SlideShare a Scribd company logo
1 of 9
Download to read offline
MX ELECTRONICS
MANUFACTURING – SAN DIEGO
METRICS REVIEW FOR OCTOBER 2014
1
On Time Delivery ISI
Target 98%
2
San Diego
On time Delivery – 84.5% average
First Pass Yield –
After the SMT machine – 40% - found misalignment problem with components –
tracked it back to stencil printer, replaced motor and encoder 11/18
After the Wave Solder – 25% - cleaned the solder pots after 4 years of usage – 11/5
After the touch up from the wave solder – 60% - assemblers still forgetting to place
all components on – re-work affecting class 3 jobs
After the hand trimming of the leads after touch up – 90% - looking into getting
automated machine
After the insert of LED’s on the back side – 80%, because there are no batch sizes,
interruptions are happening affecting components being placed 100%
After the wash and at final inspection – 90%, process improved due to switch in
solder mask, and new washer
Before
AFTER
The lead and lead-free solder pots had not been cleaned for more
than 4 years effecting quality, requiring touch-up and re-work;
resulting in, field failures for class 2 - 3 projects.
1. Bins for WIP were everywhere on the production
floor
2. Inventory was in 5 locations in building
3. There was no work space on any work station due
to excessive tools/ feeder guns, garbage
BEFORE
1. Eliminated tables and work stations
2. Controlled inventory and projects in WIP
3. Implemented ESD protocols for smocks, tables, heel
straps, and floor
AFTER
1. Considered all safety hazards and
concerns – like extension cords, hanging
wires, pvc piping.
2. Removed all solder stations and replaced
them with digital equipment
3. Removed all fans from work stations and
replaced them with extraction fans
BEFORE
AFTER
Because we had a fire
on the production
floor that was
contained in our inline
washer, we were able
to get through
insurance: a new
washer, copper piping
and an air compression
station; meanwhile,
removing all old
equipment.
San Diego - October Metrics

More Related Content

What's hot

Good practice - KIP - LBC - LE 180397
Good practice - KIP - LBC - LE 180397Good practice - KIP - LBC - LE 180397
Good practice - KIP - LBC - LE 180397Sanjay Singh
 
Advanced Anemometer With Datalogger by ACMAS Technologies Pvt Ltd.
Advanced Anemometer With Datalogger by ACMAS Technologies Pvt Ltd.Advanced Anemometer With Datalogger by ACMAS Technologies Pvt Ltd.
Advanced Anemometer With Datalogger by ACMAS Technologies Pvt Ltd.Acmas Technologies Pvt. Ltd.
 
RooterPLUS! More about us!
RooterPLUS! More about us!RooterPLUS! More about us!
RooterPLUS! More about us!RooterPLUS
 
Welcome to the 4 companies of apx (2)
Welcome to the 4 companies of apx (2)Welcome to the 4 companies of apx (2)
Welcome to the 4 companies of apx (2)Andrew Papoutsis
 
Ross Valve - Pre Engineered Vault
Ross Valve - Pre Engineered VaultRoss Valve - Pre Engineered Vault
Ross Valve - Pre Engineered VaultVito Pagano
 
Clean room hvac equipment
Clean room hvac equipmentClean room hvac equipment
Clean room hvac equipmentmakcleanair1
 
Wood Moisture Meter Analytical by ACMAS Technologies Pvt Ltd.
Wood Moisture Meter Analytical by ACMAS Technologies Pvt Ltd.Wood Moisture Meter Analytical by ACMAS Technologies Pvt Ltd.
Wood Moisture Meter Analytical by ACMAS Technologies Pvt Ltd.Acmas Technologies Pvt. Ltd.
 
Wood Moisture Meters by ACMAS Technologies Pvt Ltd.
Wood Moisture Meters by ACMAS Technologies Pvt Ltd.Wood Moisture Meters by ACMAS Technologies Pvt Ltd.
Wood Moisture Meters by ACMAS Technologies Pvt Ltd.Acmas Technologies Pvt. Ltd.
 
Table Top Air Particle Counter by ACMAS Technologies Pvt Ltd.
Table Top Air Particle Counter by ACMAS Technologies Pvt Ltd.Table Top Air Particle Counter by ACMAS Technologies Pvt Ltd.
Table Top Air Particle Counter by ACMAS Technologies Pvt Ltd.Acmas Technologies Pvt. Ltd.
 
DALLAN and DALCOS production system - company presentation
DALLAN and DALCOS production system - company presentationDALLAN and DALCOS production system - company presentation
DALLAN and DALCOS production system - company presentationAndrea Dallan
 

What's hot (12)

Good practice - KIP - LBC - LE 180397
Good practice - KIP - LBC - LE 180397Good practice - KIP - LBC - LE 180397
Good practice - KIP - LBC - LE 180397
 
Advanced Anemometer With Datalogger by ACMAS Technologies Pvt Ltd.
Advanced Anemometer With Datalogger by ACMAS Technologies Pvt Ltd.Advanced Anemometer With Datalogger by ACMAS Technologies Pvt Ltd.
Advanced Anemometer With Datalogger by ACMAS Technologies Pvt Ltd.
 
RooterPLUS! More about us!
RooterPLUS! More about us!RooterPLUS! More about us!
RooterPLUS! More about us!
 
Minac 25-40kW
Minac 25-40kWMinac 25-40kW
Minac 25-40kW
 
Welcome to the 4 companies of apx (2)
Welcome to the 4 companies of apx (2)Welcome to the 4 companies of apx (2)
Welcome to the 4 companies of apx (2)
 
Ross Valve - Pre Engineered Vault
Ross Valve - Pre Engineered VaultRoss Valve - Pre Engineered Vault
Ross Valve - Pre Engineered Vault
 
Clean room hvac equipment
Clean room hvac equipmentClean room hvac equipment
Clean room hvac equipment
 
Wood Moisture Meter Analytical by ACMAS Technologies Pvt Ltd.
Wood Moisture Meter Analytical by ACMAS Technologies Pvt Ltd.Wood Moisture Meter Analytical by ACMAS Technologies Pvt Ltd.
Wood Moisture Meter Analytical by ACMAS Technologies Pvt Ltd.
 
Wood Moisture Meters by ACMAS Technologies Pvt Ltd.
Wood Moisture Meters by ACMAS Technologies Pvt Ltd.Wood Moisture Meters by ACMAS Technologies Pvt Ltd.
Wood Moisture Meters by ACMAS Technologies Pvt Ltd.
 
Avnet Service Brief: Thermal Management
Avnet Service Brief: Thermal ManagementAvnet Service Brief: Thermal Management
Avnet Service Brief: Thermal Management
 
Table Top Air Particle Counter by ACMAS Technologies Pvt Ltd.
Table Top Air Particle Counter by ACMAS Technologies Pvt Ltd.Table Top Air Particle Counter by ACMAS Technologies Pvt Ltd.
Table Top Air Particle Counter by ACMAS Technologies Pvt Ltd.
 
DALLAN and DALCOS production system - company presentation
DALLAN and DALCOS production system - company presentationDALLAN and DALCOS production system - company presentation
DALLAN and DALCOS production system - company presentation
 

Viewers also liked

Viewers also liked (12)

Datos personales
Datos personalesDatos personales
Datos personales
 
The Latest Developments regarding IP and Trade Secrets - Law and Practice-Hef...
The Latest Developments regarding IP and Trade Secrets - Law and Practice-Hef...The Latest Developments regarding IP and Trade Secrets - Law and Practice-Hef...
The Latest Developments regarding IP and Trade Secrets - Law and Practice-Hef...
 
Music magazine analysis
Music magazine analysis Music magazine analysis
Music magazine analysis
 
Los valores
Los valoresLos valores
Los valores
 
Aircraft Noise Prediction and Community Noise (1)
Aircraft Noise Prediction and Community Noise (1)Aircraft Noise Prediction and Community Noise (1)
Aircraft Noise Prediction and Community Noise (1)
 
Townhouse in Algarve
Townhouse in AlgarveTownhouse in Algarve
Townhouse in Algarve
 
Twitter
TwitterTwitter
Twitter
 
Terapia antimicrobica nella sepsi addominale
Terapia antimicrobica nella sepsi addominaleTerapia antimicrobica nella sepsi addominale
Terapia antimicrobica nella sepsi addominale
 
Biografia 3 e
Biografia 3 eBiografia 3 e
Biografia 3 e
 
Clase Invertida - "Flipped Classroom"
Clase Invertida - "Flipped Classroom"Clase Invertida - "Flipped Classroom"
Clase Invertida - "Flipped Classroom"
 
How to Audit PPC (Adwords) Accounts - Complete Checklist
How to Audit PPC (Adwords) Accounts - Complete ChecklistHow to Audit PPC (Adwords) Accounts - Complete Checklist
How to Audit PPC (Adwords) Accounts - Complete Checklist
 
Acute diarrhea 2015
Acute diarrhea 2015Acute diarrhea 2015
Acute diarrhea 2015
 

Similar to San Diego - October Metrics

AC MAINTENANCE.PPTX
AC MAINTENANCE.PPTXAC MAINTENANCE.PPTX
AC MAINTENANCE.PPTXAli N Jasim
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updatedPersonal Secret
 
S-LINE Pipe Suppliers Sharjah.pptx
S-LINE Pipe Suppliers Sharjah.pptxS-LINE Pipe Suppliers Sharjah.pptx
S-LINE Pipe Suppliers Sharjah.pptxJinoVarghese14
 
Lean Manufacturing Applications Implementation
Lean Manufacturing Applications Implementation Lean Manufacturing Applications Implementation
Lean Manufacturing Applications Implementation Mostafa Alattar
 
Report about the repairation of the Raw mill Slide Ring and shell (Modificat...
Report about the repairation of the Raw mill Slide Ring and  shell (Modificat...Report about the repairation of the Raw mill Slide Ring and  shell (Modificat...
Report about the repairation of the Raw mill Slide Ring and shell (Modificat...Moaz Emad gaber
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)SAJJAD KHUDHUR ABBAS
 
PASS/START-PROF capabilities for district heating industry
PASS/START-PROF capabilities for district heating industryPASS/START-PROF capabilities for district heating industry
PASS/START-PROF capabilities for district heating industryAlex Matveev
 
FineTek (Taiwan) Introduction to Applications in the Cement Industry
FineTek (Taiwan) Introduction to Applications in the Cement IndustryFineTek (Taiwan) Introduction to Applications in the Cement Industry
FineTek (Taiwan) Introduction to Applications in the Cement IndustryMr. FineTek
 
Instrument Technician for Maintenance new
Instrument Technician  for Maintenance newInstrument Technician  for Maintenance new
Instrument Technician for Maintenance newNoel Roque
 
ACCOMPLISHMENTS 1986 -2013
ACCOMPLISHMENTS 1986 -2013ACCOMPLISHMENTS 1986 -2013
ACCOMPLISHMENTS 1986 -2013Joseph Barile
 
Trailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit BreakersTrailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit BreakersMarty Stevenson
 

Similar to San Diego - October Metrics (20)

contamination control
contamination controlcontamination control
contamination control
 
AC MAINTENANCE.PPTX
AC MAINTENANCE.PPTXAC MAINTENANCE.PPTX
AC MAINTENANCE.PPTX
 
CV-ATO-3 (1)
CV-ATO-3 (1)CV-ATO-3 (1)
CV-ATO-3 (1)
 
PPT-on-false-air.ppt
PPT-on-false-air.pptPPT-on-false-air.ppt
PPT-on-false-air.ppt
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
S-LINE Pipe Suppliers Sharjah.pptx
S-LINE Pipe Suppliers Sharjah.pptxS-LINE Pipe Suppliers Sharjah.pptx
S-LINE Pipe Suppliers Sharjah.pptx
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Lean Manufacturing Applications Implementation
Lean Manufacturing Applications Implementation Lean Manufacturing Applications Implementation
Lean Manufacturing Applications Implementation
 
Report about the repairation of the Raw mill Slide Ring and shell (Modificat...
Report about the repairation of the Raw mill Slide Ring and  shell (Modificat...Report about the repairation of the Raw mill Slide Ring and  shell (Modificat...
Report about the repairation of the Raw mill Slide Ring and shell (Modificat...
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
C.V
C.VC.V
C.V
 
Barry Cutting - Booster fans Angus Place Colliery
Barry Cutting  - Booster fans Angus Place CollieryBarry Cutting  - Booster fans Angus Place Colliery
Barry Cutting - Booster fans Angus Place Colliery
 
PASS/START-PROF capabilities for district heating industry
PASS/START-PROF capabilities for district heating industryPASS/START-PROF capabilities for district heating industry
PASS/START-PROF capabilities for district heating industry
 
FineTek (Taiwan) Introduction to Applications in the Cement Industry
FineTek (Taiwan) Introduction to Applications in the Cement IndustryFineTek (Taiwan) Introduction to Applications in the Cement Industry
FineTek (Taiwan) Introduction to Applications in the Cement Industry
 
Instrument Technician for Maintenance new
Instrument Technician  for Maintenance newInstrument Technician  for Maintenance new
Instrument Technician for Maintenance new
 
ACCOMPLISHMENTS 1986 -2013
ACCOMPLISHMENTS 1986 -2013ACCOMPLISHMENTS 1986 -2013
ACCOMPLISHMENTS 1986 -2013
 
Mwhe manual
Mwhe manualMwhe manual
Mwhe manual
 
Trailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit BreakersTrailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit Breakers
 
076 circuit breaker install 1.0
076 circuit breaker install 1.0076 circuit breaker install 1.0
076 circuit breaker install 1.0
 
BP[1] Copy
BP[1] CopyBP[1] Copy
BP[1] Copy
 

San Diego - October Metrics

  • 1. MX ELECTRONICS MANUFACTURING – SAN DIEGO METRICS REVIEW FOR OCTOBER 2014 1
  • 2. On Time Delivery ISI Target 98% 2 San Diego On time Delivery – 84.5% average First Pass Yield – After the SMT machine – 40% - found misalignment problem with components – tracked it back to stencil printer, replaced motor and encoder 11/18 After the Wave Solder – 25% - cleaned the solder pots after 4 years of usage – 11/5 After the touch up from the wave solder – 60% - assemblers still forgetting to place all components on – re-work affecting class 3 jobs After the hand trimming of the leads after touch up – 90% - looking into getting automated machine After the insert of LED’s on the back side – 80%, because there are no batch sizes, interruptions are happening affecting components being placed 100% After the wash and at final inspection – 90%, process improved due to switch in solder mask, and new washer
  • 3. Before AFTER The lead and lead-free solder pots had not been cleaned for more than 4 years effecting quality, requiring touch-up and re-work; resulting in, field failures for class 2 - 3 projects.
  • 4. 1. Bins for WIP were everywhere on the production floor 2. Inventory was in 5 locations in building 3. There was no work space on any work station due to excessive tools/ feeder guns, garbage BEFORE
  • 5. 1. Eliminated tables and work stations 2. Controlled inventory and projects in WIP 3. Implemented ESD protocols for smocks, tables, heel straps, and floor AFTER
  • 6. 1. Considered all safety hazards and concerns – like extension cords, hanging wires, pvc piping. 2. Removed all solder stations and replaced them with digital equipment 3. Removed all fans from work stations and replaced them with extraction fans BEFORE
  • 8. Because we had a fire on the production floor that was contained in our inline washer, we were able to get through insurance: a new washer, copper piping and an air compression station; meanwhile, removing all old equipment.