SlideShare a Scribd company logo
1 of 39
Download to read offline
Using the Risk Register in Integrated
    Cost/Schedule Risk Analysis
    with Monte Carlo Simulation

         David T. Hulett, Ph.D.
          Hulett & Associates, LLC
        Dr. Dan Patterson, PMP
                   Acumen

         NASA PM Challenge
          Daytona Beach, FL
         February 24-25, 2009

            © 2009 Hulett & Associates,
                   AcumenPM
Agenda
• Explain “Risk Factors” approach
• Apply Risk Factors to schedule and cost risk
• Apply Risk Factors to simple space vehicle
  development schedule as an example




                   © 2009 Hulett & Associates,
                          AcumenPM
Limitations with the Traditional
  3-point Estimate of Activity Duration
• Typical schedule risk analysis starts with the
  activity that is impacted by risks
  – Estimates the 3-point estimate for optimistic, most
    likely and pessimistic duration
  – Implies the risk is 100% likely with uncertain impact
• Which risks cause the most overall schedule
  risk? Cannot say directly, but indirectly:
  – Sensitivity to activity durations
  – Criticality of activity durations




                     © 2009 Hulett & Associates,
                            AcumenPM
Some Problems with Traditional
             Approach
• Can tell which activities are crucial, but not
  directly which risks are driving
• Makes poor use of the Risk Register that
  is usually available
• Cannot decompose the overall schedule
  risk into its components BY RISK
  – Ability to assign the risk to its specific risk
    drivers helps with communication of risk
    causes and risk mitigation

                   © 2009 Hulett & Associates,
                          AcumenPM
We Propose a Different Approach:
      Start with the Risks Themselves
• Drive the schedule risk by the risks already
  prioritized in the Risk Register
• For each risk, specify:
  – Probability it will occur (NEW)
  – Impact on time if it does (multiplicative factors, allows it to
    affect different duration activities)
  – Assign to the activities it will affect
• Starting with the risks themselves gives us benefits
  – Links qualitative analysis to the quantitative analysis
  – Estimates the impact of specific risks for prioritized
    mitigation purposes
  – Correlations between activities modeled automatically
                        © 2009 Hulett & Associates,
                               AcumenPM
Simple Example of Risk Register Risks




• Use the Risk Factors module in Pertmaster 8
• Collect probability and impact data on risks
• Map the risks to activities


                 © 2009 Hulett & Associates,
                        AcumenPM
Risk Factors Mechanics (1)
• The risk factor is assigned to one or several
  activities, affecting their durations by a
  multiplicative factor
  – E.g., the factor may be .90 for optimistic, 1.0 for most
    likely and 1.25 for pessimistic
  – These factors multiply the schedule durations of the
    activities to which they are assigned
• Risks can be assigned to one or more activities
• Activity durations can be influenced by one or
  more risks
                     © 2009 Hulett & Associates,
                            AcumenPM
Risk Factors Mechanics (2)
• Risk Factors are assigned a probability of
  occurring on any iteration
   – When the risk occurs, the factor used is chosen at
     random from the 3-point estimate and operates on all
     activities to which it is assigned
   – When not occurring on an iteration the risk factor
     takes the value 1.0, a neutral value
• When an activity is influenced by more than one
  risk, their factors are multiplied together, if they
  happen, on any iteration

                    © 2009 Hulett & Associates,
                           AcumenPM
Risk Factor
Probability is 100%, Factor can be + or -

                                       0 0 1 0 - C o n s tr u c tio n : D u r a tio n
                                                                                                      1 0 0% 11 5
                      2 50
                                                                                                      9 5 % 1 11


Here the                                                                                              9 0 % 1 09

                                                                                                      8 5 % 1 08
                                                                                                                                           For the
Ranges are            2 00
                                                                                                      8 0 % 1 06

                                                                                                      7 5 % 1 05
                                                                                                                                           examples we
based on                                                                                              7 0 % 1 04                           use an activity
                                                                                                      6 5 % 1 04
deviations +                                                                                                                               with 100 days




                                                                                                                    Cumulative Frequency
                                                                                                      6 0 % 1 03
                      1 50

and – from                                                                                            5 5 % 1 02
                                                                                                                                           in the
               Hits




                                                                                                      5 0 % 1 01

the Plan.                                                                                             4 5 % 1 01

                                                                                                      4 0 % 1 00
                                                                                                                                           schedule
                      1 00
Probability                                                                                           35% 99

                                                                                                      30% 99
is 100%                                                                                               25% 98

                       50                                                                             20% 97

                                                                                                      15% 96

                                                                                                      10% 95

                                                                                                      5 % 94

                        0                                                                             0 % 90
                             90   95             10 0                  1 05             1 10   11 5
                                            D istrib u tio n (sta rt o f in te rva l)




                                   © 2009 Hulett & Associates,
                                          AcumenPM
Assigning a Probability Less than 100%


                                 0010 - Construction : Duration                                                                             0040 - Technology Design : Duration
                                                                                      100% 115                                                                                             100% 130

Spike                                                                                 95% 107                                                                                              95% 123



contains
                                                                                      90% 103                                  1200                                                        90% 120
                                                                                                                                                                                                                             Spike
                                                                                      85% 101                                                                                              85% 118


70% of
                     2000
                                                                                      80% 100                                                                                              80% 116                           contains
the
                                                                                      75% 100

                                                                                      70% 100
                                                                                                                               1000                                                        75% 114

                                                                                                                                                                                           70% 113
                                                                                                                                                                                                                             40% of
probability
                                                                                      65% 100                                                                                              65% 111
                                                                                                                                                                                                                             the




                                                                                                                                                                                                      Cumulative Frequency
                                                                                                 Cumulative Frequency
                     1500
                                                                                      60% 100                                  800                                                         60% 110

                                                                                      55% 100                                                                                              55% 109                           probability

                                                                                                                        Hits
              Hits




                                                                                      50% 100                                                                                              50% 107

                                                                                      45% 100                                  600                                                         45% 105

                     1000                                                                                                                                                                  40% 100
                                                                                      40% 100

                                                                                      35% 100                                                                                              35% 100

                                                                                      30% 100                                  400                                                         30% 100

                                                                                      25% 100                                                                                              25% 100

                     500                                                              20% 100                                                                                              20% 100

                                                                                      15% 100                                  200                                                         15% 100

                                                                                      10% 99                                                                                               10% 100

                                                                                      5% 97                                                                                                5% 100

                                                                                                                                 0                                                         0% 100
                       0                                                              0% 91
                                                                                                                                      100        110                         120     130
                            95        100              105             110      115
                                    Distribution (start of interval)                                                                              Distribution (start of interval)




                                                                             © 2009 Hulett & Associates,
                                                                                    AcumenPM
Assigning
   More than One Risk to an Activity
• If more than one risk is acting on an
  activity, the resulting ranges are the
  multiplication of the factors
• The activity duration range is derived from
  the risk factors that affect the risk
  – Model how the activity duration range is
    generated
  – Focus on the causes of activity duration
    ranges
                 © 2009 Hulett & Associates,
                        AcumenPM
Two Risks affect One Activity
      using Factors that Occur 100%

                                0040 - T echnology Design : Duration
                                                                                        100% 144

                                                                                        95% 130

                                                                                        90% 127
                    140
                                                                                        85% 124

                                                                                        80% 123

                    120                                                                 75% 121

                                                                                        70% 119

Range               100
                                                                                        65% 118




                                                                                                   Cumulative Frequency
                                                                                        60% 117
from 90 to                                                                              55% 116
             Hits




150 days,            80                                                                 50% 115

                                                                                        45% 114

Peak about           60
                                                                                        40% 113

                                                                                        35% 111
113 days                                                                                30% 110

                     40                                                                 25% 109

                                                                                        20% 108

                                                                                        15% 106
                     20
                                                                                        10% 104

                                                                                        5% 102

                      0                                                                 0% 93
                          100         110              120                  130   140
                                      Distribution (sta rt of inte rva l)


                          © 2009 Hulett & Associates,
                                 AcumenPM
Two Risks with Less than 100%
          Probability Affecting one Activity

                                        0040 - T echnology Design : Duration
                           1100                                                                 100% 144

                                                                                                95% 123


The spike at               1000                                                                 90% 119

                                                                                                85% 116

100 days                    900
                                                                                                80% 113

                                                                                                75% 111
represents (1)              800
                                                                                                70% 110


the likelihood              700
                                                                                                65% 108




                                                                                                           Cumulative Frequency
                                                                                                60% 106

that neither risk           600                                                                 55% 104
                    Hits




                                                                                                50% 102
occurs and (2)              500                                                                 45% 101


the chance that             400
                                                                                                40% 100

                                                                                                35% 100

100 days is                 300
                                                                                                30% 100

                                                                                                25% 100
picked when                 200
                                                                                                20% 100


one or both                 100
                                                                                                15% 100

                                                                                                10% 99

occur                                                                                           5% 97

                              0                                                                 0% 91
                                  100          110               120                130   140
                                              Distribution (sta rt of inte rva l)




                                  © 2009 Hulett & Associates,
                                         AcumenPM
Risk Factors Model How Correlation Occurs
      Coefficients are Calculated (1)
                            Risk #1
                         P = 50%, Factors
                          .95, 1.05, 1.15




         Activity A                            Activity B

                   Activities A and B
                   Correlation is Calculated
                   to be 100%




                 © 2009 Hulett & Associates,
                        AcumenPM
Risk Factors Model How Correlation Occurs
      Coefficients are Calculated (2)
    Risk #2                      Risk #1                      Risk #3
  P = 25%, Factors            P = 50%, Factors              P = 45%, Factors
    .8, .95, 1.05              .95, 1.05, 1.15                1.0, 1.1, 1.2




               Activity A                             Activity B

                            Activities A and B
                            Correlation is Calculated
                            to be 48%

            Correlation is modeled as it is caused in the project
            Correlation coefficients are generated, not guessed

                        © 2009 Hulett & Associates,
                               AcumenPM
Sensitivity to the Risk Factors


The tornado
diagram
focuses on
risks, not
activities




                  © 2009 Hulett & Associates,
                         AcumenPM
Simple 2-Stage Space Vehicle Schedule




          Software used: Pertmaster v. 8
                 © 2009 Hulett & Associates,
                        AcumenPM
Case Study: Simple Space Vehicle
         Development Schedule
•   87 month schedule
•   11 work activities linked, 3 major milestones
•   Beginning 3 March 2008
•   PDR on 11 September 2009
•   CDR on 3 June 2011
•   Delivery to launch site 12 June 2015




                    © 2009 Hulett & Associates,
                           AcumenPM
Two Types of Risk
• Background risk based on typical general
  risk, estimating error
  – Used Quick Risk of -5% and +10%
• Discrete risks derived from Risk Register
  – Summarized from detailed Risk Register
  – These have a probability of occurring and an
    impact on specific activities if they do
  – Parallel to their Risk Register information
  – Risk Register is used in data collection

                 © 2009 Hulett & Associates,
                        AcumenPM
Standard 3-point Range Representing
          Schedule Estimating Error



Background
risk:
Optimistic -5%
Pessimistic
+10%




                 © 2009 Hulett & Associates,
                        AcumenPM
Results with
Schedule Estimating Error Only
                             Spacecraft Program
                            Entire Plan : Finish Date
                                                                          100% 30/Dec/15
                                                                          95% 27/Oct/15
         400
                                                                          90% 15/Oct/15
                                                                          85% 07/Oct/15
                                                                          80% 30/Sep/15
                                                                                                                  Deterministic:
                                                                          75% 24/Sep/15                           12JUN15 is <1%
         300                                                              70% 18/Sep/15




                                                                                           Cumulative Frequency
                                                                          65% 14/Sep/15
                                                                          60% 09/Sep/15
                                                                                                                  P-80 is 30SEP15,
                                                                          55% 04/Sep/15                           about 3.5 months
  Hits




         200
                                                                          50% 01/Sep/15
                                                                          45% 26/Aug/15
                                                                                                                  later than planned
                                                                          40% 21/Aug/15
                                                                          35% 18/Aug/15                           Spread from P-5 to
                                                                          30% 12/Aug/15
                                                                                                                  P-95 is 5JUL15 to
                                                                          25% 07/Aug/15
         100
                                                                          20% 31/Jul/15                           27OCT15 for 3.7
                                                                          15% 24/Jul/15
                                                                          10% 17/Jul/15
                                                                                                                  months
                                                                          5% 06/Jul/15
           0                                                              0% 14/May/15
               31/May/15              08/Sep/15               17/Dec/15
                           Distribution (start of interval)


                                      © 2009 Hulett & Associates,
                                             AcumenPM
Risk Analysis on Space Vehicle Project
   Risk Factors are from Risk Register
                                                  Time Impact Range                   Cost Impact Range
                                  Probability Minimum Most Likely Maximum   Minimum      Most Likely      Maximum
Requirements have not been 
                                    30%       95%       105%      120%
decided
Several alternative designs 
                                    60%       95%       100%      115%
considered
New designs not yet proven          40%       96%       103%      112%
Fabricaton requires new 
                                    50%       96%       105%      115%
materials
Lost know‐how since last full 
                                    30%       95%       100%      105%
spacecraft
Funding from Congress is 
                                    70%       90%       105%      115%
problematic
Schedule for testing is 
                                    100%      100%      120%      130%
aggressive
Cost Risk is based on immature 
                                    100%                                     95%           105%            110%
data


                                            © 2009 Hulett & Associates,
                                                   AcumenPM
Mapping Risks to Activities (1)
                                      FS
                      Requirements                                      FS          Test FS
Risk                                  Preliminary     FS Final Design
                      Definition                                        Fabrication Engine
                                      Design
Requirements Not
                           X
Complete
Alternative Designs
                                             X
Possible
Designs Not Proven                                             X
New Materials in
                                                                            X
Fabrication
Lost Know-How                                                               X
Funding Problematic                          X                 X            X            X
Testing Schedule
                                                                                         X
Aggressive
Cost Estimate is
based on Immature          X                 X                 X            X            X
Data


                                     © 2009 Hulett & Associates,
                                            AcumenPM
Mapping Risks to Activities (2)
                      US
                                    US Final                                                Integratio
Risk                  Preliminary                US Fabrication     US Test   Integration
                                    Design                                                  n Testing
                      Design
Requirements Not
Complete
Alternative Designs
                           X
Possible
Designs Not
                                         X
Proven
New Materials in
                                                         X
Fabrication
Lost Know-How                                            X                         X
Funding
                           X             X               X             X           X            X
Problematic
Testing Schedule
                                                                       X                        X
Aggressive
Cost Estimate is
based on Immature          X             X               X             X           X            X
Data


                                      © 2009 Hulett & Associates,
                                             AcumenPM
Results Adding
   Risk Factors to the Background Risk
                                                        Spacecraft for PMChallenge 2009
                                                            Entire Plan : Finish Date
                                                                                                                           100% 03/May/17
                                  350

                                                                                                                           95% 05/Oct/16


                                                                                                                           90% 11/Aug/16


Baseline 12JUN 15                 300                                                                                      85% 01/Jul/16


                                                                                                                           80% 26/May/16
is only 3% likely                                                                                                          75% 02/May/16

                                  250

The 80th percentile
                                                                                                                           70% 06/Apr/16


                                                                                                                           65% 15/Mar/16


(P-80) is 26MAY16,                                                                                                         60% 24/Feb/16




                                                                                                                                            Cumulative Frequency
                                  200
11.5 months later                                                                                                          55% 04/Feb/16



                           Hits
                                                                                                                           50% 15/Jan/16



Spread P-5 to P-95                150
                                                                                                                           45% 30/Dec/15


                                                                                                                           40% 16/Dec/15

is 13JUL15 to                                                                                                              35% 01/Dec/15


5OCT16, for 15.5                  100
                                                                                                                           30% 16/Nov/15



months                                                                                                                     25% 02/Nov/15


                                                                                                                           20% 15/Oct/15


                                                                                                                           15% 25/Sep/15
                                  50

                                                                                                                           10% 27/Aug/15


                                                                                                                           5% 13/Jul/15


                                   0                                                                                       0% 21/Jan/15
                                        20/Feb/15   08/Sep/15               26/Mar/16              12/Oct/16   30/Apr/17
                                                                Distribution (start of interval)



                      © 2009 Hulett & Associates,
                             AcumenPM
Activity Tornado Chart
                                  from All-In Simulation
                                   Spacecraft for PMChallenge 2009
                                            Duration Sensitivity




       00025 - US Fabrication                                                                81%   Risky Activities:
                                                                                             80%
                                                                                                   Fabrication,
       00011 - FS Fabrication

                                                                                                   Integration, Final
            00028 - Integration                                                          78%
                                                                                                   Design, Preliminary
      00009 - FS Final Design                                                          76%         Design, Testing
                                                                                       76%
                                                                                                   This is the typical
     00023 - US Final Design

                                                                                                   sensitivity analysis of
00021 - US Preliminary Design                                                    69%
                                                                                                   3-point estimating
00007 - FS Preliminary Design                                                    69%




      00012 - Test FS Engine                                               63%




    00029 - Integration Testing                                           62%




              00026 - US Test                                             61%




                                                           © 2009 Hulett & Associates,
                                                                  AcumenPM
Risk Factor Tornado
                                         from All-In Simulation
                                        Driving Schedule Risk Factors



  6 - Funding from Congress is problematic




      4 - Fabricaton requires new materials




            3 - New designs not yet proven
                                                                                              The main RISK,
      7 - Schedule for testing is aggressive
                                                                                              however, is funding
                                                                                              from Congress, which
5 - Lost know-how since last full spacecraft                                                  affects all activities. This
                                                                                              is the main risk to
 2 - Several alternative designs considered
                                                                                              mitigate, if possible
  1 - Requirements have not been decided




                                               0.00   0.20        0.40          0.60   0.80
                                                                  Correlation




                                                             © 2009 Hulett & Associates,
                                                                    AcumenPM
Contribution of
  Each Risk to the Time Contingency (1)
                                  Explain the Contingency to the P-80
                                   P-80 Date                             Contribution of Risk
All Risks In                       26-May-16                Days Saved                % of Contingency
                                   Specific Risks Taken Out in Order
Funding Risk                       22-Jan-16                    125                             36%

Testing Schedule is Aggressive     1-Dec-15                     52                              15%

Design Requires New Materials      28-Oct-15                    34                              10%

New Design Risk                    15-Oct-15                    13                              4%
Alternative Design Risk             6-Oct-15                     9                              3%
Requirements Risk                   1-Oct-15                     5                              1%
Lost Know How Risk                 30-Sep-15                     1                              0%
                                 Background Schedule Estimating Risks
Background Risk                    12-Jun-15                    110                             32%
      Total Contingency                                         349                             100%



                                  © 2009 Hulett & Associates,
                                         AcumenPM
Contribution of
Each Risk to the Time Contingency (2)
                 g                                                                          g
                                                                                                                                                              100%



                                                                                                                                                              90%




                                                                                                       26/May /16
                                                                 01/Dec /15
                     12/J un/15




                                                01/O c t/15
                                                30/Sep/15
                                                06/O c t/15
                                                16/O c t/15
                                                28/O c t/15




                                                                              20/J an/16
                                                                                                                                                              80%



                                                                                                                                                              70%




                                                                                                                                                                     Cum ulative P robability
                                                                                                                                                              60%



                                                                                                                                                              50%



                                                                                                                                                              40%



                                                                                                                                                              30%



                                                                                                                                                              20%



                                                                                                                                                              10%



                                                                                                                                                              0%
   06/ Apr/ 15                    15/ Jul/ 15      23/ Oct/ 15                31/ Jan/ 16       10/ May/ 16         18/ Aug/ 16   26/ Nov/ 16   06/ Mar/ 17




                                                              © 2009 Hulett & Associates,
                                                                     AcumenPM
Resources and Cost

Estimate is
$6.86 billion




                    © 2009 Hulett & Associates,
                           AcumenPM
Cost Risk Results
                                                    Spacecraft for PMChallenge 2009
                                                          Entire Plan : Cost
                                                                                                             100% $9,283,008,684


                                                                                                             95% $8,429,356,166
                                  650

                                                                                                             90% $8,234,937,806

Baseline $6.86 billion            600
                                                                                                             85% $8,088,750,149



is only 5% likely                 550
                                                                                                             80% $7,976,966,619


                                                                                                             75% $7,890,603,866

                                  500

The 80th percentile                                                                                          70% $7,813,239,105


                                  450                                                                        65% $7,749,200,097

(P-80) is $7.98 B for                                                                                        60% $7,687,432,085




                                                                                                                                   Cumulative Frequency
a $1.1 B contingency       Hits
                                  400
                                                                                                             55% $7,630,117,222


                                  350                                                                        50% $7,568,332,545


Spread P-5 to P-95                300
                                                                                                             45% $7,514,273,968



is $6.86 to $8.43, for            250
                                                                                                             40% $7,452,396,460


                                                                                                             35% $7,391,997,593

$1.57 B                           200
                                                                                                             30% $7,331,963,666


                                                                                                             25% $7,258,107,546

                                  150
                                                                                                             20% $7,188,049,098


                                  100                                                                        15% $7,101,752,271


                                                                                                             10% $7,007,130,725
                                   50
                                                                                                             5% $6,861,086,752


                                   0                                                                         0% $6,189,493,454
                                        $7,000,000,000                 $8,000,000,000       $9,000,000,000
                                                         Distribution (start of interval)



                         © 2009 Hulett & Associates,
                                AcumenPM
Contribution of
Each Risk to the Cost Contingency
                 Contributions of Individual Risks to Cost Risk
All Risks                                                         $ millions
Cost Risk is based on immature data                                  287
Funding from Congress is problematic                                 277
Fabricaton requires new materials                                    168
Schedule Estimate inaccurate                                         110
Schedule for testing is aggressive                                    63
New designs not yet proven                                            31
Lost know‐how since last full spacecraft                              2
Several alternative designs considered                                1
Requirements have not been decided                                    0


                          © 2009 Hulett & Associates,
                                 AcumenPM
Scatter Diagram of Time and Cost
                                                                                                                    Spacecraft for PMChallenge 2009
                                                            Deterministic Point                                                      Inside both limits                                  Outside both limits

                                                                                       3%

There is a 94%                         $9,200,000,000
                                                         1%                                                                                                                                                    94%


chance of                              $9,000,000,000


overrunning both                       $8,800,000,000



cost and                               $8,600,000,000



schedule                               $8,400,000,000



Notice the slope                       $8,200,000,000




of the scatter –                       $8,000,000,000
                   Entire Plan: Cost




time drives cost                       $7,800,000,000




in this model                          $7,600,000,000



                                       $7,400,000,000



                                       $7,200,000,000



                                       $7,000,000,000

                                                                                                                                                                                                                     5%
                                       $6,800,000,000   $6,861,500,000



                                       $6,600,000,000



                                       $6,400,000,000


                                                         2%                               12/ Jun/ 15                                                                                                          3%
                                       $6,200,000,000
                                                              20/Feb/15           31/May/15             08/Sep/15       17/Dec/15               26/Mar/16   04/Jul/16   12/Oct/16   20/Jan/17                  30/Apr/17
                                                                                                                                    Entire Plan: Finish




                                                                                     © 2009 Hulett & Associates,
                                                                                            AcumenPM
Probabilistic Cash Flow
                                                                                                                                 Resource Flow for Cost
                                                                                                                                              Filter: Entire Plan

                       Mean                                                                                                                 P20                                                                                                                                                           P80




This monthly                                                                                                                                                                                                                                                                                                              9,000,000,000


probabilistic cash
                                                                                                                                                                                                                                                                                                                          8,000,000,000

flow can be
compared to the                                                                                  Deterministic Cost: $6,861,500,000                                                                                                                                                                                       7,000,000,000




budget to adjust the                                                                                                                                                                                                                                                                                                      6,000,000,000


spending patterns




                                                                                                                                                                                                                                                                                                                                          Cu m u lative
                                                                                                                                                                                                                                                                                                                          5,000,000,000

when considering




                                                                                                                                                                                                                        D eterm inis tic F inis h: 12/J un/15
risk                                                                                                                                                                                                                                                                                                                      4,000,000,000




                                                                                                                                                                                                                                                                                                                          3,000,000,000




                                                                                                                                                                                                                                                                                                                          2,000,000,000




                                                                                                                                                                                                                                                                                                                          1,000,000,000




                                                                                                                                                                                                                                                                                                                           0
                        26/ Jul/ 08   11/ Feb/ 09   30/ Aug/ 09   18/ Mar/ 10   04/ Oct/ 10   22/ Apr/ 11    08/ Nov/ 11      26/ May/ 12    12/ Dec/ 12        30/ Jun/ 13   16/ Jan/ 14   04/ Aug/ 14   20/ Feb/ 15                                           08/ Sep/ 15   26/ Mar/ 16   12/ Oct/ 16         30/ Apr/ 17
                                                                                                                                            Time




                                                         © 2009 Hulett & Associates,
                                                                AcumenPM
Probabilistic Cash Flow
Compared to Planned




      © 2009 Hulett & Associates,
             AcumenPM
Summary (1)
• The focus is on the risks, not their impact
• Risks “explain” the need for a contingency
• Management appreciates this focus on
  risks
• Risk interviews are conducted at 10,000
  foot level, where people typically think of
  risk
• Interviews go faster, stick to the substance
                © 2009 Hulett & Associates,
                       AcumenPM
Summary (2)
• Use Risk Register for quantitative analysis
• Specific risks can be quantified and assigned to
  schedule activities
  – Quantification is probability and impact
  – A risk can affect several activities
  – An activity can be affected by several risks
• Risk Factors can be combined with other more
  traditional approaches such as 3-point estimates
  for background risk or probabilistic branching


                    © 2009 Hulett & Associates,
                           AcumenPM
Summary (3)
• Schedule uncertainty creates cost
  uncertainty
• Analysis of cost simultaneously with time
  requires inserting the budget/resources
  into the schedule and simulating both
  together
• More accurate cost risk analysis and full
  appreciation of the role of schedule risk in
  creating cost risk
                 © 2009 Hulett & Associates,
                        AcumenPM
Using the Risk Register in Integrated
    Cost/Schedule Risk Analysis
    with Monte Carlo Simulation

         David T. Hulett, Ph.D.
          Hulett & Associates, LLC
        Dr. Dan Patterson, PMP
                 Acumenpm

         NASA PM Challenge
          Daytona Beach, FL
         February 24-25, 2009

            © 2009 Hulett & Associates,
                   AcumenPM

More Related Content

Viewers also liked

Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Fuller.david
Fuller.davidFuller.david
Fuller.davidNASAPMC
 
Neil.dennehy
Neil.dennehyNeil.dennehy
Neil.dennehyNASAPMC
 
Frost.jim
Frost.jimFrost.jim
Frost.jimNASAPMC
 
Arthur.chmielewski
Arthur.chmielewskiArthur.chmielewski
Arthur.chmielewskiNASAPMC
 
Shinn.s.hunter.h
Shinn.s.hunter.hShinn.s.hunter.h
Shinn.s.hunter.hNASAPMC
 
Graybill.michael
Graybill.michaelGraybill.michael
Graybill.michaelNASAPMC
 
Carmichael.kevin
Carmichael.kevinCarmichael.kevin
Carmichael.kevinNASAPMC
 
Chen.tim
Chen.timChen.tim
Chen.timNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
York.melba
York.melbaYork.melba
York.melbaNASAPMC
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.ciolettiNASAPMC
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzalesNASAPMC
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidyNASAPMC
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vinceNASAPMC
 
James.smith
James.smithJames.smith
James.smithNASAPMC
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathyNASAPMC
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNASAPMC
 
Inter mitchell
Inter mitchellInter mitchell
Inter mitchellNASAPMC
 

Viewers also liked (20)

Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Lukas
LukasLukas
Lukas
 
Fuller.david
Fuller.davidFuller.david
Fuller.david
 
Neil.dennehy
Neil.dennehyNeil.dennehy
Neil.dennehy
 
Frost.jim
Frost.jimFrost.jim
Frost.jim
 
Arthur.chmielewski
Arthur.chmielewskiArthur.chmielewski
Arthur.chmielewski
 
Shinn.s.hunter.h
Shinn.s.hunter.hShinn.s.hunter.h
Shinn.s.hunter.h
 
Graybill.michael
Graybill.michaelGraybill.michael
Graybill.michael
 
Carmichael.kevin
Carmichael.kevinCarmichael.kevin
Carmichael.kevin
 
Chen.tim
Chen.timChen.tim
Chen.tim
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
York.melba
York.melbaYork.melba
York.melba
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.cioletti
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzales
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidy
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vince
 
James.smith
James.smithJames.smith
James.smith
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathy
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_case
 
Inter mitchell
Inter mitchellInter mitchell
Inter mitchell
 

More from NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

More from NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Recently uploaded

Instant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School SpiritInstant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School Spiritegoetzinger
 
The Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfThe Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfGale Pooley
 
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...Pooja Nehwal
 
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...Call Girls in Nagpur High Profile
 
Vip Call US 📞 7738631006 ✅Call Girls In Sakinaka ( Mumbai )
Vip Call US 📞 7738631006 ✅Call Girls In Sakinaka ( Mumbai )Vip Call US 📞 7738631006 ✅Call Girls In Sakinaka ( Mumbai )
Vip Call US 📞 7738631006 ✅Call Girls In Sakinaka ( Mumbai )Pooja Nehwal
 
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsHigh Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Top Rated Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...
Top Rated  Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...Top Rated  Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...
Top Rated Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...Call Girls in Nagpur High Profile
 
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...Suhani Kapoor
 
Booking open Available Pune Call Girls Wadgaon Sheri 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Wadgaon Sheri  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Wadgaon Sheri  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Wadgaon Sheri 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
The Economic History of the U.S. Lecture 18.pdf
The Economic History of the U.S. Lecture 18.pdfThe Economic History of the U.S. Lecture 18.pdf
The Economic History of the U.S. Lecture 18.pdfGale Pooley
 
05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx
05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx
05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptxFinTech Belgium
 
The Economic History of the U.S. Lecture 26.pdf
The Economic History of the U.S. Lecture 26.pdfThe Economic History of the U.S. Lecture 26.pdf
The Economic History of the U.S. Lecture 26.pdfGale Pooley
 
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...ssifa0344
 
CALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual serviceanilsa9823
 
The Economic History of the U.S. Lecture 22.pdf
The Economic History of the U.S. Lecture 22.pdfThe Economic History of the U.S. Lecture 22.pdf
The Economic History of the U.S. Lecture 22.pdfGale Pooley
 
The Economic History of the U.S. Lecture 20.pdf
The Economic History of the U.S. Lecture 20.pdfThe Economic History of the U.S. Lecture 20.pdf
The Economic History of the U.S. Lecture 20.pdfGale Pooley
 
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 

Recently uploaded (20)

Instant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School SpiritInstant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School Spirit
 
The Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfThe Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdf
 
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
 
Veritas Interim Report 1 January–31 March 2024
Veritas Interim Report 1 January–31 March 2024Veritas Interim Report 1 January–31 March 2024
Veritas Interim Report 1 January–31 March 2024
 
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...
 
Vip Call US 📞 7738631006 ✅Call Girls In Sakinaka ( Mumbai )
Vip Call US 📞 7738631006 ✅Call Girls In Sakinaka ( Mumbai )Vip Call US 📞 7738631006 ✅Call Girls In Sakinaka ( Mumbai )
Vip Call US 📞 7738631006 ✅Call Girls In Sakinaka ( Mumbai )
 
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsHigh Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Top Rated Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...
Top Rated  Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...Top Rated  Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...
Top Rated Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...
 
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
 
Booking open Available Pune Call Girls Wadgaon Sheri 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Wadgaon Sheri  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Wadgaon Sheri  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Wadgaon Sheri 6297143586 Call Hot Ind...
 
The Economic History of the U.S. Lecture 18.pdf
The Economic History of the U.S. Lecture 18.pdfThe Economic History of the U.S. Lecture 18.pdf
The Economic History of the U.S. Lecture 18.pdf
 
05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx
05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx
05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx
 
The Economic History of the U.S. Lecture 26.pdf
The Economic History of the U.S. Lecture 26.pdfThe Economic History of the U.S. Lecture 26.pdf
The Economic History of the U.S. Lecture 26.pdf
 
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
 
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
 
CALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual service
 
The Economic History of the U.S. Lecture 22.pdf
The Economic History of the U.S. Lecture 22.pdfThe Economic History of the U.S. Lecture 22.pdf
The Economic History of the U.S. Lecture 22.pdf
 
Commercial Bank Economic Capsule - April 2024
Commercial Bank Economic Capsule - April 2024Commercial Bank Economic Capsule - April 2024
Commercial Bank Economic Capsule - April 2024
 
The Economic History of the U.S. Lecture 20.pdf
The Economic History of the U.S. Lecture 20.pdfThe Economic History of the U.S. Lecture 20.pdf
The Economic History of the U.S. Lecture 20.pdf
 
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
 

Patterson.dan

  • 1. Using the Risk Register in Integrated Cost/Schedule Risk Analysis with Monte Carlo Simulation David T. Hulett, Ph.D. Hulett & Associates, LLC Dr. Dan Patterson, PMP Acumen NASA PM Challenge Daytona Beach, FL February 24-25, 2009 © 2009 Hulett & Associates, AcumenPM
  • 2. Agenda • Explain “Risk Factors” approach • Apply Risk Factors to schedule and cost risk • Apply Risk Factors to simple space vehicle development schedule as an example © 2009 Hulett & Associates, AcumenPM
  • 3. Limitations with the Traditional 3-point Estimate of Activity Duration • Typical schedule risk analysis starts with the activity that is impacted by risks – Estimates the 3-point estimate for optimistic, most likely and pessimistic duration – Implies the risk is 100% likely with uncertain impact • Which risks cause the most overall schedule risk? Cannot say directly, but indirectly: – Sensitivity to activity durations – Criticality of activity durations © 2009 Hulett & Associates, AcumenPM
  • 4. Some Problems with Traditional Approach • Can tell which activities are crucial, but not directly which risks are driving • Makes poor use of the Risk Register that is usually available • Cannot decompose the overall schedule risk into its components BY RISK – Ability to assign the risk to its specific risk drivers helps with communication of risk causes and risk mitigation © 2009 Hulett & Associates, AcumenPM
  • 5. We Propose a Different Approach: Start with the Risks Themselves • Drive the schedule risk by the risks already prioritized in the Risk Register • For each risk, specify: – Probability it will occur (NEW) – Impact on time if it does (multiplicative factors, allows it to affect different duration activities) – Assign to the activities it will affect • Starting with the risks themselves gives us benefits – Links qualitative analysis to the quantitative analysis – Estimates the impact of specific risks for prioritized mitigation purposes – Correlations between activities modeled automatically © 2009 Hulett & Associates, AcumenPM
  • 6. Simple Example of Risk Register Risks • Use the Risk Factors module in Pertmaster 8 • Collect probability and impact data on risks • Map the risks to activities © 2009 Hulett & Associates, AcumenPM
  • 7. Risk Factors Mechanics (1) • The risk factor is assigned to one or several activities, affecting their durations by a multiplicative factor – E.g., the factor may be .90 for optimistic, 1.0 for most likely and 1.25 for pessimistic – These factors multiply the schedule durations of the activities to which they are assigned • Risks can be assigned to one or more activities • Activity durations can be influenced by one or more risks © 2009 Hulett & Associates, AcumenPM
  • 8. Risk Factors Mechanics (2) • Risk Factors are assigned a probability of occurring on any iteration – When the risk occurs, the factor used is chosen at random from the 3-point estimate and operates on all activities to which it is assigned – When not occurring on an iteration the risk factor takes the value 1.0, a neutral value • When an activity is influenced by more than one risk, their factors are multiplied together, if they happen, on any iteration © 2009 Hulett & Associates, AcumenPM
  • 9. Risk Factor Probability is 100%, Factor can be + or - 0 0 1 0 - C o n s tr u c tio n : D u r a tio n 1 0 0% 11 5 2 50 9 5 % 1 11 Here the 9 0 % 1 09 8 5 % 1 08 For the Ranges are 2 00 8 0 % 1 06 7 5 % 1 05 examples we based on 7 0 % 1 04 use an activity 6 5 % 1 04 deviations + with 100 days Cumulative Frequency 6 0 % 1 03 1 50 and – from 5 5 % 1 02 in the Hits 5 0 % 1 01 the Plan. 4 5 % 1 01 4 0 % 1 00 schedule 1 00 Probability 35% 99 30% 99 is 100% 25% 98 50 20% 97 15% 96 10% 95 5 % 94 0 0 % 90 90 95 10 0 1 05 1 10 11 5 D istrib u tio n (sta rt o f in te rva l) © 2009 Hulett & Associates, AcumenPM
  • 10. Assigning a Probability Less than 100% 0010 - Construction : Duration 0040 - Technology Design : Duration 100% 115 100% 130 Spike 95% 107 95% 123 contains 90% 103 1200 90% 120 Spike 85% 101 85% 118 70% of 2000 80% 100 80% 116 contains the 75% 100 70% 100 1000 75% 114 70% 113 40% of probability 65% 100 65% 111 the Cumulative Frequency Cumulative Frequency 1500 60% 100 800 60% 110 55% 100 55% 109 probability Hits Hits 50% 100 50% 107 45% 100 600 45% 105 1000 40% 100 40% 100 35% 100 35% 100 30% 100 400 30% 100 25% 100 25% 100 500 20% 100 20% 100 15% 100 200 15% 100 10% 99 10% 100 5% 97 5% 100 0 0% 100 0 0% 91 100 110 120 130 95 100 105 110 115 Distribution (start of interval) Distribution (start of interval) © 2009 Hulett & Associates, AcumenPM
  • 11. Assigning More than One Risk to an Activity • If more than one risk is acting on an activity, the resulting ranges are the multiplication of the factors • The activity duration range is derived from the risk factors that affect the risk – Model how the activity duration range is generated – Focus on the causes of activity duration ranges © 2009 Hulett & Associates, AcumenPM
  • 12. Two Risks affect One Activity using Factors that Occur 100% 0040 - T echnology Design : Duration 100% 144 95% 130 90% 127 140 85% 124 80% 123 120 75% 121 70% 119 Range 100 65% 118 Cumulative Frequency 60% 117 from 90 to 55% 116 Hits 150 days, 80 50% 115 45% 114 Peak about 60 40% 113 35% 111 113 days 30% 110 40 25% 109 20% 108 15% 106 20 10% 104 5% 102 0 0% 93 100 110 120 130 140 Distribution (sta rt of inte rva l) © 2009 Hulett & Associates, AcumenPM
  • 13. Two Risks with Less than 100% Probability Affecting one Activity 0040 - T echnology Design : Duration 1100 100% 144 95% 123 The spike at 1000 90% 119 85% 116 100 days 900 80% 113 75% 111 represents (1) 800 70% 110 the likelihood 700 65% 108 Cumulative Frequency 60% 106 that neither risk 600 55% 104 Hits 50% 102 occurs and (2) 500 45% 101 the chance that 400 40% 100 35% 100 100 days is 300 30% 100 25% 100 picked when 200 20% 100 one or both 100 15% 100 10% 99 occur 5% 97 0 0% 91 100 110 120 130 140 Distribution (sta rt of inte rva l) © 2009 Hulett & Associates, AcumenPM
  • 14. Risk Factors Model How Correlation Occurs Coefficients are Calculated (1) Risk #1 P = 50%, Factors .95, 1.05, 1.15 Activity A Activity B Activities A and B Correlation is Calculated to be 100% © 2009 Hulett & Associates, AcumenPM
  • 15. Risk Factors Model How Correlation Occurs Coefficients are Calculated (2) Risk #2 Risk #1 Risk #3 P = 25%, Factors P = 50%, Factors P = 45%, Factors .8, .95, 1.05 .95, 1.05, 1.15 1.0, 1.1, 1.2 Activity A Activity B Activities A and B Correlation is Calculated to be 48% Correlation is modeled as it is caused in the project Correlation coefficients are generated, not guessed © 2009 Hulett & Associates, AcumenPM
  • 16. Sensitivity to the Risk Factors The tornado diagram focuses on risks, not activities © 2009 Hulett & Associates, AcumenPM
  • 17. Simple 2-Stage Space Vehicle Schedule Software used: Pertmaster v. 8 © 2009 Hulett & Associates, AcumenPM
  • 18. Case Study: Simple Space Vehicle Development Schedule • 87 month schedule • 11 work activities linked, 3 major milestones • Beginning 3 March 2008 • PDR on 11 September 2009 • CDR on 3 June 2011 • Delivery to launch site 12 June 2015 © 2009 Hulett & Associates, AcumenPM
  • 19. Two Types of Risk • Background risk based on typical general risk, estimating error – Used Quick Risk of -5% and +10% • Discrete risks derived from Risk Register – Summarized from detailed Risk Register – These have a probability of occurring and an impact on specific activities if they do – Parallel to their Risk Register information – Risk Register is used in data collection © 2009 Hulett & Associates, AcumenPM
  • 20. Standard 3-point Range Representing Schedule Estimating Error Background risk: Optimistic -5% Pessimistic +10% © 2009 Hulett & Associates, AcumenPM
  • 21. Results with Schedule Estimating Error Only Spacecraft Program Entire Plan : Finish Date 100% 30/Dec/15 95% 27/Oct/15 400 90% 15/Oct/15 85% 07/Oct/15 80% 30/Sep/15 Deterministic: 75% 24/Sep/15 12JUN15 is <1% 300 70% 18/Sep/15 Cumulative Frequency 65% 14/Sep/15 60% 09/Sep/15 P-80 is 30SEP15, 55% 04/Sep/15 about 3.5 months Hits 200 50% 01/Sep/15 45% 26/Aug/15 later than planned 40% 21/Aug/15 35% 18/Aug/15 Spread from P-5 to 30% 12/Aug/15 P-95 is 5JUL15 to 25% 07/Aug/15 100 20% 31/Jul/15 27OCT15 for 3.7 15% 24/Jul/15 10% 17/Jul/15 months 5% 06/Jul/15 0 0% 14/May/15 31/May/15 08/Sep/15 17/Dec/15 Distribution (start of interval) © 2009 Hulett & Associates, AcumenPM
  • 22. Risk Analysis on Space Vehicle Project Risk Factors are from Risk Register Time Impact Range Cost Impact Range Probability Minimum Most Likely Maximum Minimum Most Likely Maximum Requirements have not been  30% 95% 105% 120% decided Several alternative designs  60% 95% 100% 115% considered New designs not yet proven 40% 96% 103% 112% Fabricaton requires new  50% 96% 105% 115% materials Lost know‐how since last full  30% 95% 100% 105% spacecraft Funding from Congress is  70% 90% 105% 115% problematic Schedule for testing is  100% 100% 120% 130% aggressive Cost Risk is based on immature  100% 95% 105% 110% data © 2009 Hulett & Associates, AcumenPM
  • 23. Mapping Risks to Activities (1) FS Requirements FS Test FS Risk Preliminary FS Final Design Definition Fabrication Engine Design Requirements Not X Complete Alternative Designs X Possible Designs Not Proven X New Materials in X Fabrication Lost Know-How X Funding Problematic X X X X Testing Schedule X Aggressive Cost Estimate is based on Immature X X X X X Data © 2009 Hulett & Associates, AcumenPM
  • 24. Mapping Risks to Activities (2) US US Final Integratio Risk Preliminary US Fabrication US Test Integration Design n Testing Design Requirements Not Complete Alternative Designs X Possible Designs Not X Proven New Materials in X Fabrication Lost Know-How X X Funding X X X X X X Problematic Testing Schedule X X Aggressive Cost Estimate is based on Immature X X X X X X Data © 2009 Hulett & Associates, AcumenPM
  • 25. Results Adding Risk Factors to the Background Risk Spacecraft for PMChallenge 2009 Entire Plan : Finish Date 100% 03/May/17 350 95% 05/Oct/16 90% 11/Aug/16 Baseline 12JUN 15 300 85% 01/Jul/16 80% 26/May/16 is only 3% likely 75% 02/May/16 250 The 80th percentile 70% 06/Apr/16 65% 15/Mar/16 (P-80) is 26MAY16, 60% 24/Feb/16 Cumulative Frequency 200 11.5 months later 55% 04/Feb/16 Hits 50% 15/Jan/16 Spread P-5 to P-95 150 45% 30/Dec/15 40% 16/Dec/15 is 13JUL15 to 35% 01/Dec/15 5OCT16, for 15.5 100 30% 16/Nov/15 months 25% 02/Nov/15 20% 15/Oct/15 15% 25/Sep/15 50 10% 27/Aug/15 5% 13/Jul/15 0 0% 21/Jan/15 20/Feb/15 08/Sep/15 26/Mar/16 12/Oct/16 30/Apr/17 Distribution (start of interval) © 2009 Hulett & Associates, AcumenPM
  • 26. Activity Tornado Chart from All-In Simulation Spacecraft for PMChallenge 2009 Duration Sensitivity 00025 - US Fabrication 81% Risky Activities: 80% Fabrication, 00011 - FS Fabrication Integration, Final 00028 - Integration 78% Design, Preliminary 00009 - FS Final Design 76% Design, Testing 76% This is the typical 00023 - US Final Design sensitivity analysis of 00021 - US Preliminary Design 69% 3-point estimating 00007 - FS Preliminary Design 69% 00012 - Test FS Engine 63% 00029 - Integration Testing 62% 00026 - US Test 61% © 2009 Hulett & Associates, AcumenPM
  • 27. Risk Factor Tornado from All-In Simulation Driving Schedule Risk Factors 6 - Funding from Congress is problematic 4 - Fabricaton requires new materials 3 - New designs not yet proven The main RISK, 7 - Schedule for testing is aggressive however, is funding from Congress, which 5 - Lost know-how since last full spacecraft affects all activities. This is the main risk to 2 - Several alternative designs considered mitigate, if possible 1 - Requirements have not been decided 0.00 0.20 0.40 0.60 0.80 Correlation © 2009 Hulett & Associates, AcumenPM
  • 28. Contribution of Each Risk to the Time Contingency (1) Explain the Contingency to the P-80 P-80 Date Contribution of Risk All Risks In 26-May-16 Days Saved % of Contingency Specific Risks Taken Out in Order Funding Risk 22-Jan-16 125 36% Testing Schedule is Aggressive 1-Dec-15 52 15% Design Requires New Materials 28-Oct-15 34 10% New Design Risk 15-Oct-15 13 4% Alternative Design Risk 6-Oct-15 9 3% Requirements Risk 1-Oct-15 5 1% Lost Know How Risk 30-Sep-15 1 0% Background Schedule Estimating Risks Background Risk 12-Jun-15 110 32% Total Contingency 349 100% © 2009 Hulett & Associates, AcumenPM
  • 29. Contribution of Each Risk to the Time Contingency (2) g g 100% 90% 26/May /16 01/Dec /15 12/J un/15 01/O c t/15 30/Sep/15 06/O c t/15 16/O c t/15 28/O c t/15 20/J an/16 80% 70% Cum ulative P robability 60% 50% 40% 30% 20% 10% 0% 06/ Apr/ 15 15/ Jul/ 15 23/ Oct/ 15 31/ Jan/ 16 10/ May/ 16 18/ Aug/ 16 26/ Nov/ 16 06/ Mar/ 17 © 2009 Hulett & Associates, AcumenPM
  • 30. Resources and Cost Estimate is $6.86 billion © 2009 Hulett & Associates, AcumenPM
  • 31. Cost Risk Results Spacecraft for PMChallenge 2009 Entire Plan : Cost 100% $9,283,008,684 95% $8,429,356,166 650 90% $8,234,937,806 Baseline $6.86 billion 600 85% $8,088,750,149 is only 5% likely 550 80% $7,976,966,619 75% $7,890,603,866 500 The 80th percentile 70% $7,813,239,105 450 65% $7,749,200,097 (P-80) is $7.98 B for 60% $7,687,432,085 Cumulative Frequency a $1.1 B contingency Hits 400 55% $7,630,117,222 350 50% $7,568,332,545 Spread P-5 to P-95 300 45% $7,514,273,968 is $6.86 to $8.43, for 250 40% $7,452,396,460 35% $7,391,997,593 $1.57 B 200 30% $7,331,963,666 25% $7,258,107,546 150 20% $7,188,049,098 100 15% $7,101,752,271 10% $7,007,130,725 50 5% $6,861,086,752 0 0% $6,189,493,454 $7,000,000,000 $8,000,000,000 $9,000,000,000 Distribution (start of interval) © 2009 Hulett & Associates, AcumenPM
  • 32. Contribution of Each Risk to the Cost Contingency Contributions of Individual Risks to Cost Risk All Risks $ millions Cost Risk is based on immature data 287 Funding from Congress is problematic 277 Fabricaton requires new materials 168 Schedule Estimate inaccurate 110 Schedule for testing is aggressive 63 New designs not yet proven 31 Lost know‐how since last full spacecraft 2 Several alternative designs considered 1 Requirements have not been decided 0 © 2009 Hulett & Associates, AcumenPM
  • 33. Scatter Diagram of Time and Cost Spacecraft for PMChallenge 2009 Deterministic Point Inside both limits Outside both limits 3% There is a 94% $9,200,000,000 1% 94% chance of $9,000,000,000 overrunning both $8,800,000,000 cost and $8,600,000,000 schedule $8,400,000,000 Notice the slope $8,200,000,000 of the scatter – $8,000,000,000 Entire Plan: Cost time drives cost $7,800,000,000 in this model $7,600,000,000 $7,400,000,000 $7,200,000,000 $7,000,000,000 5% $6,800,000,000 $6,861,500,000 $6,600,000,000 $6,400,000,000 2% 12/ Jun/ 15 3% $6,200,000,000 20/Feb/15 31/May/15 08/Sep/15 17/Dec/15 26/Mar/16 04/Jul/16 12/Oct/16 20/Jan/17 30/Apr/17 Entire Plan: Finish © 2009 Hulett & Associates, AcumenPM
  • 34. Probabilistic Cash Flow Resource Flow for Cost Filter: Entire Plan Mean P20 P80 This monthly 9,000,000,000 probabilistic cash 8,000,000,000 flow can be compared to the Deterministic Cost: $6,861,500,000 7,000,000,000 budget to adjust the 6,000,000,000 spending patterns Cu m u lative 5,000,000,000 when considering D eterm inis tic F inis h: 12/J un/15 risk 4,000,000,000 3,000,000,000 2,000,000,000 1,000,000,000 0 26/ Jul/ 08 11/ Feb/ 09 30/ Aug/ 09 18/ Mar/ 10 04/ Oct/ 10 22/ Apr/ 11 08/ Nov/ 11 26/ May/ 12 12/ Dec/ 12 30/ Jun/ 13 16/ Jan/ 14 04/ Aug/ 14 20/ Feb/ 15 08/ Sep/ 15 26/ Mar/ 16 12/ Oct/ 16 30/ Apr/ 17 Time © 2009 Hulett & Associates, AcumenPM
  • 35. Probabilistic Cash Flow Compared to Planned © 2009 Hulett & Associates, AcumenPM
  • 36. Summary (1) • The focus is on the risks, not their impact • Risks “explain” the need for a contingency • Management appreciates this focus on risks • Risk interviews are conducted at 10,000 foot level, where people typically think of risk • Interviews go faster, stick to the substance © 2009 Hulett & Associates, AcumenPM
  • 37. Summary (2) • Use Risk Register for quantitative analysis • Specific risks can be quantified and assigned to schedule activities – Quantification is probability and impact – A risk can affect several activities – An activity can be affected by several risks • Risk Factors can be combined with other more traditional approaches such as 3-point estimates for background risk or probabilistic branching © 2009 Hulett & Associates, AcumenPM
  • 38. Summary (3) • Schedule uncertainty creates cost uncertainty • Analysis of cost simultaneously with time requires inserting the budget/resources into the schedule and simulating both together • More accurate cost risk analysis and full appreciation of the role of schedule risk in creating cost risk © 2009 Hulett & Associates, AcumenPM
  • 39. Using the Risk Register in Integrated Cost/Schedule Risk Analysis with Monte Carlo Simulation David T. Hulett, Ph.D. Hulett & Associates, LLC Dr. Dan Patterson, PMP Acumenpm NASA PM Challenge Daytona Beach, FL February 24-25, 2009 © 2009 Hulett & Associates, AcumenPM