MURUGAN MUNUSAMY
Position: OPERATION MANAGER – PROJECTS DEPARTMENT
Date of Birth: 11th
April 1972
Nationality: Malaysian
Email muruganmunusami@gmail.com
TRAINING
1. Contract Management
2. Basic maintenance and operation of Diamond Wire Cutting machine.
3. Construction Industry Development Board Malaysia
4. H2S Awareness & Escape, Petroleum Development of Oman
5. Permit Holder course, Petroleum Development of Oman
6. Job Hazard Analysis, Petroleum Development of Oman
7. Enhanced Site Supervision workshop, Petroleum Development of Oman
8. Basic Diesel Engine Course in Tractors Malaysia.
9. Enviropeel application training at Alocit Australisia, Perth, Australia
10. Permit to work course for Britannia in Aberdeen, Scotland, United Kingdom.
11. Permit to work course for Britannia in Aberdeen, Scotland, United Kingdom
12. Blasting & Painting Surpervision Course IMM, Malaysia
WORK EXPERIENCE
GROUTING PROJECTS
October 2014 Emas Energy, Thailand
Project Manager for provision of ROV freespan correction, offshore Thailand.
October 2014 PT Pima Mitranata (Star Energy)
Project Manager for provision of ROV freespan correction, offshore Indonesia.
October 2014 PT Mc Dermott
Project Manager for provision of Banyu pile grouting project, offshore Indonesia.
October 2014 Freespan Correction for PT Cakrawala Amartha Jaya
Project Manager for provision of Diver freespan correction project , offshore Indonesia.
May 2014 grouting for Petrofac (West Desaru)
Project Manager for Provision of Conductor Leg Fatigue repair project, onshore Indonesia.
March 2014 Swiber Offshore Pte Ltd
Project Manager for provision of DWC Services for Zawtika EPCIC 03, offshore Myanmar.
September 2013 SOME
Project Manager for provision of pile grouting services for Zawatika P12, offshore Myanmar
Agust 2013 PT Rajawala Swiber Chakrawala
Project Manager for provision of ROV freespan correction project for Ruby field offshore
Indonesia.
July 2013 PT Rajawala Swiber Chakrawala
MURUGAN MUNUSAMY
Project Manager for provision of diver installed freespan correction project in South Belut field
offshore Indonesia.
June 2013 Saipem
Project Manager for provision of Grouting Services for Ruby Field WHP & PQP jacket, offshore
Indonesia.
June 2013 Vietsopetro
Project Manager for Free span Correction Services for 26” spool for Bien Dong 1 Field
Development Project, offshore Vietnam
April 2013 Saipem
Project Manager for provision of Grouting Services for Zawatika ZPQ Project, offshore Myanmar
March 2013 OCS/L&T
Project Manager for provision of Grouting Services for Zawatika Wellhead – Offshore, Myanmar.
(3rd Mob)
November 2012 HHI
Project Manager for provision of Free Span Correction for 14” pipeline, offshore Thailand.
May 2012 Swiber Offshore
Project Manager for provision of Grouting Services for ONGC D1 Development & B193 Jackets,
offshore India.
March 2012 - 2013 Swiber Offshore
Project Manager for provision of Grouting Services for ONGC B193 (B 28 A-A, LP Tripod, AP
Jacket) Jackets, offshore India.
April 2012 Swiber Offshore
Project Manager for provision of Grouting Services for ONGC D1 Development, Jackets, offshore
India.
February 2012 Swiber Offshore D1 Development
Project Manager for provision of Grouting Services for ONGC D1 (D1- B) Development, Jackets,
offshore India.
January 2012 Swiber Offshore
Project Manager for provision of Grouting Services for ONGC B193 (AP & AQ) Jackets, offshore
India.
November 2011 Swiber Offshore
Project Manager for provision of Grouting Services for ONGC B193 (B28-A ) Jacket, offshore India.
July 2011 TL Offshore
Project Manager for provision of Grouting Services for Shell F28 Jacket, offshore Malaysia.
June 2011 Swiber Offshore
Project Manager for provision of Grouting Services for ONGC North Tapti (NTP-2 Jacket) field
development project, offshore India
May 2011 Swiber Offshore
Project Manager for provision of Grouting Services for ONGC North Tapti (DH 2 Jacket) field
development project, offshore India.
April 2011 Swiber Offshore
Project Manager for provision of Grouting Services for ONGC B 193 field development project on
B 172 –A Jacket, offshore India.
MURUGAN MUNUSAMY
March 2011 Swiber Offshore North Tapti & B 193
Project Manager for provision of Grouting Services for ONGC NTP-1 & B 179 A Jacket , offshore
India.
February 2011 North Tapti & B 193
Project Manager for provision of Grouting Services for ONGC NTP-2 & B 178 A Jacket , offshore
India
January - March 2011 Swiber Offshore
Involved in the grouting operation for Swiber/ONGC Project in Offshore India.
August 2010 AME/Petronas
Involved in the grouting operation for Petronas Carigali Project TBDR-A, TBCP-A & MELOR Jacket,
Offshore Malaysia
April 2010 AME/Petronas
Involved in the grouting operation for Petronas Carigali Kumang Field KAKG A & LHD A Jacket
Project in Offshore Malaysia
March 2010 Sapura Acergy
Involved in the production of grout matters project in Batam Yard, Indonesia.
Jun 2009 Swiber Offshore North Belut
Involved in the grouting operation for Swiber North Belut (CPP & WHPD Jacket) Project in
Offshore Indonesia.
October 2007 Belumut Jacket
Involved in the grouting operation for Belumut Jacket offshore, Terengganu, Malaysia.
August 2006 Seaway Heavy Lifting
Involved in the grouting operation for Chiswick Jacket offshore North Sea, United Kingdom
August 2006 Herema
Involved in the grouting operation for Britsat (Britannia Satelite Platform) Jacket offshore, United
Kingdom
MARINE GROWTH PREVENTION PROJECTS
March 2014 Nigerdock Nigeria PlC-FZE
Supervise the assembly and installation of Marine Growth Preventer on the newly built platform,
offshore India.
Structure: OFD 3 & 5.
March 2009 Larson & Toubro
Supervise the assembly and installation of Marine Growth Preventer for Conductors on the newly
built platform, offshore India.
Structure: RS 17 Jacket.
July 2007 Petronas Carigali Sdn Bhd
Perform site survey before the installation of Marine Growth Preventer to check on the condition
of marine growth and coating on existing platform at offshore Kertih, Terengganu, Malaysia.
Structure: Duyong Central Processing Platform.
August 2004 Conoco
Supervise the assembly of Marine Growth Preventer for Conductors on newly built platform
(Chunxiao Gas Development Project) offshore China.
MURUGAN MUNUSAMY
Structure: CHX, TWT & CEP Jacket
November 1999 Petronas Carigali Sdn Bhd
Project Supervisor for the Design and Installation of Marine Growth Preventer for Conductors on
newly built platform at offshore Terengganu, Malaysia.
Structure: Resak RDP-A & RCPP Jacket
June 1999 Petronas Carigali Sdn Bhd
Project Supervisor for the Design and Installation of Marine Growth Preventer’s on newly
fabricated platform, at SSE Fabrication yard in Johor, Malaysia.
Structure: Resak RDP-A & RCPP Jacket
July 1997 Petronas Penapisan Melaka Sdn Bhd
Project Supervisor for the Design and Installation of Marine Growth Remover and Preventer’s on
existing jetty at Melaka, Malaysia.
Structure: Melaka Refinery Marine Facilities
October 1996 Star Cruise Terminal
Project Supervisor for the Design and Installation of Marine Growth Preventer’s on existing Jetty
at West Port Klang, Selangor.
Structure: Star Cruise Jetty
June 1996 Sabah Shell Bhd
Project Supervisor for the Design and Installation of Marine Growth Preventer on newly
fabricated platform in MSE Fabrication yard in Johor and offshore Sarawak, Malaysia.
Structure: KNDP-A
April 1996 P.T. Badak NGL Co.
Project Supervisor for the Design and Installation of Marine Growth Preventer on existing Jetty at
Bontang LPG Marine Structure in East Kalimantan.
Structure: Bontang LPG Facility
March 1995 Petronas Carigali Sdn Bhd
Project Supervisor for the Design and Installation of Marine Growth Preventer on newly
fabricated platform in Sime Sembawang’s fabrication yard in Johor, Malaysia and offshore
Terengganu.
Structure: Dulang D
February 1995 PTT Thailand
Site Supervisor for the Installation of Marine Growth Remover and Preventer at Sri Racha Marine
Terminal in Gulf of Thailand.
Structure: Sri – Racha Jetty
January 1995 Total Indonesie
Site Supervisor for the Installation of Marine Growth Preventer on existing platform in East
Kalimantan, Indonesia.
Structure: BF Platform
March 1993 Atlantic Rich Field Indonesia
Site Supervisor for the installation of Marine Growth Preventer on newly built platforms for ARII
Foxtrot field in Java Sea Indonesia.
Structure: FSA, FSWA & FZA
November 1992 Maxus South Sumatra Inc.
Site Supervisor for the Installation of Marine Growth Remover and Preventer‘s on existing and
new platform in Java Sea, Indonesia.
Structure: Indri A & NE Intan
MURUGAN MUNUSAMY
April 1992 Total Exploration and Production Thailand
Site Supervisor for the Installation of Marine Growth Preventer on newly built platform in
Bongkot Field, Offshore East Coast South China Sea Thailand.
Structure: WP1
Feb – March 1992 Maxus South Sumatra Inc.
Site Supervisor for the installation of Marine Growth Remover and Preventer‘s on existing and
new platform, in Java Sea Indonesia.
Structure: Widuri C, Widuri, Cinta B & Cinta C
CATHODIC PROTECTION PROJECTS
November 2008
to February 2009 Petroleum Technical Service Company (PTSC)
Project Manager for the installation and commissioning of Impressed Current Chatodic
Protection system for Spirial Sheet Piles, for Dung Quat Refinery Jetty, Quang Ngai, Vietnam.
June 2005 Nacap Asia Pacific
Involved in the Pre – Commissioning of CP system for Trans Thailand Malaysia (TTM) Gas pipeline
project from Prai to Changlun.
February – March 2005 MLNG
Pipe to soil potential survey at MLNG 1, 2 & 3
December 2004
to January 2005 Nacap Asia Pacific
Supervise the installation of Test Post, Bonding Box, Zink Ribbon and other installations for CP
system for Trans Thailand Malaysia (TTM) Gas pipeline project from Prai to Changlun.
February 2004 Nacap Asia Pacific
Current Drainage Test at HDD locations for Trans Thailand Malaysia (TTM) Gas pipeline project
from Prai to Changlun.
February 2004 PT.Badak NGL Co
Close interval potential survey (CIPS) & Direct Current Voltage Gradean Survey (DCVG) for 16” gas
pipeline at Bontang LPG plant in East Kalimantan, Indonesia.
December 2003
to January 2004 Nacap Asia Pacific
Soil Resistivity Survey for Trans Thailand Malaysia (TTM) Gas pipeline project from Prai to
Changlun.
May 2003 Gas Malaysia Sdn Bhd
Installation and commissioning of sacrificial anode CP system for 4” gas pipeline for Petronas
NGV at Kluang, Johor.
May 2003 Gas Malaysia Sdn Bhd
Soil resistivity survey, Installation and commissioning of sacrificial anode CP system for 4” Gas
pipeline NGDS System to Hospital Serdang, Serdang Selangor Darul Ehsan.
May 2003 Gas Malaysia Sdn Bhd
Installation and commissioning of sacrificial anode CP system for 4” gas pipeline at Petronas NGV
in Batu Cave, Selangor.
MURUGAN MUNUSAMY
April – July 2003 Gas Malaysia Sdn Bhd
Soil resistivity survey, Installation and commissioning of sacrificial anode CP system for 8” & 6”
Gas pipeline NGDS System to Benarang FL 1/ DL 1 Package 2, Pajam, Negeri Sembilan Darul
Khusus and Beranang Selangor Darul Ehsan.
January 2003 Petronas Carigali Sdn Bhd
Pipe Current Mapping & Direct Current Voltage Gradean survey (DCVG) for 16” gas pipeline from
Sabah Gas Terminal to Powertron in Kota Kinabalu, Sabah Malaysia.
February
to November 2002 Petroleum Development Oman / Gulf Petrochemical Services LLC
Direct Current Voltage Gradian Survey for impressed current system at South & Central Oman.
December 2001 Optimal Glycol (M) Sdn Bhd
Cathodic Protection monthly Audit Survey for Underground Cooling Water Supply and Return
pipeline and Tank Bottom Plates at EOG & Utility plant facilities, Kerteh, Terengganu
October 2000 Petronas Gas Berhad – ICCP
Installation and commissioning of Impressed Current Cathodic Protection system, at Tanjung
Langsat Pasir Gudang, Johor.
September 2000 Petronas Gas Berhad
Close interval potential survey (CIPS) & Direct Current Voltage Gradean Survey (DCVG) for
impressed current and sacrificial cathodic protection system at selected areas in Kerteh,
Terengganu and Pasir Gudang, Johor.
July 2000 Petronas Dagangan Sdn Bhd
Installation and commissioning of Impressed Current CP system for underground mounded bullet
tank.
June 2000 Gas Malaysia Sdn Bhd
Design, Installation and commissioning of sacrificial anode CP system for 4” gas pipeline at Yi Lai
industrial Park, Kulai, Johor
June 2000 Gas Malaysia Sdn Bhd
Design, Installation and commissioning of sacrificial anode CP system for 6” gas pipeline at Kapar,
Klang, Selangor.
May 2000 Gas Malaysia Sdn Bhd
Refurbishment work of exisisting sacrificial anode CP system at Kg Baru, Kuala Lumpur.
April 2000 Gas Malaysia Sdn Bhd
Installation and commissioning of sacrificial anodes CP system for 8” gas pipeline at Mount Kiara,
Sri Hartamas, Damansara, Selangor
April 2000 Gas Malaysia Sdn Bhd
Installation and commissioning of sacrificial anodes CP system for 8” gas pipeline at Kluang,
Johor.
March 2000 Petronas Gas Berhad.
Direct Current Voltage Gradean Survey (DCVG) Loop 1, total of 80km on selected areas from
Meru to Kuantan
February 2000 Petronas Gas Bhd
Direct Current Voltage Gradean Survey (DCVG) for Petronas Gas PGU 2 Sector 1 Pipeline at
various locations in Malaysia.
MURUGAN MUNUSAMY
January 1999 Petronas Gas Bhd
Installation of Zinc Ribbon at low Potential area in Port Dickson
October 1997 Petronas Carigali Malaysia.
Involved in accessing the corrosion condition on the riser and perform potential checks.
October 1997 Gas Malaysia Bhd
Installation of sacrificial anode for 6” gas pipeline in Pasir Gudang, Johor
September 1997 Kerteh Port Malaysia.
Involved in CP audit survey on Jetty piles.
August 1996 Petronas Gas Bhd
Close Interval Potential Survey (CIPS) for Petronas Gas PGU 2 Sector 3 (220 km)
Pipeline from Segamat to Pasir Gudang, Johor
COLD CUTTING PROECTS
November 1999 Saudi Aramco
Cutting an Old Pipeline by using Diamond Wire cutting Machine offshore, Saudi Arabia
July – TS/SEV/03/032
Involved in TS-45 well jacket decommissioning using Diamond Wire Cutting machine offshore
Saudi Arabia
July TS/SEV/03/032
Involved in TS-45 well jacket using a clamshell cutter offshore, Saudi Arabia
November TS/SEV/03/031
Cutting operation of Tripod removal Baram 8 for South China Sea, Sarawak
August – MA/SEV/04/023
Cutting operation of Tripod removable for South China Sea, Terengganu
COATING PROJECTS
November 2007
to April 2008 Petroleum Technical Services Company (PTSC)
Site superintendent for the application of Alocit Underwater Coating on 290 Spiril Sheet Pile for
Dung Quat Refinery Jetty, Quang Ngai, Vietnam.
August 2008 Vietsopetro, Vietnam
Demonstration of Alocit Underwater Coating Application for VSP, Vung Tau, Vietnam
May 2008
to October 2008 Cienco 1
Site Superintendent for the application of Alocit Underwater Coating on 1083 Spiril Sheet Pile for
Dung Quat Refinery Jetty, Quang Ngai, Vietnam.
January 2007 Petroleum Technical Services Company (PTSC)
Demonstration of Alocit underwater coating at Dung Quat, Vietnam
October 2006 Petro Vietnam Gas Company (PVGC) Vietnam
Demonstration of Alocit underwater coating at Vung Tau, Vietnam
October 2006 Vietsopetro (VSP) Vietnam
MURUGAN MUNUSAMY
Demonstration of Alocit underwater coating at BK 1 Platform Offshore, Vietnam.
March 2006 RNC Technology (M) Sdn Bhd
Demonstration of Alocit Underwater coating at SSPG Jetty, Melaka.
September 2005 Vietsopetro (VSP) Vietnam
Demonstration of Alocit underwater coating at VSP jetty in Vung Tau, Vietnam.
November 1997 EPMl Malaysia.
Repair & application of splash zone coating on riser for EPMI platform in offshore Terengganu
Malaysia.
October 1997 Petronas Carigali Malaysia.
Repair & application of splash zone coating on platform legs for Petronas Carigali in offshore
Terengganu, Malaysia.
September 1997 Kerteh Port Malaysia.
Repair & application of new coating on jetty pile at Kerteh Port, Malaysia.
September 1997 Kuantan Port Malaysia.
Application of underwater coating system on jetty sheet piles and Involved in accessing the
corrosion condition on the riser in Kuantan Port, Malaysia.
April 1997 Star Cruise Terminal Malaysia.
Involved in accessing the corrosion condition on fenders, repair & application of new coating at
Star Cruise Terminal West Port Klang, Malaysia.
November 1996 Petronas Carigali Malaysia.
Involved in accessing the corrosion condition on the Conductor, repair & application of splash
zone coating using an underwater coating system in Duyung B platform offshoreTerengganu.
March 1996 P.T Karakatau Steel Indonesia.
Application of new coating on jetty piles using an underwater coating system at Plant PLTU 400
MW Jetty in Indonesia
August 1995 Pentha Ocean Muhibbah
Involved in accessing the corrosion condition on the steel piles, repair & application of new
coating on steel jetty pile using an underwater coating system in Terengganu Malaysia.
July 1995 Total Thailand.
Involved in accessing the corrosion condition on the steel piles, repair & application of splash
zone coating using an underwater coating system on conductor pipes in Total Thailand.
May 1995 Maxus Indonesia.
Involved in accessing the corrosion condition on the steel piles, repair & application of splash
zone coating using an under water coating system on Krishna B platform in Maxus Indonesia.
February 1995 PTT Thailand.
Involved in accessing the corrosion condition on the steel piles, repair & application of new
coating using an underwater coating system in Thailand
September 1994 Pentha Ocean Muhibbah.
Involved in accessing the corrosion condition on the steel piles, repair & application of new
coating using an underwater coating system in offshore Terengganu, Malaysia
MURUGAN MUNUSAMY
DIAMOND WIRE CUTTING SERVICES
May 2007 TL Offshore
Severance of 30’’ conductor on CPWJ – 09 Platform using Dublexo in Offshore, Brunei.
December 2006 TL Offshore
Severance of 30’’ conductor on CPWJ – 09 Platform using Dublexo in Offshore, Brunei.
July 2004 Maridive & Oil Services (S.A.E)
Decommissioning of the TS-45 collapsed platform using Diamond Wire Cutting System and
pruning of a conductor using a mechanical casing cutter.
July 2004 Maridive & Oil Services (S.A.E)
Involved in the decommissioning of TS-45 Well Jacket at Hout field using Sonsub diamond wire
cutting machine from Valentine Marine Regina 250 work barge in Saudi Arabia.
November 1999 Saudi Aramco, Saudi Arabia
Supervise the operation of cutting on the old pipeline (8", 20” & 36") using Diamond wire-cutting
machine from Mc Dermot DB 27 work barge for Saudi Aramco in Gulf Sea, Saudi Arabia.
DREDGING / TRENCHING
November 2004 TL offshore Sdn Bhd
Involved in the trenchnig operation of Tripod removal for Baram 8 using Rotech T4000 mass flow
excavation tool from the Global 332 DL Barge in South China Sea, Miri Sarawak.
April 2004 Woodside, Australia
Involve in the operation of trenching the existing pipeline prior before repair work using Rotech
T4000 tool from the vessel in offshore Australia.
ABRASIVE WATER JET CUTTING
April 2006 PT ACERGY
Involved in the cutting operation of SPM Buoy Riser & Anchor Chain from Marsol Pride vessel at
Jawa Sea, Indonesia.
November 2004 TL offshore Sdn Bhd
Involved in the cutting operation of Tripod removal for Baram 8 from the Global 332 DL Barge in
South China Sea, Miri Sarawak.
August 2004 TL Offshore Sdn Bhd
Involved in the cutting operation of Tripod removal for Guntong “F” from the Kuruisho 2 DL Barge
in South China Sea, Terengganu.
ENVIROPEEL PROJECTS (Thermoplastic Coating Application)
August 2008 Vietsopetro (VSP) Vietnam
Demonstration of Enviropeel Application for VSP, Vung Tau, Vietnam
June 2007 Petrovietnam Fertilizer & Chemicals Co (PvFCCO) – Vietnam
Demonstration of Enviropeel Application using Enviropeel Applicator Machine on various size’s
of flanges.
March 2007 Britannia Platform
MURUGAN MUNUSAMY
Application of Enviropeel on various sizes of flanges on Britannia Platform in North Sea, United
Kingdom.
October 2006 Petro Vietnam Gas Company (PVGC) Vietnam
Demonstration of Enviropeel Application on 6” flange at Vung Tau, Vietnam.
October 2006 Vietsopetro (VSP) Vietnam
Demonstration of Enviropeel Application on Riser Clamp for BK 1 Platform Offshore, Vietnam.
May to June 2006 Hong Kong Gas Receiving Station (HKGRS)
Application of Enviropeel at Hong Kong Gas Receiving Station.
March 2006 BASF Petronas Chemicals
Demonstration of Enviropeel applications at BASF Tank Farm, Kuantan Port, Malaysia.
November 2005 PT Pupuk Palembang, Indonesia
Demonstration of Enviropeel applications at Palembang Indonesia
October 2005 Petronas Gas Berhad
Demonstration of Enviropeel applications for Petronas Gas Berhad at ML 206 Block value Station
in Senawang, Seremban.
June to July 2005 Britannia Platform
Application of Enviropeel on various sizes of flanges on Britannia Platform in North Sea, United
Kingdom.
May 2005 Japan Vietnam Petroleum Company (JVPC)
Enviropeel demonstration for JVPC Rang Dong Field in Offshore, Vietnam.
ZINC TAPE (Anti Corrosion Tape)
August 2009 Petronas Carigali Vietnam Limited (PCV)
Demonstration of Zinc Tape Application on offshore structures, Vung Tau, Vietnam
August 2008 Vietsopetro (VSP), Vietnam
Demonstration of Zinc Tape Application for VSP, Vung Tau, Vietnam
November 2006 Town Gas, Hong Kong.
Demonstration of Isozin Zinc Tape Application on 2” cooling tower, megawater pipe at, Hong
Kong
November 2006 Hong Kong Gas Relay Station (HKGRS) Hong Kong.
Demonstration of Zinc Tape Application on 2” utility pipe at HKGRS, Hong Kong
October 2006 Petro Vietnam Feterlizer Chemical Company (PVFCC) Vietnam
Demonstration of Zinc Tape Application on 20” Pipe Vung Tau, Vietnam.
October 2006 Petro Vietnam Gas Company (PVGC) Vietnam
Demonstration of Zinc Tape Application on 6” Pipe Vung Tau, Vietnam
MURUGAN MUNUSAMY
Other Work Experience;
IEV GROUP SDN BHD (2013 - Present)
OPERATION MANAGER
IEV GROUP SDN BHD (2011 - 2013)
SENIOR PROJECT MANAGER
IEV GROUP SDN BHD (2010 - 2011)
PROJECT MANAGER
IEV GROUP SDN BHD (2008-2009)
HEAD OF SUBSEA AND CORROSION CONTROL SERVCES
IEV GROUP SDN BHD (2006 - 2007)
SUPERINTENDENT
IEV GROUP SDN BHD (2004 - 2005)
LEAD TECHNICIAN
DVS ENGINEERING SDN BHD (2002 – 2003)
CATHODIC PROTECTION TECHNICAN (Contract)
IEV SDN BHD (2001 – 2002)
TECHNICAN (Contract)
HEMPLE COATING (M) SDN BHD (2000 - 2001)
COATING ADVISOR (Contract)
IEV SDN BHD (1992 – 2000)
TECHNICAL COORDINATOR

More Related Content

Similar to Muru

Petrohans Company Experience Presentation
Petrohans Company Experience PresentationPetrohans Company Experience Presentation
Petrohans Company Experience Presentationhvandruten
 
Petrohans Company Experience Presentation 2011
Petrohans Company Experience Presentation 2011Petrohans Company Experience Presentation 2011
Petrohans Company Experience Presentation 2011hvandruten
 
PT. Nadi Marin Subsea - Company Profile 2018
PT. Nadi Marin Subsea -  Company Profile 2018PT. Nadi Marin Subsea -  Company Profile 2018
PT. Nadi Marin Subsea - Company Profile 2018PT. NADI MARIN SUBSEA
 
CURRICULUM VITAE- Saut Hutapea
CURRICULUM VITAE- Saut HutapeaCURRICULUM VITAE- Saut Hutapea
CURRICULUM VITAE- Saut HutapeaSAUT HUTAPEA
 
Presentasi Media Gathering dari Rekind
Presentasi Media Gathering dari RekindPresentasi Media Gathering dari Rekind
Presentasi Media Gathering dari RekindRuslan Chandra
 
ALVIN'S CURRICULUM VITAE 2017
ALVIN'S CURRICULUM VITAE 2017ALVIN'S CURRICULUM VITAE 2017
ALVIN'S CURRICULUM VITAE 2017Alvin Chen
 
CURICULUM VITAE (CV)
CURICULUM VITAE (CV)CURICULUM VITAE (CV)
CURICULUM VITAE (CV)Apr Eddie
 
CV_Ye Ni Soe_24 March 2015
CV_Ye Ni Soe_24 March 2015CV_Ye Ni Soe_24 March 2015
CV_Ye Ni Soe_24 March 2015Ye Ni Soe
 
CV_Ye Ni Soe_24 March 2015
CV_Ye Ni Soe_24 March 2015CV_Ye Ni Soe_24 March 2015
CV_Ye Ni Soe_24 March 2015Soe Ye Ni
 
Update CV-Junaidi_Juni 2016
Update CV-Junaidi_Juni 2016Update CV-Junaidi_Juni 2016
Update CV-Junaidi_Juni 2016junaidi medy
 
Company Profile 2022.pdf
Company Profile 2022.pdfCompany Profile 2022.pdf
Company Profile 2022.pdfTaufiq380509
 
C.H.Scott Goodwin (2)
C.H.Scott Goodwin (2)C.H.Scott Goodwin (2)
C.H.Scott Goodwin (2)Scott Goodwin
 
Bechtel Resume - Capt Guru N. Misra - August 1 2014
Bechtel Resume - Capt Guru N. Misra - August 1 2014Bechtel Resume - Capt Guru N. Misra - August 1 2014
Bechtel Resume - Capt Guru N. Misra - August 1 2014Guru Misra
 
Bechtel Resume - Capt Guru N. Misra - August 1 2014
Bechtel Resume - Capt Guru N. Misra - August 1 2014Bechtel Resume - Capt Guru N. Misra - August 1 2014
Bechtel Resume - Capt Guru N. Misra - August 1 2014Guru Misra
 

Similar to Muru (20)

Petrohans Company Experience Presentation
Petrohans Company Experience PresentationPetrohans Company Experience Presentation
Petrohans Company Experience Presentation
 
Petrohans Company Experience Presentation 2011
Petrohans Company Experience Presentation 2011Petrohans Company Experience Presentation 2011
Petrohans Company Experience Presentation 2011
 
CV-Jamal-2015Rev01
CV-Jamal-2015Rev01CV-Jamal-2015Rev01
CV-Jamal-2015Rev01
 
subhash__cv
subhash__cvsubhash__cv
subhash__cv
 
PT. Nadi Marin Subsea - Company Profile 2018
PT. Nadi Marin Subsea -  Company Profile 2018PT. Nadi Marin Subsea -  Company Profile 2018
PT. Nadi Marin Subsea - Company Profile 2018
 
Sanjeev Barwal
Sanjeev BarwalSanjeev Barwal
Sanjeev Barwal
 
CURRICULUM VITAE- Saut Hutapea
CURRICULUM VITAE- Saut HutapeaCURRICULUM VITAE- Saut Hutapea
CURRICULUM VITAE- Saut Hutapea
 
Presentasi Media Gathering dari Rekind
Presentasi Media Gathering dari RekindPresentasi Media Gathering dari Rekind
Presentasi Media Gathering dari Rekind
 
ALVIN'S CURRICULUM VITAE 2017
ALVIN'S CURRICULUM VITAE 2017ALVIN'S CURRICULUM VITAE 2017
ALVIN'S CURRICULUM VITAE 2017
 
CURICULUM VITAE (CV)
CURICULUM VITAE (CV)CURICULUM VITAE (CV)
CURICULUM VITAE (CV)
 
CV_Ye Ni Soe_24 March 2015
CV_Ye Ni Soe_24 March 2015CV_Ye Ni Soe_24 March 2015
CV_Ye Ni Soe_24 March 2015
 
CV_Ye Ni Soe_24 March 2015
CV_Ye Ni Soe_24 March 2015CV_Ye Ni Soe_24 March 2015
CV_Ye Ni Soe_24 March 2015
 
Update CV-Junaidi_Juni 2016
Update CV-Junaidi_Juni 2016Update CV-Junaidi_Juni 2016
Update CV-Junaidi_Juni 2016
 
CV.HARIS SIREGAR
CV.HARIS SIREGARCV.HARIS SIREGAR
CV.HARIS SIREGAR
 
PONGPANIT Resume 2016
PONGPANIT Resume 2016PONGPANIT Resume 2016
PONGPANIT Resume 2016
 
Company Profile 2022.pdf
Company Profile 2022.pdfCompany Profile 2022.pdf
Company Profile 2022.pdf
 
Andryanto - CV
Andryanto - CVAndryanto - CV
Andryanto - CV
 
C.H.Scott Goodwin (2)
C.H.Scott Goodwin (2)C.H.Scott Goodwin (2)
C.H.Scott Goodwin (2)
 
Bechtel Resume - Capt Guru N. Misra - August 1 2014
Bechtel Resume - Capt Guru N. Misra - August 1 2014Bechtel Resume - Capt Guru N. Misra - August 1 2014
Bechtel Resume - Capt Guru N. Misra - August 1 2014
 
Bechtel Resume - Capt Guru N. Misra - August 1 2014
Bechtel Resume - Capt Guru N. Misra - August 1 2014Bechtel Resume - Capt Guru N. Misra - August 1 2014
Bechtel Resume - Capt Guru N. Misra - August 1 2014
 

Muru

  • 1. MURUGAN MUNUSAMY Position: OPERATION MANAGER – PROJECTS DEPARTMENT Date of Birth: 11th April 1972 Nationality: Malaysian Email muruganmunusami@gmail.com TRAINING 1. Contract Management 2. Basic maintenance and operation of Diamond Wire Cutting machine. 3. Construction Industry Development Board Malaysia 4. H2S Awareness & Escape, Petroleum Development of Oman 5. Permit Holder course, Petroleum Development of Oman 6. Job Hazard Analysis, Petroleum Development of Oman 7. Enhanced Site Supervision workshop, Petroleum Development of Oman 8. Basic Diesel Engine Course in Tractors Malaysia. 9. Enviropeel application training at Alocit Australisia, Perth, Australia 10. Permit to work course for Britannia in Aberdeen, Scotland, United Kingdom. 11. Permit to work course for Britannia in Aberdeen, Scotland, United Kingdom 12. Blasting & Painting Surpervision Course IMM, Malaysia WORK EXPERIENCE GROUTING PROJECTS October 2014 Emas Energy, Thailand Project Manager for provision of ROV freespan correction, offshore Thailand. October 2014 PT Pima Mitranata (Star Energy) Project Manager for provision of ROV freespan correction, offshore Indonesia. October 2014 PT Mc Dermott Project Manager for provision of Banyu pile grouting project, offshore Indonesia. October 2014 Freespan Correction for PT Cakrawala Amartha Jaya Project Manager for provision of Diver freespan correction project , offshore Indonesia. May 2014 grouting for Petrofac (West Desaru) Project Manager for Provision of Conductor Leg Fatigue repair project, onshore Indonesia. March 2014 Swiber Offshore Pte Ltd Project Manager for provision of DWC Services for Zawtika EPCIC 03, offshore Myanmar. September 2013 SOME Project Manager for provision of pile grouting services for Zawatika P12, offshore Myanmar Agust 2013 PT Rajawala Swiber Chakrawala Project Manager for provision of ROV freespan correction project for Ruby field offshore Indonesia. July 2013 PT Rajawala Swiber Chakrawala
  • 2. MURUGAN MUNUSAMY Project Manager for provision of diver installed freespan correction project in South Belut field offshore Indonesia. June 2013 Saipem Project Manager for provision of Grouting Services for Ruby Field WHP & PQP jacket, offshore Indonesia. June 2013 Vietsopetro Project Manager for Free span Correction Services for 26” spool for Bien Dong 1 Field Development Project, offshore Vietnam April 2013 Saipem Project Manager for provision of Grouting Services for Zawatika ZPQ Project, offshore Myanmar March 2013 OCS/L&T Project Manager for provision of Grouting Services for Zawatika Wellhead – Offshore, Myanmar. (3rd Mob) November 2012 HHI Project Manager for provision of Free Span Correction for 14” pipeline, offshore Thailand. May 2012 Swiber Offshore Project Manager for provision of Grouting Services for ONGC D1 Development & B193 Jackets, offshore India. March 2012 - 2013 Swiber Offshore Project Manager for provision of Grouting Services for ONGC B193 (B 28 A-A, LP Tripod, AP Jacket) Jackets, offshore India. April 2012 Swiber Offshore Project Manager for provision of Grouting Services for ONGC D1 Development, Jackets, offshore India. February 2012 Swiber Offshore D1 Development Project Manager for provision of Grouting Services for ONGC D1 (D1- B) Development, Jackets, offshore India. January 2012 Swiber Offshore Project Manager for provision of Grouting Services for ONGC B193 (AP & AQ) Jackets, offshore India. November 2011 Swiber Offshore Project Manager for provision of Grouting Services for ONGC B193 (B28-A ) Jacket, offshore India. July 2011 TL Offshore Project Manager for provision of Grouting Services for Shell F28 Jacket, offshore Malaysia. June 2011 Swiber Offshore Project Manager for provision of Grouting Services for ONGC North Tapti (NTP-2 Jacket) field development project, offshore India May 2011 Swiber Offshore Project Manager for provision of Grouting Services for ONGC North Tapti (DH 2 Jacket) field development project, offshore India. April 2011 Swiber Offshore Project Manager for provision of Grouting Services for ONGC B 193 field development project on B 172 –A Jacket, offshore India.
  • 3. MURUGAN MUNUSAMY March 2011 Swiber Offshore North Tapti & B 193 Project Manager for provision of Grouting Services for ONGC NTP-1 & B 179 A Jacket , offshore India. February 2011 North Tapti & B 193 Project Manager for provision of Grouting Services for ONGC NTP-2 & B 178 A Jacket , offshore India January - March 2011 Swiber Offshore Involved in the grouting operation for Swiber/ONGC Project in Offshore India. August 2010 AME/Petronas Involved in the grouting operation for Petronas Carigali Project TBDR-A, TBCP-A & MELOR Jacket, Offshore Malaysia April 2010 AME/Petronas Involved in the grouting operation for Petronas Carigali Kumang Field KAKG A & LHD A Jacket Project in Offshore Malaysia March 2010 Sapura Acergy Involved in the production of grout matters project in Batam Yard, Indonesia. Jun 2009 Swiber Offshore North Belut Involved in the grouting operation for Swiber North Belut (CPP & WHPD Jacket) Project in Offshore Indonesia. October 2007 Belumut Jacket Involved in the grouting operation for Belumut Jacket offshore, Terengganu, Malaysia. August 2006 Seaway Heavy Lifting Involved in the grouting operation for Chiswick Jacket offshore North Sea, United Kingdom August 2006 Herema Involved in the grouting operation for Britsat (Britannia Satelite Platform) Jacket offshore, United Kingdom MARINE GROWTH PREVENTION PROJECTS March 2014 Nigerdock Nigeria PlC-FZE Supervise the assembly and installation of Marine Growth Preventer on the newly built platform, offshore India. Structure: OFD 3 & 5. March 2009 Larson & Toubro Supervise the assembly and installation of Marine Growth Preventer for Conductors on the newly built platform, offshore India. Structure: RS 17 Jacket. July 2007 Petronas Carigali Sdn Bhd Perform site survey before the installation of Marine Growth Preventer to check on the condition of marine growth and coating on existing platform at offshore Kertih, Terengganu, Malaysia. Structure: Duyong Central Processing Platform. August 2004 Conoco Supervise the assembly of Marine Growth Preventer for Conductors on newly built platform (Chunxiao Gas Development Project) offshore China.
  • 4. MURUGAN MUNUSAMY Structure: CHX, TWT & CEP Jacket November 1999 Petronas Carigali Sdn Bhd Project Supervisor for the Design and Installation of Marine Growth Preventer for Conductors on newly built platform at offshore Terengganu, Malaysia. Structure: Resak RDP-A & RCPP Jacket June 1999 Petronas Carigali Sdn Bhd Project Supervisor for the Design and Installation of Marine Growth Preventer’s on newly fabricated platform, at SSE Fabrication yard in Johor, Malaysia. Structure: Resak RDP-A & RCPP Jacket July 1997 Petronas Penapisan Melaka Sdn Bhd Project Supervisor for the Design and Installation of Marine Growth Remover and Preventer’s on existing jetty at Melaka, Malaysia. Structure: Melaka Refinery Marine Facilities October 1996 Star Cruise Terminal Project Supervisor for the Design and Installation of Marine Growth Preventer’s on existing Jetty at West Port Klang, Selangor. Structure: Star Cruise Jetty June 1996 Sabah Shell Bhd Project Supervisor for the Design and Installation of Marine Growth Preventer on newly fabricated platform in MSE Fabrication yard in Johor and offshore Sarawak, Malaysia. Structure: KNDP-A April 1996 P.T. Badak NGL Co. Project Supervisor for the Design and Installation of Marine Growth Preventer on existing Jetty at Bontang LPG Marine Structure in East Kalimantan. Structure: Bontang LPG Facility March 1995 Petronas Carigali Sdn Bhd Project Supervisor for the Design and Installation of Marine Growth Preventer on newly fabricated platform in Sime Sembawang’s fabrication yard in Johor, Malaysia and offshore Terengganu. Structure: Dulang D February 1995 PTT Thailand Site Supervisor for the Installation of Marine Growth Remover and Preventer at Sri Racha Marine Terminal in Gulf of Thailand. Structure: Sri – Racha Jetty January 1995 Total Indonesie Site Supervisor for the Installation of Marine Growth Preventer on existing platform in East Kalimantan, Indonesia. Structure: BF Platform March 1993 Atlantic Rich Field Indonesia Site Supervisor for the installation of Marine Growth Preventer on newly built platforms for ARII Foxtrot field in Java Sea Indonesia. Structure: FSA, FSWA & FZA November 1992 Maxus South Sumatra Inc. Site Supervisor for the Installation of Marine Growth Remover and Preventer‘s on existing and new platform in Java Sea, Indonesia. Structure: Indri A & NE Intan
  • 5. MURUGAN MUNUSAMY April 1992 Total Exploration and Production Thailand Site Supervisor for the Installation of Marine Growth Preventer on newly built platform in Bongkot Field, Offshore East Coast South China Sea Thailand. Structure: WP1 Feb – March 1992 Maxus South Sumatra Inc. Site Supervisor for the installation of Marine Growth Remover and Preventer‘s on existing and new platform, in Java Sea Indonesia. Structure: Widuri C, Widuri, Cinta B & Cinta C CATHODIC PROTECTION PROJECTS November 2008 to February 2009 Petroleum Technical Service Company (PTSC) Project Manager for the installation and commissioning of Impressed Current Chatodic Protection system for Spirial Sheet Piles, for Dung Quat Refinery Jetty, Quang Ngai, Vietnam. June 2005 Nacap Asia Pacific Involved in the Pre – Commissioning of CP system for Trans Thailand Malaysia (TTM) Gas pipeline project from Prai to Changlun. February – March 2005 MLNG Pipe to soil potential survey at MLNG 1, 2 & 3 December 2004 to January 2005 Nacap Asia Pacific Supervise the installation of Test Post, Bonding Box, Zink Ribbon and other installations for CP system for Trans Thailand Malaysia (TTM) Gas pipeline project from Prai to Changlun. February 2004 Nacap Asia Pacific Current Drainage Test at HDD locations for Trans Thailand Malaysia (TTM) Gas pipeline project from Prai to Changlun. February 2004 PT.Badak NGL Co Close interval potential survey (CIPS) & Direct Current Voltage Gradean Survey (DCVG) for 16” gas pipeline at Bontang LPG plant in East Kalimantan, Indonesia. December 2003 to January 2004 Nacap Asia Pacific Soil Resistivity Survey for Trans Thailand Malaysia (TTM) Gas pipeline project from Prai to Changlun. May 2003 Gas Malaysia Sdn Bhd Installation and commissioning of sacrificial anode CP system for 4” gas pipeline for Petronas NGV at Kluang, Johor. May 2003 Gas Malaysia Sdn Bhd Soil resistivity survey, Installation and commissioning of sacrificial anode CP system for 4” Gas pipeline NGDS System to Hospital Serdang, Serdang Selangor Darul Ehsan. May 2003 Gas Malaysia Sdn Bhd Installation and commissioning of sacrificial anode CP system for 4” gas pipeline at Petronas NGV in Batu Cave, Selangor.
  • 6. MURUGAN MUNUSAMY April – July 2003 Gas Malaysia Sdn Bhd Soil resistivity survey, Installation and commissioning of sacrificial anode CP system for 8” & 6” Gas pipeline NGDS System to Benarang FL 1/ DL 1 Package 2, Pajam, Negeri Sembilan Darul Khusus and Beranang Selangor Darul Ehsan. January 2003 Petronas Carigali Sdn Bhd Pipe Current Mapping & Direct Current Voltage Gradean survey (DCVG) for 16” gas pipeline from Sabah Gas Terminal to Powertron in Kota Kinabalu, Sabah Malaysia. February to November 2002 Petroleum Development Oman / Gulf Petrochemical Services LLC Direct Current Voltage Gradian Survey for impressed current system at South & Central Oman. December 2001 Optimal Glycol (M) Sdn Bhd Cathodic Protection monthly Audit Survey for Underground Cooling Water Supply and Return pipeline and Tank Bottom Plates at EOG & Utility plant facilities, Kerteh, Terengganu October 2000 Petronas Gas Berhad – ICCP Installation and commissioning of Impressed Current Cathodic Protection system, at Tanjung Langsat Pasir Gudang, Johor. September 2000 Petronas Gas Berhad Close interval potential survey (CIPS) & Direct Current Voltage Gradean Survey (DCVG) for impressed current and sacrificial cathodic protection system at selected areas in Kerteh, Terengganu and Pasir Gudang, Johor. July 2000 Petronas Dagangan Sdn Bhd Installation and commissioning of Impressed Current CP system for underground mounded bullet tank. June 2000 Gas Malaysia Sdn Bhd Design, Installation and commissioning of sacrificial anode CP system for 4” gas pipeline at Yi Lai industrial Park, Kulai, Johor June 2000 Gas Malaysia Sdn Bhd Design, Installation and commissioning of sacrificial anode CP system for 6” gas pipeline at Kapar, Klang, Selangor. May 2000 Gas Malaysia Sdn Bhd Refurbishment work of exisisting sacrificial anode CP system at Kg Baru, Kuala Lumpur. April 2000 Gas Malaysia Sdn Bhd Installation and commissioning of sacrificial anodes CP system for 8” gas pipeline at Mount Kiara, Sri Hartamas, Damansara, Selangor April 2000 Gas Malaysia Sdn Bhd Installation and commissioning of sacrificial anodes CP system for 8” gas pipeline at Kluang, Johor. March 2000 Petronas Gas Berhad. Direct Current Voltage Gradean Survey (DCVG) Loop 1, total of 80km on selected areas from Meru to Kuantan February 2000 Petronas Gas Bhd Direct Current Voltage Gradean Survey (DCVG) for Petronas Gas PGU 2 Sector 1 Pipeline at various locations in Malaysia.
  • 7. MURUGAN MUNUSAMY January 1999 Petronas Gas Bhd Installation of Zinc Ribbon at low Potential area in Port Dickson October 1997 Petronas Carigali Malaysia. Involved in accessing the corrosion condition on the riser and perform potential checks. October 1997 Gas Malaysia Bhd Installation of sacrificial anode for 6” gas pipeline in Pasir Gudang, Johor September 1997 Kerteh Port Malaysia. Involved in CP audit survey on Jetty piles. August 1996 Petronas Gas Bhd Close Interval Potential Survey (CIPS) for Petronas Gas PGU 2 Sector 3 (220 km) Pipeline from Segamat to Pasir Gudang, Johor COLD CUTTING PROECTS November 1999 Saudi Aramco Cutting an Old Pipeline by using Diamond Wire cutting Machine offshore, Saudi Arabia July – TS/SEV/03/032 Involved in TS-45 well jacket decommissioning using Diamond Wire Cutting machine offshore Saudi Arabia July TS/SEV/03/032 Involved in TS-45 well jacket using a clamshell cutter offshore, Saudi Arabia November TS/SEV/03/031 Cutting operation of Tripod removal Baram 8 for South China Sea, Sarawak August – MA/SEV/04/023 Cutting operation of Tripod removable for South China Sea, Terengganu COATING PROJECTS November 2007 to April 2008 Petroleum Technical Services Company (PTSC) Site superintendent for the application of Alocit Underwater Coating on 290 Spiril Sheet Pile for Dung Quat Refinery Jetty, Quang Ngai, Vietnam. August 2008 Vietsopetro, Vietnam Demonstration of Alocit Underwater Coating Application for VSP, Vung Tau, Vietnam May 2008 to October 2008 Cienco 1 Site Superintendent for the application of Alocit Underwater Coating on 1083 Spiril Sheet Pile for Dung Quat Refinery Jetty, Quang Ngai, Vietnam. January 2007 Petroleum Technical Services Company (PTSC) Demonstration of Alocit underwater coating at Dung Quat, Vietnam October 2006 Petro Vietnam Gas Company (PVGC) Vietnam Demonstration of Alocit underwater coating at Vung Tau, Vietnam October 2006 Vietsopetro (VSP) Vietnam
  • 8. MURUGAN MUNUSAMY Demonstration of Alocit underwater coating at BK 1 Platform Offshore, Vietnam. March 2006 RNC Technology (M) Sdn Bhd Demonstration of Alocit Underwater coating at SSPG Jetty, Melaka. September 2005 Vietsopetro (VSP) Vietnam Demonstration of Alocit underwater coating at VSP jetty in Vung Tau, Vietnam. November 1997 EPMl Malaysia. Repair & application of splash zone coating on riser for EPMI platform in offshore Terengganu Malaysia. October 1997 Petronas Carigali Malaysia. Repair & application of splash zone coating on platform legs for Petronas Carigali in offshore Terengganu, Malaysia. September 1997 Kerteh Port Malaysia. Repair & application of new coating on jetty pile at Kerteh Port, Malaysia. September 1997 Kuantan Port Malaysia. Application of underwater coating system on jetty sheet piles and Involved in accessing the corrosion condition on the riser in Kuantan Port, Malaysia. April 1997 Star Cruise Terminal Malaysia. Involved in accessing the corrosion condition on fenders, repair & application of new coating at Star Cruise Terminal West Port Klang, Malaysia. November 1996 Petronas Carigali Malaysia. Involved in accessing the corrosion condition on the Conductor, repair & application of splash zone coating using an underwater coating system in Duyung B platform offshoreTerengganu. March 1996 P.T Karakatau Steel Indonesia. Application of new coating on jetty piles using an underwater coating system at Plant PLTU 400 MW Jetty in Indonesia August 1995 Pentha Ocean Muhibbah Involved in accessing the corrosion condition on the steel piles, repair & application of new coating on steel jetty pile using an underwater coating system in Terengganu Malaysia. July 1995 Total Thailand. Involved in accessing the corrosion condition on the steel piles, repair & application of splash zone coating using an underwater coating system on conductor pipes in Total Thailand. May 1995 Maxus Indonesia. Involved in accessing the corrosion condition on the steel piles, repair & application of splash zone coating using an under water coating system on Krishna B platform in Maxus Indonesia. February 1995 PTT Thailand. Involved in accessing the corrosion condition on the steel piles, repair & application of new coating using an underwater coating system in Thailand September 1994 Pentha Ocean Muhibbah. Involved in accessing the corrosion condition on the steel piles, repair & application of new coating using an underwater coating system in offshore Terengganu, Malaysia
  • 9. MURUGAN MUNUSAMY DIAMOND WIRE CUTTING SERVICES May 2007 TL Offshore Severance of 30’’ conductor on CPWJ – 09 Platform using Dublexo in Offshore, Brunei. December 2006 TL Offshore Severance of 30’’ conductor on CPWJ – 09 Platform using Dublexo in Offshore, Brunei. July 2004 Maridive & Oil Services (S.A.E) Decommissioning of the TS-45 collapsed platform using Diamond Wire Cutting System and pruning of a conductor using a mechanical casing cutter. July 2004 Maridive & Oil Services (S.A.E) Involved in the decommissioning of TS-45 Well Jacket at Hout field using Sonsub diamond wire cutting machine from Valentine Marine Regina 250 work barge in Saudi Arabia. November 1999 Saudi Aramco, Saudi Arabia Supervise the operation of cutting on the old pipeline (8", 20” & 36") using Diamond wire-cutting machine from Mc Dermot DB 27 work barge for Saudi Aramco in Gulf Sea, Saudi Arabia. DREDGING / TRENCHING November 2004 TL offshore Sdn Bhd Involved in the trenchnig operation of Tripod removal for Baram 8 using Rotech T4000 mass flow excavation tool from the Global 332 DL Barge in South China Sea, Miri Sarawak. April 2004 Woodside, Australia Involve in the operation of trenching the existing pipeline prior before repair work using Rotech T4000 tool from the vessel in offshore Australia. ABRASIVE WATER JET CUTTING April 2006 PT ACERGY Involved in the cutting operation of SPM Buoy Riser & Anchor Chain from Marsol Pride vessel at Jawa Sea, Indonesia. November 2004 TL offshore Sdn Bhd Involved in the cutting operation of Tripod removal for Baram 8 from the Global 332 DL Barge in South China Sea, Miri Sarawak. August 2004 TL Offshore Sdn Bhd Involved in the cutting operation of Tripod removal for Guntong “F” from the Kuruisho 2 DL Barge in South China Sea, Terengganu. ENVIROPEEL PROJECTS (Thermoplastic Coating Application) August 2008 Vietsopetro (VSP) Vietnam Demonstration of Enviropeel Application for VSP, Vung Tau, Vietnam June 2007 Petrovietnam Fertilizer & Chemicals Co (PvFCCO) – Vietnam Demonstration of Enviropeel Application using Enviropeel Applicator Machine on various size’s of flanges. March 2007 Britannia Platform
  • 10. MURUGAN MUNUSAMY Application of Enviropeel on various sizes of flanges on Britannia Platform in North Sea, United Kingdom. October 2006 Petro Vietnam Gas Company (PVGC) Vietnam Demonstration of Enviropeel Application on 6” flange at Vung Tau, Vietnam. October 2006 Vietsopetro (VSP) Vietnam Demonstration of Enviropeel Application on Riser Clamp for BK 1 Platform Offshore, Vietnam. May to June 2006 Hong Kong Gas Receiving Station (HKGRS) Application of Enviropeel at Hong Kong Gas Receiving Station. March 2006 BASF Petronas Chemicals Demonstration of Enviropeel applications at BASF Tank Farm, Kuantan Port, Malaysia. November 2005 PT Pupuk Palembang, Indonesia Demonstration of Enviropeel applications at Palembang Indonesia October 2005 Petronas Gas Berhad Demonstration of Enviropeel applications for Petronas Gas Berhad at ML 206 Block value Station in Senawang, Seremban. June to July 2005 Britannia Platform Application of Enviropeel on various sizes of flanges on Britannia Platform in North Sea, United Kingdom. May 2005 Japan Vietnam Petroleum Company (JVPC) Enviropeel demonstration for JVPC Rang Dong Field in Offshore, Vietnam. ZINC TAPE (Anti Corrosion Tape) August 2009 Petronas Carigali Vietnam Limited (PCV) Demonstration of Zinc Tape Application on offshore structures, Vung Tau, Vietnam August 2008 Vietsopetro (VSP), Vietnam Demonstration of Zinc Tape Application for VSP, Vung Tau, Vietnam November 2006 Town Gas, Hong Kong. Demonstration of Isozin Zinc Tape Application on 2” cooling tower, megawater pipe at, Hong Kong November 2006 Hong Kong Gas Relay Station (HKGRS) Hong Kong. Demonstration of Zinc Tape Application on 2” utility pipe at HKGRS, Hong Kong October 2006 Petro Vietnam Feterlizer Chemical Company (PVFCC) Vietnam Demonstration of Zinc Tape Application on 20” Pipe Vung Tau, Vietnam. October 2006 Petro Vietnam Gas Company (PVGC) Vietnam Demonstration of Zinc Tape Application on 6” Pipe Vung Tau, Vietnam
  • 11. MURUGAN MUNUSAMY Other Work Experience; IEV GROUP SDN BHD (2013 - Present) OPERATION MANAGER IEV GROUP SDN BHD (2011 - 2013) SENIOR PROJECT MANAGER IEV GROUP SDN BHD (2010 - 2011) PROJECT MANAGER IEV GROUP SDN BHD (2008-2009) HEAD OF SUBSEA AND CORROSION CONTROL SERVCES IEV GROUP SDN BHD (2006 - 2007) SUPERINTENDENT IEV GROUP SDN BHD (2004 - 2005) LEAD TECHNICIAN DVS ENGINEERING SDN BHD (2002 – 2003) CATHODIC PROTECTION TECHNICAN (Contract) IEV SDN BHD (2001 – 2002) TECHNICAN (Contract) HEMPLE COATING (M) SDN BHD (2000 - 2001) COATING ADVISOR (Contract) IEV SDN BHD (1992 – 2000) TECHNICAL COORDINATOR