SlideShare a Scribd company logo
1 of 34
Key Strategies for Achieving Programme
Objectives
(Improve and Enhance Distribution
Network )
Part 4
Affordable 24x7 Power To All @2019- Fuel
Security & Distribution Reforms -
Improve and Enhance Distribution
Network
Improve and Enhance Distribution
Network
Presence of a robust distribution network is vital to achieve ‘affordable power
to all by 2019’. At present, the distribution network in the country comprises
of a total of 8,603,136 circuit kilometers of distribution lines catering to
nearly 200 million consumers.
Since majority of the distribution utilities are owned by the State
Governments, they are subject to their control and influence in their day to
day functioning as well as in the policies pursued by them.
Improve and Enhance Distribution
Network
Listed below are some of the suggestions for improving the distribution
network in the country-
Upgrade existing distribution network - It has been witnessed that discoms
are unable to meet the demand for electricity, which is evident from the
frequent load shedding, poor voltage and high degree of interruptions in
supply. The programme objectives can be achieved not only by increasing the
generation capacity but also by ensuring adequate quality of supply.
Improve and Enhance Distribution
Network
This would entail significant investments in improving the existing distribution
networks. These would include re-conductoring of distribution lines, addition of
transformation capacities, and adequate provision of reactive power in the
system as well as adoption of smart grid technologies.
The funds required for up gradation can be raised by discoms from financial
institutions and external aid agencies. These loans can be repaid from revenues
arising on account of better efficiency in distribution management.
Improve and Enhance Distribution
Network
Undertake research study to estimate future demand for power:
It has been noticed, that at present discoms do not properly plan future
requirement of power. Programme success will require accurate estimation of
demand suitably factoring in the increased electrification of rural areas and
other locations.
Improve and Enhance Distribution
Network
For this, each state would need to undertake an exhaustive study focusing on
load estimation / growth and assessing the current level of transmission and
distribution losses. Once the information on load profiles and system losses is
available, the utilities can adequately plan for power procurement to meet the
projected demand.
Improve and Enhance Distribution
Network
Difficulty in obtaining the right of way (ROW) –
During the 12th Plan period, there is a target to add about 107,440 circuit
kilometers (ckm) of transmission lines, 270,000 MVA of AC transformation
capacity and 12,750 MW of HVDC systems to the existing transmission system.
One of the major challenges faced in the expansion of new transmission lines is
the difficulty in obtaining additional right of way (ROW). In order to build the
transmission lines targeted in the 12th Plan, about 1.4 million acres of land is
required.
Improve and Enhance Distribution
Network
Electrification of Un-electrified Households:
As per 2011 census, six states in the country have more than 40% of their
households without electricity. The situation is even worse in north-east states,
where more than 50% of its households are without electricity even though
resources for power generation are relatively abundant.
Improve and Enhance Distribution
Network
Under the programme, the highest priority should be accorded to
accomplishing 100% electrification of un-electrified households. For this, a
mission mode approach can be adopted, particularly in states, which witness
less than the national average proportion of electrified households.
Improve and Enhance Distribution
Network
Target reduction in AT&C Losses:
The success of the programme rides significantly on the reduction of AT&C
losses. The National Electricity Plan targets reduction of AT&C losses to about
17.5% by 2018-19. To achieve this, special programs can be developed to
strengthen distribution networks and to reduce unauthorized use of power.
Improve and Enhance Distribution
Network
This will require substantial investments in upgrading the distribution
networks by converting low voltage distribution lines into High Voltage
Distribution Systems (HVDS), rigorous energy auditing, preventing theft of
power by switching to aerial-bunched cables (ABC) and by improving the
metering system in the rural and urban areas.
Improve and Enhance Distribution
Network
Comprehensive adoption of consumer level and DTC level metering:
The strategy for ‘Affordable 24*7 power for all by 2019’ must include
universalization of consumer level and DTC level metering. Absence of
metering and accounting of energy at different levels in the distribution
network causes losses to discoms. Due to these losses, there is increasing
burden of subsidy payments on the State Governments and, in some cases,
unsustainably high tariff for the paying consumers.
Improve and Enhance Distribution
Network
The SERCs should mandate implementation of DTC metering with advanced
metering systems as part of the capital expenditure of the distribution utilities.
Improve and Enhance Distribution
Network
Need for reforms around electricity supply to agricultural sector –
There is a pressing need for reforms around electricity supply to the agriculture
sector. It has been noticed, that in most states, the supply to the agriculture
sector is unmetered and subsidized which results in losses for the discoms.
Though the subsidy payments by the state government are a relief but are not
adequate to cover the cost of supply to the agriculture sector. Also, the payment
of subsidy by State Governments is not made on a timely basis in spite of the
legal requirement of advance payment of subsidy under the Electricity Act, 2003.
Improve and Enhance Distribution
Network
Adoption of energy efficient measures in the agricultural sector –
There is a significant potential for adoption of energy efficient measures in the
agricultural sector. There have been instances of successful pilot projects
across several states like Gujarat, Maharashtra and Karnataka, where inefficient
irrigation pumps were replaced with star rated pumps resulting in energy
savings up to 25-30%. Going forward, several discoms should start investing in
energy efficient pumps with the help of energy saving companies (ESCOs).
Improve and Enhance Distribution
Network
Establish dedicated feeders for agricultural use:
There is an urgent need for states to take up feeder segregation to regulate
electricity supply to the agriculture sector. The states which book significant
electricity consumption for irrigation purposes should consider setting up
dedicated agricultural feeders which are separate from the rural feeders so as
to ensure 24x7 supply to consumers and to reduce peak demand by avoiding
supply to irrigation pump sets during peak hours.
Improve and Enhance Distribution
Network
This step will not only help in regulating the quantity of subsidized supplies,
but will also support in scheduling supply to the agriculture sector during off-
peak hours. Example- Gujarat has implemented a feeder separation
programme under the name ‘Jyothi Grama Yojana’. This programme has been
successful in supplying power to the agriculture sector for about 8–10 hours a
day and 24x7. Other states such as Punjab, Madhya Pradesh, Andhra Pradesh
and Karnataka have also adopted feeder separation programs to regulate
electricity supply to the agriculture sector.
Improve and Enhance Distribution
Network
Leverage solar energy for meeting irrigation requirement-
Solar energy can be leveraged to power irrigation pumps, given the softening
of prices of solar PV cells in recent years. This will help in solving irrigation
problems especially on sunny days, when the requirement for irrigating crops
is maximum. The resultant savings in energy will also help in reducing the
subsidy burden on the State Governments and non-agricultural consumers.
Government should initiate a major programme for incentivizing the use of
solar power for irrigation pump sets to progressively reduce the use of grid
power for irrigation.
Improve and Enhance Distribution
Network
Reform the management culture in discoms- There is an urgent need to
reform the culture in discoms which currently lacks commercial direction,
merely focusing on providing services without much regard for financial
returns. The distribution utilities are therefore caught in a vicious cycle of
poor quality supply, leading to inadequate recovery of cost of service, which
affects their ability to incur capital and maintenance expenditure to improve
the quality of supply.
Improve and Enhance Distribution
Network
The discom resources including the field / operations staff and the
management need to be trained in techno-commercial and regulatory
aspects to increase both their technical efficiency and financial accountability.
For this purpose, Government should consider establishing Power Sector
Management Training Centers in each State.
Improve and Enhance Distribution
Network
Improve financial effectiveness of discoms:
The non-recovery charges for discoms from consumers such as farmers, local
bodies and even government departments are massive, amounting to INR
70,000 crore per year. Consequently, these discoms are unable to procure the
required quantity of electricity due to their weak financial position. As a
result, the discoms have not been able to make necessary investments to
strengthen the distribution networks and adopt standard maintenance
practices to ensure satisfactory quality of supply.
Improve and Enhance Distribution
Network
The viability of the entire power sector depends upon the financial health and
the operational efficiency of the discoms. Therefore, it is important to focus
on improving their performance, especially the performance of the
Government owned discoms. These discoms need to be reoriented to adhere
to operational procedures so as to achieve the overall programme objectives.
Improve and Enhance Distribution
Network
The availability of adequate institutional finance, timely payment of subsidies
by State Governments and adequacy and regularity of tariff revision by the
State Regulatory Commissions will go a long way in securing the financial
effectiveness of discoms.
Improve and Enhance Distribution
Network
Remodel the subsidy payment system-
One of the main reasons responsible for the poor financial viability of discoms
is the inadequate returns from the subsidized consumer categories such as
farmers and other weaker sections. Due to the poor financial position of the
state governments in some states, the subsidy payments to discoms are
either delayed or irregular, thereby further compounding their problems.
Therefore, in order to address this issue, it is imperative to design a system of
ensuring that payment of subsidies to electricity utilities for free or subsidized
supply is made a priority charge on the state finances.
Improve and Enhance Distribution
Network
Adequate and timely revision of tariffs by SERCs –
There is a need for adequate and regular tariff revisions by the State
Electricity Regulatory Commission to ensure effective functioning of discoms.
Guided by a notification issued by the Appellate Tribunal for Electricity in
November 2012, the SERCs have been introducing tariff revisions in some
states where tariff revision was delayed or was irregular in the past. This
measure needs to be replicated in SERCs across other states as well.
Improve and Enhance Distribution
Network
Financial restructuring of unviable discoms-
It has been witnessed, that majority of the discoms have not availed the
option of financial restructuring that was available under the Shunglu
committee report. Most distribution utilities have not only recorded
accumulated losses, but also unrecoverable arrears on their balance sheets as
part of their assets. Therefore, the financial restructuring scheme needs to be
modified to identify the actual financial strength of discoms by excluding such
unrecoverable dues and making applicable to all distribution utilities which
are in need of institutional finance to implement distribution reforms.
Improve and Enhance Distribution
Network
Set up power planning cells under the guidance of central electricity
authority-
There is a need to set up power planning cells at the state level to support
discoms in preparing and submitting plans for the next 5-10 years. At present,
most states do not have an agency to support the overall planning and
coordination for the development of the power sector.
Improve and Enhance Distribution
Network
Adoption of Smart Grid technology-
Recently, the government initiated National Smart Grid Mission to make the
Indian power infrastructure cost effective, responsive and reliable.
Smart-grid facilitates efficient and reliable end-to-end intelligent two-way
delivery system from source to sink through integration of renewable energy
sources, smart transmission and distribution.
Improve and Enhance Distribution
Network
Smart- grid also enables real time monitoring and control of power system as
well as helps in reduction of AT&C losses, demand response and demand side
management, power quality management, outage management, smart home
energy system, etc.
Smart-grid technologies are being increasingly deployed in developing and
industrially developed, countries. Smart-grid technologies enable utilities and
their customers to enhance energy efficiency, increase the reliability and
resilience of power supplies, and reduce greenhouse gas emissions at the
same time. In this way, smart-grid technology brings efficiency and
sustainability in meeting the growing electricity demand.
Improve and Enhance Distribution
Network
Commercial and industrial facilities account for nearly 50 percent of peak
electricity demand in India. That puts great value on the smart grid
technology that can improve energy efficiency and intelligently adjust to grid
supply-and-demand conditions.
Improve and Enhance Distribution
Network
Recently, Honeywell and Tata Power Delhi Distribution (TPDDL) announced
installation of automated demand response (ADR) system for commercial and
industrial companies in an area in New Delhi. This ADR system enables the
utility to optimize grid performance, that is, reduce energy consumption
during times when grid supply is low or strained. Further, this technology also
helps in reducing brownouts and blackouts that periodically affect residents
and businesses across the covered area.
Improve and Enhance Distribution
Network
Smart-grid technology and systems, along with renewable energies such as
solar and wind power, can reduce the need to mine and burn more coal and
import oil while greatly expanding energy access and security. Going forward,
smart grid technology can play a pivotal role in addressing longstanding
sustainable energy and development challenges in India.
THANK YOU
Email: jyoti.gadia@resurgentindia.com Call Us: +91 124 4754550
www.resurgentindia.com
Read full report on : http://blog.resurgentindia.com/affordable-24x7-power-to-all-2019-
programme-objectives-background/

More Related Content

What's hot

Day-3, Mr. Reji Kumar SG Roadmap presentation
Day-3, Mr. Reji Kumar SG Roadmap presentationDay-3, Mr. Reji Kumar SG Roadmap presentation
Day-3, Mr. Reji Kumar SG Roadmap presentationIPPAI
 
GSMA FINAL PROJECT EMILY KHAMULA LUNGU
GSMA FINAL PROJECT EMILY KHAMULA LUNGUGSMA FINAL PROJECT EMILY KHAMULA LUNGU
GSMA FINAL PROJECT EMILY KHAMULA LUNGUFavour Lunguh
 
Tariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An OverviewTariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An OverviewIOSR Journals
 
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...Resurgent India
 
14.10.2019 proposed framework for real time market for electricity
14.10.2019 proposed framework for real time market for electricity14.10.2019 proposed framework for real time market for electricity
14.10.2019 proposed framework for real time market for electricityVijay Menghani
 
Day-3, Mr. Vimal Kirti Singh, IAS
Day-3, Mr. Vimal Kirti Singh, IASDay-3, Mr. Vimal Kirti Singh, IAS
Day-3, Mr. Vimal Kirti Singh, IASIPPAI
 
Indian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorIndian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorVijay Menghani
 
Environmental show of the south 2014 new entrants in electricity generation
Environmental show of the south 2014 new entrants in electricity generationEnvironmental show of the south 2014 new entrants in electricity generation
Environmental show of the south 2014 new entrants in electricity generationTNenergy
 
Energy comsats 12_oct13_2
Energy comsats 12_oct13_2Energy comsats 12_oct13_2
Energy comsats 12_oct13_2Faizan Shabbir
 
Aaron Milano, Portland General Electric: Transportation Electrification
Aaron Milano, Portland General Electric: Transportation Electrification Aaron Milano, Portland General Electric: Transportation Electrification
Aaron Milano, Portland General Electric: Transportation Electrification Forth
 
South Africa solar power programmes – Ed Hill – Specialised Solar Systems
South Africa solar power programmes – Ed Hill – Specialised Solar SystemsSouth Africa solar power programmes – Ed Hill – Specialised Solar Systems
South Africa solar power programmes – Ed Hill – Specialised Solar SystemsIIED
 
Eli Morris, Pacific Power Transportation Electrification
Eli Morris, Pacific Power Transportation ElectrificationEli Morris, Pacific Power Transportation Electrification
Eli Morris, Pacific Power Transportation ElectrificationForth
 
ScottMadden's 51st State Roadmap
ScottMadden's 51st State RoadmapScottMadden's 51st State Roadmap
ScottMadden's 51st State RoadmapScottMadden, Inc.
 
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPA
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPAIndian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPA
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPAIPPAI
 

What's hot (19)

Day-3, Mr. Reji Kumar SG Roadmap presentation
Day-3, Mr. Reji Kumar SG Roadmap presentationDay-3, Mr. Reji Kumar SG Roadmap presentation
Day-3, Mr. Reji Kumar SG Roadmap presentation
 
GSMA FINAL PROJECT EMILY KHAMULA LUNGU
GSMA FINAL PROJECT EMILY KHAMULA LUNGUGSMA FINAL PROJECT EMILY KHAMULA LUNGU
GSMA FINAL PROJECT EMILY KHAMULA LUNGU
 
pdt 2018 in india
pdt 2018 in indiapdt 2018 in india
pdt 2018 in india
 
Presentation steel
 Presentation steel  Presentation steel
Presentation steel
 
Restructuring of power grid
Restructuring of power gridRestructuring of power grid
Restructuring of power grid
 
Tariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An OverviewTariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An Overview
 
Power sector mis
Power sector misPower sector mis
Power sector mis
 
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
 
14.10.2019 proposed framework for real time market for electricity
14.10.2019 proposed framework for real time market for electricity14.10.2019 proposed framework for real time market for electricity
14.10.2019 proposed framework for real time market for electricity
 
Day-3, Mr. Vimal Kirti Singh, IAS
Day-3, Mr. Vimal Kirti Singh, IASDay-3, Mr. Vimal Kirti Singh, IAS
Day-3, Mr. Vimal Kirti Singh, IAS
 
Indian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorIndian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power Sector
 
Environmental show of the south 2014 new entrants in electricity generation
Environmental show of the south 2014 new entrants in electricity generationEnvironmental show of the south 2014 new entrants in electricity generation
Environmental show of the south 2014 new entrants in electricity generation
 
Energy comsats 12_oct13_2
Energy comsats 12_oct13_2Energy comsats 12_oct13_2
Energy comsats 12_oct13_2
 
Aaron Milano, Portland General Electric: Transportation Electrification
Aaron Milano, Portland General Electric: Transportation Electrification Aaron Milano, Portland General Electric: Transportation Electrification
Aaron Milano, Portland General Electric: Transportation Electrification
 
Fuel Cells- A Potential Solution for Telecommunications Backup Power
Fuel Cells- A Potential Solution for Telecommunications Backup PowerFuel Cells- A Potential Solution for Telecommunications Backup Power
Fuel Cells- A Potential Solution for Telecommunications Backup Power
 
South Africa solar power programmes – Ed Hill – Specialised Solar Systems
South Africa solar power programmes – Ed Hill – Specialised Solar SystemsSouth Africa solar power programmes – Ed Hill – Specialised Solar Systems
South Africa solar power programmes – Ed Hill – Specialised Solar Systems
 
Eli Morris, Pacific Power Transportation Electrification
Eli Morris, Pacific Power Transportation ElectrificationEli Morris, Pacific Power Transportation Electrification
Eli Morris, Pacific Power Transportation Electrification
 
ScottMadden's 51st State Roadmap
ScottMadden's 51st State RoadmapScottMadden's 51st State Roadmap
ScottMadden's 51st State Roadmap
 
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPA
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPAIndian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPA
Indian Captive Power Producers Association - Rajiv Agrawal, Secretary, ICPPA
 

Similar to Affordable 24x7 Power To All @2019 - Key Strategies (Improve and Enhance Distribution Network ) - Part - 4

Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distributionDay-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distributionIPPAI
 
Power Sector Reform in India
Power Sector Reform in IndiaPower Sector Reform in India
Power Sector Reform in Indiamohkab1
 
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Resurgent India
 
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms Resurgent India
 
presentation_energy_nama_gambia2.pptx
presentation_energy_nama_gambia2.pptxpresentation_energy_nama_gambia2.pptx
presentation_energy_nama_gambia2.pptxgammawarsama
 
PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...
PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...
PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...prashantkumarchinama
 
Choosing Green: Status and Challenges of RE based Open Access
Choosing Green: Status and Challenges of RE based Open AccessChoosing Green: Status and Challenges of RE based Open Access
Choosing Green: Status and Challenges of RE based Open AccessWRI India
 
Energy distribution in Pakistan
Energy distribution in PakistanEnergy distribution in Pakistan
Energy distribution in PakistanUzma Fatima Ch.
 
WEBINAR | RESILIENCE RELIABILITY ENERGY PROJECTS NEPAL | Mini/Micro Hydropow...
 WEBINAR | RESILIENCE RELIABILITY ENERGY PROJECTS NEPAL | Mini/Micro Hydropow... WEBINAR | RESILIENCE RELIABILITY ENERGY PROJECTS NEPAL | Mini/Micro Hydropow...
WEBINAR | RESILIENCE RELIABILITY ENERGY PROJECTS NEPAL | Mini/Micro Hydropow...Smart Villages
 
Energy_conservation_paper_presentation
Energy_conservation_paper_presentationEnergy_conservation_paper_presentation
Energy_conservation_paper_presentationNageswar Rao
 
Pathways to Low Carbon Development: Impediments and Opportunities: Sri Lanka
Pathways to Low Carbon Development: Impediments and Opportunities: Sri LankaPathways to Low Carbon Development: Impediments and Opportunities: Sri Lanka
Pathways to Low Carbon Development: Impediments and Opportunities: Sri LankaClimate Action Network South Asia
 
Load Research Concept and Approach _Kolkata.pptx
Load Research Concept and Approach  _Kolkata.pptxLoad Research Concept and Approach  _Kolkata.pptx
Load Research Concept and Approach _Kolkata.pptxRAMAPANDA6
 
Economy and energy security for pakistan
Economy and energy security for pakistanEconomy and energy security for pakistan
Economy and energy security for pakistanFaizan Shabbir
 
Electricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardElectricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardIPPAI
 
Internship presentation anudeep-final
Internship presentation anudeep-finalInternship presentation anudeep-final
Internship presentation anudeep-finalanu141
 
Power Distribution Overview
Power Distribution OverviewPower Distribution Overview
Power Distribution OverviewHIMADRI BANERJI
 
GIS Based Power Distribution System: A Case study for the Junagadh City
GIS Based Power Distribution System: A Case study for the Junagadh CityGIS Based Power Distribution System: A Case study for the Junagadh City
GIS Based Power Distribution System: A Case study for the Junagadh Cityijsrd.com
 

Similar to Affordable 24x7 Power To All @2019 - Key Strategies (Improve and Enhance Distribution Network ) - Part - 4 (20)

DSM
DSMDSM
DSM
 
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distributionDay-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
 
Power Sector Reform in India
Power Sector Reform in IndiaPower Sector Reform in India
Power Sector Reform in India
 
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
 
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms
 
presentation_energy_nama_gambia2.pptx
presentation_energy_nama_gambia2.pptxpresentation_energy_nama_gambia2.pptx
presentation_energy_nama_gambia2.pptx
 
PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...
PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...
PES-Webinar-4-PPTs-Sreekumar-New_Challenges_in_Electricity_Distribution--22-M...
 
Choosing Green: Status and Challenges of RE based Open Access
Choosing Green: Status and Challenges of RE based Open AccessChoosing Green: Status and Challenges of RE based Open Access
Choosing Green: Status and Challenges of RE based Open Access
 
Ppt nep n ntp
Ppt nep n ntpPpt nep n ntp
Ppt nep n ntp
 
Energy distribution in Pakistan
Energy distribution in PakistanEnergy distribution in Pakistan
Energy distribution in Pakistan
 
WEBINAR | RESILIENCE RELIABILITY ENERGY PROJECTS NEPAL | Mini/Micro Hydropow...
 WEBINAR | RESILIENCE RELIABILITY ENERGY PROJECTS NEPAL | Mini/Micro Hydropow... WEBINAR | RESILIENCE RELIABILITY ENERGY PROJECTS NEPAL | Mini/Micro Hydropow...
WEBINAR | RESILIENCE RELIABILITY ENERGY PROJECTS NEPAL | Mini/Micro Hydropow...
 
Energy_conservation_paper_presentation
Energy_conservation_paper_presentationEnergy_conservation_paper_presentation
Energy_conservation_paper_presentation
 
Pathways to Low Carbon Development: Impediments and Opportunities: Sri Lanka
Pathways to Low Carbon Development: Impediments and Opportunities: Sri LankaPathways to Low Carbon Development: Impediments and Opportunities: Sri Lanka
Pathways to Low Carbon Development: Impediments and Opportunities: Sri Lanka
 
Load Research Concept and Approach _Kolkata.pptx
Load Research Concept and Approach  _Kolkata.pptxLoad Research Concept and Approach  _Kolkata.pptx
Load Research Concept and Approach _Kolkata.pptx
 
Economy and energy security for pakistan
Economy and energy security for pakistanEconomy and energy security for pakistan
Economy and energy security for pakistan
 
Electricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardElectricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forward
 
Internship presentation anudeep-final
Internship presentation anudeep-finalInternship presentation anudeep-final
Internship presentation anudeep-final
 
Internship Presentation Anudeep Final
Internship Presentation Anudeep FinalInternship Presentation Anudeep Final
Internship Presentation Anudeep Final
 
Power Distribution Overview
Power Distribution OverviewPower Distribution Overview
Power Distribution Overview
 
GIS Based Power Distribution System: A Case study for the Junagadh City
GIS Based Power Distribution System: A Case study for the Junagadh CityGIS Based Power Distribution System: A Case study for the Junagadh City
GIS Based Power Distribution System: A Case study for the Junagadh City
 

More from Resurgent India

Acquisition Opportunity! Exploring the Future of Ayurvedic & Unani Medicines!
 Acquisition Opportunity! Exploring the Future of Ayurvedic & Unani Medicines! Acquisition Opportunity! Exploring the Future of Ayurvedic & Unani Medicines!
Acquisition Opportunity! Exploring the Future of Ayurvedic & Unani Medicines!Resurgent India
 
Msme funding – Opportunities & Challenges (Part 5)
Msme funding – Opportunities & Challenges (Part 5)Msme funding – Opportunities & Challenges (Part 5)
Msme funding – Opportunities & Challenges (Part 5)Resurgent India
 
Funding Sme – MSME FINANCE – DEMAND & SUPPLY - Part - 9
Funding Sme – MSME FINANCE – DEMAND & SUPPLY - Part - 9Funding Sme – MSME FINANCE – DEMAND & SUPPLY - Part - 9
Funding Sme – MSME FINANCE – DEMAND & SUPPLY - Part - 9Resurgent India
 
Funding Sme – The Challenges And Risk Within - Mezzanine Financing - Part - 8
Funding Sme – The Challenges And Risk Within - Mezzanine Financing - Part - 8Funding Sme – The Challenges And Risk Within - Mezzanine Financing - Part - 8
Funding Sme – The Challenges And Risk Within - Mezzanine Financing - Part - 8Resurgent India
 
Funding Sme – The Challenges And Risk Within - Alternative financing sources ...
Funding Sme – The Challenges And Risk Within - Alternative financing sources ...Funding Sme – The Challenges And Risk Within - Alternative financing sources ...
Funding Sme – The Challenges And Risk Within - Alternative financing sources ...Resurgent India
 
Funding Sme – The Challenges And Risk Within - MSME FUNDING - NEED FOR ALTERN...
Funding Sme – The Challenges And Risk Within - MSME FUNDING - NEED FOR ALTERN...Funding Sme – The Challenges And Risk Within - MSME FUNDING - NEED FOR ALTERN...
Funding Sme – The Challenges And Risk Within - MSME FUNDING - NEED FOR ALTERN...Resurgent India
 
Funding Sme – The Challenges And Risk Within - MSMEs CONTRIBUTION TO ECONOMY ...
Funding Sme – The Challenges And Risk Within - MSMEs CONTRIBUTION TO ECONOMY ...Funding Sme – The Challenges And Risk Within - MSMEs CONTRIBUTION TO ECONOMY ...
Funding Sme – The Challenges And Risk Within - MSMEs CONTRIBUTION TO ECONOMY ...Resurgent India
 
MSME Financing - Alternative Financing Instruments - Part - 14
MSME Financing - Alternative Financing Instruments - Part - 14MSME Financing - Alternative Financing Instruments - Part - 14
MSME Financing - Alternative Financing Instruments - Part - 14Resurgent India
 
MSME Financing - Financing options available to MSMEs-II - Part -10
MSME Financing - Financing options available to MSMEs-II - Part -10MSME Financing - Financing options available to MSMEs-II - Part -10
MSME Financing - Financing options available to MSMEs-II - Part -10Resurgent India
 
MSME Financing - FINANCING MSME’S IN INDIA - Part - 7
MSME Financing - FINANCING MSME’S IN INDIA - Part - 7MSME Financing - FINANCING MSME’S IN INDIA - Part - 7
MSME Financing - FINANCING MSME’S IN INDIA - Part - 7Resurgent India
 
Indian Insurance Industry - Recent Industry Trends - Part - 5
Indian Insurance Industry - Recent Industry Trends - Part - 5Indian Insurance Industry - Recent Industry Trends - Part - 5
Indian Insurance Industry - Recent Industry Trends - Part - 5Resurgent India
 
Indian Insurance Industry - Key Issues and Challenges - Part - 2
Indian Insurance Industry - Key Issues and Challenges - Part - 2Indian Insurance Industry - Key Issues and Challenges - Part - 2
Indian Insurance Industry - Key Issues and Challenges - Part - 2Resurgent India
 
DMIC Summit - Financing - Part - 4
DMIC Summit - Financing - Part - 4DMIC Summit - Financing - Part - 4
DMIC Summit - Financing - Part - 4Resurgent India
 
DMIC Summit - Implementation and Institutional Framework - Part - 2
DMIC Summit - Implementation and Institutional Framework - Part - 2DMIC Summit - Implementation and Institutional Framework - Part - 2
DMIC Summit - Implementation and Institutional Framework - Part - 2Resurgent India
 
DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1
DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1
DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1Resurgent India
 
Smart Cities - Global Case Studies - Part - 5
Smart Cities - Global Case Studies - Part - 5Smart Cities - Global Case Studies - Part - 5
Smart Cities - Global Case Studies - Part - 5Resurgent India
 
Smart Cities - Global Case Studies - Part - 4
Smart Cities - Global Case Studies - Part - 4Smart Cities - Global Case Studies - Part - 4
Smart Cities - Global Case Studies - Part - 4Resurgent India
 
Empowering MSMEs - Benefits of Credit Rating in MSME - Part - 8
Empowering MSMEs - Benefits of Credit Rating in MSME - Part - 8Empowering MSMEs - Benefits of Credit Rating in MSME - Part - 8
Empowering MSMEs - Benefits of Credit Rating in MSME - Part - 8Resurgent India
 
Empowering MSMEs - Skills Development of the MSME Sector - Part - 7
Empowering MSMEs - Skills Development of the MSME Sector - Part - 7Empowering MSMEs - Skills Development of the MSME Sector - Part - 7
Empowering MSMEs - Skills Development of the MSME Sector - Part - 7Resurgent India
 

More from Resurgent India (20)

Acquisition Opportunity! Exploring the Future of Ayurvedic & Unani Medicines!
 Acquisition Opportunity! Exploring the Future of Ayurvedic & Unani Medicines! Acquisition Opportunity! Exploring the Future of Ayurvedic & Unani Medicines!
Acquisition Opportunity! Exploring the Future of Ayurvedic & Unani Medicines!
 
Demonetization part 2
Demonetization part 2Demonetization part 2
Demonetization part 2
 
Msme funding – Opportunities & Challenges (Part 5)
Msme funding – Opportunities & Challenges (Part 5)Msme funding – Opportunities & Challenges (Part 5)
Msme funding – Opportunities & Challenges (Part 5)
 
Funding Sme – MSME FINANCE – DEMAND & SUPPLY - Part - 9
Funding Sme – MSME FINANCE – DEMAND & SUPPLY - Part - 9Funding Sme – MSME FINANCE – DEMAND & SUPPLY - Part - 9
Funding Sme – MSME FINANCE – DEMAND & SUPPLY - Part - 9
 
Funding Sme – The Challenges And Risk Within - Mezzanine Financing - Part - 8
Funding Sme – The Challenges And Risk Within - Mezzanine Financing - Part - 8Funding Sme – The Challenges And Risk Within - Mezzanine Financing - Part - 8
Funding Sme – The Challenges And Risk Within - Mezzanine Financing - Part - 8
 
Funding Sme – The Challenges And Risk Within - Alternative financing sources ...
Funding Sme – The Challenges And Risk Within - Alternative financing sources ...Funding Sme – The Challenges And Risk Within - Alternative financing sources ...
Funding Sme – The Challenges And Risk Within - Alternative financing sources ...
 
Funding Sme – The Challenges And Risk Within - MSME FUNDING - NEED FOR ALTERN...
Funding Sme – The Challenges And Risk Within - MSME FUNDING - NEED FOR ALTERN...Funding Sme – The Challenges And Risk Within - MSME FUNDING - NEED FOR ALTERN...
Funding Sme – The Challenges And Risk Within - MSME FUNDING - NEED FOR ALTERN...
 
Funding Sme – The Challenges And Risk Within - MSMEs CONTRIBUTION TO ECONOMY ...
Funding Sme – The Challenges And Risk Within - MSMEs CONTRIBUTION TO ECONOMY ...Funding Sme – The Challenges And Risk Within - MSMEs CONTRIBUTION TO ECONOMY ...
Funding Sme – The Challenges And Risk Within - MSMEs CONTRIBUTION TO ECONOMY ...
 
MSME Financing - Alternative Financing Instruments - Part - 14
MSME Financing - Alternative Financing Instruments - Part - 14MSME Financing - Alternative Financing Instruments - Part - 14
MSME Financing - Alternative Financing Instruments - Part - 14
 
MSME Financing - Financing options available to MSMEs-II - Part -10
MSME Financing - Financing options available to MSMEs-II - Part -10MSME Financing - Financing options available to MSMEs-II - Part -10
MSME Financing - Financing options available to MSMEs-II - Part -10
 
MSME Financing - FINANCING MSME’S IN INDIA - Part - 7
MSME Financing - FINANCING MSME’S IN INDIA - Part - 7MSME Financing - FINANCING MSME’S IN INDIA - Part - 7
MSME Financing - FINANCING MSME’S IN INDIA - Part - 7
 
Indian Insurance Industry - Recent Industry Trends - Part - 5
Indian Insurance Industry - Recent Industry Trends - Part - 5Indian Insurance Industry - Recent Industry Trends - Part - 5
Indian Insurance Industry - Recent Industry Trends - Part - 5
 
Indian Insurance Industry - Key Issues and Challenges - Part - 2
Indian Insurance Industry - Key Issues and Challenges - Part - 2Indian Insurance Industry - Key Issues and Challenges - Part - 2
Indian Insurance Industry - Key Issues and Challenges - Part - 2
 
DMIC Summit - Financing - Part - 4
DMIC Summit - Financing - Part - 4DMIC Summit - Financing - Part - 4
DMIC Summit - Financing - Part - 4
 
DMIC Summit - Implementation and Institutional Framework - Part - 2
DMIC Summit - Implementation and Institutional Framework - Part - 2DMIC Summit - Implementation and Institutional Framework - Part - 2
DMIC Summit - Implementation and Institutional Framework - Part - 2
 
DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1
DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1
DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1
 
Smart Cities - Global Case Studies - Part - 5
Smart Cities - Global Case Studies - Part - 5Smart Cities - Global Case Studies - Part - 5
Smart Cities - Global Case Studies - Part - 5
 
Smart Cities - Global Case Studies - Part - 4
Smart Cities - Global Case Studies - Part - 4Smart Cities - Global Case Studies - Part - 4
Smart Cities - Global Case Studies - Part - 4
 
Empowering MSMEs - Benefits of Credit Rating in MSME - Part - 8
Empowering MSMEs - Benefits of Credit Rating in MSME - Part - 8Empowering MSMEs - Benefits of Credit Rating in MSME - Part - 8
Empowering MSMEs - Benefits of Credit Rating in MSME - Part - 8
 
Empowering MSMEs - Skills Development of the MSME Sector - Part - 7
Empowering MSMEs - Skills Development of the MSME Sector - Part - 7Empowering MSMEs - Skills Development of the MSME Sector - Part - 7
Empowering MSMEs - Skills Development of the MSME Sector - Part - 7
 

Recently uploaded

/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportMintel Group
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 

Recently uploaded (20)

/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample Report
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 

Affordable 24x7 Power To All @2019 - Key Strategies (Improve and Enhance Distribution Network ) - Part - 4

  • 1. Key Strategies for Achieving Programme Objectives (Improve and Enhance Distribution Network ) Part 4 Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms -
  • 2. Improve and Enhance Distribution Network
  • 3. Improve and Enhance Distribution Network Presence of a robust distribution network is vital to achieve ‘affordable power to all by 2019’. At present, the distribution network in the country comprises of a total of 8,603,136 circuit kilometers of distribution lines catering to nearly 200 million consumers. Since majority of the distribution utilities are owned by the State Governments, they are subject to their control and influence in their day to day functioning as well as in the policies pursued by them.
  • 4. Improve and Enhance Distribution Network Listed below are some of the suggestions for improving the distribution network in the country- Upgrade existing distribution network - It has been witnessed that discoms are unable to meet the demand for electricity, which is evident from the frequent load shedding, poor voltage and high degree of interruptions in supply. The programme objectives can be achieved not only by increasing the generation capacity but also by ensuring adequate quality of supply.
  • 5. Improve and Enhance Distribution Network This would entail significant investments in improving the existing distribution networks. These would include re-conductoring of distribution lines, addition of transformation capacities, and adequate provision of reactive power in the system as well as adoption of smart grid technologies. The funds required for up gradation can be raised by discoms from financial institutions and external aid agencies. These loans can be repaid from revenues arising on account of better efficiency in distribution management.
  • 6. Improve and Enhance Distribution Network Undertake research study to estimate future demand for power: It has been noticed, that at present discoms do not properly plan future requirement of power. Programme success will require accurate estimation of demand suitably factoring in the increased electrification of rural areas and other locations.
  • 7. Improve and Enhance Distribution Network For this, each state would need to undertake an exhaustive study focusing on load estimation / growth and assessing the current level of transmission and distribution losses. Once the information on load profiles and system losses is available, the utilities can adequately plan for power procurement to meet the projected demand.
  • 8. Improve and Enhance Distribution Network Difficulty in obtaining the right of way (ROW) – During the 12th Plan period, there is a target to add about 107,440 circuit kilometers (ckm) of transmission lines, 270,000 MVA of AC transformation capacity and 12,750 MW of HVDC systems to the existing transmission system. One of the major challenges faced in the expansion of new transmission lines is the difficulty in obtaining additional right of way (ROW). In order to build the transmission lines targeted in the 12th Plan, about 1.4 million acres of land is required.
  • 9. Improve and Enhance Distribution Network Electrification of Un-electrified Households: As per 2011 census, six states in the country have more than 40% of their households without electricity. The situation is even worse in north-east states, where more than 50% of its households are without electricity even though resources for power generation are relatively abundant.
  • 10. Improve and Enhance Distribution Network Under the programme, the highest priority should be accorded to accomplishing 100% electrification of un-electrified households. For this, a mission mode approach can be adopted, particularly in states, which witness less than the national average proportion of electrified households.
  • 11. Improve and Enhance Distribution Network Target reduction in AT&C Losses: The success of the programme rides significantly on the reduction of AT&C losses. The National Electricity Plan targets reduction of AT&C losses to about 17.5% by 2018-19. To achieve this, special programs can be developed to strengthen distribution networks and to reduce unauthorized use of power.
  • 12. Improve and Enhance Distribution Network This will require substantial investments in upgrading the distribution networks by converting low voltage distribution lines into High Voltage Distribution Systems (HVDS), rigorous energy auditing, preventing theft of power by switching to aerial-bunched cables (ABC) and by improving the metering system in the rural and urban areas.
  • 13. Improve and Enhance Distribution Network Comprehensive adoption of consumer level and DTC level metering: The strategy for ‘Affordable 24*7 power for all by 2019’ must include universalization of consumer level and DTC level metering. Absence of metering and accounting of energy at different levels in the distribution network causes losses to discoms. Due to these losses, there is increasing burden of subsidy payments on the State Governments and, in some cases, unsustainably high tariff for the paying consumers.
  • 14. Improve and Enhance Distribution Network The SERCs should mandate implementation of DTC metering with advanced metering systems as part of the capital expenditure of the distribution utilities.
  • 15. Improve and Enhance Distribution Network Need for reforms around electricity supply to agricultural sector – There is a pressing need for reforms around electricity supply to the agriculture sector. It has been noticed, that in most states, the supply to the agriculture sector is unmetered and subsidized which results in losses for the discoms. Though the subsidy payments by the state government are a relief but are not adequate to cover the cost of supply to the agriculture sector. Also, the payment of subsidy by State Governments is not made on a timely basis in spite of the legal requirement of advance payment of subsidy under the Electricity Act, 2003.
  • 16. Improve and Enhance Distribution Network Adoption of energy efficient measures in the agricultural sector – There is a significant potential for adoption of energy efficient measures in the agricultural sector. There have been instances of successful pilot projects across several states like Gujarat, Maharashtra and Karnataka, where inefficient irrigation pumps were replaced with star rated pumps resulting in energy savings up to 25-30%. Going forward, several discoms should start investing in energy efficient pumps with the help of energy saving companies (ESCOs).
  • 17. Improve and Enhance Distribution Network Establish dedicated feeders for agricultural use: There is an urgent need for states to take up feeder segregation to regulate electricity supply to the agriculture sector. The states which book significant electricity consumption for irrigation purposes should consider setting up dedicated agricultural feeders which are separate from the rural feeders so as to ensure 24x7 supply to consumers and to reduce peak demand by avoiding supply to irrigation pump sets during peak hours.
  • 18. Improve and Enhance Distribution Network This step will not only help in regulating the quantity of subsidized supplies, but will also support in scheduling supply to the agriculture sector during off- peak hours. Example- Gujarat has implemented a feeder separation programme under the name ‘Jyothi Grama Yojana’. This programme has been successful in supplying power to the agriculture sector for about 8–10 hours a day and 24x7. Other states such as Punjab, Madhya Pradesh, Andhra Pradesh and Karnataka have also adopted feeder separation programs to regulate electricity supply to the agriculture sector.
  • 19. Improve and Enhance Distribution Network Leverage solar energy for meeting irrigation requirement- Solar energy can be leveraged to power irrigation pumps, given the softening of prices of solar PV cells in recent years. This will help in solving irrigation problems especially on sunny days, when the requirement for irrigating crops is maximum. The resultant savings in energy will also help in reducing the subsidy burden on the State Governments and non-agricultural consumers. Government should initiate a major programme for incentivizing the use of solar power for irrigation pump sets to progressively reduce the use of grid power for irrigation.
  • 20. Improve and Enhance Distribution Network Reform the management culture in discoms- There is an urgent need to reform the culture in discoms which currently lacks commercial direction, merely focusing on providing services without much regard for financial returns. The distribution utilities are therefore caught in a vicious cycle of poor quality supply, leading to inadequate recovery of cost of service, which affects their ability to incur capital and maintenance expenditure to improve the quality of supply.
  • 21. Improve and Enhance Distribution Network The discom resources including the field / operations staff and the management need to be trained in techno-commercial and regulatory aspects to increase both their technical efficiency and financial accountability. For this purpose, Government should consider establishing Power Sector Management Training Centers in each State.
  • 22. Improve and Enhance Distribution Network Improve financial effectiveness of discoms: The non-recovery charges for discoms from consumers such as farmers, local bodies and even government departments are massive, amounting to INR 70,000 crore per year. Consequently, these discoms are unable to procure the required quantity of electricity due to their weak financial position. As a result, the discoms have not been able to make necessary investments to strengthen the distribution networks and adopt standard maintenance practices to ensure satisfactory quality of supply.
  • 23. Improve and Enhance Distribution Network The viability of the entire power sector depends upon the financial health and the operational efficiency of the discoms. Therefore, it is important to focus on improving their performance, especially the performance of the Government owned discoms. These discoms need to be reoriented to adhere to operational procedures so as to achieve the overall programme objectives.
  • 24. Improve and Enhance Distribution Network The availability of adequate institutional finance, timely payment of subsidies by State Governments and adequacy and regularity of tariff revision by the State Regulatory Commissions will go a long way in securing the financial effectiveness of discoms.
  • 25. Improve and Enhance Distribution Network Remodel the subsidy payment system- One of the main reasons responsible for the poor financial viability of discoms is the inadequate returns from the subsidized consumer categories such as farmers and other weaker sections. Due to the poor financial position of the state governments in some states, the subsidy payments to discoms are either delayed or irregular, thereby further compounding their problems. Therefore, in order to address this issue, it is imperative to design a system of ensuring that payment of subsidies to electricity utilities for free or subsidized supply is made a priority charge on the state finances.
  • 26. Improve and Enhance Distribution Network Adequate and timely revision of tariffs by SERCs – There is a need for adequate and regular tariff revisions by the State Electricity Regulatory Commission to ensure effective functioning of discoms. Guided by a notification issued by the Appellate Tribunal for Electricity in November 2012, the SERCs have been introducing tariff revisions in some states where tariff revision was delayed or was irregular in the past. This measure needs to be replicated in SERCs across other states as well.
  • 27. Improve and Enhance Distribution Network Financial restructuring of unviable discoms- It has been witnessed, that majority of the discoms have not availed the option of financial restructuring that was available under the Shunglu committee report. Most distribution utilities have not only recorded accumulated losses, but also unrecoverable arrears on their balance sheets as part of their assets. Therefore, the financial restructuring scheme needs to be modified to identify the actual financial strength of discoms by excluding such unrecoverable dues and making applicable to all distribution utilities which are in need of institutional finance to implement distribution reforms.
  • 28. Improve and Enhance Distribution Network Set up power planning cells under the guidance of central electricity authority- There is a need to set up power planning cells at the state level to support discoms in preparing and submitting plans for the next 5-10 years. At present, most states do not have an agency to support the overall planning and coordination for the development of the power sector.
  • 29. Improve and Enhance Distribution Network Adoption of Smart Grid technology- Recently, the government initiated National Smart Grid Mission to make the Indian power infrastructure cost effective, responsive and reliable. Smart-grid facilitates efficient and reliable end-to-end intelligent two-way delivery system from source to sink through integration of renewable energy sources, smart transmission and distribution.
  • 30. Improve and Enhance Distribution Network Smart- grid also enables real time monitoring and control of power system as well as helps in reduction of AT&C losses, demand response and demand side management, power quality management, outage management, smart home energy system, etc. Smart-grid technologies are being increasingly deployed in developing and industrially developed, countries. Smart-grid technologies enable utilities and their customers to enhance energy efficiency, increase the reliability and resilience of power supplies, and reduce greenhouse gas emissions at the same time. In this way, smart-grid technology brings efficiency and sustainability in meeting the growing electricity demand.
  • 31. Improve and Enhance Distribution Network Commercial and industrial facilities account for nearly 50 percent of peak electricity demand in India. That puts great value on the smart grid technology that can improve energy efficiency and intelligently adjust to grid supply-and-demand conditions.
  • 32. Improve and Enhance Distribution Network Recently, Honeywell and Tata Power Delhi Distribution (TPDDL) announced installation of automated demand response (ADR) system for commercial and industrial companies in an area in New Delhi. This ADR system enables the utility to optimize grid performance, that is, reduce energy consumption during times when grid supply is low or strained. Further, this technology also helps in reducing brownouts and blackouts that periodically affect residents and businesses across the covered area.
  • 33. Improve and Enhance Distribution Network Smart-grid technology and systems, along with renewable energies such as solar and wind power, can reduce the need to mine and burn more coal and import oil while greatly expanding energy access and security. Going forward, smart grid technology can play a pivotal role in addressing longstanding sustainable energy and development challenges in India.
  • 34. THANK YOU Email: jyoti.gadia@resurgentindia.com Call Us: +91 124 4754550 www.resurgentindia.com Read full report on : http://blog.resurgentindia.com/affordable-24x7-power-to-all-2019- programme-objectives-background/