DOCUMENT:
SOP-XX.XX
REVISION:
0.1
EFFECTIVE DATE:
9 JANUARY, 2012
DOCUMENT TITLE:
CONSTRUCTION REPORTING
PROCEDURE: PHOTOGRAPHY
AUTHORS:
PATRICK HUCKELS, CULMEN INTERNATIONAL
LEE FINEWOOD, US DOE/NNSA, DEFENSE NUCLEAR
NONPROLIFERATION, OFFICE OF SECOND LINE DEFENSE
U.S. Department of Energy
National Nuclear Security Administration
Defense Nuclear Nonproliferation
Office of Second Line Defense
CONSTRUCTION REPORTING
Standard Operating Procedure
for Photographic Recording
of Site Construction Activities
National Nuclear Security Administration
Construction Reporting Procedure: Photography Pg. 2 of 10
Doc Number: [Procedure Template-004###] Rev: [##]
U.S. DEPARTMENT OF ENERGY
NATIONAL NUCLEAR
SECURTY ADMINISTRATION
1000 INDEPENDENCE AVE., SW
WASHINGTON, DC 20585
(202) 586-5000
HTTP://WWW.NNSA.ENERGY.GOV/
Official Use Only (OUO)
Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official
need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
National Nuclear Security Administration
Construction Reporting Procedure: Photography Pg. 3 of 10
Doc Number: [Procedure Template-004###] Rev: [##]
PROCEDURE TEMPLATE
Document History
REVISION HISTORY
AUTHOR REVISED SECTION/PARAGRAPH REV RELEASED
[First Last Name] [Initial Release, Section 2, etc] [##) See [Document
Control System]
APPROVALS
All approvals are maintained and controlled in the [Document Control System] system.
Please refer to the [Document Control System] system for the current controlled revision and approval records.
Name Title
Name Title
DISTRIBUTION
This document has been distributed to:
Name Title
Name Title
Draft and Archived/Obsolete revisions are not to be used.
Access [Document Control System] system to verify revision.
Official Use Only (OUO)
Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official
need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
National Nuclear Security Administration
Construction Reporting Procedure: Photography Pg. 4 of 10
Doc Number: [Procedure Template-004###] Rev: [##]
Table of Contents
1. PURPOSE..............................................................................................................................................................................5
2. SCOPE...................................................................................................................................................................................5
3. RESPONSIBILITIES...........................................................................................................................................................5
4. PROCEDURE.......................................................................................................................................................................5
4.1 PROCESS FLOW ...........................................................................................................................................................5
4.2 PROCEDURE..................................................................................................................................................................5
5. DEFINITIONS......................................................................................................................................................................9
6. APPLICABLE REFERENCES...........................................................................................................................................9
7. QUALITY RECORDS.........................................................................................................................................................9
Official Use Only (OUO)
Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official
need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
National Nuclear Security Administration
Construction Reporting Procedure: Photography Pg. 5 of 10
Doc Number: [Procedure Template-004###] Rev: [##]
1. PURPOSE
This document serves as the Standard Operating Procedures (SOP) for the collection of
photographs for site construction activity reporting. It will provide: general requirements of all
photographs, including naming and requirements of information to be captured (date, location,
subject(s) and activity(ies), direction of view, scale) and required linkages to other documents (i.e.
as-builts, finaly construction reports).
It will also include, as an appendix, a list of minimum required photographs (and circumstances)
including what needs to be captured of what and when (e.g. trenches and all conduits, conduit end
cross-sections and post backfill compaction immediately following trenching and before paving).
2. SCOPE
Briefly describe the coverage or scope of what is covered and/or exempted from this process.
Please refrain from adding policy or procedure detail in this section.
3. RESPONSIBILITIES
• Responsible Party – Describe the responsible party responsibilities
• Responsible Party – Describe the responsible party responsibilities
• DICCE Contractor – will provide photos as prescribed…
• Designated Civil & Electrical QC manager will be held responsible for the thorough and
timely recording and transmittal of these photographs via Daily Reports and other manners,
as necessary. In addition, they shall ensure that these photographs are included in the
appropriate locations of appropriate Project documents, such as “as built” drawings and
Final Installation Reports.
• DOE and Support Contractors – will provide review and further direction, as needed.
• ??? -
4. PROCEDURE
Use Body Text to add text under Heading 1.
4.1 Process Flow
If applicable insert simple process flow chart or picture here. Keep the flowchart
descriptions simple putting the detail in the next subsection. If there is not a flow chart or
picture write “Not Applicable”.
4.2 Procedure
The following paragraphs will define general requirements to be met for all photographs,
including information to be captured and required linkages to other documents. Details of images
to be captured during particular work types will also be discussed below with a detailed checklist
to be compiled in the Appendix.
Official Use Only (OUO)
Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official
need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
National Nuclear Security Administration
Construction Reporting Procedure: Photography Pg. 6 of 10
Doc Number: [Procedure Template-004###] Rev: [##]
4.2.1 Overview
4.2.1.1 General Requirements: All site construction photographs will share, at a
minimum, the following requirements.
• Naming of photographs shall include… a uniform, standardized format for photo
titling will need to be determined and used during the length of the project. Two (2)
possible types are descriptive wording such as ‘casting of concrete_ lane 001_
looking north_date’ or by employing a designated alpha-numeric system with a
description adjacent to the photo in the daily work log (photo log). The latter type
may be advantageous when incorporating photo titles onto the GA , Red-Line
drawings and later incorporation onto the As-Built Final Package Drawings and
Final Construction Reports.
• The information to be captured in each photograph is to be clear and in a
standardized format. The associated photo log for the image will include at least:
date, location, subject(s) and activity(ies) captured in the image, the direction of
view, what was used for scale and an approximate size (see below for greater detail).
• Scalable measurements: the photographs will indicate subject dimensions whenever
possible using items such as, but not limited to, measuring tape and objects of known
dimensions (e.g. US coins or folders/binders).
• Hidden Works Documentation: Photographs will be taken of ALL works that will be
eventually hidden from view upon completion. See specific details below for more
information.
• Additional Photos: The DOE retains the right to request additional photos to be taken
in order to clarify ambiguous or problematic photo subject matter.
4.2.1.2 Photographic Records and Project Documents into which they are to be
included
Required linkages to other documents will be defined here and each photo log will cross-
reference the images location and linkage in those other project documents.
Incorporation of Photos into Project Documents
• Site Survey Photos-GA Drawings: The contractor will give evidence in photographic
form, all existing site conditions that are project development related. The photo title
will be shown on the initial GA drawings where the DICCE intends on developing or
resolving in-situ problems discovered during the site visit(s).
o Shall be indicated on the initial submission of the GA drawings giving
evidence on how the DICCE will interface with existing site conditions and
connections.
• QC reports
o Concrete pre-pour/placement report
o Backfilling report
o Compression Tests (28 day, etc.)
• Daily Reports: Shall include at least XXX photos indicating daily progress and
procedures
Official Use Only (OUO)
Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official
need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
National Nuclear Security Administration
Construction Reporting Procedure: Photography Pg. 7 of 10
Doc Number: [Procedure Template-004###] Rev: [##]
o As indicated above, the DOE will state what is the minimum required photos
inserted into the daily report. The DOE will have the right to request for more
detailed photos if required.
• Red-Line Drawings
o Photograph titles will be incorporated onto the red-line drawings indicating in
which location and direction the photograph was taken
• As-Built Drawings
o Will contain all photographic information as per finalized red-line drawings.
They may also contain photos taken during the SLAT review at the DOE’s
discretion. This is as per SOW sections 1.21/2.2.15
• Construction reports
o Any technical drawing or other depiction of an installation, or part thereof,
such as foundations, concrete slabs, trenches and conduits, electrical boxes,
wiring diagrams, and the like shall include a photograph(s) of the same, as
practicable.
4.2.2 Details
A detailed checklist of the minimum reporting requirements will be provided in Appendix I.
The list is meant to provide guidance by example of what is to be captured, in what detail,
how and when, as well a list of contingencies that would require additional photographic
records (e.g. failure of a component that requires images of the failure(s) and cause(s) as
well as the repair work performed and the final product of that work). It is by no means
meant to be exhaustive and additional photographic documentation may be initiated by
either DOE or the DICCE Designated Civil & Electrical QC manager onsite.
4.2.2.1 Photograph Content by Work Type
Civil Work: All Civil work photos shall contain, but not limited to, the following activities
• All photos shall be recorded on concrete pre-pour/placement and/or backfilling
report
• Excavation condition, location and dimensions
• Soil conditions prior to permanent material placement
• Reinforcing bar and associated structural material dimensions and placement
• Concrete ‘block-out’ dimensions and placement where required
• Anchor bolt or other fastener dimensions and placement
• Vapor or moisture material placement where required
• Dimensions and condition of existing infrastructure materials such as asphalt,
concrete or paver pavement , pavement sub-base(s), and fill soil.
• Interference of any other existing infrastructure not previously detected during site
surveys including sloping towards new construction.
• Pavement jointing including thermal control or construction types
• Use of construction equipment
Official Use Only (OUO)
Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official
need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
National Nuclear Security Administration
Construction Reporting Procedure: Photography Pg. 8 of 10
Doc Number: [Procedure Template-004###] Rev: [##]
• Pavement sloping indicating rain water moving away from new construction and
lack of ponding
• Construction material testing such as soil compaction, asphalt and concrete strength
tests, concrete slump, at material testing lab or in-situ
• Weather related project progress or material impacts
• Anchoring of all structural components
• Substrate condition prior to the application of horizontal traffic markings
Electrical Work: All Electrical work photos shall contain, but not limited to, the following
activities:
• All photos shall be recorded on the concrete pre-pour/placement or backfilling report
• Trenching dimensions and existing conditions
• Trench bed preparation including bedding type and thickness
• Placement of conduit(s) and/or direct bury cable(s)
• Distances between power and communication cables/conduits
• Cable type and sizing
• Connections of conduits with pull/hand boxes, both above and in-ground
• Placement of underground cable/conduit protection devices such as warning tape or
tiles
• Final backfilling and compaction
• Power and Control panel component placement and wiring, including labeling
• Panel’s moisture control material/system including drainage type (if required)
• Anchoring of all electrical components
• Power and communication tie-ins at host country’s panels/boxes
• All other connections of infrastructure to host country’s equipment (e.g. antennas)
• Earthing/Grounding system(s), materials used and location associated to existing
infrastructure
• Above ground conduit supports and sub-ups
• Conduit or cable penetrations through walls including moisture control techniques
• Spare conduits with associated pull strings/rope
Technical Solutions (IT and Communications): All technical solutions installation work photos
shall contain, but not limited to, the following activities:
• ?
• ??
• ???
4.2.2.2 Photographic Content for Other Efforts
Official Use Only (OUO)
Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official
need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
National Nuclear Security Administration
Construction Reporting Procedure: Photography Pg. 9 of 10
Doc Number: [Procedure Template-004###] Rev: [##]
• Safety: The DICCE shall give evidence that they are following established safe
construction acts and procedures when performing their work. The use of personal
protection equipment (PPE) will be evident in at least weekly photos.
5. DEFINITIONS
• Word – Definition
• Word – Definition
6. APPLICABLE REFERENCES
List of applicable reference documents.
• N/A
7. QUALITY RECORDS
List of applicable Quality records.
• N/A
Official Use Only (OUO)
Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official
need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
National Nuclear Security Administration
Construction Reporting Procedure: Photography Pg. 10 of 10
Doc Number: [Procedure Template-004###] Rev: [##]
Appendix I
This will be a checklist of the minimum (“including but not limited to…”) reporting requirements
to detail what is to be captured how and when, as well a list of contingencies that would require
additional photographic records (e.g. failure of a component that requires images of the failure(s)
and cause(s) as well as the repair work performed and the final product of that work).
Official Use Only (OUO)
Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official
need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.

More Related Content

Viewers also liked (8)

Joshua-L-Gandy-Resume
Joshua-L-Gandy-ResumeJoshua-L-Gandy-Resume
Joshua-L-Gandy-Resume
 
Magazine analysis
Magazine analysisMagazine analysis
Magazine analysis
 
Bienvenido
BienvenidoBienvenido
Bienvenido
 
Music video
Music videoMusic video
Music video
 
CAÑON PP TURBINA (Sectorial) 1 1/2”- LUXOR SIME
CAÑON PP TURBINA (Sectorial) 1 1/2”- LUXOR SIMECAÑON PP TURBINA (Sectorial) 1 1/2”- LUXOR SIME
CAÑON PP TURBINA (Sectorial) 1 1/2”- LUXOR SIME
 
Anvesh Updated resume-2016
Anvesh Updated resume-2016Anvesh Updated resume-2016
Anvesh Updated resume-2016
 
Aparatos de ortodoncia
Aparatos de ortodonciaAparatos de ortodoncia
Aparatos de ortodoncia
 
E&I_coursework1
E&I_coursework1E&I_coursework1
E&I_coursework1
 

Similar to My Published Government Document SOP-Construction_Photograph_Procedure_Rv2 1 (1)

Daycare construction project
Daycare construction projectDaycare construction project
Daycare construction project
YOUBEJOSEPH
 
Appendix b functionaldesignphasebusinessequirementsdocument021805
Appendix b functionaldesignphasebusinessequirementsdocument021805Appendix b functionaldesignphasebusinessequirementsdocument021805
Appendix b functionaldesignphasebusinessequirementsdocument021805
Udaya Kumar
 
Smart Grid Maturity Model
Smart Grid Maturity ModelSmart Grid Maturity Model
Smart Grid Maturity Model
Durga Telaprolu
 
INFORMATION TECHNOLOGY DISASTER RECOVERY PLAN 1250.docx
INFORMATION TECHNOLOGY DISASTER RECOVERY PLAN 1250.docxINFORMATION TECHNOLOGY DISASTER RECOVERY PLAN 1250.docx
INFORMATION TECHNOLOGY DISASTER RECOVERY PLAN 1250.docx
annettsparrow
 
Sheet1WBSTask Name1Product development1.1 Electronics1.1.1 .docx
Sheet1WBSTask Name1Product development1.1   Electronics1.1.1      .docxSheet1WBSTask Name1Product development1.1   Electronics1.1.1      .docx
Sheet1WBSTask Name1Product development1.1 Electronics1.1.1 .docx
lesleyryder69361
 
general_civil_construction_standard.pdf
general_civil_construction_standard.pdfgeneral_civil_construction_standard.pdf
general_civil_construction_standard.pdf
LuisMogrovejo3
 
general_civil_construction_standard.pdf
general_civil_construction_standard.pdfgeneral_civil_construction_standard.pdf
general_civil_construction_standard.pdf
LuisMogrovejo3
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
toltonkendal
 

Similar to My Published Government Document SOP-Construction_Photograph_Procedure_Rv2 1 (1) (20)

Daycare construction project
Daycare construction projectDaycare construction project
Daycare construction project
 
Engineering symbology prints and drawings 1
Engineering symbology   prints and drawings 1Engineering symbology   prints and drawings 1
Engineering symbology prints and drawings 1
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
Appendix b functionaldesignphasebusinessequirementsdocument021805
Appendix b functionaldesignphasebusinessequirementsdocument021805Appendix b functionaldesignphasebusinessequirementsdocument021805
Appendix b functionaldesignphasebusinessequirementsdocument021805
 
Smart Grid Maturity Model
Smart Grid Maturity ModelSmart Grid Maturity Model
Smart Grid Maturity Model
 
Substationv0
Substationv0Substationv0
Substationv0
 
Aashto guide specifications for lrfd seismic
Aashto guide specifications for lrfd seismicAashto guide specifications for lrfd seismic
Aashto guide specifications for lrfd seismic
 
INFORMATION TECHNOLOGY DISASTER RECOVERY PLAN 1250.docx
INFORMATION TECHNOLOGY DISASTER RECOVERY PLAN 1250.docxINFORMATION TECHNOLOGY DISASTER RECOVERY PLAN 1250.docx
INFORMATION TECHNOLOGY DISASTER RECOVERY PLAN 1250.docx
 
Sheet1WBSTask Name1Product development1.1 Electronics1.1.1 .docx
Sheet1WBSTask Name1Product development1.1   Electronics1.1.1      .docxSheet1WBSTask Name1Product development1.1   Electronics1.1.1      .docx
Sheet1WBSTask Name1Product development1.1 Electronics1.1.1 .docx
 
general_civil_construction_standard.pdf
general_civil_construction_standard.pdfgeneral_civil_construction_standard.pdf
general_civil_construction_standard.pdf
 
general_civil_construction_standard.pdf
general_civil_construction_standard.pdfgeneral_civil_construction_standard.pdf
general_civil_construction_standard.pdf
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
 
90Sep_Pongsuwan
90Sep_Pongsuwan90Sep_Pongsuwan
90Sep_Pongsuwan
 
Tracking Project WBS
Tracking Project WBSTracking Project WBS
Tracking Project WBS
 
TECHNIP
TECHNIPTECHNIP
TECHNIP
 
Geotechnical engineering procedures for foundation
Geotechnical engineering procedures for foundationGeotechnical engineering procedures for foundation
Geotechnical engineering procedures for foundation
 
Standards for Working Drawings
Standards for Working DrawingsStandards for Working Drawings
Standards for Working Drawings
 
Plano gerenciamento da qualidade - exemplo real (em inglês)
Plano gerenciamento da qualidade - exemplo real (em inglês)Plano gerenciamento da qualidade - exemplo real (em inglês)
Plano gerenciamento da qualidade - exemplo real (em inglês)
 
UON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdfUON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdf
 
Procedures
ProceduresProcedures
Procedures
 

My Published Government Document SOP-Construction_Photograph_Procedure_Rv2 1 (1)

  • 1. DOCUMENT: SOP-XX.XX REVISION: 0.1 EFFECTIVE DATE: 9 JANUARY, 2012 DOCUMENT TITLE: CONSTRUCTION REPORTING PROCEDURE: PHOTOGRAPHY AUTHORS: PATRICK HUCKELS, CULMEN INTERNATIONAL LEE FINEWOOD, US DOE/NNSA, DEFENSE NUCLEAR NONPROLIFERATION, OFFICE OF SECOND LINE DEFENSE U.S. Department of Energy National Nuclear Security Administration Defense Nuclear Nonproliferation Office of Second Line Defense CONSTRUCTION REPORTING Standard Operating Procedure for Photographic Recording of Site Construction Activities
  • 2. National Nuclear Security Administration Construction Reporting Procedure: Photography Pg. 2 of 10 Doc Number: [Procedure Template-004###] Rev: [##] U.S. DEPARTMENT OF ENERGY NATIONAL NUCLEAR SECURTY ADMINISTRATION 1000 INDEPENDENCE AVE., SW WASHINGTON, DC 20585 (202) 586-5000 HTTP://WWW.NNSA.ENERGY.GOV/ Official Use Only (OUO) Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
  • 3. National Nuclear Security Administration Construction Reporting Procedure: Photography Pg. 3 of 10 Doc Number: [Procedure Template-004###] Rev: [##] PROCEDURE TEMPLATE Document History REVISION HISTORY AUTHOR REVISED SECTION/PARAGRAPH REV RELEASED [First Last Name] [Initial Release, Section 2, etc] [##) See [Document Control System] APPROVALS All approvals are maintained and controlled in the [Document Control System] system. Please refer to the [Document Control System] system for the current controlled revision and approval records. Name Title Name Title DISTRIBUTION This document has been distributed to: Name Title Name Title Draft and Archived/Obsolete revisions are not to be used. Access [Document Control System] system to verify revision. Official Use Only (OUO) Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
  • 4. National Nuclear Security Administration Construction Reporting Procedure: Photography Pg. 4 of 10 Doc Number: [Procedure Template-004###] Rev: [##] Table of Contents 1. PURPOSE..............................................................................................................................................................................5 2. SCOPE...................................................................................................................................................................................5 3. RESPONSIBILITIES...........................................................................................................................................................5 4. PROCEDURE.......................................................................................................................................................................5 4.1 PROCESS FLOW ...........................................................................................................................................................5 4.2 PROCEDURE..................................................................................................................................................................5 5. DEFINITIONS......................................................................................................................................................................9 6. APPLICABLE REFERENCES...........................................................................................................................................9 7. QUALITY RECORDS.........................................................................................................................................................9 Official Use Only (OUO) Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
  • 5. National Nuclear Security Administration Construction Reporting Procedure: Photography Pg. 5 of 10 Doc Number: [Procedure Template-004###] Rev: [##] 1. PURPOSE This document serves as the Standard Operating Procedures (SOP) for the collection of photographs for site construction activity reporting. It will provide: general requirements of all photographs, including naming and requirements of information to be captured (date, location, subject(s) and activity(ies), direction of view, scale) and required linkages to other documents (i.e. as-builts, finaly construction reports). It will also include, as an appendix, a list of minimum required photographs (and circumstances) including what needs to be captured of what and when (e.g. trenches and all conduits, conduit end cross-sections and post backfill compaction immediately following trenching and before paving). 2. SCOPE Briefly describe the coverage or scope of what is covered and/or exempted from this process. Please refrain from adding policy or procedure detail in this section. 3. RESPONSIBILITIES • Responsible Party – Describe the responsible party responsibilities • Responsible Party – Describe the responsible party responsibilities • DICCE Contractor – will provide photos as prescribed… • Designated Civil & Electrical QC manager will be held responsible for the thorough and timely recording and transmittal of these photographs via Daily Reports and other manners, as necessary. In addition, they shall ensure that these photographs are included in the appropriate locations of appropriate Project documents, such as “as built” drawings and Final Installation Reports. • DOE and Support Contractors – will provide review and further direction, as needed. • ??? - 4. PROCEDURE Use Body Text to add text under Heading 1. 4.1 Process Flow If applicable insert simple process flow chart or picture here. Keep the flowchart descriptions simple putting the detail in the next subsection. If there is not a flow chart or picture write “Not Applicable”. 4.2 Procedure The following paragraphs will define general requirements to be met for all photographs, including information to be captured and required linkages to other documents. Details of images to be captured during particular work types will also be discussed below with a detailed checklist to be compiled in the Appendix. Official Use Only (OUO) Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
  • 6. National Nuclear Security Administration Construction Reporting Procedure: Photography Pg. 6 of 10 Doc Number: [Procedure Template-004###] Rev: [##] 4.2.1 Overview 4.2.1.1 General Requirements: All site construction photographs will share, at a minimum, the following requirements. • Naming of photographs shall include… a uniform, standardized format for photo titling will need to be determined and used during the length of the project. Two (2) possible types are descriptive wording such as ‘casting of concrete_ lane 001_ looking north_date’ or by employing a designated alpha-numeric system with a description adjacent to the photo in the daily work log (photo log). The latter type may be advantageous when incorporating photo titles onto the GA , Red-Line drawings and later incorporation onto the As-Built Final Package Drawings and Final Construction Reports. • The information to be captured in each photograph is to be clear and in a standardized format. The associated photo log for the image will include at least: date, location, subject(s) and activity(ies) captured in the image, the direction of view, what was used for scale and an approximate size (see below for greater detail). • Scalable measurements: the photographs will indicate subject dimensions whenever possible using items such as, but not limited to, measuring tape and objects of known dimensions (e.g. US coins or folders/binders). • Hidden Works Documentation: Photographs will be taken of ALL works that will be eventually hidden from view upon completion. See specific details below for more information. • Additional Photos: The DOE retains the right to request additional photos to be taken in order to clarify ambiguous or problematic photo subject matter. 4.2.1.2 Photographic Records and Project Documents into which they are to be included Required linkages to other documents will be defined here and each photo log will cross- reference the images location and linkage in those other project documents. Incorporation of Photos into Project Documents • Site Survey Photos-GA Drawings: The contractor will give evidence in photographic form, all existing site conditions that are project development related. The photo title will be shown on the initial GA drawings where the DICCE intends on developing or resolving in-situ problems discovered during the site visit(s). o Shall be indicated on the initial submission of the GA drawings giving evidence on how the DICCE will interface with existing site conditions and connections. • QC reports o Concrete pre-pour/placement report o Backfilling report o Compression Tests (28 day, etc.) • Daily Reports: Shall include at least XXX photos indicating daily progress and procedures Official Use Only (OUO) Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
  • 7. National Nuclear Security Administration Construction Reporting Procedure: Photography Pg. 7 of 10 Doc Number: [Procedure Template-004###] Rev: [##] o As indicated above, the DOE will state what is the minimum required photos inserted into the daily report. The DOE will have the right to request for more detailed photos if required. • Red-Line Drawings o Photograph titles will be incorporated onto the red-line drawings indicating in which location and direction the photograph was taken • As-Built Drawings o Will contain all photographic information as per finalized red-line drawings. They may also contain photos taken during the SLAT review at the DOE’s discretion. This is as per SOW sections 1.21/2.2.15 • Construction reports o Any technical drawing or other depiction of an installation, or part thereof, such as foundations, concrete slabs, trenches and conduits, electrical boxes, wiring diagrams, and the like shall include a photograph(s) of the same, as practicable. 4.2.2 Details A detailed checklist of the minimum reporting requirements will be provided in Appendix I. The list is meant to provide guidance by example of what is to be captured, in what detail, how and when, as well a list of contingencies that would require additional photographic records (e.g. failure of a component that requires images of the failure(s) and cause(s) as well as the repair work performed and the final product of that work). It is by no means meant to be exhaustive and additional photographic documentation may be initiated by either DOE or the DICCE Designated Civil & Electrical QC manager onsite. 4.2.2.1 Photograph Content by Work Type Civil Work: All Civil work photos shall contain, but not limited to, the following activities • All photos shall be recorded on concrete pre-pour/placement and/or backfilling report • Excavation condition, location and dimensions • Soil conditions prior to permanent material placement • Reinforcing bar and associated structural material dimensions and placement • Concrete ‘block-out’ dimensions and placement where required • Anchor bolt or other fastener dimensions and placement • Vapor or moisture material placement where required • Dimensions and condition of existing infrastructure materials such as asphalt, concrete or paver pavement , pavement sub-base(s), and fill soil. • Interference of any other existing infrastructure not previously detected during site surveys including sloping towards new construction. • Pavement jointing including thermal control or construction types • Use of construction equipment Official Use Only (OUO) Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
  • 8. National Nuclear Security Administration Construction Reporting Procedure: Photography Pg. 8 of 10 Doc Number: [Procedure Template-004###] Rev: [##] • Pavement sloping indicating rain water moving away from new construction and lack of ponding • Construction material testing such as soil compaction, asphalt and concrete strength tests, concrete slump, at material testing lab or in-situ • Weather related project progress or material impacts • Anchoring of all structural components • Substrate condition prior to the application of horizontal traffic markings Electrical Work: All Electrical work photos shall contain, but not limited to, the following activities: • All photos shall be recorded on the concrete pre-pour/placement or backfilling report • Trenching dimensions and existing conditions • Trench bed preparation including bedding type and thickness • Placement of conduit(s) and/or direct bury cable(s) • Distances between power and communication cables/conduits • Cable type and sizing • Connections of conduits with pull/hand boxes, both above and in-ground • Placement of underground cable/conduit protection devices such as warning tape or tiles • Final backfilling and compaction • Power and Control panel component placement and wiring, including labeling • Panel’s moisture control material/system including drainage type (if required) • Anchoring of all electrical components • Power and communication tie-ins at host country’s panels/boxes • All other connections of infrastructure to host country’s equipment (e.g. antennas) • Earthing/Grounding system(s), materials used and location associated to existing infrastructure • Above ground conduit supports and sub-ups • Conduit or cable penetrations through walls including moisture control techniques • Spare conduits with associated pull strings/rope Technical Solutions (IT and Communications): All technical solutions installation work photos shall contain, but not limited to, the following activities: • ? • ?? • ??? 4.2.2.2 Photographic Content for Other Efforts Official Use Only (OUO) Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
  • 9. National Nuclear Security Administration Construction Reporting Procedure: Photography Pg. 9 of 10 Doc Number: [Procedure Template-004###] Rev: [##] • Safety: The DICCE shall give evidence that they are following established safe construction acts and procedures when performing their work. The use of personal protection equipment (PPE) will be evident in at least weekly photos. 5. DEFINITIONS • Word – Definition • Word – Definition 6. APPLICABLE REFERENCES List of applicable reference documents. • N/A 7. QUALITY RECORDS List of applicable Quality records. • N/A Official Use Only (OUO) Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.
  • 10. National Nuclear Security Administration Construction Reporting Procedure: Photography Pg. 10 of 10 Doc Number: [Procedure Template-004###] Rev: [##] Appendix I This will be a checklist of the minimum (“including but not limited to…”) reporting requirements to detail what is to be captured how and when, as well a list of contingencies that would require additional photographic records (e.g. failure of a component that requires images of the failure(s) and cause(s) as well as the repair work performed and the final product of that work). Official Use Only (OUO) Official Use Only (OUO) is a US Government marking to protect sensitive information. This information is only releasable to individuals with an official need for the document. All draft and/or previous versions of this document are obsolete and should not be used or referenced.