SlideShare a Scribd company logo
1 of 56
Download to read offline
STRENGTHENING THE CAPACITY
                                                                   OF THE MINISTRY OF SOCIAL
                                                                   SOLIDARITY PROJECT

                           The Project Board Meeting 30/6/2012




Ministry of Supply and Internal Trade     Ministry of Insurance and Social Affairs   Ministry of Foreign Affairs



               Prepared by :
   Consultant Eng. Moheeb Aabdel Sattar                                                         July 2012
         UNDP Project Manager
                                                                                                                   1
STRENGTHENING THE
       PROJECT                   CAPACITY OF THE
       ACHIEVEMENTS 2011         MINISTRY OF SOCIAL
                                 SOLIDARITY PROJECT

       CONTENTS:

I.     Introduction

II.    Executive Summary

III.   Conclusions

IV.    Recommendations

V.     Lessons Learnt

VI.    Project Expected Outputs: (Progress)

                                                      2
STRENGTHENING THE
           Introduction:                        CAPACITY OF THE
                                                MINISTRY OF SOCIAL
                                                SOLIDARITY PROJECT



   The project was launched in 2006 with a timeframe of 2006-2009
    with a total budget of US $2.2 Million
    (MOSS contribution US$ 1.851 Million and UNDP contribution
    amounting to US$ 350 Thousand).

   The Project Board has agreed to increase the project’s funding
    by US $2,650 thousand to continue and expand its activities as follows:
       US$ 900 thousand in 2010/2011.

       US$ 900 thousand in 2011/2012.

       US$ 850 thousand in 2012/2013.



   In April 2011 the Project Board has agreed to extend the project duration
    until the end of year 2012.
                                                                              3
STRENGTHENING THE
       Introduction:                        CAPACITY OF THE
                                            MINISTRY OF SOCIAL
                                            SOLIDARITY PROJECT

The project aims to:
      Develop and build the capacity of the Ministry of Social
       Solidarity (MOSS) to design and implement social policies.

      Increase the relevance and efficiency of social protection
       schemes and social intervention including local development.

      Contribute to elaborating a new social contract, namely in the
       field of poverty reduction through better empowerment and
       participation of the poor and civil society organizations.

      Establishing an advisory support unit for policy advice and
       capacity building in MOSS is a key output of this project and an
       entry point to other outputs and activities.


                                                                          4
STRENGTHENING THE
            Executive Summary:                        CAPACITY OF THE
                                                      MINISTRY OF SOCIAL
                                                      SOLIDARITY PROJECT

The project has six outputs:

   The first output (MOSS TAU Established):
    To support MOSS in recruiting outside expertise to assist it carry out the
    project’s targets.
   The second output (MOSS NEW STRUCTURE):
    To developing MOSS’ mission & vision to respond to its new mandate.
   The third output (MOSS CAPACITY DEVELOPMENT):
    To develop capacity building for MOSS and NGOs.
   The fourth output (ACCREDIT & ELIGIBILITY for NGOs):
    To create an accreditation & eligibility system for NGOs in Egypt.
   The fifth output (NEW SOCIAL PROTECTION SYSTEM):
    To design a more effective system for social protection.
   The sixth output (IMPROVING NASSER SOCIAL BANK):
    To evaluate NSB and prepare it for restructuring.
                                                                                 5
STRENGTHENING THE
             Executive Summary:                       CAPACITY OF THE
                                                      MINISTRY OF SOCIAL
                                                      SOLIDARITY PROJECT

   The rank of the first Output is satisfactory.
   The analysis shows that the rank of the second output is satisfactory.
   The progress of the third output and its expected outcome seem marginally
    satisfactory.
   The rank of the fourth output and its expected outcome are unsatisfactory.
   For the fifth output :
     MOSS developed the productive families associations, link them to other
        institutions in Europe that provided them with design and training, and then
        marketed their products abroad.
     MOSS investigated leakage in the subsidies system.
        The solution was to use ICT to monitor and follow-up on disbursed solidarity
        checks, subsidized food items, such as cooking oil, and distributing gas
        cylinders to the deserved population through the use of coupons.
     The efforts of the project, and MOSS at large, to achieve this output and its
        outcome are remarkable, and thus the fifth output ranks as satisfactory.     6
STRENGTHENING THE
           Executive Summary:                       CAPACITY OF THE
                                                    MINISTRY OF SOCIAL
                                                    SOLIDARITY PROJECT


   The sixth output was to evaluate NSB. Project experts elaborated an
    assessment, and recommendations for an action plan for NSB.
    The development and upgrading NSB has taken steps in the right directions,
    yet there are more needed actions.
    Assessment of NSB and its improvements are also a step towards enhancing
    the environment for both the workers and the clients.
    The rank of this output and its outcome is highly satisfactory.

   Consequently, UNDP project to strengthen the capacities of MOSS is
    satisfactory.
   Resources allocated to project activities, as indicated in the auditors’ annual
    report, seem to be efficiently used.


                                                                                      7
STRENGTHENING THE
            Executive Summary:                   CAPACITY OF THE
                                                 MINISTRY OF SOCIAL
                                                 SOLIDARITY PROJECT


    The output concerned with NGOs needs more attention. Having
    a database is not enough. There is a need to revise the law, and other
    elements of the institutional framework that governs the work of NGOs
    to stimulate them.
   There is a need to evaluate these experiences, then draw lessons learnt
    and best practices to scale-up the use of these tools to a national policy.
   The project will need to elaborate a log-frame with indicators, risks,
    external factors and other elements of designing an intervention, and
    propose means for integrating the various outputs.
   The project needs to lay-out a plan for phasing out, and
    A strategy of sustaining the achievements.
                                                                             8
STRENGTHENING THE
        Executive Summary:                  CAPACITY OF THE
                                            MINISTRY OF SOCIAL
                                            SOLIDARITY PROJECT

   Obviously, there is a need for another phase, but with a design
    based on a different philosophy to meet the current aspirations
    following the January 25th revolution.
   The new phase has to seek linkages between the various entities
    of MOSS. It also needs to pay more attention to NGOs to be a
    complete partner and able to reach those who live in informal
    areas and rural settlements.
   The new phase has to experiment with tools for enabling and
    empowering the people who live in misery to be in-charge of
    their resources and future.


                                                                      9
STRENGTHENING THE
        Executive Summary:                   CAPACITY OF THE
                                             MINISTRY OF SOCIAL
                                             SOLIDARITY PROJECT


   The project faced number of challenges, such as lack of reliable,
    valid and complete information; financial limitations,
    cooperation of other public bodies, resistance to change, etc.

   The main factor for the success of this project is the support and
    attention that the former Minister paid to the project.
    The advisors have authority, and working closely with their
    counterparts by coaching them to make presentations to the
    former Minister, involving them in the different processes, such
    as conducting a study or an assessment.



                                                                         10
STRENGTHENING THE
        Executive Summary:                CAPACITY OF THE
                                          MINISTRY OF SOCIAL
                                          SOLIDARITY PROJECT


Output 1: An Advisory Unit established
The first output is a Technical Advisory Unit (TAU) at MOSS. This
  unit will be responsible for:
 • Strategic policy advice including strategic options, research and
   coordination, and situation and prospective analyses;
 • Restructuring MOSS including organizational structure, internal
   governance, human resources and mainstreaming the use of
   Information Technology (IT); and
 • Program implementation support, such as training,
   communication, etc.

                                                                  11
STRENGTHENING THE
          Executive Summary:                    CAPACITY OF THE
                                                MINISTRY OF SOCIAL
                                                SOLIDARITY PROJECT

Output 2: MOSS new proposed structure submitted for
          decision making
• Proposing an organizational structure for MOSS is central to fulfilling
    its mandate and mission.
•   The “merger” of two established institutions, i.e., the Ministry of
    Supply and Ministry of Social Affairs requires a new organizational
    structure to assure smooth cooperation and synergies within the newly
    established institution.
•   The “split” of Ministry of Solidarity and Social Justice into two
    established institutions, i.e., the Ministry of Supply and Internal Trade
    and Ministry of Insurance and Social Affairs requires a new
    organizational structure to assure smooth cooperation and synergies
    within the newly established institutions.
                                                                            12
STRENGTHENING THE
     Executive Summary:                  CAPACITY OF THE
                                         MINISTRY OF SOCIAL
                                         SOLIDARITY PROJECT


Output 3: Capacity Development of key staff institutionalized
 • The project avails training to key staff at MOSS, such as
   social workers, and their partners, particularly NGOs.
 • In addition to delivering training, the project will contribute to
   elaborating an efficient and dynamic communication strategy
   to convey relevant messages to the population, properly
   reflect the image of MOSS.




                                                                   13
STRENGTHENING THE
         Executive Summary:                      CAPACITY OF THE
                                                 MINISTRY OF SOCIAL
                                                 SOLIDARITY PROJECT


Output 4: A system for accrediting NGOs developed
• MOSS is the official regulatory body for NGOs active in Egypt.
• NGOs are instrumental in achieving the mission of MOSS, and thus are
  among the most significant partners of MOSS.
• They are able to reach those marginalized and unprivileged sub-population
  groups, such as female-headed households.
• NGOs receive financial and technical support. For this reason, it is of utmost
  importance that MOSS has a system for monitoring NGOs to effectively
  eradicate poverty. Thus a database of the 20 thousand NGOs registered with
  MOSS is essential to achieve the mission and mandate of MOSS.
• Equally important is to setup a system of accrediting and eligibility for
  NGOs. These two steps are central to producing a periodic report on NGOs,
  to monitor their activities, and provide them with necessary support.

                                                                               14
STRENGTHENING THE
           Executive Summary:                 CAPACITY OF THE
                                              MINISTRY OF SOCIAL
                                              SOLIDARITY PROJECT


Output 5: A more developed and effective system for social protection
• Today, capability poverty substitutes the notion of monetary measure of
  poverty.
• Several studies indicated that fallacy of Poverty Lines (PL). Capability
  poverty provides means for targeting the poor, who are they? Where
  they live? What exactly they need to move to an improved standard of
  living.
• Designing an adequate social protection system requires a better
  mechanism for targeting the poor. This mechanism serves as a vehicle
  to setting priorities straight, efficient and effective interventions to
  alleviate poverty.

                                                                       15
STRENGTHENING THE
         Executive Summary:                 CAPACITY OF THE
                                            MINISTRY OF SOCIAL
                                            SOLIDARITY PROJECT


Output 6: Nasser Social Bank evaluated
• The project funded that assessment of Nasser Social Bank (NSB),
  and its role.
• The assessment highlights the strengths and weaknesses of NSB, as
  well as the available opportunities for improving its role in poverty
  alleviation in areas such as sponsoring Small and Micro Enterprises
  (SMEs) and threats, i.e., risks, in the external environment of NSB
  that might limit its effectiveness.
• UNDP helped in recruiting a team of national and international
  experts to conduct the assessment and layout a business plan for NSB
  emulating successful experiences in Asia and Latin America.

                                                                     16
STRENGTHENING THE
        Conclusions :                         CAPACITY OF THE
                                              MINISTRY OF SOCIAL
                                              SOLIDARITY PROJECT


 Consequently, UNDP project to strengthen the capacities of
 MOSS is satisfactory.
• The project used number of tools to ration subsidies, such as targeting
  the poor and the use of smart cards.
• There are other practices to alleviate poverty, such as CCT and
  productive families.
• Assessment of NSB and its improvements are also a step towards
  enhancing the environment for both the workers and the clients.
• The output concerned with NGOs needs more attention. Having a
  database is not enough. There is a need to revise the law, and other
  elements of the institutional framework that governs the work of NGOs
  to stimulate them.
                                                                        17
STRENGTHENING THE
                                                    CAPACITY OF THE
         Recommendations :                          MINISTRY OF SOCIAL
                                                    SOLIDARITY PROJECT


• The project is coming to an end, yet there are some unfinished businesses and
  loose ends to tie. There is a need to evaluate these experiences, then draw
  lessons learnt and best practices to scale-up the use of these tools to a national
  policy.
  The project will need to elaborate a log-frame with indicators, risks, external
  factors and other elements of designing an intervention, and propose means for
  integrating the various outputs.
  The project needs to lay-out a plan for phasing out, and a strategy of sustaining
  the achievements.
• Obviously, there is a need for another phase, but with a design based on a
  different philosophy to meet the current aspirations following the January 25th
  revolution. The new phase has to seek linkages between the various entities of
  MOSS, It also needs to pay more attention to NGOs to be a complete partner
  and able to reach those who live in informal areas and rural settlements.
  The new phase has to experiment with tools for enabling and empowering the
  people who live in misery to be in-charge of their resources and future.        18
STRENGTHENING THE
                                                     CAPACITY OF THE
         Lessons learnt :                            MINISTRY OF SOCIAL
                                                     SOLIDARITY PROJECT


• ICT is not always the solution, particularly in a country that lacks reliable,
   valid and continuous data. ICT can help in development, but has limits.
• Strengthening the capacities of a public institution is extremely difficult as it
   requires transformations in beliefs. Change is possible, but often is resisted
   from within the public institution.
• If MOSS wants to succeed in fulfilling its mandate and mission, then there is a
   need to engage private-sector companies and NGOs in the processes of
   decision-making to assure their ownership and responsibility for
   implementation.
• Most of the decisions made within public bodies are based on “political'”
   rather than “technical" considerations. Among the reasons for this situation,
   that future is sometimes uncertain. Conditions within the public institution and
   outside it always changes, thus precise prediction, projection and forecasting
   are not often possible.                                                       19
STRENGTHENING THE
                                                     CAPACITY OF THE
         Lessons learnt :                            MINISTRY OF SOCIAL
                                                     SOLIDARITY PROJECT


• When a public institution engages with another institution, whether public,
   private or non-profit, then the element of change is probably of special
   importance. The other institution tries to impose change on the public
   institution, thus forcing the institution to consider serious counter-measures.
• Public institutions often do not advertise action plan action in advance to avoid
   opposition.
• To the contrary, private-sector companies are radically different.
    Decisions are made to maximize profit and minimize costs.
   For this reason decisions are based on technical considerations as well as
   political and social acceptances.
   Private-sector companies always have the shareholders, clients, competitors
   and collaborators, such as financing institutions, in perspective.
   Thus advertising is important, and the image is crucial to test ideas, target
   specific groups and so forth.
                                                                                     20
STRENGTHENING THE
PROJECT                              CAPACITY OF THE
ACHIEVEMENTS 2011                    MINISTRY OF SOCIAL
                                     SOLIDARITY PROJECT

CONTENTS:
 I - PROJECT EXPECTED OUTPUTS: (PROGRESS)
   1 - ADVISORY UNIT

   2 - RESTRUCTURING

   3 - CAPACITY BUILDING

   4 - NGO’S ACCREDDITATION SYSTEM

   5 - SOCIAL PROTECTION SYSTEM

   6 - NASSER SOCIAL BANK

 II- PROJECT FINANCES

 III- PROJECT’S RISKS & ITS MANAGEMENT

 IV- FUTURE PLANS & CHALLENGES

                                                          21
STRENGTHENING THE
 I - PROJECT                           CAPACITY OF THE
                                       MINISTRY OF SOCIAL
 EXPECTED OUTPUTS                      SOLIDARITY PROJECT


THE FOLLOWING OUTPUTS SHALL BE ACHIEVED DURING THE
PROJECT’S DURATION (year 2011).



 Output: 1    Advisory Unit is Established.

 Output: 2    Proposed New Structure is Submitted

 Output: 3    Capacity Development is Institutionalized.

 Output: 4    NGO’S Accreditation & Eligibility System is in Place.

 Output: 5    An Effective Social Protection System is Designed.

 Output: 6    Nasser Social Bank is Evaluated.

                                                                      22
STRENGTHENING THE
       I - PROJECT                               CAPACITY OF THE
       EXPECTED OUTPUTS                          MINISTRY OF SOCIAL
                                                 SOLIDARITY PROJECT



Output: 1     ADVISORY UNIT IS ESTABLISHED

PROGRESS           In 2011 the project contracted 7 additional consultants &
(year 2011)         technical support staff and assigned them to various tasks
                    within MoSS’ departments, and in direct contacts with MoSS’
                    senior & middle level staff, including:
                        Minister Consultant for mega bakeries,
                        Minister consultant for media, and
                        6 technical support & administrative staff.

                   9 consultant, technical support & administrative staff quite.

                   The project now has 40 contracted staff in total.


                                                                               23
STRENGTHENING THE
           I - PROJECT                                     CAPACITY OF THE
           EXPECTED OUTPUTS                                MINISTRY OF SOCIAL
                                                           SOLIDARITY PROJECT

 Output: 2     PROPOSED NEW STRUCTURE IS SUBMITTED
                Central Agency for Restructuring Projects ( Completed ):
                 • Establishment (20) projects (from a total of 62 draft)
                 • Development (9) projects (from a total of 18 draft)
PROGRESS
(year 2011)  Educational Buildings Authority projects (Been completed):
                 • Establishment (5) projects (out of 10 total projects)
                 • Development (7) projects (out of 9 total projects)
                 • Raising the efficiency of one project (out of 2 total projects)
                Housing Directorates Projects in Governorates :
                 Follow-up completion of (15) projects being implemented by housing
                 directorates in Governorates.
                Court building project of the new ministry building in Agouza:
                  Been ratified by the Ministry of Planning and International Cooperation, the
                 transfer of 8 million L.E. of building allocations General Board (16 million
                 L.E.) paid for Military Works Department of Forced Armed as down payment.
                Raise the efficiency of social units Projects :
                 Upgrading of (9) social units (out of total 33 units) planned to be raised the
                 efficiency.                                                                 24
STRENGTHENING THE
              I - PROJECT                                      CAPACITY OF THE
              EXPECTED OUTPUTS                                 MINISTRY OF SOCIAL
                                                               SOLIDARITY PROJECT

 Output: 3        CAPACITY DEVELOPMENT IS INSTITUTIONALIZED
                  (Information Technology)
                  Smart Cards:
                  • Defined matching rules of the input data for the ration cards with the exchange
                    data and sent it to the smart cards companies.
PROGRESS
                  • Smart cards companies designed programs necessary to be matching.
(year 2011)       • Testing the matching programs in some Governorates Such as Port Said & Aswan.
                  Family Database System:
                  • Finalize rollout of the system in 27 Governorates.
                  • Technical support for Family Database.
                  Targeting:
                  • Technical support for Targeting Program.
                  • Exporting Targeting data of finished Governorates to a format of SPSS statistics.
                  Social Solidarity Pensions from Post Offices:
                  • Following up the monthly implantation circulation of Social Solidarity Pensions
                    from Post Offices.
                  • Transferring Social Solidarity Pensions database of El-Monofeya , Kafr El Shiekh
                    and El-Gharbya from SIO to Family Profile Program.
                  • Co-operation with Governorates and social administrative offices and Information
                    Center of MoSS to solve all the networks and technical problems.                25
STRENGTHENING THE
              I - PROJECT                                   CAPACITY OF THE
              EXPECTED OUTPUTS                              MINISTRY OF SOCIAL
                                                            SOLIDARITY PROJECT

 Output: 3     CAPACITY DEVELOPMENT IS INSTITUTIONALIZED
               (Information Technology)
                  NGOs Application:
                  • The system has been updated according to the requirements of the central
                    department of NGO’s.
PROGRESS
                  • Adding new screens (training programs - Membership & Contributions –
(year 2011)         Committees Members of Board of Directors - Meetings of Board of Directors -
                    Members of the Assembly - the Assembly meetings - volunteers - NGO
                    problems - research experience - revenues and expenses - budget).
                  • Designed of the required reports (Statistics - detailed data).
                  Pilgrimage System:
                  • Finalize system updates.
                  Call Center Project:
                  • Finalize system updates.
                  ERP Project:
                  • Finalize system updates.
                 Designing of a new system for distributing subsidized Natural Gas
                  Cylinders is completed .                                                    26
STRENGTHENING THE
              I - PROJECT                                        CAPACITY OF THE
              EXPECTED OUTPUTS                                   MINISTRY OF SOCIAL
                                                                 SOLIDARITY PROJECT

 Output: 3        CAPACITY DEVELOPMENT IS INSTITUTIONALIZED
                  (Information Technology)

                 GIS System:
                  GIS work includes 3 main items:
PROGRESS          1. GIS Web Portal linked to Ministry main web site.
(year 2011)       2. Mapping Supply services:
                      Creating GIS maps for the current supply services on the street level detailed
                      maps (scale 1:5000) covers all Egypt Governorates.
                  3. Mapping Target Project results:
                      Creating GIS printouts highlight the result of targeting project with co-operation of
                      institute of social study.

                 Redesign & development of MoSS Website:
                   • Analysis of the current web site, and identifying the restructuring needed and
                     the information and services to be included on the new website.
                   • Developing the new website information structure.
                   • Selecting and evaluating the platform to be used in development the new
                     website.
                   • Creating the design of the new web site, and implementing sample homepage
                     and an internal page.
                                                                                                        27
STRENGTHENING THE
             I - PROJECT                           CAPACITY OF THE
             EXPECTED OUTPUTS                      MINISTRY OF SOCIAL
                                                   SOLIDARITY PROJECT


 Output: 3     CAPACITY DEVELOPMENT IS INSTITUTIONALIZED
               (Information Technology)

PROGRESS  Productive families projects were increased by 8000, with 11000
(year 2011) beneficiaries.

              The training of (1128)  MoSS’ employees is completed. The training
               programs’ specifics included the following breakdown:
               • Training (30) of Executive Management ,
               • Training (728) of Social Employees at the Social Services Units,
               • Training (250) of Social Services Units’ Secretaries
                  (Transfer Training),
               • Training (120) of Daman staff members and Information Centre's
                 employees on MoSS Family Profile Database of 23 Governorates,



                                                                                28
STRENGTHENING THE
              I - PROJECT                                    CAPACITY OF THE
              EXPECTED OUTPUTS                               MINISTRY OF SOCIAL
                                                             SOLIDARITY PROJECT

 Output: 3       CAPACITY DEVELOPMENT IS INSTITUTIONALIZED
                 (Information Technology)

                Activities of short term National Consultants:
PROGRESS          • Prepare draft version of “the National Body of Food Subsidy” law.
                  • Prepare Case Study on “General Structure of MEGA Bakeries and merging of Small
(year 2011)         Bakeries”.
                  • Prepare Case Study on “Supply Chain Study” to the Minister.
                  • Finalize Case Study of “Measuring of the Balady Bread Production Cost” through
                    field survey on 5 bakeries.
                  • Prepare TOR of “Build and design a new efficient and effective system for Balady
                    Bread through removing government intervention from initial stages of the Balady
                    Bread Supply Chain to its last stage.

                Cooperation with WFP and international experts:
                 • Review Egyptian country strategy for the World Food Program 2012 to 2016.
                 • Build and design a new efficient and effective system foe Balady bread.
                 • Draw structured implementation plan for the new Balady Bread system.
                 • Design a pilot project for the first phase of the implementation of the new
                   enhanced and efficient Balady Bread system.

                                                                                                 29
STRENGTHENING THE
            I - PROJECT                                       CAPACITY OF THE
            EXPECTED OUTPUTS                                  MINISTRY OF SOCIAL
                                                              SOLIDARITY PROJECT

Output: 4         NGO’S ACCREDITATION & ELEGIBILITY SYSTEM

                 to develop a system for accrediting NGOs,
                  MOSS in collaboration with CAPMAS and the Union for NGOs, established
                  a database of NGOs, and set a system for accreditation of NGOs, which has not be
PROGRESS          functional yet. There is limited cooperation between the project staff responsible
(year 2011)       for this output and their counterpart within MOSS.

                 The NGOs Accreditation Criteria and the form for implementation were finalized,
                   • Implementation for 100 NGOs and results analyzed.
                   • Additional criteria were developed for NGOs dealing with disability.

                 The NGOs’ Database is being revamped. Its aim to develop a database for the
                  NGOs in Egypt and produce unified statistics. The work achieved during this period
                  includes:
                    • Defining data items to be added into the System (required by CAPMAS &
                      Union of NGO’s),
                   • Design and development of the system are completed.

                                                                                                 30
STRENGTHENING THE
              I - PROJECT                                   CAPACITY OF THE
              EXPECTED OUTPUTS                              MINISTRY OF SOCIAL
                                                            SOLIDARITY PROJECT

 Output: 5          NEW SOCIAL PROTECTION SYSTEM
               Smart Cards:
                   Defined the rules of matching the input data for the ration cards with the
                    exchange data and sent it to the smart card companies.
PROGRESS           The smart card companies designed programs necessary to the matching.
                    Testing the matching programs in some Governorates such as Port Said and
(year 2011)     
                    Aswan.

               Targeting Database Project:
                 Technical support for Targeting Program.

                 Exporting Targeting data for the completed governorates in a format that easy

                  for SPSS statistics analysis.

               Social Solidarity Pensions from Post Offices:
                 Following up the monthly operation of Social Solidarity Pensions from Post

                  Offices.
                 Extracted and transferring Social Solidarity Pensions database of El-Kaliopia and

                  El-Behira from Social Insurance Organization, SIO to Family Profile Program.
                 Co-operating with Governorates and social administrative offices and Information

                  Center of MoSS to solve all the networks and technical problems of the project.
                                                                                                 31
STRENGTHENING THE
             I - PROJECT                                          CAPACITY OF THE
                                                                  MINISTRY OF SOCIAL
             EXPECTED OUTPUTS                                     SOLIDARITY PROJECT

Output: 6        IMPROVING NASSER SOCIAL BANK
                Revamping the current data center at NSB Head Office to enable the operation of
                  a newly developed state-of-the-art digital network.
PROGRESS  Established an NSB Human Capital Development Center (HCDC).
(year 2011)
             Developed new/revised bank regulations.
                Developed a model for the look-and-feel of rebranded bank branches, hired well over
                  400 new employees based on predefined set of selection criteria, and opened 3 new
                  branches conforming to the new rebranded branch model.

                NSB automation project will fully automate all NSB services and connect all of its 90
                  branches through a sophisticated/secured network. It will also ensure that the bank
                  uses state-of-the-art technologies and information systems. The project will incorporate
                  an efficient business continuity solution to ensure data integrity and around the clock
                  availability of services. In addition, the project will enable the bank to provide a set of
                  services that it is not currently possible due to the nature of its legacy/outdated
                  information systems and technologies.


                                                                                                         32
STRENGTHENING THE
            I - PROJECT                                CAPACITY OF THE
                                                       MINISTRY OF SOCIAL
            EXPECTED OUTPUTS                           SOLIDARITY PROJECT

Output: 6      IMPROVING NASSER SOCIAL BANK

              The bank is undertaking an aggressive human capital development
                initiative and succession plan. The initiative will begin with a massive
PROGRESS        human capital assessment and gap analysis phase followed by a
(year 2011)     customized human capital development program that targets
                employees across the organization to change/improve its culture.

              The bank has developed a three-year plan to revamp its ninety
                branches across Egypt.

               In 2010, NSB managed to develop a model for the newly branded
                branches and revamped three branches. Now the processes, consulting
                offices, and implementation contractors are on board and according to
                the plan the bank revamped 19 branches in 2011 and the remaining
                branches will be done by 2014.


                                                                                       33
STRENGTHENING THE
                                                                     CAPACITY OF THE
                                                                     MINISTRY OF SOCIAL
II – PROJECT FINANCES                                                SOLIDARITY PROJECT


   THE PROJECT FINANCES : 2006 - 2011

Output             Description     2006         2007        2008          2009          2010          2011


Output 1 Advisory Unit           $51,893.65   $198,255.7 $313,102.98 $314,442.12     $361,160.83   $248,303.73


Output 2 Restructuring               _            _       $17,163.56   $117,375.12   $150,801.85   $145,691.64


Output 3 Capacity Building           _            _       $7,560.06    $16,067.22    $30,775.01    $26,525.80

           NGOs Accreditation
Output 4                             _            _        $290.14     $93,686.15    $84,071.56    $65,524.80
            System

           Social Protection
Output 5                         $11,783.96   $29,635.5   $56,251.8    $140,757.76   $58,844.01    $41,004.69
           System

Output 6 Nasser Social Bank          _        $52,784.5   $31,974.47   $112,959.51   $149,693.27   $38,069.48


           Total                 $63,677.61 $280,675.70 $426,343.01 $795,287.88      $835,346.53   $565,131.50



                                                                                                                 34
STRENGTHENING THE
                                                           CAPACITY OF THE
    II – PROJECT FINANCES                                  MINISTRY OF SOCIAL
                                                           SOLIDARITY PROJECT

      THE PROJECT FINANCES : 2006 - 2011

The project was able to achieve major financial savings as a direct result of the
following contributing factors:

   The nature of the work planned and achieved for this project is intentionally carried out in
    gradual, incremental in order to ensure future sustainability.

   All costs related to MoSS’s developing of social units were funded from MoSS’ budget.

   All costs related to MoSS’s training programs were funded from MoSS’ budget, but the
    training programs were devised and supervised by the Project’s contracted staff.

   All the costs related to upgrading MoSS’ IT infrastructure, including software, hardware, and
    other equipment were paid from MoSS’ own budget or through MCIT and MSAD.

   All the costs related to Nasser Social Bank’s training programs and IT upgrading, including
    the purchasing of software, hardware, as well as other reform/restructuring expenditures
    were paid from the bank’s own budget.

   All the administrative aspects of the project fixed assets were funded by MoSS, including
    furbishing, equipments, IT requirements, etc,


                                                                                                   35
STRENGTHENING THE
        III – PROJECT RISK &                     CAPACITY OF THE
                                                 MINISTRY OF SOCIAL
            ITS MANAGEMENT                       SOLIDARITY PROJECT


      THE PROJECT RISKS & RISK MANAGEMENT:


           PROJECT RISKS                     PROJECT RISK MANAGEMENT


The capacity of the MoSS staff to      The Project has supported and expanded
adapt and absorb changes introduced    all types of training programs of MoSS
by the project is limited.             staff, in order to ensure adoption of
                                       introduced reforms by MoSS’ staff.


                                       The Project management ensured that
                                       all contracted Senior Advisors,
The PMU is not fully integrated with   Consultants, and Specialists are assigned
MoSS.                                  to interact and work directly with MoSS’
                                       senior and middle level staff, in order to
                                       ensure transfer of Knowledge &
                                       expertise.



                                                                               36
STRENGTHENING THE
          IV – FUTURE PLANS &                       CAPACITY OF THE
                                                    MINISTRY OF SOCIAL
               CHALLANGES                           SOLIDARITY PROJECT


    THE PROJECT’S FUTURE PLANS AND CHALLENGES:

    Here are the project’s future plans to implement and the challenges to be
    addressed during year 2012:


•   Conduct a Project Evaluation Exercise during the first quarter of 2012, in order
    to measure progress achieved during year 2011, identify shortfalls, effectiveness
    and efficiencies (through the contracting of an expert/company).

•   Project extended to the end of December 2012.

•   Financing is required from the Ministry of Finance to fund MoSS’s large-scale
    services improvement and development programs.




                                                                                    37
STRENGTHENING THE CAPACITY OF
                                                THE MINISTRY OF SOCIAL
                                                SOLIDARITY PROJECT


Effectiveness and Efficiency of Current Information Systems
(Strengths and Weaknesses)
•    Strengths:
    1. Users need assessments was done to meet MoSS requirements.
    2. Team work consisted of national consultants working together with MoSS
       staff to build and increase their capabilities to be able to operate and
       maintain the MoSS Information System in the future.
    3. MoSS Information System was built using the up-to date technology with
       standards documentation (to be completed).

•    Weaknesses:
    1. Lack of exchange data between the Governmental Agencies.
    2. MoSS Information Strategic Plan Not established at the beginning of the project.
    3. System Design was not built to ensure databases integration.

                                                                                   38
STRENGTHENING THE CAPACITY OF
                                               THE MINISTRY OF SOCIAL
                                               SOLIDARITY PROJECT

Constrains and barriers to manage and improve availability and
accessibility of data and information.
The most significant constraint to establish Integrated Information
Systems in Egypt :

 1. The lack of reliable and timely information.
 2. The existing data and information is not sufficient managed.
 3. The lack of financial resources (MoSS), trained workforce, awareness and
   availability of information and/or institutional setup.
 4. The processes of Socio-Economic information collection, production and
   dissemination are not clear in Egypt.
 5. The monitoring organizations do not feed their results into a common
   information system.
 6. Absence of a comprehensive methodology.
                                                                               39
STRENGTHENING THE CAPACITY
 Implementation Challenges :         OF THE MINISTRY OF SOCIAL
                                     SOLIDARITY PROJECT


1. Management of expectations.
2. Knowledge and assimilative capacity of Governmental
  Agencies initially low making it difficult for them to express
  their needs.
3. Lack of realistic performance measures.
4. Rapid changes in technology.
5. Reluctance to provide or share data due to concerns about
  implications for data owners.




                                                                   40
STRENGTHENING THE CAPACITY
  Lessons Learned:                 OF THE MINISTRY OF SOCIAL
                                   SOLIDARITY PROJECT


1. The MoSS Information System started small rather than big
   by building capacity and slowly increasing the scope of work.

2. Use the RBM to create realistic work plans and to manage
   expectations.

3. Reporting is most effective when done on an outcome and
   output basis with accurate reporting of results and
   scheduling.

4. Accepted and worked in consideration of the assimilative
   capacity of MoSS which has substantial grown.

5. Make provisions for rapid changes in technology by creating
   flexibility in work plans (i.e. short duration activities).




                                                                   41
STRENGTHENING THE CAPACITY
     Lessons Learned:       (Cont.)
                                        OF THE MINISTRY OF SOCIAL
                                        SOLIDARITY PROJECT


6.    Ensure counterpart staff are available at a management level
      ,also useful at a technical level.

7.    Use of a participatory approach at all levels in MoSS requiring
      daily interaction with MoSS Agencies.

8.    Need for continuous communication with UNDP.

9.    Need to arrange a monthly meeting with all partners to follow
      up all MoSS implementation activities.

10. It is very important for all MoSS focal points & coordinators to
    attend all the technical meetings.

11. Need to assign incentives for all employees of MoSS that
    already auditing the data and using the system.

                                                                        42
Annual Report 2012

                                                                                  STRENGTHENING THE
                     Annual Work Plan                                             CAPACITY OF THE
                                                                                  MINISTRY OF SOCIAL
                     AWP 2012                                                     SOLIDARITY PROJECT
  Description: Annual Review Report of Strengthening the Ministry of Social Solidarity
  Implementing Partner: Ministry of Social Solidarity, MoSS is divided into 2 ministries
                              (Ministry of Supply and Internal Trade & Ministry of Insurance and Social Affairs)

  Project Issues:


  Updated Project Risks:                                          Updated Project Risk Management:

  1. MoSS has a weak infrastructure mainly in its financial       1. The Project hired a Senior Accounting Manager, with
     reporting capacity due to the lack of international             strong financial background, to ensure the proper
     experience with donors.                                         financial management of the project resources in
                                                                     accordance with rules and regulations.

  2. The capacity of the MoSS staff to adapt and absorb           2. The Project has supported and expanded all types of
     changes introduced by the project is limited.                   training programs of MoSS staff, in order to ensure
                                                                     adoption of introduced reforms by MoSS’ staff.

  3. The PMU is not fully integrated with MoSS.                   3. The Project management ensured that all contracted
                                                                     Senior Advisors, Consultants, and Specialists are
                                                                     assigned to interact and work directly with MoSS’
                                                                     senior and middle level staff, in order to ensure
                                                                     transfer of Knowledge & expertise.

                                                                                                                           43
STRENGTHENING THE
 Annual Work Plan                      CAPACITY OF THE
                                       MINISTRY OF SOCIAL
 AWP 2012                              SOLIDARITY PROJECT


THE FOLLOWING OUTPUTS SHALL BE ACHIEVED DURING THE
PROJECT’S DURATION.



 Output: 1    Advisory Unit established at the MOSS

 Output: 2    Proposed New Structure for decision making

  Output: 3   Capacity Development is Institutionalized

  Output: 4   NGO’S Accreditation & Eligibility System is in Place

  Output: 5   More Effective Social Protection System


  Output: 6   Nasser Social Bank Evaluated

                                                                     44
STRENGTHENING THE
            Annual Work Plan                             CAPACITY OF THE
            AWP 2012                                     MINISTRY OF SOCIAL
                                                         SOLIDARITY PROJECT


Output: 1          Advisory Unit established at the MOSS


Description: To support MOSS in recruiting outside expertise to assist it carry out the
             project’s targets.


YYYY target: 2012

1. Set-up and organized regular senior staff meetings with regard to presenting the various
   projects of MoSS to all Consultants, with the purpose of facilitating communication and
   cooperation among all project staff, Consultants and various task managers.




                                                                                             45
STRENGTHENING THE
             Annual Work Plan                           CAPACITY OF THE
             AWP 2012                                   MINISTRY OF SOCIAL
                                                        SOLIDARITY PROJECT

  Output: 2        Proposed New Structure for decision making

Description: To developing Moss’ mission & vision to respond to its new mandate.
 YYYY Target: 2012

1. Follow-up establishment of (80) projects being implemented by Central Agency for
   Reconstruction.
2. Follow-up establishment of (21) projects being implemented by Educational Buildings
   Authority.
3. Follow-up establishment of (15) projects being implemented by Housing Directorates in
   Governorates.
4. Follow-up establishment of new ministry building in Agouza being implemented by the
   Military Works Department of Armed Forces which planned to be completed in
   31/12/2012 to be outfitted with fiscal year plan 2012/2013.
5. Follow-up the efficiency raising of (33) social units in many Governorates by local
   contractors.
6. Ratification to start establishment of (13) new social services centers and development
   of (15) social units in addition to equipped (103) service projects in many
   Governorates.                                                                        46
STRENGTHENING THE
             Annual Work Plan                        CAPACITY OF THE
             AWP 2012                                MINISTRY OF SOCIAL
                                                     SOLIDARITY PROJECT

Output: 3        Capacity Development is Institutionalized

Description: To develop capacity building for MOSS and NGO’s.

YYYY target:2012

1. Family Database System:
       Interface with Smart Card Companies via web services.
       Interface with Social Insurance Organization via web services.
       Finalize rollout of the system for all governorates.
       Hosting Family Database at Social Insurance Organization Information Center.

2. GIS System:
       Produce GIS reports for targeting system.
       Integrate with systems of Ministry of State for Administrative Development
        (E. Government).


                                                                                     47
STRENGTHENING THE
             Annual Work Plan                         CAPACITY OF THE
             AWP 2012                                 MINISTRY OF SOCIAL
                                                      SOLIDARITY PROJECT

Output: 3        Capacity Development is Institutionalized

Description: To develop capacity building for MOSS and NGO’s.

3. Establishing the Ministry IT infrastructure:
       Finalize outsourcing Hosting of Data Center at Social Insurance
        Organization Information Center.
       Finalize setting up a Disaster Recovery Center.

4. NGOs System:
       Develop the system to meet all the needs of Central Department of NGO’s
        of Ministry of Insurance and Social Affairs.
       Complete the design of the required reports (statistics - detailed data).

5. Pilgrimage System :
       Enhancement for running Hajj Program.
       Design a new set of reports.

                                                                                    48
STRENGTHENING THE
               Annual Work Plan                                  CAPACITY OF THE
               AWP 2012                                          MINISTRY OF SOCIAL
                                                                 SOLIDARITY PROJECT

Output: 3           Capacity Development is Institutionalized

Description: To develop capacity building for MOSS and NGO’s.
6. MOSS Website:
   Develop the website of the 2 ministries (Ministry of Supply and Internal Trade & Ministry of Insurance
   and Social Affairs) through:
    Coordinating with Project IT Team, the ministry's IT department and Media Consultant to gather
     information about the current MoSS web site and the needs to be met in the new web site.
    Analysis of the current web site, and identifying the restructuring needed and the information and
     services to be included on the new website.
    Developing the new website information structure.
    Preparing the development environment.
    Creating the design of the new web site, and implementing sample homepage and an internal page.


7. Call Center Project :
      Implement new services and updates.
      Rollout of MoSS new updates, services and requirements.
      Integration of Call Center Database and Complains Database on Website.

8. ERP System:
      Keep the project on track.
                                                                                                       49
STRENGTHENING THE
               Annual Work Plan                            CAPACITY OF THE
               AWP 2012                                    MINISTRY OF SOCIAL
                                                           SOLIDARITY PROJECT

  Output: 3        Capacity Development is Institutionalized

Description: To develop capacity building for MOSS and NGO’s.

9. Training Activities:

    A- Ministry of Supply and Internal Trade:
        Training (60) directors and managers of the sectors (Senior Management).

        Training (80) employees of Citizens Service Department (Executive Management).

        Training (45) employees of Public Relations and Media Department (Executive
         Management).

        Training (125) inspectors of Central Department for Inspection (Middle Management).

        Training (80) employees of Supply Departments and Offices (Middle Management).

        Training (80) employees of Internal Trade Sector (Middle Management).
                                                                                               50
STRENGTHENING THE
                  Annual Work Plan                                CAPACITY OF THE
                  AWP 2012                                        MINISTRY OF SOCIAL
                                                                  SOLIDARITY PROJECT

   Output: 3           Capacity Development is Institutionalized

Description: To develop capacity building for MOSS and NGO’s.
9. Training Activities :
   B- Ministry of Insurance and Social Affairs :

       Conversion Training (160) of Social Units secretarial employees to work as assistant
        social specialist (Executive Management).
       Training (80) social specialists to develop skills and increase functional capacity
         (Middle Management).
       Training (160) social specialists to use Family Database System (Middle Management).
       Workshops for )400) of social specialist on the New Social Protection Law (Middle
        Management).
       Training (20) of Senior Managers on Total Quality Management (TQM).
       Training (20) of employees on the Computer Skills (Executive Management).
       Training (20) of employees on English language (Middle Management).
                                                                                               51
STRENGTHENING THE
              Annual Work Plan                           CAPACITY OF THE
              AWP 2012                                   MINISTRY OF SOCIAL
                                                         SOLIDARITY PROJECT

  Output: 4       NGO’S ACCREDITATION & ELEGIBILITY SYSTEM

Description: To create an accreditation & eligibility system for NGO in Egypt

YYYY Target: 2012

    Establishing the Audit Committee and implementing of its role and responsibilities.

    Training governorates relevant staff on the eligibility criteria forms application.

    Evaluation and analysis the results of the eligibility criteria of NGOs.

    Arrange for tailored training courses to cover the main weakness elements in the
     majority of NGOs based on the analysis of the criteria evaluation results.

    Drafting the guiding report for the NGOs.



                                                                                           52
STRENGTHENING THE
               Annual Work Plan                              CAPACITY OF THE
               AWP 2012                                      MINISTRY OF SOCIAL
                                                             SOLIDARITY PROJECT

 Output: 5         NEW SOCIAL PROTECTION SYSTEM

Description: To Review & Improve targeting

YYYY target: 2012

 1. Targeting Database Project:
     Complete Data entry of 1000 villages.
     Targeting criteria and formula is used.
     Complete Data of supply card beneficiaries to contain all targeting criteria.
     Exporting Targeting data for the completed Governorates in easy format for SPSS
      statistics analysis.

 2.    Smart Cards:
       Rollout of smart cards for Solidarity Pension Service throughout all Governorates.
       Develop and implement interface with wholesale companies.


 3. Social Solidarity Pensions from Post Offices:
     Finalize issuing Social Solidarity Pension from any Post Office in the same Governorate
      by family smart card.
                                                                                                53
STRENGTHENING THE
               Annual Work Plan                             CAPACITY OF THE
                                                            MINISTRY OF SOCIAL
               AWP 2012                                     SOLIDARITY PROJECT

     Output: 6     IMPROVING NASSER SOCIAL BANK

Description: To assess Nasser Social Bank and prepare it for restructuring.
YYYY target: 2012
1. Prepare revised set of regulations for NSB Investment, “Takaful”, “Takeraats/Akarats” and
     Legal divisions.
2.   Continue to:
      Connect central departments to newly commissioned NSB’s digital network.
      Investigate means to modernize archiving capabilities.
      Introduce ATM services to NSB clients and employees.
      Redefine branches’ performance criteria to match NSB’s philosophies/mission.
      Develop NSB website.
      Develop NSB intranet site (for internal use).
      Develop a preliminary concept for a revamped main branch at 35 Kasr El Nil-Cairo.
      Implement Year 2012 NBE training program.
      Continue monitoring progress at the three new branches: Nasr City, 6 Oct., and Zakazeek.
      Prepare a human development program for NSB staff.
      Monitor progress of the new Human Capital Development Centre (HCDC).

                                                                                               54
STRENGTHENING THE
               Annual Work Plan                               CAPACITY OF THE
                                                              MINISTRY OF SOCIAL
               AWP 2012                                       SOLIDARITY PROJECT

   Output: 6        IMPROVING NASSER SOCIAL BANK
Description: To assess Nasser Social Bank and prepare it for restructuring.

YYYY target: 2012

3. Evaluate 6 branches of NSB and “Zakaat” committees in Southern Egypt.
4. Finalize revised regulations for Investment, “Takaful”, “Takeraats/Akarats” and Legal divisions.
5. Connect central departments to NSB’s newly commissioned digital network.
6. Issue the strategy formulation process with NSB’s executives.
7. Initiate contact with Engineering Authority of Armed Forced to revamp upper Egypt branches,
   and Initiate a study to formulate functionalities and roles to introduce new NSB access points
8. Revamped, completely, the Information and Computer Center of NSB, connecting 10
   Database Centers of NSB branches.

9. Establish the bank’s Call Center, and documenting all operational regulations.
                                                                                                55
STRENGTHENING THE CAPACITY
OF THE MINISTRY OF SOCIAL
SOLIDARITY PROJECT




  THANK YOU



                             56

More Related Content

Viewers also liked

Project Report, Design Project 2 - ICT Intervention for Improvisation of Mate...
Project Report, Design Project 2 - ICT Intervention for Improvisation of Mate...Project Report, Design Project 2 - ICT Intervention for Improvisation of Mate...
Project Report, Design Project 2 - ICT Intervention for Improvisation of Mate...Mannu Amrit
 
Mechanisms of adaptation to drought and waterlogging in Brachiaria grasses
Mechanisms of adaptation to drought and waterlogging in Brachiaria grassesMechanisms of adaptation to drought and waterlogging in Brachiaria grasses
Mechanisms of adaptation to drought and waterlogging in Brachiaria grassesCIAT
 
Notifying the people about waterlogging places
Notifying the people about waterlogging placesNotifying the people about waterlogging places
Notifying the people about waterlogging placesGaurav Agarwal
 
Powerpoint slids' made for sef
Powerpoint slids' made for sefPowerpoint slids' made for sef
Powerpoint slids' made for sefNEERAJ SRIVASTAVA
 
water logging and salinity in pakistan by Musadiq Rehmani
water logging and salinity in pakistan by Musadiq Rehmaniwater logging and salinity in pakistan by Musadiq Rehmani
water logging and salinity in pakistan by Musadiq Rehmanimusadiqrehmani
 
How to Grow Your Career by Influencing Others
How to Grow Your Career by Influencing OthersHow to Grow Your Career by Influencing Others
How to Grow Your Career by Influencing OthersBruce Kasanoff
 

Viewers also liked (7)

Project Report, Design Project 2 - ICT Intervention for Improvisation of Mate...
Project Report, Design Project 2 - ICT Intervention for Improvisation of Mate...Project Report, Design Project 2 - ICT Intervention for Improvisation of Mate...
Project Report, Design Project 2 - ICT Intervention for Improvisation of Mate...
 
Mechanisms of adaptation to drought and waterlogging in Brachiaria grasses
Mechanisms of adaptation to drought and waterlogging in Brachiaria grassesMechanisms of adaptation to drought and waterlogging in Brachiaria grasses
Mechanisms of adaptation to drought and waterlogging in Brachiaria grasses
 
Notifying the people about waterlogging places
Notifying the people about waterlogging placesNotifying the people about waterlogging places
Notifying the people about waterlogging places
 
Powerpoint slids' made for sef
Powerpoint slids' made for sefPowerpoint slids' made for sef
Powerpoint slids' made for sef
 
water logging and salinity in pakistan by Musadiq Rehmani
water logging and salinity in pakistan by Musadiq Rehmaniwater logging and salinity in pakistan by Musadiq Rehmani
water logging and salinity in pakistan by Musadiq Rehmani
 
Water logging
Water loggingWater logging
Water logging
 
How to Grow Your Career by Influencing Others
How to Grow Your Career by Influencing OthersHow to Grow Your Career by Influencing Others
How to Grow Your Career by Influencing Others
 

Similar to UNDP MoSS Project Board Meeting 30062012

Q1 2012 Progress Report MoSS
Q1 2012 Progress Report   MoSSQ1 2012 Progress Report   MoSS
Q1 2012 Progress Report MoSSMoheebSattar
 
Annual Work Plan 2012 Final
Annual Work Plan 2012 FinalAnnual Work Plan 2012 Final
Annual Work Plan 2012 FinalMoheebSattar
 
Q4 2011 Progress Report MoSS
Q4 2011 Progress Report   MoSSQ4 2011 Progress Report   MoSS
Q4 2011 Progress Report MoSSMoheebSattar
 
Q2 2012 Progress Report MoSS
Q2 2012 Progress Report   MoSSQ2 2012 Progress Report   MoSS
Q2 2012 Progress Report MoSSMoheebSattar
 
1. Development Plan Career Activity. Respond to the following
1. Development Plan Career Activity. Respond to the following1. Development Plan Career Activity. Respond to the following
1. Development Plan Career Activity. Respond to the followingAbbyWhyte974
 
1. Development Plan Career Activity. Respond to the following
1. Development Plan Career Activity. Respond to the following1. Development Plan Career Activity. Respond to the following
1. Development Plan Career Activity. Respond to the followingMartineMccracken314
 
Core Skills For Public Sector Innovation
Core Skills For Public Sector InnovationCore Skills For Public Sector Innovation
Core Skills For Public Sector InnovationColaborativismo
 
Better future for social economy EU policy
Better future for social economy EU policyBetter future for social economy EU policy
Better future for social economy EU policyLucie Evers
 
Community led total sanitation (clts) community-based total sanitation (stbm)...
Community led total sanitation (clts) community-based total sanitation (stbm)...Community led total sanitation (clts) community-based total sanitation (stbm)...
Community led total sanitation (clts) community-based total sanitation (stbm)...Sekretariat STBM
 
MindLab's UNDP Knowledge and Innovation evaluation
MindLab's UNDP Knowledge and Innovation evaluationMindLab's UNDP Knowledge and Innovation evaluation
MindLab's UNDP Knowledge and Innovation evaluationUNDP Eurasia
 
The Multi- Stakeholder Approach to Policy Influence for ICT led Inclusive Growth
The Multi- Stakeholder Approach to Policy Influence for ICT led Inclusive GrowthThe Multi- Stakeholder Approach to Policy Influence for ICT led Inclusive Growth
The Multi- Stakeholder Approach to Policy Influence for ICT led Inclusive GrowthShipra Sharma
 
Community-Based Total Sanitation (STBM). Milestone, Strategic Plan, Lessons L...
Community-Based Total Sanitation (STBM). Milestone, Strategic Plan, Lessons L...Community-Based Total Sanitation (STBM). Milestone, Strategic Plan, Lessons L...
Community-Based Total Sanitation (STBM). Milestone, Strategic Plan, Lessons L...Oswar Mungkasa
 
LECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptxLECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptxmansoor584949
 
DPE guidelines on CSR for CPSE 2010
DPE guidelines on CSR for CPSE 2010DPE guidelines on CSR for CPSE 2010
DPE guidelines on CSR for CPSE 2010Dinesh Agrawal
 
Publicpolicy econference
Publicpolicy econferencePublicpolicy econference
Publicpolicy econferencesurajguha1984
 
Restart+ Module 4 Turning Community Regeneration Ideas into Action
Restart+ Module 4 Turning Community Regeneration Ideas into ActionRestart+ Module 4 Turning Community Regeneration Ideas into Action
Restart+ Module 4 Turning Community Regeneration Ideas into Actioncaniceconsulting
 

Similar to UNDP MoSS Project Board Meeting 30062012 (20)

Q1 2012 Progress Report MoSS
Q1 2012 Progress Report   MoSSQ1 2012 Progress Report   MoSS
Q1 2012 Progress Report MoSS
 
Annual Work Plan 2012 Final
Annual Work Plan 2012 FinalAnnual Work Plan 2012 Final
Annual Work Plan 2012 Final
 
Q4 2011 Progress Report MoSS
Q4 2011 Progress Report   MoSSQ4 2011 Progress Report   MoSS
Q4 2011 Progress Report MoSS
 
Q2 2012 Progress Report MoSS
Q2 2012 Progress Report   MoSSQ2 2012 Progress Report   MoSS
Q2 2012 Progress Report MoSS
 
MOVE Congress 2015: Innovative Fundraising
MOVE Congress 2015: Innovative FundraisingMOVE Congress 2015: Innovative Fundraising
MOVE Congress 2015: Innovative Fundraising
 
1. Development Plan Career Activity. Respond to the following
1. Development Plan Career Activity. Respond to the following1. Development Plan Career Activity. Respond to the following
1. Development Plan Career Activity. Respond to the following
 
1. Development Plan Career Activity. Respond to the following
1. Development Plan Career Activity. Respond to the following1. Development Plan Career Activity. Respond to the following
1. Development Plan Career Activity. Respond to the following
 
Core Skills For Public Sector Innovation
Core Skills For Public Sector InnovationCore Skills For Public Sector Innovation
Core Skills For Public Sector Innovation
 
Better future for social economy EU policy
Better future for social economy EU policyBetter future for social economy EU policy
Better future for social economy EU policy
 
BUILD UPON Project Summary
BUILD UPON Project SummaryBUILD UPON Project Summary
BUILD UPON Project Summary
 
Community led total sanitation (clts) community-based total sanitation (stbm)...
Community led total sanitation (clts) community-based total sanitation (stbm)...Community led total sanitation (clts) community-based total sanitation (stbm)...
Community led total sanitation (clts) community-based total sanitation (stbm)...
 
MindLab's UNDP Knowledge and Innovation evaluation
MindLab's UNDP Knowledge and Innovation evaluationMindLab's UNDP Knowledge and Innovation evaluation
MindLab's UNDP Knowledge and Innovation evaluation
 
The Multi- Stakeholder Approach to Policy Influence for ICT led Inclusive Growth
The Multi- Stakeholder Approach to Policy Influence for ICT led Inclusive GrowthThe Multi- Stakeholder Approach to Policy Influence for ICT led Inclusive Growth
The Multi- Stakeholder Approach to Policy Influence for ICT led Inclusive Growth
 
Community-Based Total Sanitation (STBM). Milestone, Strategic Plan, Lessons L...
Community-Based Total Sanitation (STBM). Milestone, Strategic Plan, Lessons L...Community-Based Total Sanitation (STBM). Milestone, Strategic Plan, Lessons L...
Community-Based Total Sanitation (STBM). Milestone, Strategic Plan, Lessons L...
 
ST.MICHEAL PROJECT
ST.MICHEAL  PROJECTST.MICHEAL  PROJECT
ST.MICHEAL PROJECT
 
LECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptxLECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptx
 
DPE guidelines on CSR for CPSE 2010
DPE guidelines on CSR for CPSE 2010DPE guidelines on CSR for CPSE 2010
DPE guidelines on CSR for CPSE 2010
 
Publicpolicy econference
Publicpolicy econferencePublicpolicy econference
Publicpolicy econference
 
Restart+ Module 4 Turning Community Regeneration Ideas into Action
Restart+ Module 4 Turning Community Regeneration Ideas into ActionRestart+ Module 4 Turning Community Regeneration Ideas into Action
Restart+ Module 4 Turning Community Regeneration Ideas into Action
 
Aguilarnssdbrochure
AguilarnssdbrochureAguilarnssdbrochure
Aguilarnssdbrochure
 

UNDP MoSS Project Board Meeting 30062012

  • 1. STRENGTHENING THE CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT The Project Board Meeting 30/6/2012 Ministry of Supply and Internal Trade Ministry of Insurance and Social Affairs Ministry of Foreign Affairs Prepared by : Consultant Eng. Moheeb Aabdel Sattar July 2012 UNDP Project Manager 1
  • 2. STRENGTHENING THE PROJECT CAPACITY OF THE ACHIEVEMENTS 2011 MINISTRY OF SOCIAL SOLIDARITY PROJECT CONTENTS: I. Introduction II. Executive Summary III. Conclusions IV. Recommendations V. Lessons Learnt VI. Project Expected Outputs: (Progress) 2
  • 3. STRENGTHENING THE Introduction: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT  The project was launched in 2006 with a timeframe of 2006-2009 with a total budget of US $2.2 Million (MOSS contribution US$ 1.851 Million and UNDP contribution amounting to US$ 350 Thousand).  The Project Board has agreed to increase the project’s funding by US $2,650 thousand to continue and expand its activities as follows:  US$ 900 thousand in 2010/2011.  US$ 900 thousand in 2011/2012.  US$ 850 thousand in 2012/2013.  In April 2011 the Project Board has agreed to extend the project duration until the end of year 2012. 3
  • 4. STRENGTHENING THE Introduction: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT The project aims to:  Develop and build the capacity of the Ministry of Social Solidarity (MOSS) to design and implement social policies.  Increase the relevance and efficiency of social protection schemes and social intervention including local development.  Contribute to elaborating a new social contract, namely in the field of poverty reduction through better empowerment and participation of the poor and civil society organizations.  Establishing an advisory support unit for policy advice and capacity building in MOSS is a key output of this project and an entry point to other outputs and activities. 4
  • 5. STRENGTHENING THE Executive Summary: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT The project has six outputs:  The first output (MOSS TAU Established): To support MOSS in recruiting outside expertise to assist it carry out the project’s targets.  The second output (MOSS NEW STRUCTURE): To developing MOSS’ mission & vision to respond to its new mandate.  The third output (MOSS CAPACITY DEVELOPMENT): To develop capacity building for MOSS and NGOs.  The fourth output (ACCREDIT & ELIGIBILITY for NGOs): To create an accreditation & eligibility system for NGOs in Egypt.  The fifth output (NEW SOCIAL PROTECTION SYSTEM): To design a more effective system for social protection.  The sixth output (IMPROVING NASSER SOCIAL BANK): To evaluate NSB and prepare it for restructuring. 5
  • 6. STRENGTHENING THE Executive Summary: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT  The rank of the first Output is satisfactory.  The analysis shows that the rank of the second output is satisfactory.  The progress of the third output and its expected outcome seem marginally satisfactory.  The rank of the fourth output and its expected outcome are unsatisfactory.  For the fifth output :  MOSS developed the productive families associations, link them to other institutions in Europe that provided them with design and training, and then marketed their products abroad.  MOSS investigated leakage in the subsidies system. The solution was to use ICT to monitor and follow-up on disbursed solidarity checks, subsidized food items, such as cooking oil, and distributing gas cylinders to the deserved population through the use of coupons.  The efforts of the project, and MOSS at large, to achieve this output and its outcome are remarkable, and thus the fifth output ranks as satisfactory. 6
  • 7. STRENGTHENING THE Executive Summary: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT  The sixth output was to evaluate NSB. Project experts elaborated an assessment, and recommendations for an action plan for NSB. The development and upgrading NSB has taken steps in the right directions, yet there are more needed actions. Assessment of NSB and its improvements are also a step towards enhancing the environment for both the workers and the clients. The rank of this output and its outcome is highly satisfactory.  Consequently, UNDP project to strengthen the capacities of MOSS is satisfactory.  Resources allocated to project activities, as indicated in the auditors’ annual report, seem to be efficiently used. 7
  • 8. STRENGTHENING THE Executive Summary: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT  The output concerned with NGOs needs more attention. Having a database is not enough. There is a need to revise the law, and other elements of the institutional framework that governs the work of NGOs to stimulate them.  There is a need to evaluate these experiences, then draw lessons learnt and best practices to scale-up the use of these tools to a national policy.  The project will need to elaborate a log-frame with indicators, risks, external factors and other elements of designing an intervention, and propose means for integrating the various outputs.  The project needs to lay-out a plan for phasing out, and A strategy of sustaining the achievements. 8
  • 9. STRENGTHENING THE Executive Summary: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT  Obviously, there is a need for another phase, but with a design based on a different philosophy to meet the current aspirations following the January 25th revolution.  The new phase has to seek linkages between the various entities of MOSS. It also needs to pay more attention to NGOs to be a complete partner and able to reach those who live in informal areas and rural settlements.  The new phase has to experiment with tools for enabling and empowering the people who live in misery to be in-charge of their resources and future. 9
  • 10. STRENGTHENING THE Executive Summary: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT  The project faced number of challenges, such as lack of reliable, valid and complete information; financial limitations, cooperation of other public bodies, resistance to change, etc.  The main factor for the success of this project is the support and attention that the former Minister paid to the project. The advisors have authority, and working closely with their counterparts by coaching them to make presentations to the former Minister, involving them in the different processes, such as conducting a study or an assessment. 10
  • 11. STRENGTHENING THE Executive Summary: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT Output 1: An Advisory Unit established The first output is a Technical Advisory Unit (TAU) at MOSS. This unit will be responsible for: • Strategic policy advice including strategic options, research and coordination, and situation and prospective analyses; • Restructuring MOSS including organizational structure, internal governance, human resources and mainstreaming the use of Information Technology (IT); and • Program implementation support, such as training, communication, etc. 11
  • 12. STRENGTHENING THE Executive Summary: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT Output 2: MOSS new proposed structure submitted for decision making • Proposing an organizational structure for MOSS is central to fulfilling its mandate and mission. • The “merger” of two established institutions, i.e., the Ministry of Supply and Ministry of Social Affairs requires a new organizational structure to assure smooth cooperation and synergies within the newly established institution. • The “split” of Ministry of Solidarity and Social Justice into two established institutions, i.e., the Ministry of Supply and Internal Trade and Ministry of Insurance and Social Affairs requires a new organizational structure to assure smooth cooperation and synergies within the newly established institutions. 12
  • 13. STRENGTHENING THE Executive Summary: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT Output 3: Capacity Development of key staff institutionalized • The project avails training to key staff at MOSS, such as social workers, and their partners, particularly NGOs. • In addition to delivering training, the project will contribute to elaborating an efficient and dynamic communication strategy to convey relevant messages to the population, properly reflect the image of MOSS. 13
  • 14. STRENGTHENING THE Executive Summary: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT Output 4: A system for accrediting NGOs developed • MOSS is the official regulatory body for NGOs active in Egypt. • NGOs are instrumental in achieving the mission of MOSS, and thus are among the most significant partners of MOSS. • They are able to reach those marginalized and unprivileged sub-population groups, such as female-headed households. • NGOs receive financial and technical support. For this reason, it is of utmost importance that MOSS has a system for monitoring NGOs to effectively eradicate poverty. Thus a database of the 20 thousand NGOs registered with MOSS is essential to achieve the mission and mandate of MOSS. • Equally important is to setup a system of accrediting and eligibility for NGOs. These two steps are central to producing a periodic report on NGOs, to monitor their activities, and provide them with necessary support. 14
  • 15. STRENGTHENING THE Executive Summary: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT Output 5: A more developed and effective system for social protection • Today, capability poverty substitutes the notion of monetary measure of poverty. • Several studies indicated that fallacy of Poverty Lines (PL). Capability poverty provides means for targeting the poor, who are they? Where they live? What exactly they need to move to an improved standard of living. • Designing an adequate social protection system requires a better mechanism for targeting the poor. This mechanism serves as a vehicle to setting priorities straight, efficient and effective interventions to alleviate poverty. 15
  • 16. STRENGTHENING THE Executive Summary: CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT Output 6: Nasser Social Bank evaluated • The project funded that assessment of Nasser Social Bank (NSB), and its role. • The assessment highlights the strengths and weaknesses of NSB, as well as the available opportunities for improving its role in poverty alleviation in areas such as sponsoring Small and Micro Enterprises (SMEs) and threats, i.e., risks, in the external environment of NSB that might limit its effectiveness. • UNDP helped in recruiting a team of national and international experts to conduct the assessment and layout a business plan for NSB emulating successful experiences in Asia and Latin America. 16
  • 17. STRENGTHENING THE Conclusions : CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT Consequently, UNDP project to strengthen the capacities of MOSS is satisfactory. • The project used number of tools to ration subsidies, such as targeting the poor and the use of smart cards. • There are other practices to alleviate poverty, such as CCT and productive families. • Assessment of NSB and its improvements are also a step towards enhancing the environment for both the workers and the clients. • The output concerned with NGOs needs more attention. Having a database is not enough. There is a need to revise the law, and other elements of the institutional framework that governs the work of NGOs to stimulate them. 17
  • 18. STRENGTHENING THE CAPACITY OF THE Recommendations : MINISTRY OF SOCIAL SOLIDARITY PROJECT • The project is coming to an end, yet there are some unfinished businesses and loose ends to tie. There is a need to evaluate these experiences, then draw lessons learnt and best practices to scale-up the use of these tools to a national policy. The project will need to elaborate a log-frame with indicators, risks, external factors and other elements of designing an intervention, and propose means for integrating the various outputs. The project needs to lay-out a plan for phasing out, and a strategy of sustaining the achievements. • Obviously, there is a need for another phase, but with a design based on a different philosophy to meet the current aspirations following the January 25th revolution. The new phase has to seek linkages between the various entities of MOSS, It also needs to pay more attention to NGOs to be a complete partner and able to reach those who live in informal areas and rural settlements. The new phase has to experiment with tools for enabling and empowering the people who live in misery to be in-charge of their resources and future. 18
  • 19. STRENGTHENING THE CAPACITY OF THE Lessons learnt : MINISTRY OF SOCIAL SOLIDARITY PROJECT • ICT is not always the solution, particularly in a country that lacks reliable, valid and continuous data. ICT can help in development, but has limits. • Strengthening the capacities of a public institution is extremely difficult as it requires transformations in beliefs. Change is possible, but often is resisted from within the public institution. • If MOSS wants to succeed in fulfilling its mandate and mission, then there is a need to engage private-sector companies and NGOs in the processes of decision-making to assure their ownership and responsibility for implementation. • Most of the decisions made within public bodies are based on “political'” rather than “technical" considerations. Among the reasons for this situation, that future is sometimes uncertain. Conditions within the public institution and outside it always changes, thus precise prediction, projection and forecasting are not often possible. 19
  • 20. STRENGTHENING THE CAPACITY OF THE Lessons learnt : MINISTRY OF SOCIAL SOLIDARITY PROJECT • When a public institution engages with another institution, whether public, private or non-profit, then the element of change is probably of special importance. The other institution tries to impose change on the public institution, thus forcing the institution to consider serious counter-measures. • Public institutions often do not advertise action plan action in advance to avoid opposition. • To the contrary, private-sector companies are radically different. Decisions are made to maximize profit and minimize costs. For this reason decisions are based on technical considerations as well as political and social acceptances. Private-sector companies always have the shareholders, clients, competitors and collaborators, such as financing institutions, in perspective. Thus advertising is important, and the image is crucial to test ideas, target specific groups and so forth. 20
  • 21. STRENGTHENING THE PROJECT CAPACITY OF THE ACHIEVEMENTS 2011 MINISTRY OF SOCIAL SOLIDARITY PROJECT CONTENTS: I - PROJECT EXPECTED OUTPUTS: (PROGRESS) 1 - ADVISORY UNIT 2 - RESTRUCTURING 3 - CAPACITY BUILDING 4 - NGO’S ACCREDDITATION SYSTEM 5 - SOCIAL PROTECTION SYSTEM 6 - NASSER SOCIAL BANK II- PROJECT FINANCES III- PROJECT’S RISKS & ITS MANAGEMENT IV- FUTURE PLANS & CHALLENGES 21
  • 22. STRENGTHENING THE I - PROJECT CAPACITY OF THE MINISTRY OF SOCIAL EXPECTED OUTPUTS SOLIDARITY PROJECT THE FOLLOWING OUTPUTS SHALL BE ACHIEVED DURING THE PROJECT’S DURATION (year 2011). Output: 1 Advisory Unit is Established. Output: 2 Proposed New Structure is Submitted Output: 3 Capacity Development is Institutionalized. Output: 4 NGO’S Accreditation & Eligibility System is in Place. Output: 5 An Effective Social Protection System is Designed. Output: 6 Nasser Social Bank is Evaluated. 22
  • 23. STRENGTHENING THE I - PROJECT CAPACITY OF THE EXPECTED OUTPUTS MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 1 ADVISORY UNIT IS ESTABLISHED PROGRESS  In 2011 the project contracted 7 additional consultants & (year 2011) technical support staff and assigned them to various tasks within MoSS’ departments, and in direct contacts with MoSS’ senior & middle level staff, including:  Minister Consultant for mega bakeries,  Minister consultant for media, and  6 technical support & administrative staff.  9 consultant, technical support & administrative staff quite.  The project now has 40 contracted staff in total. 23
  • 24. STRENGTHENING THE I - PROJECT CAPACITY OF THE EXPECTED OUTPUTS MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 2 PROPOSED NEW STRUCTURE IS SUBMITTED  Central Agency for Restructuring Projects ( Completed ): • Establishment (20) projects (from a total of 62 draft) • Development (9) projects (from a total of 18 draft) PROGRESS (year 2011)  Educational Buildings Authority projects (Been completed): • Establishment (5) projects (out of 10 total projects) • Development (7) projects (out of 9 total projects) • Raising the efficiency of one project (out of 2 total projects)  Housing Directorates Projects in Governorates : Follow-up completion of (15) projects being implemented by housing directorates in Governorates.  Court building project of the new ministry building in Agouza: Been ratified by the Ministry of Planning and International Cooperation, the transfer of 8 million L.E. of building allocations General Board (16 million L.E.) paid for Military Works Department of Forced Armed as down payment.  Raise the efficiency of social units Projects : Upgrading of (9) social units (out of total 33 units) planned to be raised the efficiency. 24
  • 25. STRENGTHENING THE I - PROJECT CAPACITY OF THE EXPECTED OUTPUTS MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 3 CAPACITY DEVELOPMENT IS INSTITUTIONALIZED (Information Technology)  Smart Cards: • Defined matching rules of the input data for the ration cards with the exchange data and sent it to the smart cards companies. PROGRESS • Smart cards companies designed programs necessary to be matching. (year 2011) • Testing the matching programs in some Governorates Such as Port Said & Aswan.  Family Database System: • Finalize rollout of the system in 27 Governorates. • Technical support for Family Database.  Targeting: • Technical support for Targeting Program. • Exporting Targeting data of finished Governorates to a format of SPSS statistics.  Social Solidarity Pensions from Post Offices: • Following up the monthly implantation circulation of Social Solidarity Pensions from Post Offices. • Transferring Social Solidarity Pensions database of El-Monofeya , Kafr El Shiekh and El-Gharbya from SIO to Family Profile Program. • Co-operation with Governorates and social administrative offices and Information Center of MoSS to solve all the networks and technical problems. 25
  • 26. STRENGTHENING THE I - PROJECT CAPACITY OF THE EXPECTED OUTPUTS MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 3 CAPACITY DEVELOPMENT IS INSTITUTIONALIZED (Information Technology)  NGOs Application: • The system has been updated according to the requirements of the central department of NGO’s. PROGRESS • Adding new screens (training programs - Membership & Contributions – (year 2011) Committees Members of Board of Directors - Meetings of Board of Directors - Members of the Assembly - the Assembly meetings - volunteers - NGO problems - research experience - revenues and expenses - budget). • Designed of the required reports (Statistics - detailed data).  Pilgrimage System: • Finalize system updates.  Call Center Project: • Finalize system updates.  ERP Project: • Finalize system updates.  Designing of a new system for distributing subsidized Natural Gas Cylinders is completed . 26
  • 27. STRENGTHENING THE I - PROJECT CAPACITY OF THE EXPECTED OUTPUTS MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 3 CAPACITY DEVELOPMENT IS INSTITUTIONALIZED (Information Technology)  GIS System: GIS work includes 3 main items: PROGRESS 1. GIS Web Portal linked to Ministry main web site. (year 2011) 2. Mapping Supply services: Creating GIS maps for the current supply services on the street level detailed maps (scale 1:5000) covers all Egypt Governorates. 3. Mapping Target Project results: Creating GIS printouts highlight the result of targeting project with co-operation of institute of social study.  Redesign & development of MoSS Website: • Analysis of the current web site, and identifying the restructuring needed and the information and services to be included on the new website. • Developing the new website information structure. • Selecting and evaluating the platform to be used in development the new website. • Creating the design of the new web site, and implementing sample homepage and an internal page. 27
  • 28. STRENGTHENING THE I - PROJECT CAPACITY OF THE EXPECTED OUTPUTS MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 3 CAPACITY DEVELOPMENT IS INSTITUTIONALIZED (Information Technology) PROGRESS  Productive families projects were increased by 8000, with 11000 (year 2011) beneficiaries.  The training of (1128) MoSS’ employees is completed. The training programs’ specifics included the following breakdown: • Training (30) of Executive Management , • Training (728) of Social Employees at the Social Services Units, • Training (250) of Social Services Units’ Secretaries (Transfer Training), • Training (120) of Daman staff members and Information Centre's employees on MoSS Family Profile Database of 23 Governorates, 28
  • 29. STRENGTHENING THE I - PROJECT CAPACITY OF THE EXPECTED OUTPUTS MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 3 CAPACITY DEVELOPMENT IS INSTITUTIONALIZED (Information Technology)  Activities of short term National Consultants: PROGRESS • Prepare draft version of “the National Body of Food Subsidy” law. • Prepare Case Study on “General Structure of MEGA Bakeries and merging of Small (year 2011) Bakeries”. • Prepare Case Study on “Supply Chain Study” to the Minister. • Finalize Case Study of “Measuring of the Balady Bread Production Cost” through field survey on 5 bakeries. • Prepare TOR of “Build and design a new efficient and effective system for Balady Bread through removing government intervention from initial stages of the Balady Bread Supply Chain to its last stage.  Cooperation with WFP and international experts: • Review Egyptian country strategy for the World Food Program 2012 to 2016. • Build and design a new efficient and effective system foe Balady bread. • Draw structured implementation plan for the new Balady Bread system. • Design a pilot project for the first phase of the implementation of the new enhanced and efficient Balady Bread system. 29
  • 30. STRENGTHENING THE I - PROJECT CAPACITY OF THE EXPECTED OUTPUTS MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 4 NGO’S ACCREDITATION & ELEGIBILITY SYSTEM  to develop a system for accrediting NGOs, MOSS in collaboration with CAPMAS and the Union for NGOs, established a database of NGOs, and set a system for accreditation of NGOs, which has not be PROGRESS functional yet. There is limited cooperation between the project staff responsible (year 2011) for this output and their counterpart within MOSS.  The NGOs Accreditation Criteria and the form for implementation were finalized, • Implementation for 100 NGOs and results analyzed. • Additional criteria were developed for NGOs dealing with disability.  The NGOs’ Database is being revamped. Its aim to develop a database for the NGOs in Egypt and produce unified statistics. The work achieved during this period includes: • Defining data items to be added into the System (required by CAPMAS & Union of NGO’s), • Design and development of the system are completed. 30
  • 31. STRENGTHENING THE I - PROJECT CAPACITY OF THE EXPECTED OUTPUTS MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 5 NEW SOCIAL PROTECTION SYSTEM  Smart Cards:  Defined the rules of matching the input data for the ration cards with the exchange data and sent it to the smart card companies. PROGRESS  The smart card companies designed programs necessary to the matching. Testing the matching programs in some Governorates such as Port Said and (year 2011)  Aswan.  Targeting Database Project:  Technical support for Targeting Program.  Exporting Targeting data for the completed governorates in a format that easy for SPSS statistics analysis.  Social Solidarity Pensions from Post Offices:  Following up the monthly operation of Social Solidarity Pensions from Post Offices.  Extracted and transferring Social Solidarity Pensions database of El-Kaliopia and El-Behira from Social Insurance Organization, SIO to Family Profile Program.  Co-operating with Governorates and social administrative offices and Information Center of MoSS to solve all the networks and technical problems of the project. 31
  • 32. STRENGTHENING THE I - PROJECT CAPACITY OF THE MINISTRY OF SOCIAL EXPECTED OUTPUTS SOLIDARITY PROJECT Output: 6 IMPROVING NASSER SOCIAL BANK  Revamping the current data center at NSB Head Office to enable the operation of a newly developed state-of-the-art digital network. PROGRESS  Established an NSB Human Capital Development Center (HCDC). (year 2011)  Developed new/revised bank regulations.  Developed a model for the look-and-feel of rebranded bank branches, hired well over 400 new employees based on predefined set of selection criteria, and opened 3 new branches conforming to the new rebranded branch model.  NSB automation project will fully automate all NSB services and connect all of its 90 branches through a sophisticated/secured network. It will also ensure that the bank uses state-of-the-art technologies and information systems. The project will incorporate an efficient business continuity solution to ensure data integrity and around the clock availability of services. In addition, the project will enable the bank to provide a set of services that it is not currently possible due to the nature of its legacy/outdated information systems and technologies. 32
  • 33. STRENGTHENING THE I - PROJECT CAPACITY OF THE MINISTRY OF SOCIAL EXPECTED OUTPUTS SOLIDARITY PROJECT Output: 6 IMPROVING NASSER SOCIAL BANK The bank is undertaking an aggressive human capital development initiative and succession plan. The initiative will begin with a massive PROGRESS human capital assessment and gap analysis phase followed by a (year 2011) customized human capital development program that targets employees across the organization to change/improve its culture. The bank has developed a three-year plan to revamp its ninety branches across Egypt.  In 2010, NSB managed to develop a model for the newly branded branches and revamped three branches. Now the processes, consulting offices, and implementation contractors are on board and according to the plan the bank revamped 19 branches in 2011 and the remaining branches will be done by 2014. 33
  • 34. STRENGTHENING THE CAPACITY OF THE MINISTRY OF SOCIAL II – PROJECT FINANCES SOLIDARITY PROJECT THE PROJECT FINANCES : 2006 - 2011 Output Description 2006 2007 2008 2009 2010 2011 Output 1 Advisory Unit $51,893.65 $198,255.7 $313,102.98 $314,442.12 $361,160.83 $248,303.73 Output 2 Restructuring _ _ $17,163.56 $117,375.12 $150,801.85 $145,691.64 Output 3 Capacity Building _ _ $7,560.06 $16,067.22 $30,775.01 $26,525.80 NGOs Accreditation Output 4 _ _ $290.14 $93,686.15 $84,071.56 $65,524.80 System Social Protection Output 5 $11,783.96 $29,635.5 $56,251.8 $140,757.76 $58,844.01 $41,004.69 System Output 6 Nasser Social Bank _ $52,784.5 $31,974.47 $112,959.51 $149,693.27 $38,069.48 Total $63,677.61 $280,675.70 $426,343.01 $795,287.88 $835,346.53 $565,131.50 34
  • 35. STRENGTHENING THE CAPACITY OF THE II – PROJECT FINANCES MINISTRY OF SOCIAL SOLIDARITY PROJECT THE PROJECT FINANCES : 2006 - 2011 The project was able to achieve major financial savings as a direct result of the following contributing factors:  The nature of the work planned and achieved for this project is intentionally carried out in gradual, incremental in order to ensure future sustainability.  All costs related to MoSS’s developing of social units were funded from MoSS’ budget.  All costs related to MoSS’s training programs were funded from MoSS’ budget, but the training programs were devised and supervised by the Project’s contracted staff.  All the costs related to upgrading MoSS’ IT infrastructure, including software, hardware, and other equipment were paid from MoSS’ own budget or through MCIT and MSAD.  All the costs related to Nasser Social Bank’s training programs and IT upgrading, including the purchasing of software, hardware, as well as other reform/restructuring expenditures were paid from the bank’s own budget.  All the administrative aspects of the project fixed assets were funded by MoSS, including furbishing, equipments, IT requirements, etc, 35
  • 36. STRENGTHENING THE III – PROJECT RISK & CAPACITY OF THE MINISTRY OF SOCIAL ITS MANAGEMENT SOLIDARITY PROJECT THE PROJECT RISKS & RISK MANAGEMENT: PROJECT RISKS PROJECT RISK MANAGEMENT The capacity of the MoSS staff to The Project has supported and expanded adapt and absorb changes introduced all types of training programs of MoSS by the project is limited. staff, in order to ensure adoption of introduced reforms by MoSS’ staff. The Project management ensured that all contracted Senior Advisors, The PMU is not fully integrated with Consultants, and Specialists are assigned MoSS. to interact and work directly with MoSS’ senior and middle level staff, in order to ensure transfer of Knowledge & expertise. 36
  • 37. STRENGTHENING THE IV – FUTURE PLANS & CAPACITY OF THE MINISTRY OF SOCIAL CHALLANGES SOLIDARITY PROJECT THE PROJECT’S FUTURE PLANS AND CHALLENGES: Here are the project’s future plans to implement and the challenges to be addressed during year 2012: • Conduct a Project Evaluation Exercise during the first quarter of 2012, in order to measure progress achieved during year 2011, identify shortfalls, effectiveness and efficiencies (through the contracting of an expert/company). • Project extended to the end of December 2012. • Financing is required from the Ministry of Finance to fund MoSS’s large-scale services improvement and development programs. 37
  • 38. STRENGTHENING THE CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT Effectiveness and Efficiency of Current Information Systems (Strengths and Weaknesses) • Strengths: 1. Users need assessments was done to meet MoSS requirements. 2. Team work consisted of national consultants working together with MoSS staff to build and increase their capabilities to be able to operate and maintain the MoSS Information System in the future. 3. MoSS Information System was built using the up-to date technology with standards documentation (to be completed). • Weaknesses: 1. Lack of exchange data between the Governmental Agencies. 2. MoSS Information Strategic Plan Not established at the beginning of the project. 3. System Design was not built to ensure databases integration. 38
  • 39. STRENGTHENING THE CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT Constrains and barriers to manage and improve availability and accessibility of data and information. The most significant constraint to establish Integrated Information Systems in Egypt : 1. The lack of reliable and timely information. 2. The existing data and information is not sufficient managed. 3. The lack of financial resources (MoSS), trained workforce, awareness and availability of information and/or institutional setup. 4. The processes of Socio-Economic information collection, production and dissemination are not clear in Egypt. 5. The monitoring organizations do not feed their results into a common information system. 6. Absence of a comprehensive methodology. 39
  • 40. STRENGTHENING THE CAPACITY Implementation Challenges : OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT 1. Management of expectations. 2. Knowledge and assimilative capacity of Governmental Agencies initially low making it difficult for them to express their needs. 3. Lack of realistic performance measures. 4. Rapid changes in technology. 5. Reluctance to provide or share data due to concerns about implications for data owners. 40
  • 41. STRENGTHENING THE CAPACITY Lessons Learned: OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT 1. The MoSS Information System started small rather than big by building capacity and slowly increasing the scope of work. 2. Use the RBM to create realistic work plans and to manage expectations. 3. Reporting is most effective when done on an outcome and output basis with accurate reporting of results and scheduling. 4. Accepted and worked in consideration of the assimilative capacity of MoSS which has substantial grown. 5. Make provisions for rapid changes in technology by creating flexibility in work plans (i.e. short duration activities). 41
  • 42. STRENGTHENING THE CAPACITY Lessons Learned: (Cont.) OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT 6. Ensure counterpart staff are available at a management level ,also useful at a technical level. 7. Use of a participatory approach at all levels in MoSS requiring daily interaction with MoSS Agencies. 8. Need for continuous communication with UNDP. 9. Need to arrange a monthly meeting with all partners to follow up all MoSS implementation activities. 10. It is very important for all MoSS focal points & coordinators to attend all the technical meetings. 11. Need to assign incentives for all employees of MoSS that already auditing the data and using the system. 42
  • 43. Annual Report 2012 STRENGTHENING THE Annual Work Plan CAPACITY OF THE MINISTRY OF SOCIAL AWP 2012 SOLIDARITY PROJECT Description: Annual Review Report of Strengthening the Ministry of Social Solidarity Implementing Partner: Ministry of Social Solidarity, MoSS is divided into 2 ministries (Ministry of Supply and Internal Trade & Ministry of Insurance and Social Affairs) Project Issues: Updated Project Risks: Updated Project Risk Management: 1. MoSS has a weak infrastructure mainly in its financial 1. The Project hired a Senior Accounting Manager, with reporting capacity due to the lack of international strong financial background, to ensure the proper experience with donors. financial management of the project resources in accordance with rules and regulations. 2. The capacity of the MoSS staff to adapt and absorb 2. The Project has supported and expanded all types of changes introduced by the project is limited. training programs of MoSS staff, in order to ensure adoption of introduced reforms by MoSS’ staff. 3. The PMU is not fully integrated with MoSS. 3. The Project management ensured that all contracted Senior Advisors, Consultants, and Specialists are assigned to interact and work directly with MoSS’ senior and middle level staff, in order to ensure transfer of Knowledge & expertise. 43
  • 44. STRENGTHENING THE Annual Work Plan CAPACITY OF THE MINISTRY OF SOCIAL AWP 2012 SOLIDARITY PROJECT THE FOLLOWING OUTPUTS SHALL BE ACHIEVED DURING THE PROJECT’S DURATION. Output: 1 Advisory Unit established at the MOSS Output: 2 Proposed New Structure for decision making Output: 3 Capacity Development is Institutionalized Output: 4 NGO’S Accreditation & Eligibility System is in Place Output: 5 More Effective Social Protection System Output: 6 Nasser Social Bank Evaluated 44
  • 45. STRENGTHENING THE Annual Work Plan CAPACITY OF THE AWP 2012 MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 1 Advisory Unit established at the MOSS Description: To support MOSS in recruiting outside expertise to assist it carry out the project’s targets. YYYY target: 2012 1. Set-up and organized regular senior staff meetings with regard to presenting the various projects of MoSS to all Consultants, with the purpose of facilitating communication and cooperation among all project staff, Consultants and various task managers. 45
  • 46. STRENGTHENING THE Annual Work Plan CAPACITY OF THE AWP 2012 MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 2 Proposed New Structure for decision making Description: To developing Moss’ mission & vision to respond to its new mandate. YYYY Target: 2012 1. Follow-up establishment of (80) projects being implemented by Central Agency for Reconstruction. 2. Follow-up establishment of (21) projects being implemented by Educational Buildings Authority. 3. Follow-up establishment of (15) projects being implemented by Housing Directorates in Governorates. 4. Follow-up establishment of new ministry building in Agouza being implemented by the Military Works Department of Armed Forces which planned to be completed in 31/12/2012 to be outfitted with fiscal year plan 2012/2013. 5. Follow-up the efficiency raising of (33) social units in many Governorates by local contractors. 6. Ratification to start establishment of (13) new social services centers and development of (15) social units in addition to equipped (103) service projects in many Governorates. 46
  • 47. STRENGTHENING THE Annual Work Plan CAPACITY OF THE AWP 2012 MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 3 Capacity Development is Institutionalized Description: To develop capacity building for MOSS and NGO’s. YYYY target:2012 1. Family Database System:  Interface with Smart Card Companies via web services.  Interface with Social Insurance Organization via web services.  Finalize rollout of the system for all governorates.  Hosting Family Database at Social Insurance Organization Information Center. 2. GIS System:  Produce GIS reports for targeting system.  Integrate with systems of Ministry of State for Administrative Development (E. Government). 47
  • 48. STRENGTHENING THE Annual Work Plan CAPACITY OF THE AWP 2012 MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 3 Capacity Development is Institutionalized Description: To develop capacity building for MOSS and NGO’s. 3. Establishing the Ministry IT infrastructure:  Finalize outsourcing Hosting of Data Center at Social Insurance Organization Information Center.  Finalize setting up a Disaster Recovery Center. 4. NGOs System:  Develop the system to meet all the needs of Central Department of NGO’s of Ministry of Insurance and Social Affairs.  Complete the design of the required reports (statistics - detailed data). 5. Pilgrimage System :  Enhancement for running Hajj Program.  Design a new set of reports. 48
  • 49. STRENGTHENING THE Annual Work Plan CAPACITY OF THE AWP 2012 MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 3 Capacity Development is Institutionalized Description: To develop capacity building for MOSS and NGO’s. 6. MOSS Website: Develop the website of the 2 ministries (Ministry of Supply and Internal Trade & Ministry of Insurance and Social Affairs) through:  Coordinating with Project IT Team, the ministry's IT department and Media Consultant to gather information about the current MoSS web site and the needs to be met in the new web site.  Analysis of the current web site, and identifying the restructuring needed and the information and services to be included on the new website.  Developing the new website information structure.  Preparing the development environment.  Creating the design of the new web site, and implementing sample homepage and an internal page. 7. Call Center Project :  Implement new services and updates.  Rollout of MoSS new updates, services and requirements.  Integration of Call Center Database and Complains Database on Website. 8. ERP System:  Keep the project on track. 49
  • 50. STRENGTHENING THE Annual Work Plan CAPACITY OF THE AWP 2012 MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 3 Capacity Development is Institutionalized Description: To develop capacity building for MOSS and NGO’s. 9. Training Activities: A- Ministry of Supply and Internal Trade:  Training (60) directors and managers of the sectors (Senior Management).  Training (80) employees of Citizens Service Department (Executive Management).  Training (45) employees of Public Relations and Media Department (Executive Management).  Training (125) inspectors of Central Department for Inspection (Middle Management).  Training (80) employees of Supply Departments and Offices (Middle Management).  Training (80) employees of Internal Trade Sector (Middle Management). 50
  • 51. STRENGTHENING THE Annual Work Plan CAPACITY OF THE AWP 2012 MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 3 Capacity Development is Institutionalized Description: To develop capacity building for MOSS and NGO’s. 9. Training Activities : B- Ministry of Insurance and Social Affairs :  Conversion Training (160) of Social Units secretarial employees to work as assistant social specialist (Executive Management).  Training (80) social specialists to develop skills and increase functional capacity (Middle Management).  Training (160) social specialists to use Family Database System (Middle Management).  Workshops for )400) of social specialist on the New Social Protection Law (Middle Management).  Training (20) of Senior Managers on Total Quality Management (TQM).  Training (20) of employees on the Computer Skills (Executive Management).  Training (20) of employees on English language (Middle Management). 51
  • 52. STRENGTHENING THE Annual Work Plan CAPACITY OF THE AWP 2012 MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 4 NGO’S ACCREDITATION & ELEGIBILITY SYSTEM Description: To create an accreditation & eligibility system for NGO in Egypt YYYY Target: 2012  Establishing the Audit Committee and implementing of its role and responsibilities.  Training governorates relevant staff on the eligibility criteria forms application.  Evaluation and analysis the results of the eligibility criteria of NGOs.  Arrange for tailored training courses to cover the main weakness elements in the majority of NGOs based on the analysis of the criteria evaluation results.  Drafting the guiding report for the NGOs. 52
  • 53. STRENGTHENING THE Annual Work Plan CAPACITY OF THE AWP 2012 MINISTRY OF SOCIAL SOLIDARITY PROJECT Output: 5 NEW SOCIAL PROTECTION SYSTEM Description: To Review & Improve targeting YYYY target: 2012 1. Targeting Database Project:  Complete Data entry of 1000 villages.  Targeting criteria and formula is used.  Complete Data of supply card beneficiaries to contain all targeting criteria.  Exporting Targeting data for the completed Governorates in easy format for SPSS statistics analysis. 2. Smart Cards:  Rollout of smart cards for Solidarity Pension Service throughout all Governorates.  Develop and implement interface with wholesale companies. 3. Social Solidarity Pensions from Post Offices:  Finalize issuing Social Solidarity Pension from any Post Office in the same Governorate by family smart card. 53
  • 54. STRENGTHENING THE Annual Work Plan CAPACITY OF THE MINISTRY OF SOCIAL AWP 2012 SOLIDARITY PROJECT Output: 6 IMPROVING NASSER SOCIAL BANK Description: To assess Nasser Social Bank and prepare it for restructuring. YYYY target: 2012 1. Prepare revised set of regulations for NSB Investment, “Takaful”, “Takeraats/Akarats” and Legal divisions. 2. Continue to:  Connect central departments to newly commissioned NSB’s digital network.  Investigate means to modernize archiving capabilities.  Introduce ATM services to NSB clients and employees.  Redefine branches’ performance criteria to match NSB’s philosophies/mission.  Develop NSB website.  Develop NSB intranet site (for internal use).  Develop a preliminary concept for a revamped main branch at 35 Kasr El Nil-Cairo.  Implement Year 2012 NBE training program.  Continue monitoring progress at the three new branches: Nasr City, 6 Oct., and Zakazeek.  Prepare a human development program for NSB staff.  Monitor progress of the new Human Capital Development Centre (HCDC). 54
  • 55. STRENGTHENING THE Annual Work Plan CAPACITY OF THE MINISTRY OF SOCIAL AWP 2012 SOLIDARITY PROJECT Output: 6 IMPROVING NASSER SOCIAL BANK Description: To assess Nasser Social Bank and prepare it for restructuring. YYYY target: 2012 3. Evaluate 6 branches of NSB and “Zakaat” committees in Southern Egypt. 4. Finalize revised regulations for Investment, “Takaful”, “Takeraats/Akarats” and Legal divisions. 5. Connect central departments to NSB’s newly commissioned digital network. 6. Issue the strategy formulation process with NSB’s executives. 7. Initiate contact with Engineering Authority of Armed Forced to revamp upper Egypt branches, and Initiate a study to formulate functionalities and roles to introduce new NSB access points 8. Revamped, completely, the Information and Computer Center of NSB, connecting 10 Database Centers of NSB branches. 9. Establish the bank’s Call Center, and documenting all operational regulations. 55
  • 56. STRENGTHENING THE CAPACITY OF THE MINISTRY OF SOCIAL SOLIDARITY PROJECT THANK YOU 56