Kalegran / Flare Station
1 | P a g e
www.awi.com
 Project Name: OilServ ( Kalegran ) / New Flare station with flare line
 Site Position: Construction Manager
 Project Start: 01th
February 2015
 Project Finished: 04th
April 2013
 Duration : 64 Days
 Work Done :
o Slug Catcher Slab of Area 91m2 with 0.5m depth
o FKOD slab of Area 41m2 with 0.3m Depth
o Inlet Manifold Slab of area 39m2 with 0.3 depth
o Pig launcher Skid Slab of Area 10m2 with 0.3 depth
o Propane Vessel Slab of Area 13m2 with 0.3 depth
o Flare Stack Slab of Area 9m2 with 1.3m depth
o Anchor support Slab x 3 Nos. of Area each 17 m2 with 1.2m Depth
o Pipe supports foundation with Built in Anchor Bolts x 51 Nos. of area 0.4m2 with depth range between ( 0.6
to 2.0 )m
o Cut/Fill work
 Cut work of Total Volume = 18,313m3
 Fill work of Total Volume =12,873m3
o Road Sub-base of Total Area 2385m2 with two layer depth each 0.15m
AWI
Kalegran / Flare Station
2 | P a g e
Site Before starting work
AWI
Kalegran / Flare Station
3 | P a g e
Site During and After Work:
AWI
Kalegran / Flare Station
4 | P a g e
AWI
Kalegran / Flare Station
5 | P a g e
Prepared By:
Eng. Mohammad N. Kamala

More Related Content

Similar to Oilserv Project

Conversion of Underground Mine to Open Cast Mine
Conversion of Underground Mine to Open Cast MineConversion of Underground Mine to Open Cast Mine
Conversion of Underground Mine to Open Cast MineAbdul Mujeeb
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxAGNIVORAY1
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationSiddhartha Bhamidipati
 
Seminar Underground Construction PPT.pptx
Seminar Underground Construction PPT.pptxSeminar Underground Construction PPT.pptx
Seminar Underground Construction PPT.pptxMansimishra351962
 
Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Gautam Sharma
 
nwosu chioma sylvia
nwosu chioma sylvianwosu chioma sylvia
nwosu chioma sylviachioma nwosu
 
Penta Capstone Semester 2
Penta Capstone Semester 2Penta Capstone Semester 2
Penta Capstone Semester 2dverm
 
Polavaram internship
Polavaram internshipPolavaram internship
Polavaram internshipsaibabu48
 

Similar to Oilserv Project (9)

Conversion of Underground Mine to Open Cast Mine
Conversion of Underground Mine to Open Cast MineConversion of Underground Mine to Open Cast Mine
Conversion of Underground Mine to Open Cast Mine
 
Blasting Gallery Method
Blasting Gallery MethodBlasting Gallery Method
Blasting Gallery Method
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigation
 
Seminar Underground Construction PPT.pptx
Seminar Underground Construction PPT.pptxSeminar Underground Construction PPT.pptx
Seminar Underground Construction PPT.pptx
 
Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)
 
nwosu chioma sylvia
nwosu chioma sylvianwosu chioma sylvia
nwosu chioma sylvia
 
Penta Capstone Semester 2
Penta Capstone Semester 2Penta Capstone Semester 2
Penta Capstone Semester 2
 
Polavaram internship
Polavaram internshipPolavaram internship
Polavaram internship
 

Oilserv Project

  • 1. AWI Kalegran / Flare Station 1 | P a g e www.awi.com  Project Name: OilServ ( Kalegran ) / New Flare station with flare line  Site Position: Construction Manager  Project Start: 01th February 2015  Project Finished: 04th April 2013  Duration : 64 Days  Work Done : o Slug Catcher Slab of Area 91m2 with 0.5m depth o FKOD slab of Area 41m2 with 0.3m Depth o Inlet Manifold Slab of area 39m2 with 0.3 depth o Pig launcher Skid Slab of Area 10m2 with 0.3 depth o Propane Vessel Slab of Area 13m2 with 0.3 depth o Flare Stack Slab of Area 9m2 with 1.3m depth o Anchor support Slab x 3 Nos. of Area each 17 m2 with 1.2m Depth o Pipe supports foundation with Built in Anchor Bolts x 51 Nos. of area 0.4m2 with depth range between ( 0.6 to 2.0 )m o Cut/Fill work  Cut work of Total Volume = 18,313m3  Fill work of Total Volume =12,873m3 o Road Sub-base of Total Area 2385m2 with two layer depth each 0.15m
  • 2. AWI Kalegran / Flare Station 2 | P a g e Site Before starting work
  • 3. AWI Kalegran / Flare Station 3 | P a g e Site During and After Work:
  • 4. AWI Kalegran / Flare Station 4 | P a g e
  • 5. AWI Kalegran / Flare Station 5 | P a g e Prepared By: Eng. Mohammad N. Kamala