- 1. 19 20 21 22 23 24 25 26 27
May Jun
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
ID Description
Orig
Dura
Act
Dur Start Finish Predecessors Successors
%
Compl
STOStart
Vari
Act
StartActual FinishPhysical Percent CompleteDuration At Completion
WEST PODIUM
PRECONSTRUCTION
HOLLAND CRITICAL DECISION MATRIX
BID & AWARD
No value assigned
BA1060 Bid Custom Millwork 46 98 01/06/15A 07/24/15 HCD1020FS+40d*BA1100FS* 68% Storepoint 2201/06/15 0% 144
BA1070 Bid Cabinets 41 92 01/06/15A 05/29/15 HCD1020FS+10dBA1080FS* 88% Storepoint 2201/06/15 0% 104
BA1080 Award Cabinet Contract 20 0 06/01/15 06/26/15 BA1070FS*, HDC1030FSPS1040FS* 0% Storepoint 220% 20
BA1090 Award Doors, Frames & Hardware Supplier Contract 10 0 05/14/15 05/27/15 BA1050FS PS1050FS* 0% Storepoint 220% 10
BA1140 Bid Drywall & Metal Stud 15 0 05/14/15 06/03/15 BA1130SS, HCD1020FS+20dBA1180FS* 0% Storepoint 220% 15
BA1160 Award Siding Contract 16 0 05/14/15 06/04/15 BA1120FS PS1090FS* 0% Storepoint 220% 16
BA1180 Award Drywall & Metal Stud Contract 15 0 06/04/15 06/24/15 BA1140FS* PS1130FS* 0% Storepoint 220% 15
BA1310 Bid Gypcrete 10 119 01/05/15A 07/20/15 HCD1020FS+60d*BA1320FS* 84% Storepoint 2201/05/15 0% 141
BA1320 Award Gypcrete 15 124 01/28/15A 08/10/15 BA1310FS* PS1250FS* 89% Storepoint 2201/28/15 0% 139
BA1330 Bid Trash Chute & Compactor 29 102 12/23/14A 06/16/15 HCD1020FS+30dBA1340FS* 81% Storepoint 2212/23/14 0% 126
BA1340 Award Trash Chute & Compactor 15 0 06/17/15 07/07/15 BA1330FS* PS1260FS*, PS1270FS*0% Storepoint 220% 15
BA1350 Bid Storefront 15 0 05/14/15 06/03/15 HCD1020FS+30dBA1360FS* 0% Storepoint 220% 15
BA1360 Award Storefront 34 77 02/17/15A 07/21/15 BA1350FS* PS1230FS* 69% Storepoint 2202/17/15 0% 111
BA1370 Bid Bath Accessories 15 0 05/14/15 06/03/15 HCD1020FS+30dBA1380FS* 0% Storepoint 220% 15
BA1380 Award Bath Accessories 12 0 06/04/15 06/19/15 BA1370FS* PS1280FS* 0% Storepoint 220% 12
BA1390 Bid Counter Tops 10 122 11/25/14A 05/27/15 HCD1020FS+10dBA1400FS* 92% Storepoint 2211/25/14 0% 132
BA1400 Award Counter Tops 10 72 02/17/15A 06/10/15 BA1390FS* PS1290FS* 88% Storepoint 2202/17/15 0% 82
BA1410 Bid Backsplash & Floor Ceramic Tile 10 73 02/02/15A 05/27/15 HCD1020FS+10dBA1420FS* 88% Storepoint 2202/02/15 0% 83
BA1420 Award Backsplash & Floor Tile 25 0 05/28/15 07/01/15 BA1410FS* PS1300FS* 0% Storepoint 220% 25
BA1430 Bid Roofing & Deck Coatings 25 132 11/11/14A 05/27/15 HCD1020FS BA1440FS* 93% Storepoint 2211/11/14 0% 142
BA1440 Award Roofing & Deck Coatings 39 103 01/05/15A 07/22/15 BA1430FS* PS1310FS* 72% Storepoint 2201/05/15 0% 143
BA1450 Bid Landscape 10 109 01/05/15A 08/27/15 HCD1020FS+50d*BA1460FF+1d*, BA1490FS-15d*64% Storepoint 2201/05/15 0% 169
PREPARE & SUBMIT
No value assigned
PS1050 Generate Doors Frames & Hrdwr Shop Drawings 20 0 05/28/15 06/24/15 BA1090FS* RA1050FS* 0% Storepoint 220% 20
PS1070 Generate Structural Steel Shop Drawings 24 0 05/14/15 06/16/15 BA1150FS FD1050SS+20d* 0% Storepoint 220% 24
PS1090 Generate Siding Submittal 15 0 06/05/15 06/25/15 BA1160FS* RA1090FS* 0% Storepoint 220% 15
PS1120 Generate CMU & Terracotta Submittals 15 0 05/14/15 06/03/15 BA1170FS FD1070FS, RA1110FS*0% Storepoint 220% 15
PS1130 Generate Metal Stud & Drywall Submittal 15 0 06/25/15 07/15/15 BA1180FS* RA1100FS* 0% Storepoint 220% 15
PS1140 Window Shops 15 27 04/07/15A 06/03/15 BA1200FS RA1120FS* 64% Storepoint 2204/07/15 0% 42
PS1150 HVAC 20 112 12/09/14A 05/29/15 BA1270FS RA1130FS* 90% Storepoint 2212/09/14 0% 124
PS1160 Electrical 20 197 08/12/14A 06/10/15 BA1250FS RA1140FS* 91% Storepoint 2208/12/14 0% 217
PS1220 Initial Storm Drain Submittal 5 0 05/14/15 05/20/15 BA1300FS UGU1000FS* 0% Storepoint 220% 5
PS1250 Gypcrete 10 156 01/05/15A 09/25/15 BA1320FS* RA1190FS* 82% Storepoint 2201/05/15 0% 190
PS1280 Bath Accessories 15 0 06/22/15 07/10/15 BA1380FS* RA1230FS* 0% Storepoint 220% 15
PS1290 Counter Tops 15 0 06/11/15 07/01/15 BA1400FS* RA1240FS* 0% Storepoint 220% 15
PS1310 Roofing 15 143 01/05/15A 08/05/15 BA1440FS* RA1260FS* 93% Storepoint 2201/05/15 0% 153
PS1320 Landscape 15 170 01/05/15A 10/20/15 BA1460FS* RA1270FS* 82% Storepoint 2201/05/15 0% 207
PS1330 Carpet, Sheet Goods & Base 15 0 05/14/15 06/03/15 BA1480FS RA1280FS* 0% Storepoint 220% 15
PS1350 Pool 20 93 01/05/15A 07/20/15 BA1520FS RA1300FS* 66% Storepoint 2201/05/15 0% 141
REVIEW & APPROVE
No value assigned
RA1050 Review Door Shop Drawing 10 0 06/25/15 07/08/15 PS1050FS* PS1100FS* 0% Storepoint 220% 10
RA1090 Review & Approve Siding Submittal 15 189 10/06/14A 07/30/15 PS1090FS* FD1080FS*, RA1095FS*88% Storepoint 2210/06/14 0% 214
RA1095 Review & Approve metal panels and Terracotta 1 149 01/05/15A 08/25/15 RA1090FS* 89% Storepoint 2201/05/15 0% 167
RA1110 Review & Approve CMU 10 0 06/04/15 06/17/15 PS1120FS* FD1070FS* 0% Storepoint 220% 10
RA1120 Review & Approve Windows 10 0 06/04/15 06/17/15 PS1140FS* FD1110FS+30d* 0% Storepoint 220% 10
RA1130 HVAC 10 0 06/01/15 06/12/15 PS1150FS* FD1120FS* 0% Storepoint 220% 10
RA1140 Electrical 10 193 09/15/14A 07/14/15 PS1160FS* FD1130FS* 89% Storepoint 2209/15/14 0% 217
RA1150 Plumbing 10 148 10/20/14A 06/15/15 PS1170FS FD1140FS 87% Storepoint 2210/20/14 0% 171
RA1160 Fire Protection 10 151 10/15/14A 06/16/15 PS1180FS FD1150FS* 86% Storepoint 2210/15/14 0% 175
RA1190 Gypcrete 10 190 01/05/15A 10/15/15 PS1250FS* FD1170FS* 93% Storepoint 2201/05/15 0% 204
RA1260 Roofing 10 166 12/17/14A 09/11/15 PS1310FS* FD1230FS* 86% Storepoint 2212/17/14 0% 193
RA1270 Landscape 10 207 01/05/15A 11/19/15 PS1320FS* FD1240FS* 90% Storepoint 2201/05/15 0% 229
RA1280 Carpet & Flooring 10 0 06/04/15 06/17/15 PS1330FS* FD1250FS+100d* 0% Storepoint 220% 10
RA1300 Pool 15 141 01/05/15A 10/12/15 PS1350FS* FD1280FS* 70% Storepoint 2201/05/15 0% 201
FABRICATE & DELIVER
No value assigned
FD1020 Fabricate ATS Rods 10 0 05/14/15 05/27/15 RA1030FS 0% Storepoint 220% 10
FD1050 Fabricate Structural Steel 60 0 06/11/15 09/02/15 PS1070SS+20d*PSA1030SS+20d*0% Storepoint 220% 60
FD1070 Manufactor CMU 30 0 06/18/15 07/29/15 PS1120FS, RA1110FS*WP1L1500FS* 0% Storepoint 220% 30
FD1100 Fab & Deliver Elevators 60 0 05/14/15 08/05/15 RA1010FS+40dELEV1030FS 0% Storepoint 220% 60
FD1120 HVAC 20 0 06/15/15 07/10/15 RA1130FS* 0% Storepoint 220% 20
FD1130 Electrical 20 157 12/08/14A 10/12/15 RA1140FS* 71% Storepoint 2212/08/14 0% 221
FD1150 Fire Protection 20 0 06/17/15 07/14/15 RA1160FS* 0% Storepoint 220% 20
Today
DataDate
Bid Cabinets
Award Cabinet
Award Doors, Frames & Hardware Supplier Contract
Bid Drywall & Metal Stud
Award Siding Contract
Award Drywall & Metal S
Bid Trash Chute & Compactor
Bid Storefront
Bid Bath Accessories
Award Bath Accessories
Bid Counter Tops
Award Counter Tops
Bid Backsplash & Floor Ceramic Tile
Bid Roofing & Deck Coatings
Generate Doors Frames
Generate Structural Steel Shop Drawings
Generate Siding Su
Generate CMU & Terracotta Submittals
Window Shops
HVAC
Electrical
Initial Storm Drain Submittal
Carpet, Sheet Goods & Base
Review & Approve CMU
Review & Approve Windows
HVAC
Plumbing
Fire Protection
Carpet & Flooring
Fabricate ATS Rods
Start Date: 05/13/14
Finish Date: 07/07/16
Data Date: 05/14/15
Run Date: 05/18/15
West Podium .2015.05.14.ppx Page 1A
ORENCO PODIUM WEST 05/14/2015
west podium
apartments
construction schedule
- 2. 19 20 21 22 23 24 25 26 27
May Jun
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
ID Description
Orig
Dura
Act
Dur Start Finish Predecessors Successors
%
Compl
STOStart
Vari
Act
StartActual FinishPhysical Percent CompleteDuration At Completion
UNIT FINISHES
No value assigned
HDC2070 AC & CCTV 45 161 10/01/14A 05/20/15 HCD1020FF 97% Storepoint 2210/01/14 0% 166
HDC2120 A/V Package Complete 60 0 05/14/15 08/05/15 HCD1010FF 0% Storepoint 220% 60
WEMU1000 Exterior Framing 5 0 06/03/15 06/09/15 FR3010FS* WEMU1010FS* 0% Storepoint 220% 5
WEMU1010 Building Wrap & Windows 5 0 06/10/15 06/16/15 WEMU1000FS*WEMU1020FS* 0% Storepoint 220% 5
WEMU1020 Masonry 5 0 06/17/15 06/23/15 WEMU1010FS*WEMU1030FS* 0% Storepoint 220% 5
WEMU1030 Siding 5 0 06/24/15 06/30/15 WEMU1020FS*WEMU1040FS* 0% Storepoint 220% 5
CONSTRUCTION
UNDERGROUND UTILITIES
LEVEL 1 & SUBGRADE/PARKING
No value assigned
UGU1000 Storm 5 93 01/12/15A 05/22/15 PS1220FS*, SW1010FS, SD1020FS98% Storepoint 2201/12/15 0% 95
UGU1030 Gas 10 90 01/08/15A 05/15/15 SW1010FS 98% Storepoint 2201/08/15 0% 92
FOUNDATION / CONCRETE
TOWER CRANE
No value assigned
TC1080 TC Operable In Use 365 121 11/26/14A 01/04/16 TC1070FS TC1090FS* 42% Storepoint 2211/26/14 0% 289
LEVEL 1 & SUBGRADE/PARKING
No value assigned
WP1L1284 Permanent Power To SP-1 & 2, St-1 12 77 01/27/15A 05/29/15 WP1L1280FS WP1L1282FS 87% Storepoint 2201/27/15 0% 89
LEVEL 2 PARKING
LEVEL 2 POUR 3
WP2L1112.8 Remove Perimeter Decks Grids G-K/5-12 - L2P3 5 30 04/02/15A 05/14/15 WP2L1112.7FS-1d 97% Storepoint 2204/02/15 0% 31
LEVEL 2 POUR 4
WP2L1113.8 Remove Perimeter Decks Grids 10-16/A-D - L2P4 3 0 05/14/15 05/18/15 WP2L1113.7FS 0% Storepoint 220% 3
LEVEL 2 POUR 5
WP2L1114.8 Remove Perimeter Decks Grids D-K/10-16 - L2P5 3 0 05/14/15 05/18/15 WP2L1114.7FS 0% Storepoint 220% 3
LEVEL 2 POUR 6
WP2L1115.7 Walls, Columns & Crash Walls Grids C-K/1-5 - L2P6 6 10 04/30/15A 05/15/15 WP2L1115.6FS-1d, WP2L1115.5FSWP2L1115.8FS* 83% Storepoint 2204/30/15 0% 12
WP2L1115.8 Remove Perimeter Decks Grids C-K/1-5 - L2P6 1 0 05/18/15 05/18/15 WP2L1115.7FS* 0% Storepoint 220% 1
LEVEL 2 POUR 7
WP2L1116.6 Stress & Strip Grids A-H/1-10 - L2P7 3 0 05/14/15 05/18/15 WP2L1116.5FSWP2L1116.7FS-1d*0% Storepoint 220% 3
WP2L1116.7 Walls, Columns & Crash Walls Grids A-H/1-10 - L2P7 6 0 05/18/15 05/25/15 WP2L1116.5FS, WP2L1116.6FS-1d*WP2L1116.8FS* 0% Storepoint 220% 6
WP2L1116.8 Remove Perimeter Decks Grids A-H/1-10 - L2P7 1 0 05/26/15 05/26/15 WP2L1116.7FS* 0% Storepoint 220% 1
LEVEL 3 CONCRETE
LEVEL 3 POUR 1
WP3L1010.6 Stress & Strip Grids E.5-K/8-16 - L3P1 3 0 05/21/15 05/25/15 WP3L1010.5FS+3d*WP3L1010.7FS-1d*0% Storepoint 220% 3
WP3L1010.7 Walls, Columns & Crash Walls Grids E.5-K/8-16 - L3P1 6 0 05/25/15 06/01/15 WP3L1010.6FS-1d*WP3L1010.8FS-1d*0% Storepoint 220% 6
WP3L1010.8 Remove Perimeter Decks Grids E.5-K/8-16 - L3P1 5 0 06/01/15 06/05/15 WP3L1010.7FS-1d* 0% Storepoint 220% 5
LEVEL 3 POUR 2
WP3L1020.1 MEPF Layout / Rough-in Grids A-E.5/8-16 - L3P2 5 2 05/12/15A 05/15/15 WP3L1020.0SS+4d*WP3L1020.2SS+3d*50% Storepoint 2205/12/15 0% 4
WP3L1020.2 Rebar & Tendons Grids Grids A-E.5/8-16 - L3P2 7 2 05/13/15A 05/22/15 WP3L1020.1SS+3d*WP3L1020.3FF* 25% Storepoint 2205/13/15 0% 8
WP3L1020.3 MEP Completion / Inspections Grids A-E.5/8-16 - L3P2 0 0 05/22/15 WP3L1020.2FF*WP3L1020.4FF*, WP3L1020.5FS+10% Storepoint 220% 0
WP3L1020.4 COH Inspection Reinforcing Grids A-E.5/8-16 - L3P2 0 0 05/22/15 WP3L1020.3FF*WP3L1020.5FS+1d*0% Storepoint 220% 0
WP3L1020.5 Place & Finish Grids A-E.5/8-16 - L3P2 1 0 05/26/15 05/26/15 WP3L1020.4FS+1d*, WP3L1020.3FSWP3L1020.6SS+3d*, FR3010FS*0% Storepoint 220% 1
WP3L1020.6 Stress & Strip Grids A-E.5/8-16 - L3P2 3 0 05/29/15 06/02/15 WP3L1020.5SS+3d*WP3L1020.7FS-1d*0% Storepoint 220% 3
WP3L1020.7 Walls, Columns & Crash Walls Grids A-E.5/8-16 - L3P2 6 0 06/02/15 06/09/15 WP3L1020.6FS-1d*WP3L1020.8FS-1d*0% Storepoint 220% 6
WP3L1020.8 Remove Perimeter Decks Grids A-E.5/8-16 - L3P2 5 0 06/09/15 06/15/15 WP3L1020.7FS-1d* 0% Storepoint 220% 5
LEVEL 3 POUR 3
WP3L1030.0 Form Grids E.5-K/1-8 - L3P3 10 2 05/15/15A 05/28/15 WP2L1115.6FS, WP3L1020.0SS+7dWP3L1030.1SS+6d*, WP3L1040.0S20% Storepoint 2205/15/15 0% 10
WP3L1030.1 MEPF Layout / Rough-in Grids E.5-K/1-8 - L3P3 4 0 05/25/15 05/28/15 WP3L1030.0SS+6d*WP3L1030.2SS+3d*0% Storepoint 220% 4
WP3L1030.2 Rebar & Tendons Grids E.5-K/1-8 - L3P3 5 0 05/28/15 06/03/15 WP3L1030.1SS+3d*WP3L1030.3FF* 0% Storepoint 220% 5
WP3L1030.3 MEP Completion / Inspections Grids E.5-K/1-8 - L3P3 0 0 06/03/15 WP3L1030.2FF*WP3L1030.4FF*, WP3L1030.5FS+10% Storepoint 220% 0
WP3L1030.4 COH Inspection Reinforcing Grids E.5-K/1-8 - L3P3 0 0 06/03/15 WP3L1030.3FF*WP3L1030.5FS+1d*0% Storepoint 220% 0
WP3L1030.5 Place & Finish Grids E.5-K/1-8 - L3P3 1 0 06/05/15 06/05/15 WP3L1030.4FS+1d*, WP3L1030.3FSWP3L1030.6SS+3d*0% Storepoint 220% 1
WP3L1030.6 Stress & Strip Grids E.5-K/1-8 - L3P3 3 0 06/10/15 06/12/15 WP3L1030.5SS+3d*WP3L1030.7FS-1d*0% Storepoint 220% 3
WP3L1030.7 Walls, Columns & Crash Walls Grids E.5-K/1-8 - L3P3 6 0 06/12/15 06/19/15 WP3L1030.6FS-1d*WP3L1030.8FS-1d*0% Storepoint 220% 6
WP3L1030.8 Remove Perimeter Decks Grids E.5-K/1-8 - L3P3 5 0 06/19/15 06/25/15 WP3L1030.7FS-1d* 0% Storepoint 220% 5
LEVEL 3 POUR 4
WP3L1040.0 Form Grids A-E.5/1-8 - L3P4 10 0 05/25/15 06/05/15 WP3L1030.0SS+6d*WP3L1040.1SS+4d*0% Storepoint 220% 10
WP3L1040.1 MEPF Layout / Rough-in Grids A-E.5/1-8 - L3P4 4 0 05/29/15 06/03/15 WP3L1040.0SS+4d*WP3L1040.2SS+3d*0% Storepoint 220% 4
WP3L1040.2 Rebar & Tendons Grids A-E.5/1-8 - L3P4 5 0 06/03/15 06/09/15 WP3L1040.1SS+3d*WP3L1040.3FF+1d*0% Storepoint 220% 5
WP3L1040.3 MEP Completion / Inspections Grids A-E.5/1-8 - L3P4 0 0 06/10/15 WP3L1040.2FF+1d*WP3L1040.5FS*, WP3L1040.4FF*0% Storepoint 220% 0
WP3L1040.4 COH Inspection Reinforcing Grids A-E.5/1-8 - L3P4 0 0 06/10/15 WP3L1040.3FF*WP3L1040.5FS* 0% Storepoint 220% 0
WP3L1040.5 Place & Finish Grids A-E.5/1-8 - L3P4 1 0 06/11/15 06/11/15 WP3L1040.3FS*, WP3L1040.4FS*WP3L1040.6SS+3d*0% Storepoint 220% 1
WP3L1040.6 Stress & Strip Grids A-E.5/1-8 - L3P4 3 0 06/16/15 06/18/15 WP3L1040.5SS+3d*WP3L1040.7FS-1d*, WP2L1320FS0% Storepoint 220% 3
WP3L1040.7 Walls, Columns & Crash Walls Grids A-E.5/1-8 - L3P4 6 0 06/18/15 06/25/15 WP3L1040.6FS-1d*WP3L1040.8FS-1d*, WP3L1220FS*0% Storepoint 220% 6
WP3L1040.8 Remove Perimeter Decks Grids A-E.5/1-8 - L3P4 5 0 06/25/15 07/01/15 WP3L1040.7FS-1d* 0% Storepoint 220% 5
EAST TO WEST
WP3L1220 Remove Reshores Phase 1 10 0 06/26/15 07/09/15 WP3L1040.7FS*WP3L1221FS, 1RI1010FS+10d*, 1R0% Storepoint 220% 10
Today
DataDate
AC & CCTV
Exterior Framing
Building Wrap & Windows
Masonry
Storm
Gas
Permanent Power To SP-1 & 2, St-1
Remove Perimeter Decks Grids G-K/5-12 - L2P3
Remove Perimeter Decks Grids 10-16/A-D - L2P4
Remove Perimeter Decks Grids D-K/10-16 - L2P5
Walls, Columns & Crash Walls Grids C-K/1-5 - L2P6
Remove Perimeter Decks Grids C-K/1-5 - L2P6
Stress & Strip Grids A-H/1-10 - L2P7
Walls, Columns & Crash Walls Grids A-H/1-10 - L2P7
Remove Perimeter Decks Grids A-H/1-10 - L2P7
Stress & Strip Grids E.5-K/8-16 - L3P1
Walls, Columns & Crash Walls Grids E.5-K/8-16 - L3P1
Remove Perimeter Decks Grids E.5-K/8-16 - L3P1
MEPF Layout / Rough-in Grids A-E.5/8-16 - L3P2
Rebar & Tendons Grids Grids A-E.5/8-16 - L3P2
MEP Completion / Inspections Grids A-E.5/8-16 - L3P2
COH Inspection Reinforcing Grids A-E.5/8-16 - L3P2
Place & Finish Grids A-E.5/8-16 - L3P2
Stress & Strip Grids A-E.5/8-16 - L3P2
Walls, Columns & Crash Walls Grids A-E.5/8-16 - L3P2
Remove Perimeter Decks Grids A-E.5/8-16 - L3P2
Form Grids E.5-K/1-8 - L3P3
MEPF Layout / Rough-in Grids E.5-K/1-8 - L3P3
Rebar & Tendons Grids E.5-K/1-8 - L3P3
MEP Completion / Inspections Grids E.5-K/1-8 - L3P3
COH Inspection Reinforcing Grids E.5-K/1-8 - L3P3
Place & Finish Grids E.5-K/1-8 - L3P3
Stress & Strip Grids E.5-K/1-8 - L3P3
Walls, Columns & Crash Walls Grids E.5-K/1-8
Remove Perimeter
Form Grids A-E.5/1-8 - L3P4
MEPF Layout / Rough-in Grids A-E.5/1-8 - L3P4
Rebar & Tendons Grids A-E.5/1-8 - L3P4
MEP Completion / Inspections Grids A-E.5/1-8 - L3P4
COH Inspection Reinforcing Grids A-E.5/1-8 - L3P4
Place & Finish Grids A-E.5/1-8 - L3P4
Stress & Strip Grids A-E.5/1-8 - L3P4
Walls, Columns & C
Start Date: 05/13/14
Finish Date: 07/07/16
Data Date: 05/14/15
Run Date: 05/18/15
West Podium .2015.05.14.ppx Page 2A
ORENCO PODIUM WEST 05/14/2015
- 3. 19 20 21 22 23 24 25 26 27
May Jun
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
ID Description
Orig
Dura
Act
Dur Start Finish Predecessors Successors
%
Compl
STOStart
Vari
Act
StartActual FinishPhysical Percent CompleteDuration At Completion
FRAMING
3RD FLOOR
EAST TO WEST
FR3004 3rd Floor Anchor bolt/Tie down install at L3P3 5 0 05/15/15 05/21/15 FR3002FS* FR3006FS* 0% Storepoint 220% 5
FR3006 3rd Floor Anchor bolt/Tie down install at L3P4 5 0 05/22/15 05/28/15 FR3004FS* 0% Storepoint 220% 5
FR3010 3rd Floor Framing Layout 5 0 05/27/15 06/02/15 WP3L1020.5FS*WEMU1000FS*, FR3020SS+1d*0% Storepoint 220% 5
FR3020 Frame 3rd Floor Walls 15 0 05/28/15 06/17/15 FR3010SS+1d*FR4005FS-5d*, FR3030FS*0% Storepoint 220% 15
FR3030 Wall Straightening/Backing/Pickup Framing 10 0 06/18/15 07/01/15 FR3020FS* 0% Storepoint 220% 10
4TH FLOOR
EAST TO WEST
FR4005 Roll 4th Floor Joists & Decking 10 0 06/11/15 06/24/15 FR3020FS-5d*3RI1010SS+8d*, 3RI1000SS+4d*, 3R0% Storepoint 220% 10
FR4010 4th Floor Framing Layout 5 0 06/25/15 07/01/15 FR4005FS* 0% Storepoint 220% 5
FR4020 Frame 4th Floor Walls 15 0 06/18/15 07/08/15 FR4005SS+5d*FR5005SS+5d*, PSA1020SS*, PSA10% Storepoint 220% 15
5TH FLOOR
EAST TO WEST
FR5005 Roll 5th Floor Joists & Decking 10 0 06/25/15 07/08/15 FR4020SS+5d*WP3L1231FS, 4RI1000SS+3d*, 4RI10% Storepoint 220% 10
BUILDING ENCLOSURE
PRE SKIN ACTIVITIES
No value assigned
PSA1001 East Elevation Knife Plates & Canopy Tubes 1-3 5 0 06/22/15 06/26/15 FR4020SS+2d*PSA1003FS*, PSA1010FS, PSA1000% Storepoint 220% 5
PSA1011 East Perimeter Metal Stud Framing 20 0 06/18/15 07/15/15 FR4020SS* PSA1012SS+5d* 0% Storepoint 220% 20
PSA1012 Densglass @ Exterior Metal Stud 20 0 06/25/15 07/22/15 PSA1011SS+5d*BS1015SS+5d* 0% Storepoint 220% 20
PSA1020 Install Deck Knife Plates 20 0 06/18/15 07/15/15 FR4020SS* CY1030FS*, CY1050FS0% Storepoint 220% 20
MEPF ROUGH-IN
3RD FLOOR
No value assigned
3RI1000 Fire Sprinkler Rough 15 0 06/17/15 07/07/15 FR4005SS+4d* 0% Storepoint 220% 15
3RI1010 Initial Waste & Vent 15 0 06/23/15 07/13/15 FR4005SS+8d*2FI1010FS* 0% Storepoint 220% 15
3RI1020 Drill & Box 15 0 06/23/15 07/13/15 FR4005SS+8d*3RI1030FS* 0% Storepoint 220% 15
Today
DataDate
3rd Floor Anchor bolt/Tie down install at L3P3
3rd Floor Anchor bolt/Tie down install at L3P4
3rd Floor Framing Layout
Frame 3rd Floor Walls
Roll 4th Floor Joists & D
East Elevation
Start Date: 05/13/14
Finish Date: 07/07/16
Data Date: 05/14/15
Run Date: 05/18/15
West Podium .2015.05.14.ppx Page 3A
ORENCO PODIUM WEST 05/14/2015