SlideShare a Scribd company logo
1 of 36
CAPE2020 Environmental Management and Air Quality
Prof. G..E. Andrews 2019/20
Contents
1. Introduction to the Air Quality and Environmental Management part of the module.
2. Introduction to legal framework for Air Quality legislation and the changes in the draft
Environment Bill
3. Health effects of air pollutants
4. Particulate air pollution and particle size distribution and the health effects of ultra-fine particles
5. Sources of Air pollution and Trends in emissions of pollutants that contribute to poor air quality.
6. Air quality Regulations
7. Air quality monitoring
8. Air quality limit value Regulations
9. Occupational exposure to pollution – COSHH
10. The Clean Air Acts
11. Meteorology and pollutant dispersion
12. Environmental Law
13. Town and Country Act planning law for Environmental Impact
14. Environmental Management in Industry
15. Preparing an Environmental Permit - examples
16. Emissions measurement from industrial plant
• Planning
– Controls the development and use of land in the public interest including
consideration of the impacts on the local environment and amenity
– Should assume that other regimes (e.g. Environmental Permitting
Regulations) operate effectively
• Environmental permitting
– Controls the impact on the environment and human health from the
process plant
– Ensures EU directive requirements are met including use of Best
Available Techniques (BAT)
– As a consultee to the planning process, the Environment Agency
comments on aspects relevant to the issue of a permit
Planning versus Permitting
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 3
Town and Country Planning (Environmental, Impact Assessment -
EIA) (England and Wales) Regulations 1999
Duxbury and Morton Statutes on Environmental Law 5th Ed. p.507-545, 2004
Implements EC Directive 85/337/EEC
Part 1 (3) Prohibition on granting planning permission without consideration of
environmental information.
3.2 The relevant planning authority or the Secretary of State or an
inspector shall not grant planning permission pursuant to an EIA
application for planning permission unless they have first taken the
environmental information into consideration and they shall state in
their decision that they have done so.
An ‘EIA application’ means an application for planning permission for EIA
development, which means development which is either (a) Schedule 1
development or (b) Schedule 2 development likely to have significant
effects on the environment by virtue of factors such as its nature, size
or location.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 4
‘Environmental information’ means the environmental
statement, which means a statement –
(a) that includes such of the information referred to in Part 1 of
Schedule 4 as is reasonably required to assess the
environmental effects of the development and which the
applicant can, having regard in particular to current
knowledge and methods of assessment, reasonably be
required to compile, but
(b) that includes at least the information referred to in Part II of
Schedule 4.
Note that we will deal with the specifics of how to apply this law
and what is required in an environmental statement at the end
of the course. We are summarising the legal requirements here.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 5
Schedule 1 development is the largest developments: airports
with runways >2,100m, crude oil refineries, >300MW thermal
power stations, nuclear power stations and nuclear reprocessing
sites (e.g. Sellafield), steel works and other metal manufacture
from ore, asbestos works, large chemical plants, construction
lines for main railways, motorway construction, inland
waterways (canals) construction, large road widening schemes,
waste disposal installations for incineration or chemical
treatment or landfill of hazardous waste, ground water
abstraction > 100 tonnes per day, waste water treatment plants,
petroleum or natural gas extraction, dams >10M m3 water
stored, massive poultry or pig farms, large paper and pulp
plants, large quarries, large petrochemical storage sites.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 6
Schedule 2 developments are virtually all other industries that
are smaller than the size specified in Schedule 1, but still larger
than another minimum size or are not mentioned in Schedule 1.
The principles are to specify Schedule 1 or 2 on the quantity of
material or animals or power produced. Also in Schedule 2 the
area of land involved is also used in the criteria e.g. quarries <
1000 m2 new quarry area is Schedule 2 and >25 hectacres of
total quarry size is Schedule 1. Much of Schedule 2 refers to
extension of the land area of an existing facility and is usually
>1000 m2 new land area for Schedule 2. Smaller than this and no
EIA is required when planning permission is applied for.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 7
Schedule 2 developments
1. Agriculture and aquaculture
2. Extractive Industries
3. Energy Industries
4. Production and Processing of Metals
5. Mineral Industry
6. Chemical Industry (unless in Schedule 1)
7. Food Industry
8. Textile, leather, wood and paper industries
9. Rubber industry
10. Infrastructure Project
11. Other Projects
12. Tourism and leisure
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 8
Schedule 4 – Information for inclusion in Environmental
Statements (Duxbury and Morton, Statutes in Env. Law 2004 p.544
Jack Rostron, Environmenental Law for the Built Environment, Cavendish 2001 p.61-75,
for a full discussion of the technical process of EIA.
Part 1 (Not compulsory but Part 2 is, can be asked for any or all
items in Part 1 by the Planning Officer)
1. Description of the development –
(a) physical characteristics and land-use requirements
during construction and operation.
(b) main characteristics of the production processes –
nature and quantity of materials used
(c) estimate, by type and quantity, of expected residues and
emissions (water, air and soil pollution, noise, vibration,
light, heat, radiation, etc.)
2. Outline of the main alternatives studied and an indication
of the reasons for choice, taking into account the
environmental effects.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 9
3. A description of the aspects of the environment likely to be
significantly affected by the development, including population,
fauna, flora, soil, water, air, climate factors, material assets,
architectural and archaeological heritage, landscape and their
inter-relationships.
4. A description of the likely significant effects of the development
on the environment, which should cover the direct effects and
any indirect, secondary, cumulative, short, medium and long-
term, permanent and temporary, positive and negative effects
of the development, resulting from:
(a) The existence of the development
(b) The use of natural resources
(c) The emissions of pollutants, the creation of nuisances and the
elimination of waste
And the description of the forecasting methods used.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 10
5. Description of the measures envisaged to prevent, reduce and
where possible offset any significant adverse effects on the
environment.
6. A non-technical summary of the information provided
7. An indication of any difficulties (technical deficiencies or lack
of know-how) encountered in compiling the required
information.
The ECs objective in adopting EIA was to prevent pollution at source by
requiring environmental information to be considered as part of the project
authorisation procedures and in the UK this has been done by incorporation
into the existing planning procedures. EIAs require the environmental effects
of a development to be considered by the developer and the information
provided to the planners to be used in their decision making process.
Hughes et al. Env. Law 4th Ed. 2002 p.207.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 11
Part II (These are the minimum requirements for EIA)
1. A description of the development comprising information
on the site, design and size of the development.
2. A description of the measures envisaged in order to avoid,
reduce and, if possible, remedy significant adverse effects.
3. The data required to identify and assess the main effects
which the development is likely to have on the
environment.
4. An outline of the main alternative studied and an indication
of the main reasons for the choice, taking into account the
environmental effects.
5. A non-technical summary of the information.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 12
Part V Publicity and procedures on submission of a EIA
13. Procedure where an EIA is submitted with the planning
application.
A key feature here is that the EIA is not made available for
public scrutiny.
14. Procedure where an EIA is submitted after the planning
application.
In this case the application has to be published in the local paper
stating that the EAI may be inspected by members of the
public and to give an address where this can be done,
which must be in the locality of the planning application.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 13
Part VI Notification of Decisions
20. Availability of opinions for inspection
All the documents relating to the decision have to be kept for two years. A copy of
the opinion, request or direction and any accompanying statement of reasons
must be available for public inspection.
This does not include public access to the EIA.
21 Duties to inform the public and the Sec. State of the final decision.
(c) Make available for public inspection a statement:
(i) the content and conditions of the decision
(ii) the main reasons on which the decision was based
(iii) a description of the main measures to avoid, reduce and if possible offset
the major adverse effects of the development.
This still does not give the public access to the EIA. But this is the firsts time that the
public have access to the reasons that planning consent was given. There is
still no mechanism for the public (or any third party) to appeal against a
planning consent decision. Only the developer has the right of appeal if there
is a refusal of planning consent. The public can only make representation
before the plans are approved and the system of notification of a planning
application is deeply flawed. The whole system is weighted in favour of the
developer and against the public.
Jack Rostron Env. Law for the Built Environment, Cavendish, 2001, p.54.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 14
Sustainable Planning Decision Making
Jack Rostron, Env. Law and the Built Environment, Cavendish, 2001, p.56-61.
Planning is not just about land use – there is also the issue of policy planning. This is
being driven at present in the EC by the ideal of sustainability, which grew out
of the no growth debate. The most commonly accepted definition of
sustainable development is that of the Brundtland Commission in 1987:
‘Sustainable development is development that meet the needs to the
present without compromising the ability of future generations to
meet their own needs’
There are 3 core parts to sustainable development:
(a) Inclusion of environmental considerations in policy
(b) Commitment to a fair distribution of resources
(c) Development that acknowledges health, education and the
environment considerations.
The government has had a Sustainable development panel since 1994
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 15
Gateshead Metropolitan BC v. Secretary of State for the Environment
and Northumbrian Water Group plc. 1993
Wolf and Stanley on Environmental Law 2003 p.333
Wolf and White Environmental Law 1995 p. 338-342, Cavendish.
GMBC refused outline planning permission for a clinical waste
incinerator to be built in Gateshead by NWG. The refusal was based
on the grounds that NWG had failed to supply sufficient information
to demonstrate that the plant would operate without causing a
nuisance to the surrounding locality, including the possible release of
noxious substances. The NWG appealed to the Secretary of State
and a local public enquiry was held. This recommended that the
appeal was dismissed on the grounds that ‘the impact on air quality
and agriculture in the semi-rural location is insufficiently defined and
that public disquiet over dioxin pollution cannot be allayed and so
make the application acceptable’.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 16
However, the Secretary of State for the Environment chose to act
against the public inquiry’s inspector’s recommendation and granted
planning permission. The Secretary of State accepted that the
pollution arising from the incinerator and its impact on neighbouring
land uses could constitute material considerations. However, he also
stated that:
‘While the planning system must determine the location of facilities
of this kind, taking into account of the provisions of the
development plan and other material considerations, the Secretary
of State considers that it is not the role of the planning system to
duplicate controls under the Environmental Protection Act 1990’
He went on to assert that the controls under the EPA were adequate
and control of emissions from the incinerator should be regulated by
HMIP (now EA).This would apply today to the IED being deemed
adequate control.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 17
GMBC appealed against the Secretary of States decision, but their
appeal was rejected by both the High Court and the Court of Appeal.
The High Court held that the existence of a stringent pollution control regime
under the EPA or IED was a material consideration in a planning decision. Lord
Justice Glidewell, in the Court of Appeal, accepted that the two systems of control
overlapped. However, the Court of Appeal unheld the decision of the High Court
and stated that the potential for environmental pollution would be a material
consideration when determining planning applications but so would the existence
of a system of environmental control administered by pollution control authorities.
The impact of this judgement was that it could not be argued in a planning
application that the plant would not conform to statutory air and water pollution
emission requirements, as this was for the EA to enforce. The planning permission
system could be used to ensure that the correct equipment was fitted to control the
pollution, but it could not be assumed that the equipment would not work or would
not be used – this was for the EA to police.
CAPE2020 Environmental Management and Air Quality
Prof. G..E. Andrews 2019/20
Contents
1. Introduction to the Air Quality and Environmental Management part of the module.
2. Introduction to legal framework for Air Quality legislation and the changes in the draft
Environment Bill
3. Health effects of air pollutants
4. Particulate air pollution and particle size distribution and the health effects of ultra-fine particles
5. Sources of Air pollution and Trends in emissions of pollutants that contribute to poor air quality.
6. Air quality Regulations
7. Air quality monitoring
8. Air quality limit value Regulations
9. Occupational exposure to pollution – COSHH
10. The Clean Air Acts
11. Meteorology and pollutant dispersion
12. Environmental Law
13. Town and Country Act planning law for Environmental Impact
14. Environmental Management in Industry
15. Preparing an Environmental Permit - examples
16. Emissions measurement from industrial plant
CAPE2020 Environmental Management and Air Quality
Prof. G..E. Andrews 2019/20
Contents
1. Introduction to the Air Quality and Environmental Management part of the module.
2. Introduction to legal framework for Air Quality legislation and the changes in the draft
Environment Bill
3. Health effects of air pollutants
4. Particulate air pollution and particle size distribution and the health effects of ultra-fine particles
5. Sources of Air pollution and Trends in emissions of pollutants that contribute to poor air quality.
6. Air quality Regulations
7. Air quality monitoring
8. Air quality limit value Regulations
9. Occupational exposure to pollution – COSHH
10. The Clean Air Acts
11. Meteorology and pollutant dispersion
12. Environmental Law
13. Town and Country Act planning law for Environmental Impact
14. Environmental Management in Industry
15. Preparing an Environmental Permit - examples
16. Emissions measurement from industrial plant
• Planning
– Controls the development and use of land in the public interest including
consideration of the impacts on the local environment and amenity
– Should assume that other regimes (e.g. Environmental Permitting
Regulations) operate effectively
• Environmental permitting
– Controls the impact on the environment and human health from the
process plant
– Ensures EU directive requirements are met including use of Best
Available Techniques (BAT)
– As a consultee to the planning process, the Environment Agency
comments on aspects relevant to the issue of a permit
Planning versus Permitting
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 21
Town and Country Planning (Environmental, Impact Assessment -
EIA) (England and Wales) Regulations 1999
Duxbury and Morton Statutes on Environmental Law 5th Ed. p.507-545, 2004
Implements EC Directive 85/337/EEC
Part 1 (3) Prohibition on granting planning permission without consideration of
environmental information.
3.2 The relevant planning authority or the Secretary of State or an
inspector shall not grant planning permission pursuant to an EIA
application for planning permission unless they have first taken the
environmental information into consideration and they shall state in
their decision that they have done so.
An ‘EIA application’ means an application for planning permission for EIA
development, which means development which is either (a) Schedule 1
development or (b) Schedule 2 development likely to have significant
effects on the environment by virtue of factors such as its nature, size
or location.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 22
‘Environmental information’ means the environmental
statement, which means a statement –
(a) that includes such of the information referred to in Part 1 of
Schedule 4 as is reasonably required to assess the
environmental effects of the development and which the
applicant can, having regard in particular to current
knowledge and methods of assessment, reasonably be
required to compile, but
(b) that includes at least the information referred to in Part II of
Schedule 4.
Note that we will deal with the specifics of how to apply this law
and what is required in an environmental statement at the end
of the course. We are summarising the legal requirements here.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 23
Schedule 1 development is the largest developments: airports
with runways >2,100m, crude oil refineries, >300MW thermal
power stations, nuclear power stations and nuclear reprocessing
sites (e.g. Sellafield), steel works and other metal manufacture
from ore, asbestos works, large chemical plants, construction
lines for main railways, motorway construction, inland
waterways (canals) construction, large road widening schemes,
waste disposal installations for incineration or chemical
treatment or landfill of hazardous waste, ground water
abstraction > 100 tonnes per day, waste water treatment plants,
petroleum or natural gas extraction, dams >10M m3 water
stored, massive poultry or pig farms, large paper and pulp
plants, large quarries, large petrochemical storage sites.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 24
Schedule 2 developments are virtually all other industries that
are smaller than the size specified in Schedule 1, but still larger
than another minimum size or are not mentioned in Schedule 1.
The principles are to specify Schedule 1 or 2 on the quantity of
material or animals or power produced. Also in Schedule 2 the
area of land involved is also used in the criteria e.g. quarries <
1000 m2 new quarry area is Schedule 2 and >25 hectacres of
total quarry size is Schedule 1. Much of Schedule 2 refers to
extension of the land area of an existing facility and is usually
>1000 m2 new land area for Schedule 2. Smaller than this and no
EIA is required when planning permission is applied for.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 25
Schedule 2 developments
1. Agriculture and aquaculture
2. Extractive Industries
3. Energy Industries
4. Production and Processing of Metals
5. Mineral Industry
6. Chemical Industry (unless in Schedule 1)
7. Food Industry
8. Textile, leather, wood and paper industries
9. Rubber industry
10. Infrastructure Project
11. Other Projects
12. Tourism and leisure
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 26
Schedule 4 – Information for inclusion in Environmental
Statements (Duxbury and Morton, Statutes in Env. Law 2004 p.544
Jack Rostron, Environmenental Law for the Built Environment, Cavendish 2001 p.61-75,
for a full discussion of the technical process of EIA.
Part 1 (Not compulsory but Part 2 is, can be asked for any or all
items in Part 1 by the Planning Officer)
1. Description of the development –
(a) physical characteristics and land-use requirements
during construction and operation.
(b) main characteristics of the production processes –
nature and quantity of materials used
(c) estimate, by type and quantity, of expected residues and
emissions (water, air and soil pollution, noise, vibration,
light, heat, radiation, etc.)
2. Outline of the main alternatives studied and an indication
of the reasons for choice, taking into account the
environmental effects.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 27
3. A description of the aspects of the environment likely to be
significantly affected by the development, including population,
fauna, flora, soil, water, air, climate factors, material assets,
architectural and archaeological heritage, landscape and their
inter-relationships.
4. A description of the likely significant effects of the development
on the environment, which should cover the direct effects and
any indirect, secondary, cumulative, short, medium and long-
term, permanent and temporary, positive and negative effects
of the development, resulting from:
(a) The existence of the development
(b) The use of natural resources
(c) The emissions of pollutants, the creation of nuisances and the
elimination of waste
And the description of the forecasting methods used.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 28
5. Description of the measures envisaged to prevent, reduce and
where possible offset any significant adverse effects on the
environment.
6. A non-technical summary of the information provided
7. An indication of any difficulties (technical deficiencies or lack
of know-how) encountered in compiling the required
information.
The ECs objective in adopting EIA was to prevent pollution at source by
requiring environmental information to be considered as part of the project
authorisation procedures and in the UK this has been done by incorporation
into the existing planning procedures. EIAs require the environmental effects
of a development to be considered by the developer and the information
provided to the planners to be used in their decision making process.
Hughes et al. Env. Law 4th Ed. 2002 p.207.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 29
Part II (These are the minimum requirements for EIA)
1. A description of the development comprising information
on the site, design and size of the development.
2. A description of the measures envisaged in order to avoid,
reduce and, if possible, remedy significant adverse effects.
3. The data required to identify and assess the main effects
which the development is likely to have on the
environment.
4. An outline of the main alternative studied and an indication
of the main reasons for the choice, taking into account the
environmental effects.
5. A non-technical summary of the information.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 30
Part V Publicity and procedures on submission of a EIA
13. Procedure where an EIA is submitted with the planning
application.
A key feature here is that the EIA is not made available for
public scrutiny.
14. Procedure where an EIA is submitted after the planning
application.
In this case the application has to be published in the local paper
stating that the EAI may be inspected by members of the
public and to give an address where this can be done,
which must be in the locality of the planning application.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 31
Part VI Notification of Decisions
20. Availability of opinions for inspection
All the documents relating to the decision have to be kept for two years. A copy of
the opinion, request or direction and any accompanying statement of reasons
must be available for public inspection.
This does not include public access to the EIA.
21 Duties to inform the public and the Sec. State of the final decision.
(c) Make available for public inspection a statement:
(i) the content and conditions of the decision
(ii) the main reasons on which the decision was based
(iii) a description of the main measures to avoid, reduce and if possible offset
the major adverse effects of the development.
This still does not give the public access to the EIA. But this is the firsts time that the
public have access to the reasons that planning consent was given. There is
still no mechanism for the public (or any third party) to appeal against a
planning consent decision. Only the developer has the right of appeal if there
is a refusal of planning consent. The public can only make representation
before the plans are approved and the system of notification of a planning
application is deeply flawed. The whole system is weighted in favour of the
developer and against the public.
Jack Rostron Env. Law for the Built Environment, Cavendish, 2001, p.54.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 32
Sustainable Planning Decision Making
Jack Rostron, Env. Law and the Built Environment, Cavendish, 2001, p.56-61.
Planning is not just about land use – there is also the issue of policy planning. This is
being driven at present in the EC by the ideal of sustainability, which grew out
of the no growth debate. The most commonly accepted definition of
sustainable development is that of the Brundtland Commission in 1987:
‘Sustainable development is development that meet the needs to the
present without compromising the ability of future generations to
meet their own needs’
There are 3 core parts to sustainable development:
(a) Inclusion of environmental considerations in policy
(b) Commitment to a fair distribution of resources
(c) Development that acknowledges health, education and the
environment considerations.
The government has had a Sustainable development panel since 1994
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 33
Gateshead Metropolitan BC v. Secretary of State for the Environment
and Northumbrian Water Group plc. 1993
Wolf and Stanley on Environmental Law 2003 p.333
Wolf and White Environmental Law 1995 p. 338-342, Cavendish.
GMBC refused outline planning permission for a clinical waste
incinerator to be built in Gateshead by NWG. The refusal was based
on the grounds that NWG had failed to supply sufficient information
to demonstrate that the plant would operate without causing a
nuisance to the surrounding locality, including the possible release of
noxious substances. The NWG appealed to the Secretary of State
and a local public enquiry was held. This recommended that the
appeal was dismissed on the grounds that ‘the impact on air quality
and agriculture in the semi-rural location is insufficiently defined and
that public disquiet over dioxin pollution cannot be allayed and so
make the application acceptable’.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 34
However, the Secretary of State for the Environment chose to act
against the public inquiry’s inspector’s recommendation and granted
planning permission. The Secretary of State accepted that the
pollution arising from the incinerator and its impact on neighbouring
land uses could constitute material considerations. However, he also
stated that:
‘While the planning system must determine the location of facilities
of this kind, taking into account of the provisions of the
development plan and other material considerations, the Secretary
of State considers that it is not the role of the planning system to
duplicate controls under the Environmental Protection Act 1990’
He went on to assert that the controls under the EPA were adequate
and control of emissions from the incinerator should be regulated by
HMIP (now EA).This would apply today to the IED being deemed
adequate control.
Environmental Management
Prof. Gordon E. Andrews, SCAPE, U. Leeds. 35
GMBC appealed against the Secretary of States decision, but their appeal was rejected
by both the High Court and the Court of Appeal.
The High Court held that the existence of a stringent pollution control regime under the
EPA or IED was a material consideration in a planning decision. Lord Justice Glidewell,
in the Court of Appeal, accepted that the two systems of control overlapped. However,
the Court of Appeal unheld the decision of the High Court and stated that the potential
for environmental pollution would be a material consideration when determining
planning applications but so would the existence of a system of environmental control
administered by pollution control authorities.
The impact of this judgement was that it could not be argued in a planning application
that the plant would not conform to statutory air and water pollution emission
requirements, as this was for the EA to enforce. The planning permission system could
be used to ensure that the correct equipment was fitted to control the pollution, but it
could not be assumed that the equipment would not work or would not be used – this
was for the EA to police.
CAPE2020 Environmental Management and Air Quality
Prof. G..E. Andrews 2019/20
Contents
1. Introduction to the Air Quality and Environmental Management part of the module.
2. Introduction to legal framework for Air Quality legislation and the changes in the draft
Environment Bill
3. Health effects of air pollutants
4. Particulate air pollution and particle size distribution and the health effects of ultra-fine particles
5. Sources of Air pollution and Trends in emissions of pollutants that contribute to poor air quality.
6. Air quality Regulations
7. Air quality monitoring
8. Air quality limit value Regulations
9. Occupational exposure to pollution – COSHH
10. The Clean Air Acts
11. Meteorology and pollutant dispersion
12. Environmental Law
13. Town and Country Act planning law for Environmental Impact
14. Environmental Management in Industry
15. Preparing an Environmental Permit - examples
16. Emissions measurement from industrial plant

More Related Content

Similar to Section 13 Planning Law and Environment protection CAPE2020 2021.pptx

Environment impact assessment study
Environment impact assessment studyEnvironment impact assessment study
Environment impact assessment studyArvind Kumar
 
EIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & AquacultureEIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & AquacultureKANTHARAJAN GANESAN
 
Environmental impact assessment(EIA) For Thermal Power Plants.docx.pdf
Environmental impact assessment(EIA) For Thermal Power Plants.docx.pdfEnvironmental impact assessment(EIA) For Thermal Power Plants.docx.pdf
Environmental impact assessment(EIA) For Thermal Power Plants.docx.pdfJagriti Agarwal
 
Environmental impact assessment(EIA) For Thermal Power Plants.pdf
Environmental impact assessment(EIA) For Thermal Power Plants.pdfEnvironmental impact assessment(EIA) For Thermal Power Plants.pdf
Environmental impact assessment(EIA) For Thermal Power Plants.pdfJagriti Agarwal
 
JBA Consulting Guide to Environmental Assessment for Renewable Projects
JBA Consulting Guide to Environmental Assessment for Renewable ProjectsJBA Consulting Guide to Environmental Assessment for Renewable Projects
JBA Consulting Guide to Environmental Assessment for Renewable ProjectsJBAConsulting
 
g-screening-full-text.pdf
g-screening-full-text.pdfg-screening-full-text.pdf
g-screening-full-text.pdfssuser49a2b6
 
Environmental impact assessment of mining projects 17.03.09
Environmental impact assessment of mining projects 17.03.09Environmental impact assessment of mining projects 17.03.09
Environmental impact assessment of mining projects 17.03.09Mohit Singh
 
Environmental Impact Evaluation of Mining
Environmental Impact Evaluation of MiningEnvironmental Impact Evaluation of Mining
Environmental Impact Evaluation of Miningijtsrd
 
Suraj 2 environmental protection act-1986
Suraj 2  environmental protection act-1986Suraj 2  environmental protection act-1986
Suraj 2 environmental protection act-1986DEVIKA ANTHARJANAM
 
The Environment Conservation Rules, 1997
The Environment Conservation Rules, 1997 The Environment Conservation Rules, 1997
The Environment Conservation Rules, 1997 Priodeep Chowdhury
 
Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997Abdullah Saif
 
Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997Abdullah Saif
 
AIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITY
AIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITYAIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITY
AIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITYIRJET Journal
 
AIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITY
AIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITYAIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITY
AIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITYIRJET Journal
 
KISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIAKISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIAMNIT,JAIPUR
 
Environment management Tools : EIA & Environmetal Audit
Environment management Tools : EIA & Environmetal AuditEnvironment management Tools : EIA & Environmetal Audit
Environment management Tools : EIA & Environmetal AuditKANTHARAJAN GANESAN
 

Similar to Section 13 Planning Law and Environment protection CAPE2020 2021.pptx (20)

EIA Introduction
EIA IntroductionEIA Introduction
EIA Introduction
 
Environment impact assessment study
Environment impact assessment studyEnvironment impact assessment study
Environment impact assessment study
 
EIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & AquacultureEIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & Aquaculture
 
Environmental impact assessment(EIA) For Thermal Power Plants.docx.pdf
Environmental impact assessment(EIA) For Thermal Power Plants.docx.pdfEnvironmental impact assessment(EIA) For Thermal Power Plants.docx.pdf
Environmental impact assessment(EIA) For Thermal Power Plants.docx.pdf
 
Environmental impact assessment(EIA) For Thermal Power Plants.pdf
Environmental impact assessment(EIA) For Thermal Power Plants.pdfEnvironmental impact assessment(EIA) For Thermal Power Plants.pdf
Environmental impact assessment(EIA) For Thermal Power Plants.pdf
 
JBA Consulting Guide to Environmental Assessment for Renewable Projects
JBA Consulting Guide to Environmental Assessment for Renewable ProjectsJBA Consulting Guide to Environmental Assessment for Renewable Projects
JBA Consulting Guide to Environmental Assessment for Renewable Projects
 
g-screening-full-text.pdf
g-screening-full-text.pdfg-screening-full-text.pdf
g-screening-full-text.pdf
 
Environmental impact assessment of mining projects 17.03.09
Environmental impact assessment of mining projects 17.03.09Environmental impact assessment of mining projects 17.03.09
Environmental impact assessment of mining projects 17.03.09
 
Environmental Impact Evaluation of Mining
Environmental Impact Evaluation of MiningEnvironmental Impact Evaluation of Mining
Environmental Impact Evaluation of Mining
 
Suraj 2 environmental protection act-1986
Suraj 2  environmental protection act-1986Suraj 2  environmental protection act-1986
Suraj 2 environmental protection act-1986
 
EIA.pptx
EIA.pptxEIA.pptx
EIA.pptx
 
EIA Final Version
EIA Final VersionEIA Final Version
EIA Final Version
 
The Environment Conservation Rules, 1997
The Environment Conservation Rules, 1997 The Environment Conservation Rules, 1997
The Environment Conservation Rules, 1997
 
Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997
 
Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997
 
Final booklet
Final bookletFinal booklet
Final booklet
 
AIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITY
AIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITYAIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITY
AIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITY
 
AIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITY
AIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITYAIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITY
AIR POLLUTION IMPACT ON ENVIRONMENT IN KOZHIKODE CITY
 
KISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIAKISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIA
 
Environment management Tools : EIA & Environmetal Audit
Environment management Tools : EIA & Environmetal AuditEnvironment management Tools : EIA & Environmetal Audit
Environment management Tools : EIA & Environmetal Audit
 

Recently uploaded

Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 

Recently uploaded (20)

Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 

Section 13 Planning Law and Environment protection CAPE2020 2021.pptx

  • 1. CAPE2020 Environmental Management and Air Quality Prof. G..E. Andrews 2019/20 Contents 1. Introduction to the Air Quality and Environmental Management part of the module. 2. Introduction to legal framework for Air Quality legislation and the changes in the draft Environment Bill 3. Health effects of air pollutants 4. Particulate air pollution and particle size distribution and the health effects of ultra-fine particles 5. Sources of Air pollution and Trends in emissions of pollutants that contribute to poor air quality. 6. Air quality Regulations 7. Air quality monitoring 8. Air quality limit value Regulations 9. Occupational exposure to pollution – COSHH 10. The Clean Air Acts 11. Meteorology and pollutant dispersion 12. Environmental Law 13. Town and Country Act planning law for Environmental Impact 14. Environmental Management in Industry 15. Preparing an Environmental Permit - examples 16. Emissions measurement from industrial plant
  • 2. • Planning – Controls the development and use of land in the public interest including consideration of the impacts on the local environment and amenity – Should assume that other regimes (e.g. Environmental Permitting Regulations) operate effectively • Environmental permitting – Controls the impact on the environment and human health from the process plant – Ensures EU directive requirements are met including use of Best Available Techniques (BAT) – As a consultee to the planning process, the Environment Agency comments on aspects relevant to the issue of a permit Planning versus Permitting
  • 3. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 3 Town and Country Planning (Environmental, Impact Assessment - EIA) (England and Wales) Regulations 1999 Duxbury and Morton Statutes on Environmental Law 5th Ed. p.507-545, 2004 Implements EC Directive 85/337/EEC Part 1 (3) Prohibition on granting planning permission without consideration of environmental information. 3.2 The relevant planning authority or the Secretary of State or an inspector shall not grant planning permission pursuant to an EIA application for planning permission unless they have first taken the environmental information into consideration and they shall state in their decision that they have done so. An ‘EIA application’ means an application for planning permission for EIA development, which means development which is either (a) Schedule 1 development or (b) Schedule 2 development likely to have significant effects on the environment by virtue of factors such as its nature, size or location.
  • 4. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 4 ‘Environmental information’ means the environmental statement, which means a statement – (a) that includes such of the information referred to in Part 1 of Schedule 4 as is reasonably required to assess the environmental effects of the development and which the applicant can, having regard in particular to current knowledge and methods of assessment, reasonably be required to compile, but (b) that includes at least the information referred to in Part II of Schedule 4. Note that we will deal with the specifics of how to apply this law and what is required in an environmental statement at the end of the course. We are summarising the legal requirements here.
  • 5. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 5 Schedule 1 development is the largest developments: airports with runways >2,100m, crude oil refineries, >300MW thermal power stations, nuclear power stations and nuclear reprocessing sites (e.g. Sellafield), steel works and other metal manufacture from ore, asbestos works, large chemical plants, construction lines for main railways, motorway construction, inland waterways (canals) construction, large road widening schemes, waste disposal installations for incineration or chemical treatment or landfill of hazardous waste, ground water abstraction > 100 tonnes per day, waste water treatment plants, petroleum or natural gas extraction, dams >10M m3 water stored, massive poultry or pig farms, large paper and pulp plants, large quarries, large petrochemical storage sites.
  • 6. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 6 Schedule 2 developments are virtually all other industries that are smaller than the size specified in Schedule 1, but still larger than another minimum size or are not mentioned in Schedule 1. The principles are to specify Schedule 1 or 2 on the quantity of material or animals or power produced. Also in Schedule 2 the area of land involved is also used in the criteria e.g. quarries < 1000 m2 new quarry area is Schedule 2 and >25 hectacres of total quarry size is Schedule 1. Much of Schedule 2 refers to extension of the land area of an existing facility and is usually >1000 m2 new land area for Schedule 2. Smaller than this and no EIA is required when planning permission is applied for.
  • 7. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 7 Schedule 2 developments 1. Agriculture and aquaculture 2. Extractive Industries 3. Energy Industries 4. Production and Processing of Metals 5. Mineral Industry 6. Chemical Industry (unless in Schedule 1) 7. Food Industry 8. Textile, leather, wood and paper industries 9. Rubber industry 10. Infrastructure Project 11. Other Projects 12. Tourism and leisure
  • 8. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 8 Schedule 4 – Information for inclusion in Environmental Statements (Duxbury and Morton, Statutes in Env. Law 2004 p.544 Jack Rostron, Environmenental Law for the Built Environment, Cavendish 2001 p.61-75, for a full discussion of the technical process of EIA. Part 1 (Not compulsory but Part 2 is, can be asked for any or all items in Part 1 by the Planning Officer) 1. Description of the development – (a) physical characteristics and land-use requirements during construction and operation. (b) main characteristics of the production processes – nature and quantity of materials used (c) estimate, by type and quantity, of expected residues and emissions (water, air and soil pollution, noise, vibration, light, heat, radiation, etc.) 2. Outline of the main alternatives studied and an indication of the reasons for choice, taking into account the environmental effects.
  • 9. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 9 3. A description of the aspects of the environment likely to be significantly affected by the development, including population, fauna, flora, soil, water, air, climate factors, material assets, architectural and archaeological heritage, landscape and their inter-relationships. 4. A description of the likely significant effects of the development on the environment, which should cover the direct effects and any indirect, secondary, cumulative, short, medium and long- term, permanent and temporary, positive and negative effects of the development, resulting from: (a) The existence of the development (b) The use of natural resources (c) The emissions of pollutants, the creation of nuisances and the elimination of waste And the description of the forecasting methods used.
  • 10. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 10 5. Description of the measures envisaged to prevent, reduce and where possible offset any significant adverse effects on the environment. 6. A non-technical summary of the information provided 7. An indication of any difficulties (technical deficiencies or lack of know-how) encountered in compiling the required information. The ECs objective in adopting EIA was to prevent pollution at source by requiring environmental information to be considered as part of the project authorisation procedures and in the UK this has been done by incorporation into the existing planning procedures. EIAs require the environmental effects of a development to be considered by the developer and the information provided to the planners to be used in their decision making process. Hughes et al. Env. Law 4th Ed. 2002 p.207.
  • 11. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 11 Part II (These are the minimum requirements for EIA) 1. A description of the development comprising information on the site, design and size of the development. 2. A description of the measures envisaged in order to avoid, reduce and, if possible, remedy significant adverse effects. 3. The data required to identify and assess the main effects which the development is likely to have on the environment. 4. An outline of the main alternative studied and an indication of the main reasons for the choice, taking into account the environmental effects. 5. A non-technical summary of the information.
  • 12. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 12 Part V Publicity and procedures on submission of a EIA 13. Procedure where an EIA is submitted with the planning application. A key feature here is that the EIA is not made available for public scrutiny. 14. Procedure where an EIA is submitted after the planning application. In this case the application has to be published in the local paper stating that the EAI may be inspected by members of the public and to give an address where this can be done, which must be in the locality of the planning application.
  • 13. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 13 Part VI Notification of Decisions 20. Availability of opinions for inspection All the documents relating to the decision have to be kept for two years. A copy of the opinion, request or direction and any accompanying statement of reasons must be available for public inspection. This does not include public access to the EIA. 21 Duties to inform the public and the Sec. State of the final decision. (c) Make available for public inspection a statement: (i) the content and conditions of the decision (ii) the main reasons on which the decision was based (iii) a description of the main measures to avoid, reduce and if possible offset the major adverse effects of the development. This still does not give the public access to the EIA. But this is the firsts time that the public have access to the reasons that planning consent was given. There is still no mechanism for the public (or any third party) to appeal against a planning consent decision. Only the developer has the right of appeal if there is a refusal of planning consent. The public can only make representation before the plans are approved and the system of notification of a planning application is deeply flawed. The whole system is weighted in favour of the developer and against the public. Jack Rostron Env. Law for the Built Environment, Cavendish, 2001, p.54.
  • 14. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 14 Sustainable Planning Decision Making Jack Rostron, Env. Law and the Built Environment, Cavendish, 2001, p.56-61. Planning is not just about land use – there is also the issue of policy planning. This is being driven at present in the EC by the ideal of sustainability, which grew out of the no growth debate. The most commonly accepted definition of sustainable development is that of the Brundtland Commission in 1987: ‘Sustainable development is development that meet the needs to the present without compromising the ability of future generations to meet their own needs’ There are 3 core parts to sustainable development: (a) Inclusion of environmental considerations in policy (b) Commitment to a fair distribution of resources (c) Development that acknowledges health, education and the environment considerations. The government has had a Sustainable development panel since 1994
  • 15. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 15 Gateshead Metropolitan BC v. Secretary of State for the Environment and Northumbrian Water Group plc. 1993 Wolf and Stanley on Environmental Law 2003 p.333 Wolf and White Environmental Law 1995 p. 338-342, Cavendish. GMBC refused outline planning permission for a clinical waste incinerator to be built in Gateshead by NWG. The refusal was based on the grounds that NWG had failed to supply sufficient information to demonstrate that the plant would operate without causing a nuisance to the surrounding locality, including the possible release of noxious substances. The NWG appealed to the Secretary of State and a local public enquiry was held. This recommended that the appeal was dismissed on the grounds that ‘the impact on air quality and agriculture in the semi-rural location is insufficiently defined and that public disquiet over dioxin pollution cannot be allayed and so make the application acceptable’.
  • 16. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 16 However, the Secretary of State for the Environment chose to act against the public inquiry’s inspector’s recommendation and granted planning permission. The Secretary of State accepted that the pollution arising from the incinerator and its impact on neighbouring land uses could constitute material considerations. However, he also stated that: ‘While the planning system must determine the location of facilities of this kind, taking into account of the provisions of the development plan and other material considerations, the Secretary of State considers that it is not the role of the planning system to duplicate controls under the Environmental Protection Act 1990’ He went on to assert that the controls under the EPA were adequate and control of emissions from the incinerator should be regulated by HMIP (now EA).This would apply today to the IED being deemed adequate control.
  • 17. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 17 GMBC appealed against the Secretary of States decision, but their appeal was rejected by both the High Court and the Court of Appeal. The High Court held that the existence of a stringent pollution control regime under the EPA or IED was a material consideration in a planning decision. Lord Justice Glidewell, in the Court of Appeal, accepted that the two systems of control overlapped. However, the Court of Appeal unheld the decision of the High Court and stated that the potential for environmental pollution would be a material consideration when determining planning applications but so would the existence of a system of environmental control administered by pollution control authorities. The impact of this judgement was that it could not be argued in a planning application that the plant would not conform to statutory air and water pollution emission requirements, as this was for the EA to enforce. The planning permission system could be used to ensure that the correct equipment was fitted to control the pollution, but it could not be assumed that the equipment would not work or would not be used – this was for the EA to police.
  • 18. CAPE2020 Environmental Management and Air Quality Prof. G..E. Andrews 2019/20 Contents 1. Introduction to the Air Quality and Environmental Management part of the module. 2. Introduction to legal framework for Air Quality legislation and the changes in the draft Environment Bill 3. Health effects of air pollutants 4. Particulate air pollution and particle size distribution and the health effects of ultra-fine particles 5. Sources of Air pollution and Trends in emissions of pollutants that contribute to poor air quality. 6. Air quality Regulations 7. Air quality monitoring 8. Air quality limit value Regulations 9. Occupational exposure to pollution – COSHH 10. The Clean Air Acts 11. Meteorology and pollutant dispersion 12. Environmental Law 13. Town and Country Act planning law for Environmental Impact 14. Environmental Management in Industry 15. Preparing an Environmental Permit - examples 16. Emissions measurement from industrial plant
  • 19. CAPE2020 Environmental Management and Air Quality Prof. G..E. Andrews 2019/20 Contents 1. Introduction to the Air Quality and Environmental Management part of the module. 2. Introduction to legal framework for Air Quality legislation and the changes in the draft Environment Bill 3. Health effects of air pollutants 4. Particulate air pollution and particle size distribution and the health effects of ultra-fine particles 5. Sources of Air pollution and Trends in emissions of pollutants that contribute to poor air quality. 6. Air quality Regulations 7. Air quality monitoring 8. Air quality limit value Regulations 9. Occupational exposure to pollution – COSHH 10. The Clean Air Acts 11. Meteorology and pollutant dispersion 12. Environmental Law 13. Town and Country Act planning law for Environmental Impact 14. Environmental Management in Industry 15. Preparing an Environmental Permit - examples 16. Emissions measurement from industrial plant
  • 20. • Planning – Controls the development and use of land in the public interest including consideration of the impacts on the local environment and amenity – Should assume that other regimes (e.g. Environmental Permitting Regulations) operate effectively • Environmental permitting – Controls the impact on the environment and human health from the process plant – Ensures EU directive requirements are met including use of Best Available Techniques (BAT) – As a consultee to the planning process, the Environment Agency comments on aspects relevant to the issue of a permit Planning versus Permitting
  • 21. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 21 Town and Country Planning (Environmental, Impact Assessment - EIA) (England and Wales) Regulations 1999 Duxbury and Morton Statutes on Environmental Law 5th Ed. p.507-545, 2004 Implements EC Directive 85/337/EEC Part 1 (3) Prohibition on granting planning permission without consideration of environmental information. 3.2 The relevant planning authority or the Secretary of State or an inspector shall not grant planning permission pursuant to an EIA application for planning permission unless they have first taken the environmental information into consideration and they shall state in their decision that they have done so. An ‘EIA application’ means an application for planning permission for EIA development, which means development which is either (a) Schedule 1 development or (b) Schedule 2 development likely to have significant effects on the environment by virtue of factors such as its nature, size or location.
  • 22. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 22 ‘Environmental information’ means the environmental statement, which means a statement – (a) that includes such of the information referred to in Part 1 of Schedule 4 as is reasonably required to assess the environmental effects of the development and which the applicant can, having regard in particular to current knowledge and methods of assessment, reasonably be required to compile, but (b) that includes at least the information referred to in Part II of Schedule 4. Note that we will deal with the specifics of how to apply this law and what is required in an environmental statement at the end of the course. We are summarising the legal requirements here.
  • 23. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 23 Schedule 1 development is the largest developments: airports with runways >2,100m, crude oil refineries, >300MW thermal power stations, nuclear power stations and nuclear reprocessing sites (e.g. Sellafield), steel works and other metal manufacture from ore, asbestos works, large chemical plants, construction lines for main railways, motorway construction, inland waterways (canals) construction, large road widening schemes, waste disposal installations for incineration or chemical treatment or landfill of hazardous waste, ground water abstraction > 100 tonnes per day, waste water treatment plants, petroleum or natural gas extraction, dams >10M m3 water stored, massive poultry or pig farms, large paper and pulp plants, large quarries, large petrochemical storage sites.
  • 24. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 24 Schedule 2 developments are virtually all other industries that are smaller than the size specified in Schedule 1, but still larger than another minimum size or are not mentioned in Schedule 1. The principles are to specify Schedule 1 or 2 on the quantity of material or animals or power produced. Also in Schedule 2 the area of land involved is also used in the criteria e.g. quarries < 1000 m2 new quarry area is Schedule 2 and >25 hectacres of total quarry size is Schedule 1. Much of Schedule 2 refers to extension of the land area of an existing facility and is usually >1000 m2 new land area for Schedule 2. Smaller than this and no EIA is required when planning permission is applied for.
  • 25. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 25 Schedule 2 developments 1. Agriculture and aquaculture 2. Extractive Industries 3. Energy Industries 4. Production and Processing of Metals 5. Mineral Industry 6. Chemical Industry (unless in Schedule 1) 7. Food Industry 8. Textile, leather, wood and paper industries 9. Rubber industry 10. Infrastructure Project 11. Other Projects 12. Tourism and leisure
  • 26. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 26 Schedule 4 – Information for inclusion in Environmental Statements (Duxbury and Morton, Statutes in Env. Law 2004 p.544 Jack Rostron, Environmenental Law for the Built Environment, Cavendish 2001 p.61-75, for a full discussion of the technical process of EIA. Part 1 (Not compulsory but Part 2 is, can be asked for any or all items in Part 1 by the Planning Officer) 1. Description of the development – (a) physical characteristics and land-use requirements during construction and operation. (b) main characteristics of the production processes – nature and quantity of materials used (c) estimate, by type and quantity, of expected residues and emissions (water, air and soil pollution, noise, vibration, light, heat, radiation, etc.) 2. Outline of the main alternatives studied and an indication of the reasons for choice, taking into account the environmental effects.
  • 27. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 27 3. A description of the aspects of the environment likely to be significantly affected by the development, including population, fauna, flora, soil, water, air, climate factors, material assets, architectural and archaeological heritage, landscape and their inter-relationships. 4. A description of the likely significant effects of the development on the environment, which should cover the direct effects and any indirect, secondary, cumulative, short, medium and long- term, permanent and temporary, positive and negative effects of the development, resulting from: (a) The existence of the development (b) The use of natural resources (c) The emissions of pollutants, the creation of nuisances and the elimination of waste And the description of the forecasting methods used.
  • 28. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 28 5. Description of the measures envisaged to prevent, reduce and where possible offset any significant adverse effects on the environment. 6. A non-technical summary of the information provided 7. An indication of any difficulties (technical deficiencies or lack of know-how) encountered in compiling the required information. The ECs objective in adopting EIA was to prevent pollution at source by requiring environmental information to be considered as part of the project authorisation procedures and in the UK this has been done by incorporation into the existing planning procedures. EIAs require the environmental effects of a development to be considered by the developer and the information provided to the planners to be used in their decision making process. Hughes et al. Env. Law 4th Ed. 2002 p.207.
  • 29. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 29 Part II (These are the minimum requirements for EIA) 1. A description of the development comprising information on the site, design and size of the development. 2. A description of the measures envisaged in order to avoid, reduce and, if possible, remedy significant adverse effects. 3. The data required to identify and assess the main effects which the development is likely to have on the environment. 4. An outline of the main alternative studied and an indication of the main reasons for the choice, taking into account the environmental effects. 5. A non-technical summary of the information.
  • 30. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 30 Part V Publicity and procedures on submission of a EIA 13. Procedure where an EIA is submitted with the planning application. A key feature here is that the EIA is not made available for public scrutiny. 14. Procedure where an EIA is submitted after the planning application. In this case the application has to be published in the local paper stating that the EAI may be inspected by members of the public and to give an address where this can be done, which must be in the locality of the planning application.
  • 31. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 31 Part VI Notification of Decisions 20. Availability of opinions for inspection All the documents relating to the decision have to be kept for two years. A copy of the opinion, request or direction and any accompanying statement of reasons must be available for public inspection. This does not include public access to the EIA. 21 Duties to inform the public and the Sec. State of the final decision. (c) Make available for public inspection a statement: (i) the content and conditions of the decision (ii) the main reasons on which the decision was based (iii) a description of the main measures to avoid, reduce and if possible offset the major adverse effects of the development. This still does not give the public access to the EIA. But this is the firsts time that the public have access to the reasons that planning consent was given. There is still no mechanism for the public (or any third party) to appeal against a planning consent decision. Only the developer has the right of appeal if there is a refusal of planning consent. The public can only make representation before the plans are approved and the system of notification of a planning application is deeply flawed. The whole system is weighted in favour of the developer and against the public. Jack Rostron Env. Law for the Built Environment, Cavendish, 2001, p.54.
  • 32. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 32 Sustainable Planning Decision Making Jack Rostron, Env. Law and the Built Environment, Cavendish, 2001, p.56-61. Planning is not just about land use – there is also the issue of policy planning. This is being driven at present in the EC by the ideal of sustainability, which grew out of the no growth debate. The most commonly accepted definition of sustainable development is that of the Brundtland Commission in 1987: ‘Sustainable development is development that meet the needs to the present without compromising the ability of future generations to meet their own needs’ There are 3 core parts to sustainable development: (a) Inclusion of environmental considerations in policy (b) Commitment to a fair distribution of resources (c) Development that acknowledges health, education and the environment considerations. The government has had a Sustainable development panel since 1994
  • 33. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 33 Gateshead Metropolitan BC v. Secretary of State for the Environment and Northumbrian Water Group plc. 1993 Wolf and Stanley on Environmental Law 2003 p.333 Wolf and White Environmental Law 1995 p. 338-342, Cavendish. GMBC refused outline planning permission for a clinical waste incinerator to be built in Gateshead by NWG. The refusal was based on the grounds that NWG had failed to supply sufficient information to demonstrate that the plant would operate without causing a nuisance to the surrounding locality, including the possible release of noxious substances. The NWG appealed to the Secretary of State and a local public enquiry was held. This recommended that the appeal was dismissed on the grounds that ‘the impact on air quality and agriculture in the semi-rural location is insufficiently defined and that public disquiet over dioxin pollution cannot be allayed and so make the application acceptable’.
  • 34. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 34 However, the Secretary of State for the Environment chose to act against the public inquiry’s inspector’s recommendation and granted planning permission. The Secretary of State accepted that the pollution arising from the incinerator and its impact on neighbouring land uses could constitute material considerations. However, he also stated that: ‘While the planning system must determine the location of facilities of this kind, taking into account of the provisions of the development plan and other material considerations, the Secretary of State considers that it is not the role of the planning system to duplicate controls under the Environmental Protection Act 1990’ He went on to assert that the controls under the EPA were adequate and control of emissions from the incinerator should be regulated by HMIP (now EA).This would apply today to the IED being deemed adequate control.
  • 35. Environmental Management Prof. Gordon E. Andrews, SCAPE, U. Leeds. 35 GMBC appealed against the Secretary of States decision, but their appeal was rejected by both the High Court and the Court of Appeal. The High Court held that the existence of a stringent pollution control regime under the EPA or IED was a material consideration in a planning decision. Lord Justice Glidewell, in the Court of Appeal, accepted that the two systems of control overlapped. However, the Court of Appeal unheld the decision of the High Court and stated that the potential for environmental pollution would be a material consideration when determining planning applications but so would the existence of a system of environmental control administered by pollution control authorities. The impact of this judgement was that it could not be argued in a planning application that the plant would not conform to statutory air and water pollution emission requirements, as this was for the EA to enforce. The planning permission system could be used to ensure that the correct equipment was fitted to control the pollution, but it could not be assumed that the equipment would not work or would not be used – this was for the EA to police.
  • 36. CAPE2020 Environmental Management and Air Quality Prof. G..E. Andrews 2019/20 Contents 1. Introduction to the Air Quality and Environmental Management part of the module. 2. Introduction to legal framework for Air Quality legislation and the changes in the draft Environment Bill 3. Health effects of air pollutants 4. Particulate air pollution and particle size distribution and the health effects of ultra-fine particles 5. Sources of Air pollution and Trends in emissions of pollutants that contribute to poor air quality. 6. Air quality Regulations 7. Air quality monitoring 8. Air quality limit value Regulations 9. Occupational exposure to pollution – COSHH 10. The Clean Air Acts 11. Meteorology and pollutant dispersion 12. Environmental Law 13. Town and Country Act planning law for Environmental Impact 14. Environmental Management in Industry 15. Preparing an Environmental Permit - examples 16. Emissions measurement from industrial plant