SlideShare a Scribd company logo
1 of 18
PROJECT REPORT
Risk Preferences Analysis of a Waste Water
Treatment Installation
Ashwanidua
AaronFriedlander,RobertMayers,Ashwani Dua,RohanSanas,Andrew McCormack,
LavinaChoudhary
Prof. Ricardo A. Collado
BIA-670
Risk Management: Methods and Practice
Fall 2015
1
Table of Contents
1. Project Description and Background.........................................................................................................2
1.1. Wastewater Plant Model..................................................................................................................2
1.2. Sensitivity Analysis...........................................................................................................................4
1.3. Assumptions....................................................................................................................................4
2. Model Description and Analysis................................................................................................................7
3. Explanation of Performed Analysis ...........................................................................................................8
4. Results....................................................................................................................................................8
4.1. What If Analysis...............................................................................................................................8
4.2. Monte CarloAnalysis,VaR and Semi Deviations.................................................................................9
4.3. Risk Measures:...............................................................................................................................10
4.3.1. Value at Risk:.............................................................................................................................10
4.3.2. Mean Upper Semi-Deviation:......................................................................................................12
5. Conclusions and Recommendations .......................................................................................................15
6. Participants and Responsibilities ............................................................................................................17
2
1. ProjectDescription and Background
The gold mine construction is almost nearing its completion when the team discovered
that the water dischargecontaminant level is much higher than the original forecasts.
This will lead to enormous environmentaland regulatory implications. Also, fromthe
governmentrules and regulations perspective high levels of contamination may lead to
financial loss in the formof fine or result in complete shutdown. Regulation requires
improved facilities to recover heavy metals fromthe mine water discharge. So the team
came up with the solution to bring in a Skid Wastewater Treatment module. This
module requires Investment, Operating Costs, and can potentially delay the Mine start-
up. Below is the model which team has come up with to decide which treatment plant
should be used.
1.1.Wastewater Plant Model
Analysis shows 3 main alternatives based on input factors.
A. Buy a used skid wastewater plant
B. Buy a new skid wastewater plant
C. Buy a new fixed wastewater plant
In order to choosebest alternative, wehave set tradeoffs between few factors.
3
Tradeoffs:
D. Month Delays, Costs, Payoffs
E. Initial investment, Installation, Operating cost, Salvage value
Figure 1 - Tradeoffs
In order to perform a Monte Carlo Simulation given inputs, constraints, and cost
function, we have set a goal to usedifferent risk preferences to guide our decision
making process. We areinterested in understanding how our decisions depend on our
given parameters.
4
1.2.Sensitivity Analysis
We will performa sensitivity analysis by considering a rangeof values for our
parameters. In order to do this, we vary each parameter independently of the others
and observethe outcomes. An exploration of our model reveals that our key parameters
are:
• Time to complete other distribution
• Time to complete distribution
• Acq + InstallCost
We focus on testing these parameters with an incremental percentage change. This is a
formof stress testing our model and evaluating the parameters sensitivity. This allows
us to evaluate our optimal decision (the one that minimizes cost) subjectto our
parameters risk preference.
1.3.Assumptions
Below are few assumptions wehavemade in order to performthe simulation.
AboveModel is further extended using Monte Carlo Distribution.
1) Model assumes Time to Complete alpha as 2.
2) Multiplier for Time to Complete Beta Distribution for the calculation is 27.5 with
1 constant.
3) Sigma for Normal Distribution is 0.632
5
4) Alpha for Time to Complete Beta Distribution is 2 with 3.067 Constant.
Below are the tornado graphs for each plant type, which show how sensitivethe plant
costs are to each parameter:
Figure 2- Whatif Analysis - Fixed Plant
6
Figure 3- Whatif Analysis - Skid Plant
Figure 4-Whatif Analysis - Used Plant
7
2. Model Description and Analysis
Monte Carlo simulation was used to model the outcome of the wastewater treatment
plant options. The simulations ran in Excel using the Palisades Risk module. The Monte
Carlo simulations were run for each scenario to producean estimated cost.
The cost for each scenario is calculated using this equation:
Cost= AqInstallCost+(Operating Years x Operating Cost)+ (Months Delay x Opportunity
Loss)-SalvageCost
Where:
Months Delay = MAX( Months to InstallPlant -Months to Complete Other Activities , 0)
Each scenario was measured in the following ways: Expectation, Value at Risk, and
Mean upper semi deviation. Expectation (E[C]) is the expected cost. This is a risk-neutral
measure; the plant with the lowestexpected cost is the best choice. Value at Risk (E[C]
+αVaR[C]) uses the expected value and a risk measure(VaR). The α in the VaRformula is
the quantile, which is 95% sincewe are interested in costs aboveaverage. This method
is risk aversesinceit also accounts for the chance of a higher cost. Mean Upper Semi
Deviation (E[C] +α E[[C – E[C]]+]) calculates the expected cost plus the averageof costs
greater than expected (costs lower than expected are not added). This method is also
risk averse, as it only accounts for the average costover the averagecost.
8
3. Explanation of Performed Analysis
To ensurethe correctdecision is made, management has to incorporateuncertainties in
the projectthat can pose potential risks to the projects and associated outcomes. As risk
can be related to any aspectof the project, simulation helps with executing multiple
scenarios by selecting randomvariables.
Multiple simulations being run increases the confidencein modelling. Incorporation of
Risk methods like Var and Mean Semi Deviation further assists with the decision making
by incorporating maximum loss at the given confidence level. Mean Semi-standard
deviation is a popular measure of downsideuncertainty or risk .
4. Results
As stated above, team performed both What if analysis and Monte Carlo simulation.
1000 iterations of the selected scenario (recommended by What if analysis) were
simulated to understand the probabilities that different outcomes would occur.
4.1.What If Analysis
Based on the What if Analysis (Ranked analysis), the parameters that impact the model
most wereidentified as following for Skid and Fixedoption.
1. Time to complete other distribution
2. Time to complete distribution
9
3. Acq + InstallCost
For Usedoption Parameters wereidentified as :
1. Time to complete other distribution
2. Time to complete distribution
3. Multiplier
4. Acq + InstallCost
Based on the maximum impact across options, the following parameters wereselected
for Monte Carlo Analysis:
1. Time tocomplete other distribution
2. Time tocomplete distribution
3. Acq+ Install Cost
4.2.Monte Carlo Analysis
Risk Neutral Evaluation – Expectations - Using DecisionTools @Risk, weadjusted our
parameter rangeover a 30% increment to test cost. Cost range varied from -15% to
15%. Outcomes vary with each Monte Carlo Simulation. Expectation of Costis defined
as the risk-neutralmeasureof our model obtained by a Monte Carlo Simulation,
decision with the minimum cost. We obtain our results from the @Risk simulation
report. 95% confidence interval for our cost function was selected.
Results based on 1000 iterations with Monte Carlo Simulation:
What if Analysis Results
10
Figure 5 - Expectations
As highlighted: Skid Plant was identified as the preferred option based on the
simulation.
4.3.Risk Measures:
After identifying the parameters and simulation run, various risk methods wereapplied
to understand the impact of risk preferences for decision.
4.3.1. Value at Risk:
For VAR, Projectwith minimum value is recommended as the evaluated function is a
cost function.
95% confidenceinterval was selected for our costrange. Model was created in excel
with Palisades Monte Carlo 95% level observations. Costincreased for the parameters
with increasein alpha.
Figure6 to 9: VAR charts
11
15
%
-
10
%
-
5
%
+5
%
+1
0
%
+1
5
%
$1,000.00
$1,500.00
$2,000.00
$2,500.00
$3,000.00
$3,500.00
$4,000.00
0
1
Variation
Cost
Alpha
Acq +Install Minimum value
15% -10% -5% +5% +10% +15%
-15%
-10%
-5%
0%
5%
10%
15%
$1,400.00
$1,900.00
$2,400.00
$2,900.00
$3,400.00
0
1
Variation
Cost
Alpha
Time to Complete Other Minimum Value
-15% -10% -5% 0% 5% 10% 15%
12
4.3.2. Mean Upper Semi-Deviation:
Further Mean Upper Semi- Deviation was applied to supportthe project evaluation,
Team selected -10% to 10 % change range. Based on the Mean Semi Deviation, for Acq+
InstallMean Upper Standard, at 1650, preferred projectis Fixed. Based on the other
parameters skid option is most costeffective.
Figures 10 to 16: Mean Semi Deviation.
15%
-10%
-5%
+5%
+10
%
+15
%
$-
$1,000.00
$2,000.00
$3,000.00
$4,000.00
0
1
Variation
Cost
Alpha
Time To Complete Minimum Value
15%
-10%
-5%
+5%
+10%
+15%
13
$1,400.00
$1,500.00
$1,600.00
$1,700.00
$1,800.00
$1,900.00
$2,000.00
1 2
TIMETO COMPLETEOTHERMEAN UPER
SEMIDEVIATIONFOR-10%
Fixed -10% Used -10% Skid -10%
$1,400.00
$1,450.00
$1,500.00
$1,550.00
$1,600.00
$1,650.00
$1,700.00
$1,750.00
$1,800.00
$1,850.00
1 2
TIMETO COMPLETEOTHERMEAN UPER
SEMIDEVIATIONFOR10%
Fixed +10% Used +10% Skid +10%
14
$1,250.00
$1,450.00
$1,650.00
$1,850.00
$2,050.00
$2,250.00
$2,450.00
TIME TO COMPLETE NOW MEAN
UPPER STANDARD DEVIATION 10%
Fixed -10% Used -10% Skid -10%
$1,250.00
$1,450.00
$1,650.00
$1,850.00
$2,050.00
$2,250.00
$2,450.00
TIME TO COMPLETE NOW MEAN
UPPER STANDARD DEVIATION -10%
Fixed -10% Used -10% Skid -10%
15
5. Conclusions and Recommendations
The main goal of the project was to create a model that would provideinsight into
which wastewater treatment module solution had the minimum cost. The model
analyzed the costfunction for different risk preferences, (Risk Neutral Cost Expectations,
Value at Risk, and Mean Upper Semideviation) which provided comparisons and
1200
1300
1400
1500
1600
1700
1800
1900
0 1
Acq+Install Mean Upper Standard
Deviation 10%
Fixed -10% Used -10% Skid -10%
1600
1650
1700
1750
1800
1850
1900
1950
0 1
Acq+Install Mean Upper Standard
Deviation 10%
Fixed +10% Used +10% Skid +10%
16
sensitivity analysis. The sensitivity analysis was instrumentalin helping to understand
how certain parameters (Time to complete other distribution, time to complete
distributions, acq. + install cost, opportunity loss, operating years) affected the outcome
of the model.
In conclusion, the model showed that the costs associated with buying a new skid
plant are less than the costs associated with buying a used skid plant or buying a fixed
skid plant. This means the recommendation is to install a new skid for the wastewater
treatment. The sensitivity analysis for the risk neutral costexpectations showed that
buying a new skid plant is the optimal choice (lowestcost) for each of the three
parameters used – acq. + install, time to complete other, and time to complete. The
sensitivity analysis for the mean upper semideviation was in accordancewith the risk
neutral cost expectations. Itshowed that the costvalues werelower when buying a
new skid plant compared to buying a used skid plant or a fixed skid plant. This was
consistentfor all of the input parameters.
Other tests that could have been run to help in the decision could have included more
input parameters for sensitivity analysis and more increments during the sensitivity
analysis. Also, the main factor in determining our optimal solution was cost. Itwould
have been interesting to see whatthe optimal solution would have been if there were
other main factors involved, such as time (e.g. we need minimum cost but the skid plant
17
needs to be running within 3 months of acquiring it), long-termvalue (e.g. weneed
minimum cost but the skid plant needs to operate for at least 10 years), or production
(e.g. we need minimum costbut the skid plant needs to be able to treat at least XX
gallons of water per day). There are multiple factors and parameters that could be
added to the simulation model as futuretests.
6. Participants and Responsibilities
Model/ Data / Charts Aaron Friedlander, Robert Mayers,
AshwaniDua, Rohan Sanas, Andrew
McCormack, Lavina Choudhary
Poster Aaron Friedlander, Robert Mayers,
AshwaniDua, Rohan Sanas, Andrew
McCormack, Lavina Choudhary
Report Aaron Friedlander, Robert Mayers,
AshwaniDua, Rohan Sanas

More Related Content

Similar to Waste Water Treatment Risk Analysis

Model Risk Management : Best Practices
Model Risk Management : Best PracticesModel Risk Management : Best Practices
Model Risk Management : Best PracticesQuantUniversity
 
20050314 specification based regression test selection with risk analysis
20050314 specification based regression test selection with risk analysis20050314 specification based regression test selection with risk analysis
20050314 specification based regression test selection with risk analysisWill Shen
 
A Novel Approach to Derive the Average-Case Behavior of Distributed Embedded ...
A Novel Approach to Derive the Average-Case Behavior of Distributed Embedded ...A Novel Approach to Derive the Average-Case Behavior of Distributed Embedded ...
A Novel Approach to Derive the Average-Case Behavior of Distributed Embedded ...ijccmsjournal
 
Report_TermPaper_IE5003
Report_TermPaper_IE5003Report_TermPaper_IE5003
Report_TermPaper_IE5003Arun Sankar
 
Using Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementUsing Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementMike Tulkoff
 
DSUS_MAO_2012_Jie
DSUS_MAO_2012_JieDSUS_MAO_2012_Jie
DSUS_MAO_2012_JieMDO_Lab
 
Risk-Analysis.pdf
Risk-Analysis.pdfRisk-Analysis.pdf
Risk-Analysis.pdfMaheshBika
 
PythonQuants conference - QuantUniversity presentation - Stress Testing in th...
PythonQuants conference - QuantUniversity presentation - Stress Testing in th...PythonQuants conference - QuantUniversity presentation - Stress Testing in th...
PythonQuants conference - QuantUniversity presentation - Stress Testing in th...QuantUniversity
 
AIRLINE FARE PRICE PREDICTION
AIRLINE FARE PRICE PREDICTIONAIRLINE FARE PRICE PREDICTION
AIRLINE FARE PRICE PREDICTIONIRJET Journal
 
IRJET- A Comprehensive Outline of the Types of Simulation
IRJET- A Comprehensive Outline of the Types of SimulationIRJET- A Comprehensive Outline of the Types of Simulation
IRJET- A Comprehensive Outline of the Types of SimulationIRJET Journal
 
Bloomberg va r
Bloomberg va rBloomberg va r
Bloomberg va rrohanharsh
 
Stochastic Modeling - Model Risk - Sampling Error - Scenario Reduction
Stochastic Modeling - Model Risk - Sampling Error - Scenario ReductionStochastic Modeling - Model Risk - Sampling Error - Scenario Reduction
Stochastic Modeling - Model Risk - Sampling Error - Scenario ReductionRon Harasym
 
Blog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk AnalysisBlog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk AnalysisAsaman Patnaik
 
CH&Cie white paper value-at-risk in tuburlent times_VaR
CH&Cie white paper value-at-risk in tuburlent times_VaRCH&Cie white paper value-at-risk in tuburlent times_VaR
CH&Cie white paper value-at-risk in tuburlent times_VaRThibault Le Pomellec
 

Similar to Waste Water Treatment Risk Analysis (20)

Model Risk Management : Best Practices
Model Risk Management : Best PracticesModel Risk Management : Best Practices
Model Risk Management : Best Practices
 
20050314 specification based regression test selection with risk analysis
20050314 specification based regression test selection with risk analysis20050314 specification based regression test selection with risk analysis
20050314 specification based regression test selection with risk analysis
 
Free PMP Exam Sample Question
Free PMP Exam Sample QuestionFree PMP Exam Sample Question
Free PMP Exam Sample Question
 
A Novel Approach to Derive the Average-Case Behavior of Distributed Embedded ...
A Novel Approach to Derive the Average-Case Behavior of Distributed Embedded ...A Novel Approach to Derive the Average-Case Behavior of Distributed Embedded ...
A Novel Approach to Derive the Average-Case Behavior of Distributed Embedded ...
 
PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 
Report_TermPaper_IE5003
Report_TermPaper_IE5003Report_TermPaper_IE5003
Report_TermPaper_IE5003
 
Using Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementUsing Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project Management
 
DSUS_MAO_2012_Jie
DSUS_MAO_2012_JieDSUS_MAO_2012_Jie
DSUS_MAO_2012_Jie
 
Risk Ana
Risk AnaRisk Ana
Risk Ana
 
Risk-Analysis.pdf
Risk-Analysis.pdfRisk-Analysis.pdf
Risk-Analysis.pdf
 
PythonQuants conference - QuantUniversity presentation - Stress Testing in th...
PythonQuants conference - QuantUniversity presentation - Stress Testing in th...PythonQuants conference - QuantUniversity presentation - Stress Testing in th...
PythonQuants conference - QuantUniversity presentation - Stress Testing in th...
 
Incorporation risk1
Incorporation risk1Incorporation risk1
Incorporation risk1
 
AIRLINE FARE PRICE PREDICTION
AIRLINE FARE PRICE PREDICTIONAIRLINE FARE PRICE PREDICTION
AIRLINE FARE PRICE PREDICTION
 
Cost estimation
Cost estimationCost estimation
Cost estimation
 
IRJET- A Comprehensive Outline of the Types of Simulation
IRJET- A Comprehensive Outline of the Types of SimulationIRJET- A Comprehensive Outline of the Types of Simulation
IRJET- A Comprehensive Outline of the Types of Simulation
 
Value at risk
Value at riskValue at risk
Value at risk
 
Bloomberg va r
Bloomberg va rBloomberg va r
Bloomberg va r
 
Stochastic Modeling - Model Risk - Sampling Error - Scenario Reduction
Stochastic Modeling - Model Risk - Sampling Error - Scenario ReductionStochastic Modeling - Model Risk - Sampling Error - Scenario Reduction
Stochastic Modeling - Model Risk - Sampling Error - Scenario Reduction
 
Blog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk AnalysisBlog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk Analysis
 
CH&Cie white paper value-at-risk in tuburlent times_VaR
CH&Cie white paper value-at-risk in tuburlent times_VaRCH&Cie white paper value-at-risk in tuburlent times_VaR
CH&Cie white paper value-at-risk in tuburlent times_VaR
 

Waste Water Treatment Risk Analysis

  • 1. PROJECT REPORT Risk Preferences Analysis of a Waste Water Treatment Installation Ashwanidua AaronFriedlander,RobertMayers,Ashwani Dua,RohanSanas,Andrew McCormack, LavinaChoudhary Prof. Ricardo A. Collado BIA-670 Risk Management: Methods and Practice Fall 2015
  • 2. 1 Table of Contents 1. Project Description and Background.........................................................................................................2 1.1. Wastewater Plant Model..................................................................................................................2 1.2. Sensitivity Analysis...........................................................................................................................4 1.3. Assumptions....................................................................................................................................4 2. Model Description and Analysis................................................................................................................7 3. Explanation of Performed Analysis ...........................................................................................................8 4. Results....................................................................................................................................................8 4.1. What If Analysis...............................................................................................................................8 4.2. Monte CarloAnalysis,VaR and Semi Deviations.................................................................................9 4.3. Risk Measures:...............................................................................................................................10 4.3.1. Value at Risk:.............................................................................................................................10 4.3.2. Mean Upper Semi-Deviation:......................................................................................................12 5. Conclusions and Recommendations .......................................................................................................15 6. Participants and Responsibilities ............................................................................................................17
  • 3. 2 1. ProjectDescription and Background The gold mine construction is almost nearing its completion when the team discovered that the water dischargecontaminant level is much higher than the original forecasts. This will lead to enormous environmentaland regulatory implications. Also, fromthe governmentrules and regulations perspective high levels of contamination may lead to financial loss in the formof fine or result in complete shutdown. Regulation requires improved facilities to recover heavy metals fromthe mine water discharge. So the team came up with the solution to bring in a Skid Wastewater Treatment module. This module requires Investment, Operating Costs, and can potentially delay the Mine start- up. Below is the model which team has come up with to decide which treatment plant should be used. 1.1.Wastewater Plant Model Analysis shows 3 main alternatives based on input factors. A. Buy a used skid wastewater plant B. Buy a new skid wastewater plant C. Buy a new fixed wastewater plant In order to choosebest alternative, wehave set tradeoffs between few factors.
  • 4. 3 Tradeoffs: D. Month Delays, Costs, Payoffs E. Initial investment, Installation, Operating cost, Salvage value Figure 1 - Tradeoffs In order to perform a Monte Carlo Simulation given inputs, constraints, and cost function, we have set a goal to usedifferent risk preferences to guide our decision making process. We areinterested in understanding how our decisions depend on our given parameters.
  • 5. 4 1.2.Sensitivity Analysis We will performa sensitivity analysis by considering a rangeof values for our parameters. In order to do this, we vary each parameter independently of the others and observethe outcomes. An exploration of our model reveals that our key parameters are: • Time to complete other distribution • Time to complete distribution • Acq + InstallCost We focus on testing these parameters with an incremental percentage change. This is a formof stress testing our model and evaluating the parameters sensitivity. This allows us to evaluate our optimal decision (the one that minimizes cost) subjectto our parameters risk preference. 1.3.Assumptions Below are few assumptions wehavemade in order to performthe simulation. AboveModel is further extended using Monte Carlo Distribution. 1) Model assumes Time to Complete alpha as 2. 2) Multiplier for Time to Complete Beta Distribution for the calculation is 27.5 with 1 constant. 3) Sigma for Normal Distribution is 0.632
  • 6. 5 4) Alpha for Time to Complete Beta Distribution is 2 with 3.067 Constant. Below are the tornado graphs for each plant type, which show how sensitivethe plant costs are to each parameter: Figure 2- Whatif Analysis - Fixed Plant
  • 7. 6 Figure 3- Whatif Analysis - Skid Plant Figure 4-Whatif Analysis - Used Plant
  • 8. 7 2. Model Description and Analysis Monte Carlo simulation was used to model the outcome of the wastewater treatment plant options. The simulations ran in Excel using the Palisades Risk module. The Monte Carlo simulations were run for each scenario to producean estimated cost. The cost for each scenario is calculated using this equation: Cost= AqInstallCost+(Operating Years x Operating Cost)+ (Months Delay x Opportunity Loss)-SalvageCost Where: Months Delay = MAX( Months to InstallPlant -Months to Complete Other Activities , 0) Each scenario was measured in the following ways: Expectation, Value at Risk, and Mean upper semi deviation. Expectation (E[C]) is the expected cost. This is a risk-neutral measure; the plant with the lowestexpected cost is the best choice. Value at Risk (E[C] +αVaR[C]) uses the expected value and a risk measure(VaR). The α in the VaRformula is the quantile, which is 95% sincewe are interested in costs aboveaverage. This method is risk aversesinceit also accounts for the chance of a higher cost. Mean Upper Semi Deviation (E[C] +α E[[C – E[C]]+]) calculates the expected cost plus the averageof costs greater than expected (costs lower than expected are not added). This method is also risk averse, as it only accounts for the average costover the averagecost.
  • 9. 8 3. Explanation of Performed Analysis To ensurethe correctdecision is made, management has to incorporateuncertainties in the projectthat can pose potential risks to the projects and associated outcomes. As risk can be related to any aspectof the project, simulation helps with executing multiple scenarios by selecting randomvariables. Multiple simulations being run increases the confidencein modelling. Incorporation of Risk methods like Var and Mean Semi Deviation further assists with the decision making by incorporating maximum loss at the given confidence level. Mean Semi-standard deviation is a popular measure of downsideuncertainty or risk . 4. Results As stated above, team performed both What if analysis and Monte Carlo simulation. 1000 iterations of the selected scenario (recommended by What if analysis) were simulated to understand the probabilities that different outcomes would occur. 4.1.What If Analysis Based on the What if Analysis (Ranked analysis), the parameters that impact the model most wereidentified as following for Skid and Fixedoption. 1. Time to complete other distribution 2. Time to complete distribution
  • 10. 9 3. Acq + InstallCost For Usedoption Parameters wereidentified as : 1. Time to complete other distribution 2. Time to complete distribution 3. Multiplier 4. Acq + InstallCost Based on the maximum impact across options, the following parameters wereselected for Monte Carlo Analysis: 1. Time tocomplete other distribution 2. Time tocomplete distribution 3. Acq+ Install Cost 4.2.Monte Carlo Analysis Risk Neutral Evaluation – Expectations - Using DecisionTools @Risk, weadjusted our parameter rangeover a 30% increment to test cost. Cost range varied from -15% to 15%. Outcomes vary with each Monte Carlo Simulation. Expectation of Costis defined as the risk-neutralmeasureof our model obtained by a Monte Carlo Simulation, decision with the minimum cost. We obtain our results from the @Risk simulation report. 95% confidence interval for our cost function was selected. Results based on 1000 iterations with Monte Carlo Simulation: What if Analysis Results
  • 11. 10 Figure 5 - Expectations As highlighted: Skid Plant was identified as the preferred option based on the simulation. 4.3.Risk Measures: After identifying the parameters and simulation run, various risk methods wereapplied to understand the impact of risk preferences for decision. 4.3.1. Value at Risk: For VAR, Projectwith minimum value is recommended as the evaluated function is a cost function. 95% confidenceinterval was selected for our costrange. Model was created in excel with Palisades Monte Carlo 95% level observations. Costincreased for the parameters with increasein alpha. Figure6 to 9: VAR charts
  • 12. 11 15 % - 10 % - 5 % +5 % +1 0 % +1 5 % $1,000.00 $1,500.00 $2,000.00 $2,500.00 $3,000.00 $3,500.00 $4,000.00 0 1 Variation Cost Alpha Acq +Install Minimum value 15% -10% -5% +5% +10% +15% -15% -10% -5% 0% 5% 10% 15% $1,400.00 $1,900.00 $2,400.00 $2,900.00 $3,400.00 0 1 Variation Cost Alpha Time to Complete Other Minimum Value -15% -10% -5% 0% 5% 10% 15%
  • 13. 12 4.3.2. Mean Upper Semi-Deviation: Further Mean Upper Semi- Deviation was applied to supportthe project evaluation, Team selected -10% to 10 % change range. Based on the Mean Semi Deviation, for Acq+ InstallMean Upper Standard, at 1650, preferred projectis Fixed. Based on the other parameters skid option is most costeffective. Figures 10 to 16: Mean Semi Deviation. 15% -10% -5% +5% +10 % +15 % $- $1,000.00 $2,000.00 $3,000.00 $4,000.00 0 1 Variation Cost Alpha Time To Complete Minimum Value 15% -10% -5% +5% +10% +15%
  • 14. 13 $1,400.00 $1,500.00 $1,600.00 $1,700.00 $1,800.00 $1,900.00 $2,000.00 1 2 TIMETO COMPLETEOTHERMEAN UPER SEMIDEVIATIONFOR-10% Fixed -10% Used -10% Skid -10% $1,400.00 $1,450.00 $1,500.00 $1,550.00 $1,600.00 $1,650.00 $1,700.00 $1,750.00 $1,800.00 $1,850.00 1 2 TIMETO COMPLETEOTHERMEAN UPER SEMIDEVIATIONFOR10% Fixed +10% Used +10% Skid +10%
  • 15. 14 $1,250.00 $1,450.00 $1,650.00 $1,850.00 $2,050.00 $2,250.00 $2,450.00 TIME TO COMPLETE NOW MEAN UPPER STANDARD DEVIATION 10% Fixed -10% Used -10% Skid -10% $1,250.00 $1,450.00 $1,650.00 $1,850.00 $2,050.00 $2,250.00 $2,450.00 TIME TO COMPLETE NOW MEAN UPPER STANDARD DEVIATION -10% Fixed -10% Used -10% Skid -10%
  • 16. 15 5. Conclusions and Recommendations The main goal of the project was to create a model that would provideinsight into which wastewater treatment module solution had the minimum cost. The model analyzed the costfunction for different risk preferences, (Risk Neutral Cost Expectations, Value at Risk, and Mean Upper Semideviation) which provided comparisons and 1200 1300 1400 1500 1600 1700 1800 1900 0 1 Acq+Install Mean Upper Standard Deviation 10% Fixed -10% Used -10% Skid -10% 1600 1650 1700 1750 1800 1850 1900 1950 0 1 Acq+Install Mean Upper Standard Deviation 10% Fixed +10% Used +10% Skid +10%
  • 17. 16 sensitivity analysis. The sensitivity analysis was instrumentalin helping to understand how certain parameters (Time to complete other distribution, time to complete distributions, acq. + install cost, opportunity loss, operating years) affected the outcome of the model. In conclusion, the model showed that the costs associated with buying a new skid plant are less than the costs associated with buying a used skid plant or buying a fixed skid plant. This means the recommendation is to install a new skid for the wastewater treatment. The sensitivity analysis for the risk neutral costexpectations showed that buying a new skid plant is the optimal choice (lowestcost) for each of the three parameters used – acq. + install, time to complete other, and time to complete. The sensitivity analysis for the mean upper semideviation was in accordancewith the risk neutral cost expectations. Itshowed that the costvalues werelower when buying a new skid plant compared to buying a used skid plant or a fixed skid plant. This was consistentfor all of the input parameters. Other tests that could have been run to help in the decision could have included more input parameters for sensitivity analysis and more increments during the sensitivity analysis. Also, the main factor in determining our optimal solution was cost. Itwould have been interesting to see whatthe optimal solution would have been if there were other main factors involved, such as time (e.g. we need minimum cost but the skid plant
  • 18. 17 needs to be running within 3 months of acquiring it), long-termvalue (e.g. weneed minimum cost but the skid plant needs to operate for at least 10 years), or production (e.g. we need minimum costbut the skid plant needs to be able to treat at least XX gallons of water per day). There are multiple factors and parameters that could be added to the simulation model as futuretests. 6. Participants and Responsibilities Model/ Data / Charts Aaron Friedlander, Robert Mayers, AshwaniDua, Rohan Sanas, Andrew McCormack, Lavina Choudhary Poster Aaron Friedlander, Robert Mayers, AshwaniDua, Rohan Sanas, Andrew McCormack, Lavina Choudhary Report Aaron Friedlander, Robert Mayers, AshwaniDua, Rohan Sanas