23.02.11
- 1. DAILY PROGRESS REPORT
PLANNED Vs ACTUAL
Contractor: NRP Projects PVt LTd
23.02.11
Client: CPCL, Manali, Chennai.
Qty
S. No Activity Unit Remarks
Scope Planned Achieved Balance
TANK NO:212-D-02
1 Tank 2nd Shell Cleaning Sq.m 200 100 100 0 Completed
2 Tank 2nd Shell Touch Up paint Sq.m 200 200 100 0 Completed
3 MVSS PIPE LINE FITUP inch.m 20 5 5 5 Progress
TANK NO:212-D-01
1 Boxtype Scaffolding Sq.m 750 500 250 0 Completed
3 External 4rd Shell Cleaning Sq.m 175 175 50 0 Completed
TANK NO:211-D-02
1 MVSS Pipeline Fitup inch.m 70 20 20 30 Progress
2 MVSS Pipeline welding inch.dia 70 10 10 10 Progress
TANK NO:211-D-01
MVSS PIPE LINE FOAM ERECTION WORK inch.m 10 10 10 10 COMPLETED
TANK NO:214 -D-01
1 Deflector Plate Fabriocation on Progress
2 Roof Pipe to Riser Pipe Loop Connection Sq.m 4 2 2 0 Completed
TANK NO:214-D-02
2 Slushy water Removing and Tank Cleaning Kl 200 200 200 0 Completed
sl.no Category Ramani Kasi PIPING Scafflolder Painter
1 Fabricator 1 1 1
2 Fitter 1 0 1
3 Welder 4 4 3
4 Grinder 1 1 1
5 Gascutter 1 4 0
6 Rigger 2 3 7
7 Helper 6 1 1
8 Painter 13
9 Scaffolder 16
Total 16 14 14 16 13
Grand Total 73
- 2. DAILY PROGRAM
PLANNED Vs ACTUAL
Contractor: NRP Projects PVt LTd
15.02.11
Client: CPCL, Manali, Chennai.
Qty
S. No Activity Unit Remarks
Scope Planned Achieved Balance
TANK NO:212-D-02
1 Roof Cleaning and Touch up Paint Sq.m 600 200
2 1St Shell Cleaning and Painting Sq.m 800 200
TANK NO:212-D-01
1 Boxtype Scaffolding Sq.m 750
2 MVSS Pipeline Fitup & Welding Sq.m 10
3 External 2nd Shell Cleaning Sq.m 200
TANK NO:211-D-01
1 MVSS Pipeline Fitup and welding Sq.m 10 2
TANK NO:211-D-02
1 MVSS Pipeline Fitup and welding Sq.m 10
TANK NO:214 -D-01
1 Dewatering Kl 750
2 Roof Pipe to Riser Pipe Loop Connection Sq.m 4
TANK NO:214-D-02
1 Roof Cleaning Sq.m 200
2