 2015
Construction Challenges July 2015
Post-Construction and Minor Projects May 2016
Permit Synchronization and Process Improvements August 2016
1
2
3
4
5
WHO ATTENDED?
Workshop Demographics
Workshop Demographics
Workshop Demographics
WHAT DID
WE LEARN?
Slower
agency
response
times
Permitting-
related
construction
challenges
Not enough
time or money
to plan, but
always
enough to “fix”
problems
Trends
Challenges
to Blanket
Certificate
projects
Requests for
more robust
analyses and
greater level
of data/details
Increased
number of
detailed
questions and
requests from
commenters
Trends
Want to know
the message
being
communicated
to the public
ahead of time
Don’t have
time or
resources to
respond to no
permit/no
effect requests
Need
verification that
applicant is
authorized to
consult
General Agency Insights
Only provide
information
relevant to the
authorization
A single NEPA
document
must meet
other agencies’
NEPA
requirements
Conduct
engineering
design earlier
in the planning
process
General Agency Insights
FERC Insights
Pre-Filing
process is
preferred
“Pre” Pre-Filing
outreach is
beneficial
Pre-Filing
should take at
least 7–9
months
Early agency
outreach
supported
Notify FERC to
avoid surprises
Burden of
proof for route
selection falls
on Company
not commenter
Outreach
must be
Consistent
Documented
Throughout the
life of the project
FERC Insights
Want to be
engaged
early
USACE Insights
100%
survey
coverage
not needed
for complete
application
May request
additional
items
beyond what
FERC
requests
Cannot
issue a
conditional
approval
Determine if
Mineral
Leasing Act
requirements
apply
Need robust
explanation for
rejected
alternatives
Developing a
new pre-
application
process
BLM Insights
Avoid routing a
project where
an RMP
amendment is
needed
Needed before
project review
can begin
ROW application
POD
Cost recovery
Consult prior to
conducting
field surveys
BLM Insights
Issued ESA
Compensatory
Mitigation Policy
Adding migratory bird
conservation measures
to IPaC
USFWS Insights
MBTA philosophies
differ by region
Eastern U.S. focuses on
mitigation
Western U.S. focuses on
protection of birds
Engage the correct
technical resource leads
Field office for ESA
consultations
Regional office for MBTA
coordination
USFWS Insights
NRCS Insights
Nationwide shapefiles
for NRCS easements
available
Different levels of
mitigation for WRP land
impacts
Penalty for landowner
breaking WRP agreement
Wetland impacts
Identify
adequate
workspace
during
planning and
permitting
Develop a well
thought out
access road
plan
Collocation
may result in
greater
environmental
disturbance
Contractor Insights
Continue
educating
and engaging
public and
agencies
Consider
providing
agencies with links
to draft RRs as
they are filed with
FERC
Seek to
understand
agencies’
concerns
Work with
agencies to
effectively
communicate
expectations
Improvement Strategies
Create agency
“cheat sheets”
identifying major
concerns,
requirements,
and timeframes
Ensure the right
people are
receiving
submittals
Provide clear
differentiation
when multiple
projects occur
simultaneously or
in same
geography
Improvement Strategies
Provide training
opportunities
Consider
augmenting
agency staff
Improvement Strategies
Include a
signature line
on consultation
letters
• No effect
• No historic
properties affected
Ensure permits
and MOUs cover
all phases and
aspects of project
• Easements
• Maintenance
• Access roads
Use USFWS
IPaC Tool for
“no effect”
determinations
Maintain good
records and
documentation
• Surveyed areas
• Previously disturbed/
construction
work areas
In Summary
Federal agencies are
open to…
Learning more
Maintaining an open
dialogue
Discussing options for
permit synchronization
Participants
acknowledge…
There is much work to do
Knowledge needs to be
transferred to the
state/field office level
WHAT’S NEXT?
Results of Workshops 1–4
27 Specific action items
Narrowed down to 8
Aka, the
“TOP 5”
Top 5 Action Items
Pre-application information sheet and checklist
identifying pre-application meeting
requirements, major resource concerns,
submittal requirements, and timeframes for
each of the major federal permits/authorizations
1
Lead:
Federal
agencies
Top 5 Action Items
Guidance document
on using and
submitting remote
sensing wetland data
to the USACE
Pipeline Construction
Training course for
federal/state
agencies
2
Lead:
INGAA
Foundation
Lead:
USACE
2
Top 5 Action Items
FERC Environmental
Review Process
training courses for
federal/state
agencies
Programmatic
agreement for
Section 7 ESA
consultations
3
Lead:
FERC and
USFWS
(+ industry)
Lead:
INGAA
Foundation
3
Top 5 Action Items
Agency training toolbox materials
(e.g., pipeline construction 101 video, resource-
specific construction topics)
4
Lead:
INGAA
Foundation
Top 5 Action Items
Guidance document
on FERC regulations
pertaining to “Ex
Parte Rules and
Expectations for
Federal Agencies”
Federal Agency
Environmental
Review Process 101
trainings/WebEx for
industry
5
Lead:
INGAA
Foundation
Lead:
FERC
5
Next Steps
Build on established relationships and
understanding achieved so far1
Workshop 5—Permit Synchronization
Process Improvements, Part II2
Annual workshops thereafter3
WHY DO
YOU CARE?
Opportunity to
discuss
permitting
issues
In greater detail
Multi-agency
audience
Process
improvement
tools
Guidance
documents
Authorization-
Specific
Information
Sheets
Ongoing
dialogue with
federal
agencies
Challenges
Regulatory
drivers
Trends
Lessons learned
Benefits
Stacey
Atella
Stacey.Atella@powereng.com
(303) 716-8932
www.powereng.com
Want to know more?
We’re happy to share a brown bag
presentation at your office.

More Related Content

What's hot (6)

Innovation Programme Meeting Evaluation
Innovation Programme Meeting EvaluationInnovation Programme Meeting Evaluation
Innovation Programme Meeting Evaluation
 
High level conference_timeline
High level conference_timelineHigh level conference_timeline
High level conference_timeline
 
Collective impact
Collective impactCollective impact
Collective impact
 
Relationship-based knowledge mobilization: systems-based KMb and consideratio...
Relationship-based knowledge mobilization: systems-based KMb and consideratio...Relationship-based knowledge mobilization: systems-based KMb and consideratio...
Relationship-based knowledge mobilization: systems-based KMb and consideratio...
 
JISC Project Management Guidelines
JISC Project Management GuidelinesJISC Project Management Guidelines
JISC Project Management Guidelines
 
Elements of implementing innovation platform
Elements of implementing innovation platform Elements of implementing innovation platform
Elements of implementing innovation platform
 

Viewers also liked

Nicole Segal -Short Circuit Presentation - TO's
Nicole Segal -Short Circuit Presentation - TO'sNicole Segal -Short Circuit Presentation - TO's
Nicole Segal -Short Circuit Presentation - TO's
Nicole Segal
 
Зачем и как строить личный бренд?
Зачем и как строить личный бренд?Зачем и как строить личный бренд?
Зачем и как строить личный бренд?
Alexandra Govorukha
 

Viewers also liked (20)

How to Become a Thought Leader in Your Niche
How to Become a Thought Leader in Your NicheHow to Become a Thought Leader in Your Niche
How to Become a Thought Leader in Your Niche
 
Презентація ключового законопроекту про державні фінансові гарантії щодо над...
Презентація ключового законопроекту про державні фінансові гарантії щодо над...Презентація ключового законопроекту про державні фінансові гарантії щодо над...
Презентація ключового законопроекту про державні фінансові гарантії щодо над...
 
Architectural modeling chapter 5 of omd
Architectural modeling chapter 5 of omdArchitectural modeling chapter 5 of omd
Architectural modeling chapter 5 of omd
 
Lincoln Murphy's Scaling Customer Success in NYC
Lincoln Murphy's Scaling Customer Success in NYCLincoln Murphy's Scaling Customer Success in NYC
Lincoln Murphy's Scaling Customer Success in NYC
 
AWSで始めるサーバレスな RESTful API システム
AWSで始めるサーバレスな RESTful API システムAWSで始めるサーバレスな RESTful API システム
AWSで始めるサーバレスな RESTful API システム
 
Résumé
RésuméRésumé
Résumé
 
Nicole Segal -Short Circuit Presentation - TO's
Nicole Segal -Short Circuit Presentation - TO'sNicole Segal -Short Circuit Presentation - TO's
Nicole Segal -Short Circuit Presentation - TO's
 
Continual Compliance Monitoring– PCI DSS, HIPAA, FERC/NERC, EI3PA, ISO 27001 ...
Continual Compliance Monitoring– PCI DSS, HIPAA, FERC/NERC, EI3PA, ISO 27001 ...Continual Compliance Monitoring– PCI DSS, HIPAA, FERC/NERC, EI3PA, ISO 27001 ...
Continual Compliance Monitoring– PCI DSS, HIPAA, FERC/NERC, EI3PA, ISO 27001 ...
 
Satrix Solutions 2017 Customer Success Summit Presentation
Satrix Solutions 2017 Customer Success Summit Presentation   Satrix Solutions 2017 Customer Success Summit Presentation
Satrix Solutions 2017 Customer Success Summit Presentation
 
Network Separation Policy in Korea
 Network Separation Policy in Korea Network Separation Policy in Korea
Network Separation Policy in Korea
 
Зачем и как строить личный бренд?
Зачем и как строить личный бренд?Зачем и как строить личный бренд?
Зачем и как строить личный бренд?
 
Опасные химические добавки в нашей еде
Опасные химические добавки в нашей едеОпасные химические добавки в нашей еде
Опасные химические добавки в нашей еде
 
A guy walks into a bar
A guy walks into a barA guy walks into a bar
A guy walks into a bar
 
Neetu rana
Neetu ranaNeetu rana
Neetu rana
 
General quiz finals with answers
General quiz finals with answersGeneral quiz finals with answers
General quiz finals with answers
 
Interrobang 2017 BizSciTech Quiz Prelims+Answers
Interrobang 2017 BizSciTech Quiz Prelims+AnswersInterrobang 2017 BizSciTech Quiz Prelims+Answers
Interrobang 2017 BizSciTech Quiz Prelims+Answers
 
Machine Learning und SEO: Ein Vektor sagt mehr als 1000 Wörter
Machine Learning und SEO: Ein Vektor sagt mehr als 1000 WörterMachine Learning und SEO: Ein Vektor sagt mehr als 1000 Wörter
Machine Learning und SEO: Ein Vektor sagt mehr als 1000 Wörter
 
Infecciones piel y tejidos blandos. farmacologia clínica
Infecciones piel y tejidos blandos. farmacologia clínicaInfecciones piel y tejidos blandos. farmacologia clínica
Infecciones piel y tejidos blandos. farmacologia clínica
 
Deep Dive on Amazon DynamoDB
Deep Dive on Amazon DynamoDBDeep Dive on Amazon DynamoDB
Deep Dive on Amazon DynamoDB
 
Role of medical imaging in developemental dysplasia of Hip Dr muhammad Bin Zu...
Role of medical imaging in developemental dysplasia of Hip Dr muhammad Bin Zu...Role of medical imaging in developemental dysplasia of Hip Dr muhammad Bin Zu...
Role of medical imaging in developemental dysplasia of Hip Dr muhammad Bin Zu...
 

Similar to What We Learned from the FERC 201 Workshops

michael hamilton legal project management
michael hamilton legal project managementmichael hamilton legal project management
michael hamilton legal project management
michaelhamilton
 
Secas conceptual org 20130716 edvjh5
Secas conceptual org 20130716 edvjh5Secas conceptual org 20130716 edvjh5
Secas conceptual org 20130716 edvjh5
VHerr
 
IABC Silver Quill Case Study
IABC Silver Quill Case StudyIABC Silver Quill Case Study
IABC Silver Quill Case Study
Alina Haas
 
ESLTP Setting the scene_Wardle
ESLTP Setting the scene_WardleESLTP Setting the scene_Wardle
ESLTP Setting the scene_Wardle
TERN Australia
 
2010 LMS/CMS Communication Guide
2010 LMS/CMS Communication Guide2010 LMS/CMS Communication Guide
2010 LMS/CMS Communication Guide
WCET
 
Collab Comm+For+Soc+Chg+Intro.Rev+July+2008
Collab Comm+For+Soc+Chg+Intro.Rev+July+2008Collab Comm+For+Soc+Chg+Intro.Rev+July+2008
Collab Comm+For+Soc+Chg+Intro.Rev+July+2008
UC Santa Cruz
 
Grant Writing for small college and con ed
Grant Writing for small college and con edGrant Writing for small college and con ed
Grant Writing for small college and con ed
Trenton Hightower
 
Laatsch--Skills Inventory
Laatsch--Skills InventoryLaatsch--Skills Inventory
Laatsch--Skills Inventory
Brian Laatsch
 

Similar to What We Learned from the FERC 201 Workshops (20)

AHM 2014: Session 1 "Governance and Chartering EarthCube"
AHM 2014: Session 1 "Governance and Chartering EarthCube"AHM 2014: Session 1 "Governance and Chartering EarthCube"
AHM 2014: Session 1 "Governance and Chartering EarthCube"
 
michael hamilton legal project management
michael hamilton legal project managementmichael hamilton legal project management
michael hamilton legal project management
 
Secas conceptual org 20130716 edvjh5
Secas conceptual org 20130716 edvjh5Secas conceptual org 20130716 edvjh5
Secas conceptual org 20130716 edvjh5
 
Project monitoring and evaluation by Samuel Obino Mokaya
Project monitoring and evaluation by Samuel Obino MokayaProject monitoring and evaluation by Samuel Obino Mokaya
Project monitoring and evaluation by Samuel Obino Mokaya
 
2014_BA_Resume
2014_BA_Resume2014_BA_Resume
2014_BA_Resume
 
ASAE Presentation: Managing Enterprise Projects
ASAE Presentation: Managing Enterprise ProjectsASAE Presentation: Managing Enterprise Projects
ASAE Presentation: Managing Enterprise Projects
 
IABC Silver Quill Case Study
IABC Silver Quill Case StudyIABC Silver Quill Case Study
IABC Silver Quill Case Study
 
Leveraging Social Business Tools to better manage Performance Improvement pro...
Leveraging Social Business Tools to better manage Performance Improvement pro...Leveraging Social Business Tools to better manage Performance Improvement pro...
Leveraging Social Business Tools to better manage Performance Improvement pro...
 
ESLTP Setting the scene_Wardle
ESLTP Setting the scene_WardleESLTP Setting the scene_Wardle
ESLTP Setting the scene_Wardle
 
2010 LMS/CMS Communication Guide
2010 LMS/CMS Communication Guide2010 LMS/CMS Communication Guide
2010 LMS/CMS Communication Guide
 
New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%
New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%
New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%
 
Adam cv2016july
Adam cv2016julyAdam cv2016july
Adam cv2016july
 
Joining efforts. Colocation of CRP research activities within Burkina Faso
Joining efforts. Colocation of CRP research activities within Burkina FasoJoining efforts. Colocation of CRP research activities within Burkina Faso
Joining efforts. Colocation of CRP research activities within Burkina Faso
 
Vcs platform verhaal final
Vcs platform verhaal finalVcs platform verhaal final
Vcs platform verhaal final
 
New From TRB 2010: The Emerging Federal Initiative to Reduce the Timeframe of...
New From TRB 2010: The Emerging Federal Initiative to Reduce the Timeframe of...New From TRB 2010: The Emerging Federal Initiative to Reduce the Timeframe of...
New From TRB 2010: The Emerging Federal Initiative to Reduce the Timeframe of...
 
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdfPlan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
 
Collab Comm+For+Soc+Chg+Intro.Rev+July+2008
Collab Comm+For+Soc+Chg+Intro.Rev+July+2008Collab Comm+For+Soc+Chg+Intro.Rev+July+2008
Collab Comm+For+Soc+Chg+Intro.Rev+July+2008
 
Grant Writing for small college and con ed
Grant Writing for small college and con edGrant Writing for small college and con ed
Grant Writing for small college and con ed
 
Laatsch--Skills Inventory
Laatsch--Skills InventoryLaatsch--Skills Inventory
Laatsch--Skills Inventory
 
CALORENE_PENGILLY(CPT)
CALORENE_PENGILLY(CPT)CALORENE_PENGILLY(CPT)
CALORENE_PENGILLY(CPT)
 

Recently uploaded

Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
rajputriyana310
 
Green Marketing
Green MarketingGreen Marketing
Green Marketing
Dr. Salem Baidas
 

Recently uploaded (20)

Cheap Call Girls in Dubai %(+971524965298 )# Dubai Call Girl Service By Rus...
Cheap Call Girls  in Dubai %(+971524965298 )#  Dubai Call Girl Service By Rus...Cheap Call Girls  in Dubai %(+971524965298 )#  Dubai Call Girl Service By Rus...
Cheap Call Girls in Dubai %(+971524965298 )# Dubai Call Girl Service By Rus...
 
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
 
NO1 Verified kala jadu karne wale ka contact number kala jadu karne wale baba...
NO1 Verified kala jadu karne wale ka contact number kala jadu karne wale baba...NO1 Verified kala jadu karne wale ka contact number kala jadu karne wale baba...
NO1 Verified kala jadu karne wale ka contact number kala jadu karne wale baba...
 
Cyclone Case Study Odisha 1999 Super Cyclone in India.
Cyclone Case Study Odisha 1999 Super Cyclone in India.Cyclone Case Study Odisha 1999 Super Cyclone in India.
Cyclone Case Study Odisha 1999 Super Cyclone in India.
 
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING  SYSTEMS- IGBC, GRIHA, LEED--.pptxRATING  SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
 
Call Girls Moshi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Moshi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Moshi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Moshi Call Me 7737669865 Budget Friendly No Advance Booking
 
Book Sex Workers Available Pune Call Girls Khadki 6297143586 Call Hot Indian...
Book Sex Workers Available Pune Call Girls Khadki  6297143586 Call Hot Indian...Book Sex Workers Available Pune Call Girls Khadki  6297143586 Call Hot Indian...
Book Sex Workers Available Pune Call Girls Khadki 6297143586 Call Hot Indian...
 
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
 
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...
 
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
 
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
 
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...
 
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
 
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000
 
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
 
(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7
(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7
(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7
 
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
 
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts ServicesBOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
 
Green Marketing
Green MarketingGreen Marketing
Green Marketing
 

What We Learned from the FERC 201 Workshops

  • 1. What We from the FERC 201 Workshops Insights, Strategies, & Next Steps by Stacey Atella Learned
  • 2. WHAT ARE THE FERC 201 WORKSHOPS?
  • 3. • Need for more in-depth discussion and dialogue between – Industry and Federal Agencies – FERC and Federal Agencies – Construction Contractors and Industry • Sponsored by INGAA Foundation and the EHS Committee Construction Task Force History
  • 4. • Objectives – Establish a neutral forum • Examine emerging or reoccurring challenges • Exchange information and ideas • Promote shared learning in an open and collaborative environment – Promote meaningful, productive, and interactive dialogue – Focus on solutions • Desired outcomes – Increase understanding – Identify next steps, action items, and follow-up discussions Workshop Series Overview
  • 5. FERC Pre-Filing and Environmental Reporting November 2014 2014–2016 Workshop Series Working with Other Federal Agencies March 2015 Construction Challenges July 2015 Post-Construction and Minor Projects May 2016 Permit Synchronization and Process Improvements August 2016 1 2 3 4 5
  • 11. Slower agency response times Permitting- related construction challenges Not enough time or money to plan, but always enough to “fix” problems Trends
  • 12. Challenges to Blanket Certificate projects Requests for more robust analyses and greater level of data/details Increased number of detailed questions and requests from commenters Trends
  • 13. Want to know the message being communicated to the public ahead of time Don’t have time or resources to respond to no permit/no effect requests Need verification that applicant is authorized to consult General Agency Insights
  • 14. Only provide information relevant to the authorization A single NEPA document must meet other agencies’ NEPA requirements Conduct engineering design earlier in the planning process General Agency Insights
  • 15. FERC Insights Pre-Filing process is preferred “Pre” Pre-Filing outreach is beneficial Pre-Filing should take at least 7–9 months
  • 16. Early agency outreach supported Notify FERC to avoid surprises Burden of proof for route selection falls on Company not commenter Outreach must be Consistent Documented Throughout the life of the project FERC Insights
  • 17. Want to be engaged early USACE Insights 100% survey coverage not needed for complete application May request additional items beyond what FERC requests Cannot issue a conditional approval
  • 18. Determine if Mineral Leasing Act requirements apply Need robust explanation for rejected alternatives Developing a new pre- application process BLM Insights
  • 19. Avoid routing a project where an RMP amendment is needed Needed before project review can begin ROW application POD Cost recovery Consult prior to conducting field surveys BLM Insights
  • 20. Issued ESA Compensatory Mitigation Policy Adding migratory bird conservation measures to IPaC USFWS Insights
  • 21. MBTA philosophies differ by region Eastern U.S. focuses on mitigation Western U.S. focuses on protection of birds Engage the correct technical resource leads Field office for ESA consultations Regional office for MBTA coordination USFWS Insights
  • 22. NRCS Insights Nationwide shapefiles for NRCS easements available Different levels of mitigation for WRP land impacts Penalty for landowner breaking WRP agreement Wetland impacts
  • 23. Identify adequate workspace during planning and permitting Develop a well thought out access road plan Collocation may result in greater environmental disturbance Contractor Insights
  • 24. Continue educating and engaging public and agencies Consider providing agencies with links to draft RRs as they are filed with FERC Seek to understand agencies’ concerns Work with agencies to effectively communicate expectations Improvement Strategies
  • 25. Create agency “cheat sheets” identifying major concerns, requirements, and timeframes Ensure the right people are receiving submittals Provide clear differentiation when multiple projects occur simultaneously or in same geography Improvement Strategies Provide training opportunities Consider augmenting agency staff
  • 26. Improvement Strategies Include a signature line on consultation letters • No effect • No historic properties affected Ensure permits and MOUs cover all phases and aspects of project • Easements • Maintenance • Access roads Use USFWS IPaC Tool for “no effect” determinations Maintain good records and documentation • Surveyed areas • Previously disturbed/ construction work areas
  • 27. In Summary Federal agencies are open to… Learning more Maintaining an open dialogue Discussing options for permit synchronization Participants acknowledge… There is much work to do Knowledge needs to be transferred to the state/field office level
  • 29. Results of Workshops 1–4 27 Specific action items Narrowed down to 8 Aka, the “TOP 5”
  • 30. Top 5 Action Items Pre-application information sheet and checklist identifying pre-application meeting requirements, major resource concerns, submittal requirements, and timeframes for each of the major federal permits/authorizations 1 Lead: Federal agencies
  • 31. Top 5 Action Items Guidance document on using and submitting remote sensing wetland data to the USACE Pipeline Construction Training course for federal/state agencies 2 Lead: INGAA Foundation Lead: USACE 2
  • 32. Top 5 Action Items FERC Environmental Review Process training courses for federal/state agencies Programmatic agreement for Section 7 ESA consultations 3 Lead: FERC and USFWS (+ industry) Lead: INGAA Foundation 3
  • 33. Top 5 Action Items Agency training toolbox materials (e.g., pipeline construction 101 video, resource- specific construction topics) 4 Lead: INGAA Foundation
  • 34. Top 5 Action Items Guidance document on FERC regulations pertaining to “Ex Parte Rules and Expectations for Federal Agencies” Federal Agency Environmental Review Process 101 trainings/WebEx for industry 5 Lead: INGAA Foundation Lead: FERC 5
  • 35. Next Steps Build on established relationships and understanding achieved so far1 Workshop 5—Permit Synchronization Process Improvements, Part II2 Annual workshops thereafter3
  • 37. Opportunity to discuss permitting issues In greater detail Multi-agency audience Process improvement tools Guidance documents Authorization- Specific Information Sheets Ongoing dialogue with federal agencies Challenges Regulatory drivers Trends Lessons learned Benefits
  • 38. Stacey Atella Stacey.Atella@powereng.com (303) 716-8932 www.powereng.com Want to know more? We’re happy to share a brown bag presentation at your office.