SlideShare a Scribd company logo
1 of 4
Download to read offline
Best Practices in Project Management
Sachithra Gayan Gunarathne
Sabaragamuwa University Of Sri Lanka
gayan_sac@yahoo.com
1
Abstract
Often, project managers have to monitor and many
projects concurrently. Unfortunately, some projects
were completed successfully but some were not
completed on time, over budget or being cancelled.
Some of the reasons of this project failure are: lack of
user involvement, lack of planning, incomplete
requirements, lack of resources, incorrect cost
estimation, just to name a few. There are many
project planning and scheduling techniques to
manage and help to ensure project success. Some of
these techniques, however, may not be suitable for
specific types of projects and thus, cause projects to
fail.
Grounded Theory is still regarded with skepticism as
a research methodology by many academics. The
whole Grounded Theory methodology can be seen in
operation and the concepts and categories can be seen
emerging from the data.
Keyword: Grounded Theory Methodology,
Practices, Project Management
Introduction
Project Management
The application of knowledge, skills, tools and
techniques to project activities in order to meet their
requirements. Managing a project comprises defining
goals and objectives through the planning and actions
control, activities, and tasks necessary to complete a
project successfully.
Practices in project management
The body of knowledge in project management, and
it is considered as a basic reference in this area being
"widely recognized" as the best practice, which
means that their knowledge and practices "are
applicable to most projects in most of the time and
that there is a consensus about their value and utility."
this does not mean that the knowledge described
should always be applied uniformly in all cases, that
is, the organization or the project management team
will determine what is appropriate or
Not, for a specific project.
Methodology
Developing a theory of project management best
practice
In the Grounded Theory Methodology, analysis look
for relationships and connections between the core
category and the other categories. This is known in
grounded theory as theoretical coding, a term coined
by Glaser and Strauss (1967). However, the four
categories of Managing the Customer, Managing the
Project Work, Managing Communications and
Managing Stakeholders are well known and well
established in the literature so no further comment
will be made in this text other than stating the
obvious that they must be included in project
management best practice. The three categories of
Awareing, Motivating and Knowledge Transfer are
interesting and less well documented in connection to
project management. A full analysis of the
relationships between all the categories is available
from the authors.
Awareing
This ties Awareing to all but two of the other
categories which shows its interconnectedness and
thereby its strong position in project management
best practice. However, in practice little notice is
taken of making people aware or of the PM being
aware. Thus, two types of awareness can be
distinguished: the PM’s awareness and other people’s
awareness (more appropriately called Stakeholder’s
awareness).
The PM’s awareness consists of four parts: PM’s
awareness of herself/himself, PM’s awareness of
stakeholders, PM’s awareness of project issues and
the PM’s awareness of Stakeholder’s awareness. Best
practice occurs when the PM considers all four
awarenesses.
Project stakeholders include development team
members, customers, top management, other PMs on
other projects within the organization, suppliers and
subcontractors. The concept of awareing
encapsulates the fact that a good PM has to manage
the awareness of all these people. In particular, the
PM has to manage the awareness of the customers by
Best Practices in Project Management
Sachithra Gayan Gunarathne
Sabaragamuwa University Of Sri Lanka
gayan_sac@yahoo.com
2
appraising them at all times of risks, problems and
difficulties, project progress, need for communication
and need for clear requirements. It is not enough for
the PM to inform customers of these issues, the PM
has to make the customer aware. This is another
factor in project management best practice.
Similarly, the PM has to make the development team
aware of the project’s importance, context and
benefits, of the risks, of the need for internal
communication, of the customer’s changes to
requirements, and of the actual project work. All this
comes from the analysis.
Motivating
The category of Motivating has four concepts
regarded now as properties of motivating. These are
Responsibilising Self-motivation; Awareing the team
and Leadership. Responsibilising encapsulates
delegating responsibility (as well as project work)
and managing how team members handle that
responsibility. An ability to do this is regarded as a
contribution to project management best practice.
Any absence of self-motivation in a PM must have a
negative influence in project work and project
success, whereas good self-motivation will contribute
to project success. This is a subject worthy of future
research.
Awareing the project team of difficulties and
problems appeared to help the project workers avoid
problems rather than having to fix them after they
had occurred. Good leadership, good responsibilising
and high PM motivation will motivate the
development team, whereas poor leadership coupled
with poor responsibilising and low PM motivation
will inhibit a team’s motivation. Therefore good
leadership coupled with good responsibilising and
high PM motivation are key to project success and
therefore elements in best practice. However, the
three elements of good leadership, good
responsibilising and high PM motivation are tough
concepts and difficult to achieve in practice.
There emerged a strong connection between
motivation and being aware of motivation. The
relationship between these two parts defines the
connection between motivation and managing
awareness. The two parts are absorbed by each other,
their concepts transfer by osmosis.
Knowledge transfer
The PM has an important role in knowledge transfer
(KT) because it is the PM who has to make KT
happen. When KT does take place the PM has to be
aware of the possible difficulties in the actual process
of the transfer as well as the accuracy of the
knowledge itself. When KT does not happen, the PM
has to be aware of the lack of transfer and the need
for KT to happen.
Knowledge transfer can be informal in the work place
between team members or between the PM and
technical staff or higher management. Alternatively,
KT can be formal in the form of minutes of meetings
and official documents. From this research came the
concept of unused knowledge, that is where KT did
not take place for undisclosed reasons. Therefore KT
has properties of informal, formal, and unused. The
area of KT and its properties would make interesting
future research projects.
Research findings
Project Classification
Basically, projects can be classified into three
resolution types:
I. Project success: The project is completed on-time,
on-budget, fulfilled all functions and features as
specified.
Table 1: Project success factors
Best Practices in Project Management
Sachithra Gayan Gunarathne
Sabaragamuwa University Of Sri Lanka
gayan_sac@yahoo.com
3
II. Project challenged:
The project is completed and operational but over-
budget, over the time estimate, and offers fewer
functions and features than originally specified.
III. Project impaired:
The project is cancelled at some point during the
development cycle.
Among these three types, the success rate was only
16.2%, while challenged projects accounted for
52.7%, and impaired (cancelled) was 31.1%.
Causes of project failure
Projects fail mainly because of unable to plan and
estimate correctly, or fail to implement the tasks
according to plan or failure causes by human factor.
The following sections explain these three causes of
failure:
I. Planning and Estimation factor:
This factor refers to initial cost and schedule
estimates are not revised when more information
becomes available as a project progresses. Also
plans are not used correctly or used to guide the
project forward, thus causing the project to fail.
II. Implementation factor:
This is caused by project scope changes, incorrect use
of project methodology, major changes in the
requirements and testing, and/or inspections are
poorly done.
III. Human factor:
Project managers are not trained to acquire the
necessary management skills. Also, some managers
are not able to apply and put the theory of project
management into practice. Poor communications are
also one of the human factors that cause a project to
fail.
Among these three factors, the major cause of project
failure is inappropriate use of project planning and
scheduling methodology. The next category of these
from the Standish report deals with projects that
proved to be “challenged,” that is they were
completed but were over budget, over time, or did not
contain all functions and features originally required.
Successful and challenged projects showed good
technical skills of the project managers, while failed
projects showed the project manager had only fair
skills. According to the 2002 Standish Report, three
top factors that impacted on not completed projects
are lack of user input, incomplete requirements and
specifications, and changing requirements and
specifications.
Table 2: Project challenged factors
Table 3: Project failed factors
Best Practices in Project Management
Sachithra Gayan Gunarathne
Sabaragamuwa University Of Sri Lanka
gayan_sac@yahoo.com
4
Conclusion
This paper discusses about project success and
failure, the project classification and the factors that
contributed to project success and resulted in project
failure. Also, poor planning and scheduling are the
main reasons of project failure. Other important
issues that must not be neglected are the quality of
the team leaders and team spirits among the team
members.
The PM’s awareness of motivation is key to
motivating everyone else including the customer. It is
not enough for a PM to motivate the team, the PM
has to monitor and manage the state of the team’s
motivation. Good leadership combined with good
responsibilising and high PM motivation will
increase everyone else’s motivation and lead to
reduced risk of project failure. However, good
leadership, good responsibilising and high motivation
are all tough concepts which do not occur naturally
and need to be developed.
When the process of knowledge transfer is managed
well, knowledge will flow, accumulate and build up
and this will promote better management in the team,
the project work, the customer, other stakeholders
and every aspect of project management. Knowledge
transfer increases motivation and is an essential
element in good leadership.
References
I. Gray, C. F. and Larson, E. W. Project
Management: The managerial process. 4th Edition,
McGraw–Hill Educations, Singapore, (2008).
II. Ahern, T., & Leavy, B., Byrne, P.J. Complex
Project Management as Complex Problem Solving: a
distributed knowledge management perspective.
Elsevier: Ireland (2013).
III. Clancy, T. The Standish Group Report,
Retrieved Feb 20, 2008 from
http://www.projectsmart.co.uk/reports.html, Chaos
report, (1995).
IV. Allan, G.W., The Use of Grounded Theory as a
Research Method: warts & all, in: Ray Hackney (Ed.)
Proceedings of the International Symposium on
Research Methods, Tampa, USA, (2005).
Table 4: Issues of project management success

More Related Content

What's hot

Improving IT Project Communication
Improving IT Project CommunicationImproving IT Project Communication
Improving IT Project Communicationarshriz
 
Assessment center for_project_managers
Assessment center for_project_managersAssessment center for_project_managers
Assessment center for_project_managerskarishma143
 
1 unit 1_complexity_uncertainty-reduction strategies
1 unit 1_complexity_uncertainty-reduction strategies1 unit 1_complexity_uncertainty-reduction strategies
1 unit 1_complexity_uncertainty-reduction strategiesRishabhAgarwal823918
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project ManagementGoutama Bachtiar
 
Presentation by somdatta banerjee
Presentation by somdatta banerjeePresentation by somdatta banerjee
Presentation by somdatta banerjeePMI_IREP_TP
 
Book project management
Book project managementBook project management
Book project managementsadafebaco
 
The Theory versus Practice of Project Management
The Theory versus Practice of Project ManagementThe Theory versus Practice of Project Management
The Theory versus Practice of Project ManagementGlen Alleman
 
Presentation by suhail qadir
Presentation by suhail qadirPresentation by suhail qadir
Presentation by suhail qadirPMI_IREP_TP
 
Survey: Problems Related to Human in Software Projects
Survey: Problems Related to Human in Software ProjectsSurvey: Problems Related to Human in Software Projects
Survey: Problems Related to Human in Software ProjectsIOSR Journals
 
Information Technology Project Management - part 01
Information Technology Project Management - part 01Information Technology Project Management - part 01
Information Technology Project Management - part 01Rizwan Khurram
 
FROM PMO TO STRATEGIC PMO - AN INDIRECT APPROACH
FROM PMO TO STRATEGIC PMO - AN INDIRECT APPROACHFROM PMO TO STRATEGIC PMO - AN INDIRECT APPROACH
FROM PMO TO STRATEGIC PMO - AN INDIRECT APPROACHPhilippe Husser
 
A critical success factors for software project manager in GVTs within covid-...
A critical success factors for software project manager in GVTs within covid-...A critical success factors for software project manager in GVTs within covid-...
A critical success factors for software project manager in GVTs within covid-...journalBEEI
 
Presentation by dattatraya pathak
Presentation by dattatraya pathakPresentation by dattatraya pathak
Presentation by dattatraya pathakPMI_IREP_TP
 
The Human Side of Project Management
The Human Side of Project ManagementThe Human Side of Project Management
The Human Side of Project ManagementAchchuthan Seetharan
 
Pm600 1103 a-02-schwappach-loren-p1-t2
Pm600 1103 a-02-schwappach-loren-p1-t2Pm600 1103 a-02-schwappach-loren-p1-t2
Pm600 1103 a-02-schwappach-loren-p1-t2Loren Schwappach
 

What's hot (20)

Improving IT Project Communication
Improving IT Project CommunicationImproving IT Project Communication
Improving IT Project Communication
 
PFEG_1
PFEG_1PFEG_1
PFEG_1
 
ETPM3
ETPM3ETPM3
ETPM3
 
Assessment center for_project_managers
Assessment center for_project_managersAssessment center for_project_managers
Assessment center for_project_managers
 
1 unit 1_complexity_uncertainty-reduction strategies
1 unit 1_complexity_uncertainty-reduction strategies1 unit 1_complexity_uncertainty-reduction strategies
1 unit 1_complexity_uncertainty-reduction strategies
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project Management
 
Leveraging the Science and Art of PROJECT MANAGEMENT to realize Make in India
Leveraging the Science and Art of PROJECT MANAGEMENT to realize Make in IndiaLeveraging the Science and Art of PROJECT MANAGEMENT to realize Make in India
Leveraging the Science and Art of PROJECT MANAGEMENT to realize Make in India
 
Presentation by somdatta banerjee
Presentation by somdatta banerjeePresentation by somdatta banerjee
Presentation by somdatta banerjee
 
ETCA_1
ETCA_1ETCA_1
ETCA_1
 
Praveen gupta
Praveen guptaPraveen gupta
Praveen gupta
 
Book project management
Book project managementBook project management
Book project management
 
The Theory versus Practice of Project Management
The Theory versus Practice of Project ManagementThe Theory versus Practice of Project Management
The Theory versus Practice of Project Management
 
Presentation by suhail qadir
Presentation by suhail qadirPresentation by suhail qadir
Presentation by suhail qadir
 
Survey: Problems Related to Human in Software Projects
Survey: Problems Related to Human in Software ProjectsSurvey: Problems Related to Human in Software Projects
Survey: Problems Related to Human in Software Projects
 
Information Technology Project Management - part 01
Information Technology Project Management - part 01Information Technology Project Management - part 01
Information Technology Project Management - part 01
 
FROM PMO TO STRATEGIC PMO - AN INDIRECT APPROACH
FROM PMO TO STRATEGIC PMO - AN INDIRECT APPROACHFROM PMO TO STRATEGIC PMO - AN INDIRECT APPROACH
FROM PMO TO STRATEGIC PMO - AN INDIRECT APPROACH
 
A critical success factors for software project manager in GVTs within covid-...
A critical success factors for software project manager in GVTs within covid-...A critical success factors for software project manager in GVTs within covid-...
A critical success factors for software project manager in GVTs within covid-...
 
Presentation by dattatraya pathak
Presentation by dattatraya pathakPresentation by dattatraya pathak
Presentation by dattatraya pathak
 
The Human Side of Project Management
The Human Side of Project ManagementThe Human Side of Project Management
The Human Side of Project Management
 
Pm600 1103 a-02-schwappach-loren-p1-t2
Pm600 1103 a-02-schwappach-loren-p1-t2Pm600 1103 a-02-schwappach-loren-p1-t2
Pm600 1103 a-02-schwappach-loren-p1-t2
 

Viewers also liked

LC Tim # 2, 2014. Revija LafargeHolcim Slovenija
LC Tim # 2, 2014. Revija LafargeHolcim SlovenijaLC Tim # 2, 2014. Revija LafargeHolcim Slovenija
LC Tim # 2, 2014. Revija LafargeHolcim SlovenijaLafarge Cement d.o.o.
 
LC Tim # 3, 2014. Revija LafargeHolcim Slovenija
LC Tim # 3, 2014. Revija LafargeHolcim Slovenija LC Tim # 3, 2014. Revija LafargeHolcim Slovenija
LC Tim # 3, 2014. Revija LafargeHolcim Slovenija Lafarge Cement d.o.o.
 
Bán vé máy bay vietnam airlines tân sân nhất đi quảng châu giá rẻ
Bán vé máy bay vietnam airlines tân sân nhất đi quảng châu giá rẻBán vé máy bay vietnam airlines tân sân nhất đi quảng châu giá rẻ
Bán vé máy bay vietnam airlines tân sân nhất đi quảng châu giá rẻthuy07baydep
 
What to Consider before Investing in Hotels
What to Consider before Investing in HotelsWhat to Consider before Investing in Hotels
What to Consider before Investing in HotelsBharat Lall
 
Manual instrutivo rede_atencao_urgencias
Manual instrutivo rede_atencao_urgenciasManual instrutivo rede_atencao_urgencias
Manual instrutivo rede_atencao_urgenciasAlexandra Caetano
 
Jessica flores actividad2.3_unidad2
Jessica flores actividad2.3_unidad2Jessica flores actividad2.3_unidad2
Jessica flores actividad2.3_unidad2JessiFlores25
 

Viewers also liked (11)

IOHAconfpaperMM
IOHAconfpaperMMIOHAconfpaperMM
IOHAconfpaperMM
 
Seguridad previa en comercio
Seguridad previa en comercioSeguridad previa en comercio
Seguridad previa en comercio
 
Twitter febrero 2016
Twitter febrero 2016Twitter febrero 2016
Twitter febrero 2016
 
WeddingPackages
WeddingPackagesWeddingPackages
WeddingPackages
 
LC Tim # 2, 2014. Revija LafargeHolcim Slovenija
LC Tim # 2, 2014. Revija LafargeHolcim SlovenijaLC Tim # 2, 2014. Revija LafargeHolcim Slovenija
LC Tim # 2, 2014. Revija LafargeHolcim Slovenija
 
LC Tim # 3, 2014. Revija LafargeHolcim Slovenija
LC Tim # 3, 2014. Revija LafargeHolcim Slovenija LC Tim # 3, 2014. Revija LafargeHolcim Slovenija
LC Tim # 3, 2014. Revija LafargeHolcim Slovenija
 
Bán vé máy bay vietnam airlines tân sân nhất đi quảng châu giá rẻ
Bán vé máy bay vietnam airlines tân sân nhất đi quảng châu giá rẻBán vé máy bay vietnam airlines tân sân nhất đi quảng châu giá rẻ
Bán vé máy bay vietnam airlines tân sân nhất đi quảng châu giá rẻ
 
What to Consider before Investing in Hotels
What to Consider before Investing in HotelsWhat to Consider before Investing in Hotels
What to Consider before Investing in Hotels
 
Manual instrutivo rede_atencao_urgencias
Manual instrutivo rede_atencao_urgenciasManual instrutivo rede_atencao_urgencias
Manual instrutivo rede_atencao_urgencias
 
Jessica flores actividad2.3_unidad2
Jessica flores actividad2.3_unidad2Jessica flores actividad2.3_unidad2
Jessica flores actividad2.3_unidad2
 
Drones
DronesDrones
Drones
 

Similar to Best Practices in Project Management

Project Management case analysis
Project Management case analysisProject Management case analysis
Project Management case analysisWakas Khalid
 
MGT323 SEUMid
MGT323 SEUMidMGT323 SEUMid
MGT323 SEUMidJammyDe
 
CHAPTER 2 Strategic Management and Project SelectionMore and m.docx
CHAPTER 2 Strategic Management and Project SelectionMore and m.docxCHAPTER 2 Strategic Management and Project SelectionMore and m.docx
CHAPTER 2 Strategic Management and Project SelectionMore and m.docxcravennichole326
 
Why projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsWhy projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsTa Ngoc
 
Mandarkulkarni 111003065827-phpapp01
Mandarkulkarni 111003065827-phpapp01Mandarkulkarni 111003065827-phpapp01
Mandarkulkarni 111003065827-phpapp01PMI_IREP_TP
 
Student 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxStudent 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxcpatriciarpatricia
 
Student 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxStudent 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxdeanmtaylor1545
 
Project management practices the criteria for success or failure
Project management practices the criteria for success or failureProject management practices the criteria for success or failure
Project management practices the criteria for success or failureTa Ngoc
 
3The Project Management ProcessGroups A Case StudyAft.docx
3The Project Management ProcessGroups A Case StudyAft.docx3The Project Management ProcessGroups A Case StudyAft.docx
3The Project Management ProcessGroups A Case StudyAft.docxgilbertkpeters11344
 
Project Estimating Paper
Project Estimating PaperProject Estimating Paper
Project Estimating PaperCamella Taylor
 
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...Mr.Allah Dad Khan
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Renee Jones
 
MBA 6931, Project Management Strategy and Tactics 1 C.docx
 MBA 6931, Project Management Strategy and Tactics 1 C.docx MBA 6931, Project Management Strategy and Tactics 1 C.docx
MBA 6931, Project Management Strategy and Tactics 1 C.docxaryan532920
 
Project Management Project Manager Project
Project Management Project Manager ProjectProject Management Project Manager Project
Project Management Project Manager ProjectErin Moore
 
Dilemmas in Contemporary Project Management - By Karina Rozario Varu
Dilemmas in Contemporary Project Management - By Karina Rozario VaruDilemmas in Contemporary Project Management - By Karina Rozario Varu
Dilemmas in Contemporary Project Management - By Karina Rozario VaruKarina Rozario Varu
 
Individual Project Part 3 Project Evaluation, Lessons Learned, a.docx
 Individual Project Part 3 Project Evaluation, Lessons Learned, a.docx Individual Project Part 3 Project Evaluation, Lessons Learned, a.docx
Individual Project Part 3 Project Evaluation, Lessons Learned, a.docxjoney4
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train WrecksPete Luan
 

Similar to Best Practices in Project Management (20)

Project Management case analysis
Project Management case analysisProject Management case analysis
Project Management case analysis
 
MGT323 SEUMid
MGT323 SEUMidMGT323 SEUMid
MGT323 SEUMid
 
CHAPTER 2 Strategic Management and Project SelectionMore and m.docx
CHAPTER 2 Strategic Management and Project SelectionMore and m.docxCHAPTER 2 Strategic Management and Project SelectionMore and m.docx
CHAPTER 2 Strategic Management and Project SelectionMore and m.docx
 
Why projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsWhy projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfalls
 
Mandarkulkarni 111003065827-phpapp01
Mandarkulkarni 111003065827-phpapp01Mandarkulkarni 111003065827-phpapp01
Mandarkulkarni 111003065827-phpapp01
 
Student 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxStudent 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docx
 
Student 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxStudent 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docx
 
Project management practices the criteria for success or failure
Project management practices the criteria for success or failureProject management practices the criteria for success or failure
Project management practices the criteria for success or failure
 
3The Project Management ProcessGroups A Case StudyAft.docx
3The Project Management ProcessGroups A Case StudyAft.docx3The Project Management ProcessGroups A Case StudyAft.docx
3The Project Management ProcessGroups A Case StudyAft.docx
 
Project Estimating Paper
Project Estimating PaperProject Estimating Paper
Project Estimating Paper
 
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
 
MBA 6931, Project Management Strategy and Tactics 1 C.docx
 MBA 6931, Project Management Strategy and Tactics 1 C.docx MBA 6931, Project Management Strategy and Tactics 1 C.docx
MBA 6931, Project Management Strategy and Tactics 1 C.docx
 
Project Management Project Manager Project
Project Management Project Manager ProjectProject Management Project Manager Project
Project Management Project Manager Project
 
Projects
ProjectsProjects
Projects
 
Dilemmas in Contemporary Project Management - By Karina Rozario Varu
Dilemmas in Contemporary Project Management - By Karina Rozario VaruDilemmas in Contemporary Project Management - By Karina Rozario Varu
Dilemmas in Contemporary Project Management - By Karina Rozario Varu
 
Pmbok
PmbokPmbok
Pmbok
 
Individual Project Part 3 Project Evaluation, Lessons Learned, a.docx
 Individual Project Part 3 Project Evaluation, Lessons Learned, a.docx Individual Project Part 3 Project Evaluation, Lessons Learned, a.docx
Individual Project Part 3 Project Evaluation, Lessons Learned, a.docx
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train Wrecks
 
CIB8942.pdf
CIB8942.pdfCIB8942.pdf
CIB8942.pdf
 

More from Sachithra Gayan

More from Sachithra Gayan (6)

Computer Network Security
Computer Network SecurityComputer Network Security
Computer Network Security
 
Embedded Robotics
Embedded RoboticsEmbedded Robotics
Embedded Robotics
 
Data acquisition softwares
Data acquisition softwaresData acquisition softwares
Data acquisition softwares
 
Source control
Source controlSource control
Source control
 
Software Quality Assurance
Software Quality AssuranceSoftware Quality Assurance
Software Quality Assurance
 
Test Driven Development
Test Driven DevelopmentTest Driven Development
Test Driven Development
 

Recently uploaded

Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxAbhayThakur200703
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 

Recently uploaded (20)

Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptx
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 

Best Practices in Project Management

  • 1. Best Practices in Project Management Sachithra Gayan Gunarathne Sabaragamuwa University Of Sri Lanka gayan_sac@yahoo.com 1 Abstract Often, project managers have to monitor and many projects concurrently. Unfortunately, some projects were completed successfully but some were not completed on time, over budget or being cancelled. Some of the reasons of this project failure are: lack of user involvement, lack of planning, incomplete requirements, lack of resources, incorrect cost estimation, just to name a few. There are many project planning and scheduling techniques to manage and help to ensure project success. Some of these techniques, however, may not be suitable for specific types of projects and thus, cause projects to fail. Grounded Theory is still regarded with skepticism as a research methodology by many academics. The whole Grounded Theory methodology can be seen in operation and the concepts and categories can be seen emerging from the data. Keyword: Grounded Theory Methodology, Practices, Project Management Introduction Project Management The application of knowledge, skills, tools and techniques to project activities in order to meet their requirements. Managing a project comprises defining goals and objectives through the planning and actions control, activities, and tasks necessary to complete a project successfully. Practices in project management The body of knowledge in project management, and it is considered as a basic reference in this area being "widely recognized" as the best practice, which means that their knowledge and practices "are applicable to most projects in most of the time and that there is a consensus about their value and utility." this does not mean that the knowledge described should always be applied uniformly in all cases, that is, the organization or the project management team will determine what is appropriate or Not, for a specific project. Methodology Developing a theory of project management best practice In the Grounded Theory Methodology, analysis look for relationships and connections between the core category and the other categories. This is known in grounded theory as theoretical coding, a term coined by Glaser and Strauss (1967). However, the four categories of Managing the Customer, Managing the Project Work, Managing Communications and Managing Stakeholders are well known and well established in the literature so no further comment will be made in this text other than stating the obvious that they must be included in project management best practice. The three categories of Awareing, Motivating and Knowledge Transfer are interesting and less well documented in connection to project management. A full analysis of the relationships between all the categories is available from the authors. Awareing This ties Awareing to all but two of the other categories which shows its interconnectedness and thereby its strong position in project management best practice. However, in practice little notice is taken of making people aware or of the PM being aware. Thus, two types of awareness can be distinguished: the PM’s awareness and other people’s awareness (more appropriately called Stakeholder’s awareness). The PM’s awareness consists of four parts: PM’s awareness of herself/himself, PM’s awareness of stakeholders, PM’s awareness of project issues and the PM’s awareness of Stakeholder’s awareness. Best practice occurs when the PM considers all four awarenesses. Project stakeholders include development team members, customers, top management, other PMs on other projects within the organization, suppliers and subcontractors. The concept of awareing encapsulates the fact that a good PM has to manage the awareness of all these people. In particular, the PM has to manage the awareness of the customers by
  • 2. Best Practices in Project Management Sachithra Gayan Gunarathne Sabaragamuwa University Of Sri Lanka gayan_sac@yahoo.com 2 appraising them at all times of risks, problems and difficulties, project progress, need for communication and need for clear requirements. It is not enough for the PM to inform customers of these issues, the PM has to make the customer aware. This is another factor in project management best practice. Similarly, the PM has to make the development team aware of the project’s importance, context and benefits, of the risks, of the need for internal communication, of the customer’s changes to requirements, and of the actual project work. All this comes from the analysis. Motivating The category of Motivating has four concepts regarded now as properties of motivating. These are Responsibilising Self-motivation; Awareing the team and Leadership. Responsibilising encapsulates delegating responsibility (as well as project work) and managing how team members handle that responsibility. An ability to do this is regarded as a contribution to project management best practice. Any absence of self-motivation in a PM must have a negative influence in project work and project success, whereas good self-motivation will contribute to project success. This is a subject worthy of future research. Awareing the project team of difficulties and problems appeared to help the project workers avoid problems rather than having to fix them after they had occurred. Good leadership, good responsibilising and high PM motivation will motivate the development team, whereas poor leadership coupled with poor responsibilising and low PM motivation will inhibit a team’s motivation. Therefore good leadership coupled with good responsibilising and high PM motivation are key to project success and therefore elements in best practice. However, the three elements of good leadership, good responsibilising and high PM motivation are tough concepts and difficult to achieve in practice. There emerged a strong connection between motivation and being aware of motivation. The relationship between these two parts defines the connection between motivation and managing awareness. The two parts are absorbed by each other, their concepts transfer by osmosis. Knowledge transfer The PM has an important role in knowledge transfer (KT) because it is the PM who has to make KT happen. When KT does take place the PM has to be aware of the possible difficulties in the actual process of the transfer as well as the accuracy of the knowledge itself. When KT does not happen, the PM has to be aware of the lack of transfer and the need for KT to happen. Knowledge transfer can be informal in the work place between team members or between the PM and technical staff or higher management. Alternatively, KT can be formal in the form of minutes of meetings and official documents. From this research came the concept of unused knowledge, that is where KT did not take place for undisclosed reasons. Therefore KT has properties of informal, formal, and unused. The area of KT and its properties would make interesting future research projects. Research findings Project Classification Basically, projects can be classified into three resolution types: I. Project success: The project is completed on-time, on-budget, fulfilled all functions and features as specified. Table 1: Project success factors
  • 3. Best Practices in Project Management Sachithra Gayan Gunarathne Sabaragamuwa University Of Sri Lanka gayan_sac@yahoo.com 3 II. Project challenged: The project is completed and operational but over- budget, over the time estimate, and offers fewer functions and features than originally specified. III. Project impaired: The project is cancelled at some point during the development cycle. Among these three types, the success rate was only 16.2%, while challenged projects accounted for 52.7%, and impaired (cancelled) was 31.1%. Causes of project failure Projects fail mainly because of unable to plan and estimate correctly, or fail to implement the tasks according to plan or failure causes by human factor. The following sections explain these three causes of failure: I. Planning and Estimation factor: This factor refers to initial cost and schedule estimates are not revised when more information becomes available as a project progresses. Also plans are not used correctly or used to guide the project forward, thus causing the project to fail. II. Implementation factor: This is caused by project scope changes, incorrect use of project methodology, major changes in the requirements and testing, and/or inspections are poorly done. III. Human factor: Project managers are not trained to acquire the necessary management skills. Also, some managers are not able to apply and put the theory of project management into practice. Poor communications are also one of the human factors that cause a project to fail. Among these three factors, the major cause of project failure is inappropriate use of project planning and scheduling methodology. The next category of these from the Standish report deals with projects that proved to be “challenged,” that is they were completed but were over budget, over time, or did not contain all functions and features originally required. Successful and challenged projects showed good technical skills of the project managers, while failed projects showed the project manager had only fair skills. According to the 2002 Standish Report, three top factors that impacted on not completed projects are lack of user input, incomplete requirements and specifications, and changing requirements and specifications. Table 2: Project challenged factors Table 3: Project failed factors
  • 4. Best Practices in Project Management Sachithra Gayan Gunarathne Sabaragamuwa University Of Sri Lanka gayan_sac@yahoo.com 4 Conclusion This paper discusses about project success and failure, the project classification and the factors that contributed to project success and resulted in project failure. Also, poor planning and scheduling are the main reasons of project failure. Other important issues that must not be neglected are the quality of the team leaders and team spirits among the team members. The PM’s awareness of motivation is key to motivating everyone else including the customer. It is not enough for a PM to motivate the team, the PM has to monitor and manage the state of the team’s motivation. Good leadership combined with good responsibilising and high PM motivation will increase everyone else’s motivation and lead to reduced risk of project failure. However, good leadership, good responsibilising and high motivation are all tough concepts which do not occur naturally and need to be developed. When the process of knowledge transfer is managed well, knowledge will flow, accumulate and build up and this will promote better management in the team, the project work, the customer, other stakeholders and every aspect of project management. Knowledge transfer increases motivation and is an essential element in good leadership. References I. Gray, C. F. and Larson, E. W. Project Management: The managerial process. 4th Edition, McGraw–Hill Educations, Singapore, (2008). II. Ahern, T., & Leavy, B., Byrne, P.J. Complex Project Management as Complex Problem Solving: a distributed knowledge management perspective. Elsevier: Ireland (2013). III. Clancy, T. The Standish Group Report, Retrieved Feb 20, 2008 from http://www.projectsmart.co.uk/reports.html, Chaos report, (1995). IV. Allan, G.W., The Use of Grounded Theory as a Research Method: warts & all, in: Ray Hackney (Ed.) Proceedings of the International Symposium on Research Methods, Tampa, USA, (2005). Table 4: Issues of project management success