1. AWI
Kalegran / Flare Station
1 | P a g e
www.awi.com
Project Name: OilServ ( Kalegran ) / New Flare station with flare line
Site Position: Construction Manager
Project Start: 01th
February 2015
Project Finished: 04th
April 2013
Duration : 64 Days
Work Done :
o Slug Catcher Slab of Area 91m2 with 0.5m depth
o FKOD slab of Area 41m2 with 0.3m Depth
o Inlet Manifold Slab of area 39m2 with 0.3 depth
o Pig launcher Skid Slab of Area 10m2 with 0.3 depth
o Propane Vessel Slab of Area 13m2 with 0.3 depth
o Flare Stack Slab of Area 9m2 with 1.3m depth
o Anchor support Slab x 3 Nos. of Area each 17 m2 with 1.2m Depth
o Pipe supports foundation with Built in Anchor Bolts x 51 Nos. of area 0.4m2 with depth range between ( 0.6
to 2.0 )m
o Cut/Fill work
Cut work of Total Volume = 18,313m3
Fill work of Total Volume =12,873m3
o Road Sub-base of Total Area 2385m2 with two layer depth each 0.15m