1. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
Purpose/Description of the Target Annual Progress Report for 2012:
An annual project progress report should be prepared toward the end of
each year to document the performance of each project and communicate
it to appropriate stakeholders. This review will focus on the extent to which
progress is being made towards production of deliverables required to
generate output and identification of project issues and their solutions.
Format:
Any standard appearance to which the Deliverable must conform:
Annual Project Progress Report Atlas
Derivation/Inputs:
Annual Progress Report receives inputs from:
Deliverable Descriptions
Quality Log
Issues Log
Risks Log
Quality Control Method:
Project Assurance will review the Annual Progress Report and ensure that
progress is properly documented including % progress towards deliverables,
risks and issues.
Accountabilities:
Accountabilities for producing the Annual Review Report:
Project Manager
1 of 15
2. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
Annual Report
DATE:
Award ID: 00044225
Description: Annual Review Report of Strengthening the Ministry of Social Solidarity
Implementing Partner: Ministry of Social Solidarity
Period Covered: 2012
Project Issues:
Updated Project Risks: Updated Project Risk Management
1. MoSS has a weak infrastructure mainly in its 1. The Project hired a Senior Accounting
financial reporting capacity due to the lack of Manager, with strong financial
international experience with donors. background, to ensure the proper
financial management of the project
resources in accordance with rules
and regulations.
2. The capacity of the MoSS staff to adapt and 2. The Project has supported and
absorb changes introduced by the project is expanded all types of training
limited. programs of MoSS staff, in order to
ensure adoption of introduced
reforms by MoSS’ staff.
3. Mainstreaming and inclusion of the Project 3. The Project management ensured
Management Unit (PMU). The PMU that all contracted Senior Advisors,
operates in seclusion of the remainder of the Consultants, and Specialists are
Ministry and is not yet fully integrated with assigned to interact and work directly
MoSS. with MoSS’ senior and middle level
staff, in order to ensure transfer of
Knowledge & expertise.
4. The newly formed ministry MoSS’s complex 4. Extensive efforts are underway to
and changing mandate has made it difficult formulate and broadcast MoSS’
for both Ministry staff and other government reform mandate and its vision of
counterparts to interpret its role and reform to both its staff and to the
activities. public. A broad communication
message will be launched in 2009.
5. Expected changes in both the Egyptian NGO 5. The Project/UNDP has advocated a
law and social policy pertaining to subsidies participatory approach towards both
might result in increased social pressures. change processes in order to
incorporate inputs and perspective
from a wide variety of stakeholders,
including the set-up of various internal
and external NGO Policy Review
Committees.
2 of 15
3. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
Project Performance:
OUTPUT 1: MOSS TAU ESTABLISHED
Project ID: 00044225
Description: To support MOSS in recruiting outside expertise to assist it carry out the project .
YYYY target: 2012
1. Set-up and organized regular senior staff meetings with regard to presenting the various
projects of MoSS to all Consultants, with the purpose of facilitating communication and
cooperation among all project staff, Consultants and various task managers.
YYYY Achievement:
1. The Project management ensured that all contracted Senior Advisors, Consultants, and
Specialists are assigned to interact and work directly with MoSS’ senior and middle level
staff, in order to ensure transfer of Knowledge & expertise.
OUTPUT 2: MOSS NEW STRUCTURE
Project ID: 00044225
Description: To developing Moss’ mission & vision in order to respond to its new mandate
YYYY Target: 2012
1. Central Agency for Reconstruction projects:
Follow-up establishment of (80) projects to be implementing as follow:
Establishment of (62) projects.
Development of (18) projects.
2. Educational Buildings Authority projects:
Follow-up establishment of (21) projects to be implementing by the holder as follow:
Establishment of (10) projects.
Development of (9) projects.
Raising the efficiency of (2) projects.
3. Housing Directorates Projects in Governorates:
Follow-up establishment of (15) projects being implemented by housing directorates in
Governorates.
4. Court building project for the new ministry building in Agouza:
Follow up the implementation of the project, being implemented by the Military Works
Department of Armed Forces and planned to be completed in 31/12/2011 to be outfitted
with fiscal year plan 2012/2013.
5. Raise the efficiency of social units project:
Follow-up the upgrading of (33) units, Social Directorates in Governorates were approved to
raise the efficiency of social units according to fiscal year plan 2010/2011 & 2011/2012.
3 of 15
4. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
6. Ratification to start establishment of (13) new social services centers and development of
(15) social units in addition to equipped (103) service projects in many Governorates
according to fiscal year plan 2012/2013.
7. Investment plan for the fiscal year 2011/2012 & 2012/2013:
Monitor the implementation of the investment plan for Social Affairs Sector and Supply
sector. (25.7 million L.E. allocated from Social Affairs Sector and 9.19 million L.E. allocated
from Supply Sector of an item of non-residential buildings) to complete implementation the
projects according to Investment plan for the fiscal year 2011/2012.
YYYY Achievement:
1. Projects of the Central Agency for Reconstruction (Completed):
Establishment of (33) projects (from a total of 62 projects).
Development of (9) projects (from a total of 18 projects).
2. Educational Buildings Authority projects (Been completed):
Establishment of (5) projects plus (2) projects ready to handover (out of 10 total
projects).
Development of (7) projects (out of 9 total projects).
Raising the efficiency of (2) projects (out of 2 total projects).
3. Housing Directorates Projects in Governorates:
Follow-up establishment of (15) projects being implemented by housing directorates in
Governorates.
4. Court building project for the new ministry building in Agouza:
Been ratified by the Ministry of Planning and International Cooperation, transferred of 16
million L.E. from (16 million L.E.) allocated for Court building project for the new ministry
building in Agouza and paid for Military Works Department of Forced Armed as down
payment.
5. Raise the efficiency of social units project:
Upgrading of (9) social units (out of total 33 social units) planned to be raised the efficiency.
OUTPUT 3: MOSS CAPACITY DEVELOPMENT
ID: 00044225
Description: To develop capacity building for MOSS (and NGOs).
YYYY target: 2012
First : Information Technology Activities:
1. Family Database System:
Finalize rollout of the system for all Governorates.
Interface with Smart Card Companies via web services.
Interface with Social Insurance Organization via web services.
Hosting Family Database at Social Insurance Organization Information Center.
4 of 15
5. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
2. GIS System:
Produce GIS reports for targeting system.
Integration with Ministry of State for Administrative Development systems
(E. Government).
3. Establishing the Ministry of Insurance and Social Affairs IT infrastructure:
Finalize outsourcing Hosting of Data Center at Social Insurance Organization
Information Center.
Finalize setting up a Disaster Recovery Center for Ministry of Supply and Internal Trade.
4. NGOs System:
Develop the system to meet all the requirements of Central Department of NGO’s of
Ministry of Insurance and Social Affairs.
Complete the design of the required reports (Statistics - detailed data).
5. Pilgrimage System :
Enhancement for running Hajj Program.
Design a new set of report.
6. MOSS Website:
Develop the website of the 2 ministries (Ministry of Supply and Internal Trade & Ministry of
Insurance and Social Affairs) through:
Coordinating with Project IT Team, the ministry's IT department and Media Consultant
to gather information about the current MoSS web site and the needs to be met in the
new web site.
Analysis of the current web site, and identifying the restructuring needed and
the information and services to be included on the new website.
Developing the new website information structure.
Selecting and evaluating the platform to be used in the development of the new website.
Preparing the development environment.
Creating the design of the new web site, and implementing sample homepage and an
internal page.
7. Call Center Project :
Implement new services and updates.
Rollout of MoSS new updates, services and requirements.
Integration of Call Center Database and Complains Database on Website.
8. ERP System:
Keep the project on track.
Secondly : Training Component:
A- Ministry of Supply and Internal Trade :
Training (60) directors and managers of the sectors (Senior Management).
Training (80) employees of Citizens Service Department (Executive Management).
Training (45) employees of Public Relations and Media Department (Executive
Management).
Training (125) inspectors of Central Department for Inspection (Middle Management).
Training (80) employees of Supply Departments and Offices (Middle Management).
Training (80) employees of Internal Trade Sector (Middle Management).
5 of 15
6. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
B- Ministry of Insurance and Social Affairs :
Conversion Training (160) of Social Units secretarial employees to work as assistant
social specialist (Executive Management).
Training (80) social specialists to develop skills and increase functional capacity
(Middle Management).
Training (160) social specialists for data entry of Family Database System (Middle
Management).
Establish 3 workshops for (400) of social specialist on the New Social Protection Law
(Middle Management).
Training (20) of Senior Managers on Total Quality Management TQM.
Training (20) of employees on the Computer Skills (Executive Management).
Training (20) of employees on English language (Middle Management).
YYYY Achievement:
First : Information Technology Activities:
1. Smart Cards:
Defined the rules of matching the input data for the ration cards with the exchange
data and sent it to the Smart Cards Companies.
The smart cards companies designed programs necessary to the matching.
Testing the matching programs in some Governorates Such as Port Said, Ismalia,
Aswan.
2. Family Database System:
Finalize rollout of the system in 27 governorates
Technical support for Family Database
3. Targeting:
Technical support for Targeting Program
Exporting Targeting data for the completed Governorates in a format that easy for
SPSS statistics
4. Social Solidarity Pensions from Post Offices
Following up the monthly payment of Social Solidarity Pensions from Post Offices.
Co-operating with the Governorates and social administrative offices and Information
Center to solve all networks and technical problems related to the project.
5. NGOs Application
Enhancement the system to meet the requirements of NGOs central department.
Implementation of the new screens include (training programs, membership,
contributions, committees, directors board members, directors board meetings,
assembly members, assembly meetings, volunteers, NGO problems, research
experience, revenues and expenses, budget).
Added and redesigned some required reports (Statistics & detailed data).
Due to quite of Eng. Ahmed Husien (System Developer), we are going to hire another
one to do his work.
6 of 15
7. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
6. Pilgrimage System :
The program is divided into 2 main parts:
A- Electronic lottery program:
Hajj applications for members of NGOs' directorates & ministry staff.
Implementation of all required amendments to the electronic lottery program.
B- Hajj Information System:
Includes data for the winners of the Hajj, supervisors data, financial receipts,
hotels, hotels accommodation, flights, fellow-up reports.
The current screens have been updated to increase the level of performance.
Design a new set of reports.
Enhancement for running Hajj Program.
Adding and redesign some of the Hajj program features.
Implementation a program to print the identity cards of the pilgrims and supervisors
including their data and personal photos.
Providing technical support for Hajj Program users.
Due to quite of Eng. Ahmed Husien (System Developer), we are going to hire
another one to do his work.
7. Call Center Project:
Finalize system updates, which include the following:
o Adding new services (Botagaz , Productive Families , Customer services).
o Create new complaint forms for the new services.
o Changing the mandatory/optional filed according to our business need.
o Customizing the Citizen form.
o Editing the Validation rules.
Continue established training courses for users:
o Follow up Department in Tamween Sector.
o Follow up Department in Sheoon Sector.
Keep the project on track, by continually monitoring the departments’ performance
through monthly reports.
Handover of the system to Eng. Mohamed Abd El-Fatah who will be the new
project manager instead of Eng. Ayman Abd El-Kader due to his quite.
8. ERP Project:
A. Regarding (Payroll and HR applications for Sheoon sector):
Finalizing the register employees records process (1600 record) and update
their information which include:
o General information (name, birth date, ID, Graduation information,
employee rank, promotions).
o Basic salaries.
o Training courses.
o Motivation bounce.
o Yearly bounce.
o Vacations.
Continue running the audit process of reviewing the employee’s payroll data, to
be able for issuing electronic payroll lists.
B. Regarding (Accounting, budgeting applications for Sheoon and Tamween sectors):
The employees work on day to day basis, and they deliver the Application
Output every month, as required.
7 of 15
8. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
C. Regarding (Inventory and purchasing applications for Sheoon and Tamween sectors):
The employees register departments data and keep it updated.
D. Handover of the system to Eng. Aml Helmy who will be the new project manager
instead of Eng. Ayman Abd El-Kader due to his quite.
9. GIS System:
GIS work includes three main billers, each has its status according to its scopes needs
and details, these billers are:
A. GIS Web Portal
GIS Webpage linked to Ministry main web site:
- Updating the GIS portal through linking the current GIS database with the
updated version of family database (Automatically updated link) on 3
aggregation levels (Governorates, Districts, Sub districts).
- Adding more web functions (zoom in/out & info) to facilitate the usage of the
portal.
- Working on customizing more technical function such print layouts function
using VB studio ver.10.
B. Mapping Supply services
Goal: Creating GIS maps for the current supply services on the street level detailed
maps (scale 1:5000) covers all Egypt Governorates.
Participants:
MOSS Central Department of Planning.
Al-Massryen Company.
CAPMAS.
MOSS GIS unit.
Roles and responsibilities :
CAPMAS: Based on verbal agreement between the Minster and General
Abu-Bakr Al Gindy (Head of CAPMAS), CAPMAS provides MOSS GIS unit
with complete set of GIS vector data on street level (1:5000) for all Egypt
Governorates, these maps will be used to locate the supply services
starting by subsidized bakeries with its linked outlets.
MOSS GIS unit: receiving maps from CAPMAS then prepare the paper
layouts and print each sub district separated in map size A0.
Central planning department receives the paper print outs maps to be
disseminated to different other departments responsible for Bakeries and
Outlets distribution.
Al-Massreyn Company is responsible for mapping the bakeries and outlets,
in addition to submit all details related to the bakeries such as (name, type,
quota, separated or not, address..etc).
Then all data to be back again to MOSS GIS unit to do the following actions:
o Build complete access database contains the gathered data related to
each bakery and attached its outlets.
o Locate both bakeries and outlets on the Maps which enable the decision
makers to judge the equality of their distribution over certain location.
Work status:
After many periodical visits to CAPMAS; a complete detailed digital maps
for 6 Governorates had been delivered to the MOSS GIS unit. these
8 of 15
9. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
governorates are:
(Giza, Cairo, Qaluobia, Gharbia, Sharkia, Behira).
The project starts with mapping bakeries and outlets on the governorate of
Greater Cairo Area (Cairo, Giza and Qaluobia).
Note: All finished and revised maps original copies are kept in GIS unit.
C. Mapping Target Project results:
Goal: Creating GIS printouts highlight the result of targeting project with
co-operation of Social Study Institute (Dr Ibtsam Al Gafarawy).
Work status :
GIS unit was responsible for receiving the targeting data and then preparing
the layouts which shows the result of targeting project to be printed on the
complete report, starting by Al Behira Governorate with its district.
All the work in this phase has been done and sent it to Dr Ibtsam.
A sample of the map produced showed as:
D. GIS Handover
Starting from 15 September 2011; The GIS unit had been delivered completely to
a technical committee of MOSS Information Center.
The GIS handover includes the flowing:
- GIS Hardware:
3 units - original Dell PC’s
1 unit - Plotter
1 unit - A4 Black& white laser printer
1 unit - A4 Colour printer
1 unit - Scanner
9 of 15
10. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
- GIS Software:
Handover 3 Original GIS licenses (2) ARCGIS Editor & (1) ARC Server, and
Installation packages needed for plotter, printers and scanner.
- GIS Work situation :
Detailed hand over notes and delivery reports had been submitted to the
information center committee , in addition to give them 13 days on job
training to let them be able to complete the needed whole GIS work on time .
10. Redesign & development of ministry of Insurance and Social Affairs, MISA
Website:
Coordinating with Project IT Team, the ministry's IT department and Media
Consultant to gather information about the current MISA web site and the needs to
be met in the new web site.
Analysis of the current web site, and identifying the restructuring needed and the
information and services to be included on the new website.
Developing the new website information structure.
Selecting and evaluating the platform to be used in the development of the new
website.
Preparing the development environment.
Creating the design of the new web site, and implementing sample homepage and
an internal page.
Secondly : Training Activities:
A- Ministry of Supply and Internal Trade :
Training (20) directors and managers of the sectors (Senior Management).
Training (20) employees of Citizens Service Department (Executive Management).
Training (25) employees of Public Relations and Media Department (Executive
Management).
Training (40) inspectors of Central Department for Inspection (Middle Management).
Training (30) employees of Supply Departments and Offices (Middle Management).
Training (30) employees of Internal Trade Sector (Middle Management).
B- Ministry of Insurance and Social Affairs :
Training (160) social specialists for data entry of Family Database System (Middle
Management).
Thirdly : Research & Development:
Activities of the short term National Consultants:
Scientific Coordinator with World Food Program.
Prepared memos to the minister regarding economic and management issues.
Participated in the Minster’s Meetings that related to economic issues.
Reviewed Egyptian Country Strategy for the World Food Program 2012 to 2016.
Participated in the preparation of the draft of “the National Body of Food Subsidy” law.
10 of 15
11. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
Prepare case study on “General Structure of MEGA Bakeries and Merging of Small
Bakeries”.
Finalized and Present the final result of the “Supply Chain Study” to the Minister.
Finalized conduct study of “Measuring of the Balady Bread Production Cost”.
Prepared the TOR of “Build and design a new efficient and effective system for Balady
Bread through removing government intervention from initial stages of the Balady
Bread Supply Chain to its last stage”.
Ongoing conduct in collaboration with WFP and international experts:
Build and design a new efficient and effective system for Balady bread.
Draw structured implementation plan for the new Balady Bread system.
Design a pilot project for the first phase of the implementation of the new enhanced
and efficient Balady Bread system.
Responsible for the following files:
World Bank: meetings on behalf of his Excellency the minister; drafts & executive
Islamic Bank for Development: meetings with his Excellency, drafts & executive
Summaries of MoS&SJ vision & strategies, proposed plan of collaboration.
NGO: work follow‐up & reviewing of proposed new NGO, follow‐up of successful
experiences all over the world to acquire experience in targeting the poorest.
Developing Egyptian NGO map ( geographic distribution, activities, total numbers of
beneficiaries, etc…).
UN World Food Programme: executive summary of monthly reports related to
Work in Egypt (FFT).
Executive summaries of studies & reports:
Evaluating the performance of help & social development sector in MoS&SJ.
The disaster fund.
Targeting the most vulnerable groups.
Evaluating the national module to reduce poverty.
The role of NGO in promoting human development.
Aya company for consultancy & development.
11 of 15
12. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
OUTPUT 4: ACCREDIT & ELIGIBILITY SYSTEM FOR NGO
Project ID: 00044225
Description: To create an accreditation & eligibility system for NGO in Egypt.
YYYY Target: 2012
1. Establishing the Audit Committee, and implementing of its role and responsibilities.
2. Training Governorates relevant staff on the application of the eligibility criteria forms.
3. Evaluation and analysis the criteria application results on waves of NGOs.
4. Arrange for tailored training courses to cover the main weakness elements in the majority
of NGOs based on the analysis of the criteria evaluation results.
5. Drafting the NGOs guiding report.
YYYY Achievement:
1. NGO’s Eligibility System
A. NGO’s Central Department gathering more information and data to be included in the
NGO’s report/guiding book, It is supposed to cover regulations and directives aspects,
criteria, statistics, challenges, examples of promising and successful NGO’s, granting
parties, kinds and conditions of support, large networking groups and valuable
partnerships projects, volunteers roles, regional NGO’s, ministry's targeted social
solidarity activities, recommendations, etc …
B. NGO’s Central Department follow-up the implementation of NGO’s eligibility criteria.
C. Drafting proposals to act positively towards loses deriving to meet the current aspirations
following the January 25th Revolution.
D. Follow up remarks and recommendations related to audit findings and NGO’s activities.
12 of 15
13. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
OUTPUT 5: NEW SOCIAL PROTECTION SYSTEM
Project ID: 00044225
Description: To Review & Improve targeting
YYYY target: 2012
1. Smart Cards:
Rollout of smart cards for Solidarity Pension Service throughout all Governorates.
Develop and implement interface with wholesale companies.
2. Social Solidarity Pensions from Post Offices:
Study payment from more than one post office for each social service center.
Finalize issuing Social Solidarity Pension from Post Offices by family smart card.
YYYY Achievement:
1. Smart Cards:
Defined the rules of matching the input data for the ration cards with the exchange
data and sent it to the smart card companies.
The smart card companies designed programs necessary to the matching.
Testing the matching programs in some Governorates such as Port Said and Aswan.
2. Targeting:
Technical support for Targeting Program.
Exporting Targeting data for the completed governorates in a format that easy for
SPSS statistics analysis.
3. Social Solidarity Pensions from Post Offices:
Following up the monthly implantation circulation of Social Solidarity Pensions from
Post Offices.
Co-operating with Governorates and social administrative offices and Information
Center of MoSS to solve all the networks and technical problems of the project.
13 of 15
14. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
OUTPUT 6: IMPROVING NASSER SOCIAL BANK
Project ID: 00044225
Description: To assess Nasser Social Bank and prepare it for restructuring.
YYYY target: 2012
1. Finalize prepared revised set of regulations for NSB Investment, “Takaful”,
“Takeraats/Akarats” and Legal divisions.
2. Continue to:
Connect central departments to newly commissioned NSB’s digital network.
Investigate means to modernize archiving capabilities.
Introduce ATM services to NSB clients and employees.
Redefine branches’ performance criteria to match NSB’s philosophies/mission.
Develop NSB website.
Develop NSB intranet site (for internal use).
Develop a preliminary concept for a revamped main branch at 35 Kasr El Nil-Cairo.
Implement Year 2012 NBE training program.
Continue monitoring progress of 3 new branches: Nasr City, 6 Oct., and Zakazeek.
Prepare a human development program for NSB staff.
Monitor progress of the new Human Capital Development Centre (HCDC).
3. Evaluate 6 branches of NSB and “Zakaat” committees in Southern Egypt.
4. Connect central departments to NSB’s newly commissioned digital network.
5. Issue the Strategy Formulation Process with NSB’s Executives.
6. Initiate contact with Engineering Authority of Armed Forces to revamp upper Egypt
branches, and Initiate a study to formulate functionalities and roles to introduce new NSB
access points.
7. Revamped, completely, the Bank’s Database Center, and Establish the Bank’s Call
Center and documenting all operational regulations.
8. Revamped, completely, 10 Information Center of NSB Branches, and connecting them
with the NSB Database Center.
NSB’s Reforms Pilot Project has been completed successfully.
Phase-1 of the Reforms Project begins on November 1st, 2010. It focuses on preparing,
publishing, and implementing NSB strategies for the next 3 years including:
full automation of services, executing an aggressive human capital development plan, and
physically revamping all NSB branches.
1. Conduct a third round of negotiations with the African Development Bank (AFDB) in
Tunisia.
2. Conduct a fourth round of negotiations with the AFDB in Cairo.
3. Initialized the loan and grant agreement with the AFDB.
4. Prepare memos required to increase take-home pay of NSB employees.
5. Successfully selecting, nominating, and qualifying two NSB staff members to attend a two
month training courses in India sponsored by the African Asian Rural Development
Organization (AARDO).
6. Continued to:
Work on a comprehensive automation project.
Investigate the feasibility to implement the first social business project in Sohag.
Prepare an NSB aggressive Human Capital Development program.
14 of 15
15. Annual Review Second Quarter Report for 2012
Deliverable Description Date: 1st July 2012
Conclusion:
In November, 2010 NSB’s Reforms Pilot Project has been completed successfully, and began
Phase-1 of its Reforms Project.
It focuses on preparing, publishing, and implementing NSB strategies for the next 3 years
including: full automation of services, executing an aggressive human capital development plan,
and revamping all of NSB 90 branches.
The Reforms Pilot Project included: revamping the current data center at NSB Head Office to
enable the operation of a newly developed state-of-the-art digital network, established an NSB
Human Capital Development Center (HCDC), developed new/revised bank regulations,
developed a model for the look-and-feel of rebranded bank branches, hired well over 400 new
employees based on predefined set of selection criteria, and opened 3 new branches
conforming to the new rebranded branch model.
NSB automation project will fully automate all NSB services and connect all of its 90 branches
through a sophisticated/secured network. It will also ensure that the bank uses state-of-the-art
technologies and information systems. The project will incorporate an efficient business
continuity solution to ensure data integrity and around the clock availability of services. In
addition, the project will enable the bank to provide a set of services that it is not currently
possible due to the nature of its legacy/outdated information systems and technologies.
The bank is undertaking an aggressive Human Capital Development Center initiative and
succession plan. The initiative will begin with a massive human capital assessment and gap
analysis phase followed by a customized human capital development program that targets
employees across the organization to change/improve its culture while drastically improving on
its human capital assets.
Through the project, NSB was able to upgrade and refurbish the branches of 6th of October,
Zagazig, Mohandiseen, Qous, New Valley, Aswan; then developing Madinet Nasr, and four
other branches will be finished at Asyut, Suhaj, Qena and Luxor.
Furthermore, within 2011, NSB has a plan to upgrade and refurbish 19 other branches.
Other branches are in serious need for upgrading, refurbishing and retrofitting. NSB has a plan
to continue upgrading other branches by the year 2014 through consulting engineering firms and
certified contractors.